Smiley First, LLC v. Department of Transportation ( 2023 )


Menu:
  • A.M.NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    SJC-13300
    SMILEY FIRST, LLC     vs.   DEPARTMENT OF TRANSPORTATION.
    Suffolk.    November 4, 2022. – May 23, 2023.
    Present:    Budd, C.J., Gaziano, Lowy, Cypher, Kafker, Wendlandt,
    & Georges, JJ.
    Easement. Eminent Domain, Extent of taking.      Real Property,
    Easement. Railroad.
    Civil action commenced in the Superior Court Department on
    January 24, 2020.
    The case was heard by Paul D. Wilson, J., on motions for
    summary judgment.
    The Supreme Judicial Court on its own initiative
    transferred the case from the Appeals Court.
    Paul L. Feldman (Shawn M. McCormack also present) for the
    plaintiff.
    Kendra Kinscherf, Assistant Attorney General, for the
    defendant.
    Ben Robbins & Daniel B. Winslow, for New England Legal
    Foundation, amicus curiae, submitted a brief.
    Deborah J. La Fetra, of California, Sam Spiegelman, of
    Washington, & Jonathan M. Houghton, for Pacific Legal
    Foundation, amicus curiae, submitted a brief.
    2
    GEORGES, J.     In this case, we consider whether an easement
    taken by eminent domain in 2018 (2018 easement) by the
    defendant, the Department of Transportation (MassDOT), exceeded
    the scope of an easement taken in 1991 (1991 easement) by
    MassDOT's predecessor in interest, the Department of Public
    Works (DPW), with respect to certain land in the South Boston
    section of Boston (burdened land) that presently is owned by the
    plaintiff, Smiley First, LLC (Smiley).
    DPW's 1991 order of taking (1991 taking) created an
    easement over the burdened land for purposes of "the relocation
    of the facilities of the Consolidated Rail Corporation
    [(Conrail)]," which were going to be displaced by construction
    of a haul road for the Central Artery/Tunnel Project, also known
    as the "Big Dig."1    In 2017, the Massachusetts Bay Transportation
    Authority (MBTA) announced plans to construct a test track and a
    6,000 square foot building for newly purchased subway cars (Red
    Line test track project) on the portion of Smiley's land
    burdened by the 1991 easement.     MassDOT then recorded the 2018
    confirmatory order of taking (2018 taking), which provides that
    it is to confirm and, "to the extent necessary to establish such
    1 The Central Artery/Tunnel Project rerouted the Central
    Artery, a portion of Interstate Route 93 that ran through the
    city of Boston on an elevated highway, to an underground tunnel.
    DPW and Massachusetts Bay Transportation Authority operated
    together on the Big Dig project. MassDOT is the lawful
    successor to DPW in accordance with G. L. c. 6C.
    3
    rights, acquire[]" an easement "for railroad purposes" that
    include the Red Line test track project.
    Based on its contention that the 2018 taking merely
    confirmed rights that it already held under the 1991 taking,
    MassDOT refused to pay Smiley any compensation for the 2018
    taking, and this litigation ensued.   On the parties' cross
    motions for partial summary judgment, a Superior Court judge
    determined, in reliance on his understanding that easements
    taken by eminent domain are not subject to the ordinary rules of
    interpretation of easements, that the 1991 easement was a grant
    to use the entire area of the easement for "any 'railroad
    purpose,'" including the Red Line test track project, and,
    accordingly, that Smiley was due no compensation as a result of
    the 2018 taking.
    We hold that, while the intent of the parties is not to be
    considered when an easement is taken by eminent domain, the
    ordinary rules of interpretation for easements otherwise apply.
    Thus, the "scope of the condemnor's use of the easement will be
    limited to the extent reasonably necessary for the purpose
    served by the taking, so that the landowner's right to use the
    easement area is as great as possible while remaining reasonably
    consistent with the purpose of the taking."   General Hosp. Corp.
    v. Massachusetts Bay Transp. Auth., 
    423 Mass. 759
    , 764 (1996).
    Applying this principle here, we conclude that the 1991 easement
    4
    was more limited in scope than the 2018 easement and, in
    particular, did not encompass a use such as the Red Line test
    track project.   Therefore, the summary judgment in favor of
    MassDOT must be reversed, and the matter remanded to the
    Superior Court for a determination of the appropriate
    compensation due Smiley.2
    1.   Background.    We summarize the undisputed facts set
    forth in the motion judge's decision on the parties' cross
    motions for partial summary judgment, supplemented by other
    uncontroverted facts in the summary judgment record.     See
    Williams v. Board of Appeals of Norwell, 
    490 Mass. 684
    , 685
    (2022).
    a.   Smiley's property.   In 2015, Smiley acquired an 18,088
    square foot parcel of land at the intersection of B Street and
    Cypher Street in South Boston.    Approximately 12,510 square feet
    of that property comprise the burdened land at issue here, which
    is contained within one of the parcels, parcel 60-E-RR-1,
    subject to the 1991 taking.
    b.   1991 taking.   In 1991, DPW laid out a limited access
    State highway, known as the South Boston Haul Road (haul road),
    to support construction of the extension of Interstate Route 90
    to the proposed third harbor tunnel, as part of the Central
    2 We acknowledge the amicus briefs by the New England Legal
    Foundation and the Pacific Legal Foundation.
    5
    Artery/Tunnel Project.   Construction of the haul road was a
    massive enterprise that affected over 1 million square feet of
    land spread across twenty-eight parcels owned by multiple
    different owners.
    To acquire property for the haul road, the 1991 taking took
    in fee simple approximately 400,000 square feet of land occupied
    by Conrail, which is not at issue in this appeal.   Because this
    action displaced Conrail's rail operations, the order also
    established easements on several neighboring parcels, including
    over 12,510 square feet of parcel 60-E-RR-1, so that Conrail
    could relocate its railroad operations there.   Specifically, the
    order provides:
    "In connection with the laying out of the State highway
    hereinbefore described, it is necessary to relocate
    portions of railroad rights of way and land is hereby
    acquired for said relocation as follows:
    "Easements are hereby taken in parcels 60-E-RR-1, 60-E-RR-
    5, and 60-E-RR-6, shown on the plan hereinafter referred
    to, for the relocation of facilities of the Consolidated
    Rail Corporation, including all trees and structures
    located thereon . . . .
    "Said easements (i) shall be used for railroad purposes
    only, (ii) shall not be used for the storage of any
    hazardous materials, hazardous wastes or hazardous
    substances other than in connection with the extension of
    Interstate Route 90 or the reconstruction of Interstate
    Route 93, and (iii) shall be subject to the rights of the
    owner of the underlying fee as hereinafter provided. . . .
    "Said railroad easements are acquired in limited vertical
    dimension only, said area being limited to a height of
    [twenty feet, six inches] above the top of the rails to be
    placed thereon. Included in the easements, however, is the
    6
    unlimited right to utilize the air rights above [twenty
    feet, six inches] for twelve (12) years following the date
    of recording of this taking. Thereafter, the use of said
    easements shall be subject to the rights of the owner of
    the air rights so reserved to use the area subject to the
    easements as reasonably may be required, subject to the
    approval of the party or parties having the benefit of the
    easements, for access to and to support the uses of the air
    rights."
    This order by its terms defined the 1991 easement, and, pursuant
    to it, Conrail subsequently relocated its main line to a single
    track that crosses land, now part of Smiley's property, that is
    burdened by the 1991 easement.
    c.    2018 taking.   Through a series of transactions, MassDOT
    ultimately acquired the 1991 easement.3    MassDOT subsequently
    sponsored the MBTA's Red Line test track project and authorized
    the MBTA to use MassDOT's land and rights in land for the
    project.   MassDOT and the MBTA also publicly declared that the
    entirety of the burdened land on Smiley's property was subject
    to the MBTA's exclusive use for any railroad purpose, including
    the Red Line test track project.
    After Smiley filed a complaint in the Land Court
    challenging MassDOT's authority to use the burdened land for the
    3 In 1997, the Commonwealth conveyed the 1991 easement to
    Conrail. On June 1, 1999, Conrail sold its Boston rail assets
    to New York Central Lines LLC, which subsequently merged into
    CSX Transportation, Inc. (CSX). Through a release deed dated
    June 11, 2010, CSX conveyed to MassDOT its right, title, and
    interest in the 1991 easement, subject to a retained easement
    for CSX's continued freight service.
    7
    Red Line test track project, MassDOT recorded the 2018 taking.
    That order purported to "confirm and, to the extent necessary to
    establish such rights, acquire[] an easement for railroad
    purposes as . . . set forth in the 1991 [t]aking and/or in this
    instrument," including testing and storage of rapid transit rail
    vehicles and reasonably related uses such as access, parking,
    and utility needs.    "For the further avoidance of doubt," the
    order explicitly declared that these uses included the Red Line
    test track project.
    d.   Prior proceedings.   Following dismissal of its initial
    suit without prejudice,4 in 2020, Smiley filed a new complaint
    against MassDOT in the Superior Court, seeking declaratory and
    equitable relief pursuant to G. L. c. 231A, § 1, with respect to
    the parties' respective rights under the 1991 easement as of
    January 11, 2018 (the day before the 2018 taking), and damages
    pursuant to G. L. c. 79, for the taking by MassDOT on January
    12, 2018.
    4 A Land Court judge dismissed Smiley's quiet title claims,
    but not the declaratory judgment claims, which, by agreement of
    the parties, were transferred to the Superior Court. A Superior
    Court judge dismissed those claims without prejudice, ruling
    that the remaining declaratory judgment claims had to be
    combined in a single action with a claim for land damages.
    Smiley then filed his current complaint in the Superior Court in
    January 2020; the resulting judgment is what is now before us on
    appeal.
    8
    Following a nonevidentiary hearing on the parties' cross
    motions for partial summary judgment, a Superior Court judge
    denied Smiley's motion, allowed MassDOT's cross motion, and
    dismissed Smiley's claim for compensation under G. L. c. 79.
    The judge agreed with MassDOT that the 1991 "easement, by its
    terms, may be used for any 'railroad purposes,' which includes
    the construction of a test track and building to test newly-
    purchased subway cars."      Smiley filed an appeal with the Appeals
    Court, and we transferred the case to this court on our own
    motion.
    2.    Discussion.   a.    Standard of review.   "We review a
    decision on a motion for summary judgment de novo and, thus,
    accord no deference to the decision of the motion judge"
    (quotation omitted).    Williams, 490 Mass. at 689-690, quoting
    Tracer Lane II Realty, LLC v. Waltham, 
    489 Mass. 775
    , 778
    (2022).   "The allowance of a motion for summary judgment 'is
    appropriate where there are no genuine issues of material fact
    in dispute and the moving party is entitled to judgment as a
    matter of law.'"   Williams, supra at 689, quoting Barron
    Chiropractic & Rehabilitation, P.C. v. Norfolk & Dedham Group,
    
    469 Mass. 800
    , 804 (2014).      Where both parties have moved for
    summary judgment, "the evidence is viewed in the light most
    favorable to the party against whom judgment" has been entered.
    9
    Green Mountains Ins. Co. v. Wakelin, 
    484 Mass. 222
    , 226 (2020),
    quoting Boazova v. Safety Ins. Co., 
    462 Mass. 346
    , 350 (2012).
    b.    Principles governing easements taken by eminent domain.
    "The meaning and scope of an instrument of taking, so far as it
    affects private rights in property, is a question of law."
    General Hosp. Corp., 
    423 Mass. at 764
    , citing Flagg v. Concord,
    
    222 Mass. 569
    , 572 (1916).
    We begin by reviewing the principles governing our general
    construction of easements.    "An affirmative easement 'creates a
    nonpossessory right to enter and use land in the possession of
    another and obligates the possessor not to interfere with the
    uses authorized by the easement.'"   Patterson v. Paul, 
    448 Mass. 658
    , 663 (2007), quoting Restatement (Third) of Property:
    Servitudes § 1.2(1) (2000).   "Restrictions on land 'are
    disfavored,' . . . and doubts concerning the rights of use of an
    easement 'are to be resolved in favor of freedom of land from
    servitude'" (citation omitted).   Martin v. Simmons Props., LLC,
    
    467 Mass. 1
    , 9 (2014).    "[T]he servient owner retains the use of
    his [or her] land for all purposes except such as are
    inconsistent with the right granted to the dominant owner" or
    acquired by that owner.   Merry v. Priest, 
    276 Mass. 592
    , 600
    (1931).
    The motion judge concluded that "[t]hese principles . . .
    do not assist Smiley," and Smiley's reliance on them was
    10
    misplaced, because they derive from cases that concern
    "transfers or prescriptive rights involving private parties"
    (emphasis added), Mugar v. Massachusetts Bay Transp. Auth., 
    28 Mass. App. Ct. 443
    , 445 (1990).   The conclusion that easements
    taken by eminent domain are not to be construed in favor of
    freedom of the land from servitude was error.
    As MassDOT points out, an easement taken by eminent domain
    must be construed in light of the language of the order of
    taking and the "circumstances surrounding the taking."    General
    Hosp. Corp., 
    423 Mass. at 764
    .    This approach differs in one
    respect from negotiated easements, as the intents of the owner
    and the government entity taking the easement are not relevant.
    See Mugar, 28 Mass. App. Ct. at 445 (intent of parties is
    irrelevant in construing easement taken by eminent domain
    because "[t]he taking of private property for a public purpose
    may be accomplished without the consent of the owner," and "the
    intent of the governmental body is largely beyond the scope of
    judicial scrutiny").   Thus, "principles of interpretation
    designed to give effect to the express or implied intent of
    parties contracting for or acquiring an interest in land . . .
    are, in general, inapplicable to eminent domain proceedings."
    Taylor v. Martha's Vineyard Land Bank Comm'n, 
    475 Mass. 682
    , 690
    n.17 (2016), quoting Bateman v. Board of Appeals of Georgetown,
    
    56 Mass. App. Ct. 236
    , 239 (2002).
    11
    But that does not mean that an easement taken by eminent
    domain is insulated from application of the ordinary rules of
    construction otherwise applicable to the interpretation of
    easements.   Apart from consideration of the parties' intent,
    which is inapplicable to takings by eminent domain, we
    consistently have applied the same rules of construction to
    easements taken by eminent domain as are applicable to privately
    granted easements.   Most significantly with respect to the
    issues here, whether an easement has been established by eminent
    domain or granted privately, "as a general rule, doubts as to
    the extent of a restriction in an easement 'should be resolved
    in favor of freedom of land from servitude.'"   General Hosp.
    Corp., 
    423 Mass. at 765
    , quoting Hemenway v. Bartevian, 
    321 Mass. 226
    , 229 (1947).   As with an easement that was privately
    granted,
    "[t]he scope of the condemnor's use of the easement will be
    limited to the extent reasonably necessary for the purpose
    served by the taking, so that the landowner's right to use
    the easement area is as great as possible while remaining
    reasonably consistent with the purpose of the taking. . . .
    If the condemnor takes an easement, the owner retains title
    to the land in fee and has the right to make any use of it
    that does not interfere with the public use."
    General Hosp. Corp., 
    supra at 764-765
    .   See Agostini v. North
    Adams Gaslight Co., 
    265 Mass. 70
    , 73 (1928) ("In a taking by
    eminent domain only such rights are acquired as are reasonably
    necessary to accomplish the purpose for which the taking is
    12
    made, unless the Legislature authorizes the acquiring of greater
    rights").
    With these principles in mind, we turn to consider the
    easements at issue in this case.
    c.   Scope of 1991 easement.   In determining the scope of
    the 1991 easement, we begin with the language of the 1991
    taking, which expresses the purpose for which the easement was
    taken and the circumstances of the taking.   The 1991 order
    clearly states that the purpose was to facilitate "the laying
    out of the State highway" for the Central Artery/Tunnel Project
    by "relocat[ing] portions of railroad rights of way," and, more
    specifically, "relocat[ing] . . . the facilities of [Conrail]."
    Accordingly, by its plain language, the scope of the easement is
    limited to the extent reasonably necessary to relocate Conrail's
    facilities.   See General Hosp. Corp., 
    423 Mass. at 764
    (questions about extent of eminent domain takings "should be
    resolved in favor of freedom of the land from the servitude").
    MassDOT correctly points out that the 1991 license
    agreement between the Commonwealth and Conrail permitted the
    1991 easement to be used by Conrail for ancillary activities
    that constituted "railroad purposes":
    "(i) for the construction and maintenance of the temporary
    rail yard; (ii) for materials handling and processing; and
    (iii) for use by Conrail, its authorized customers, agents
    and assigns for railroad purposes (freight or passenger),
    including the loading and unloading of rail cars or
    13
    containers, the classifying and assembling of trains, the
    temporary storage of operating rolling stock or for such
    other railroad purposes related to the transportation of
    freight and commodities by rail."
    But this license could not unilaterally expand the scope of the
    permissible use of the burdened land beyond what was stated in
    the 1991 taking.    Moreover, consistent with the purpose stated
    in the 1991 taking, the license agreement similarly recites that
    the Commonwealth is entering into the license agreement "to
    partially replace and restore the [c]urrent [Conrail] Rail
    Facilities and Conrail Land affected or eliminated by the Haul
    Road."   Thus, the Commonwealth's licensing of these activities
    was still governed by the over-all purpose set out in the 1991
    taking –- enabling Conrail to relocate the facilities being
    displaced by the haul road.
    It is also important to recognize that the 1991 easement
    for the relocation of Conrail's facilities was limited in space
    and time by the air rights reserved to the fee holder.    As
    defined in the 1991 taking, the easement included a vertical
    dimension of twenty feet and six inches "above the top of the
    rails to be placed" on the property, "subject to the rights of
    the owner of the air rights" above that height after a certain
    period of time.    For the first twelve years after the recording
    of the taking, Conrail, as the beneficiary of the easement, also
    enjoyed "the unlimited right to utilize the air rights above"
    14
    twenty feet and six inches.   "Thereafter, the use of said
    easements shall be subject to the rights of the owner of the air
    rights so reserved . . . for access to and to support the uses
    of the air rights."    Notably, the twelve-year period coincided
    with the time frame in which Conrail was to complete the
    relocation of its track and other facilities, and for the haul
    road to be constructed.   Otherwise put, the fee holder had to
    wait twelve years before developing its air rights, so as to
    allow Conrail time to relocate its operations, in accordance
    with the purpose of the taking.   Once Conrail accomplished that
    purpose by relocating a single track to the property, the scope
    of the easement established thereunder was fixed and limited to
    the right of way occupied by Conrail's track and the vertical
    dimension above it.5
    5 As we discuss further infra, the operation of the air
    rights provision in the 1991 easement was analogous to the well-
    established doctrine of practical location.
    "Where a right of way, or other easement, is granted by
    deed without fixed and defined limits, the practical
    location and use of such way or easement by the grantee
    under [the] deed, acquiesced in by the grantor at the time
    of the grant and for a long time subsequent thereto,
    operate as an assignment of the right, and are deemed to be
    that which was intended to be conveyed by the deed, and are
    the same, in legal effect, as if it had been fully
    described by the terms of the grant."
    Bannon v. Angier, 
    2 Allen 128
    , 129 (1861). See Naumkeag Steam
    Cotton Co. v. American Glue Co., 
    244 Mass. 506
    , 508 (1923)
    ("When the exact location of the easement is not precisely
    defined but has been exercised in a certain place, the grantee
    15
    Our interpretation of the extent of the 1991 easement is
    supported by one of our rulings in General Hosp. Corp.    In that
    case, Massachusetts General Hospital had acquired property that
    was subject to an easement taken by DPW for the purpose of
    constructing an elevated highway ramp.    General Hosp. Corp., 
    423 Mass. at 759-760
    .    The hospital and the MBTA then disputed the
    scope of this easement in the hospital's suit seeking damages
    for the MBTA's subsequent eminent domain takings of hospital
    property.   
    Id.
       Specifically, the MBTA contended that the
    hospital had no right to access its property across location
    lines shown on the highway ramp layout.    
    Id. at 763-764
    .
    We concluded, however, that, as the fee owner, the hospital
    had the right to access its property across these location
    lines, given that DPW had only taken an easement on the
    property, not a fee; the easement had been taken for "highway
    purposes"; and "[t]he height of the ramp where it crosse[d] [the
    has not the right afterwards to change the location to some
    other part of the land"); Chandler v. Jamaica Pond Aqueduct
    Corp., 
    125 Mass. 544
    , 550 (1878) (easement to lay pipes and keep
    and support them forever did not include right to change
    location of pipes once they had been laid). See also
    Restatement (Third) of Property: Servitudes § 4.8 comment c
    ("When improvements are constructed or installed on the servient
    estate for the enjoyment of a servitude without objection from
    the servient owner, the parties have given a practical
    construction to the instrument or agreement that created the
    servitude. Even if the instrument specifies a different
    location, the location is fixed by the placement of the
    improvements unless the language or circumstances lead to the
    conclusion that the initial location is temporary").
    16
    property] was adequate to permit the owner of the underlying fee
    to use the area under the ramp without interfering with the
    limited access highway."   Id. at 764-765.   Once DPW had
    constructed the highway ramp, the hospital was free to access
    and use the remaining land for parking, as long as the parking
    did not interfere with the highway.   See id. at 765-766.
    Similarly, here, under the 1991 taking, the fee holder of what
    is now Smiley's land was entitled to access to the burdened
    land, so long as that access did not interfere with the
    operations of the railroad track built by Conrail.
    d.   Scope of 2018 taking.   The 2018 taking provides that
    the easement for "railroad purposes" "permits [MassDOT] and its
    lawful successors and assigns to use the Remainder Railroad
    Easement Area for all lawful railroad purposes within the
    Commonwealth of Massachusetts."   The 2018 taking further
    specifies that such uses shall include "(a) the use of the
    Remainder Railroad Easement Area[6] by railroads powered by any
    source, for purposes including, but not limited to, the
    deployment, testing, calibration, and storage of rapid transit
    rail vehicles; and (b) uses reasonably related to such railroad
    6 The 2018 taking defines the "Remainder Railroad Easement
    Area" as "an easement for railroad purposes as described and
    more particularly set forth in the 1991 [t]aking and/or in this
    instrument over the parcel of land comprised of portions of the
    Easement Parcel as more particularly shown on the plan of land
    hereinafter described."
    17
    purposes such as access, parking and utility needs in connection
    therewith."
    We conclude that the scope of the 2018 easement exceeds the
    scope of the 1991 taking and that the motion judge erred in
    determining otherwise.   The judge misconstrued the extent of the
    1991 easement in large part because, in his view, certain
    ordinary rules of construction of easements were inapplicable to
    an easement taken by eminent domain.   As stated, however, other
    than the exclusion of any consideration of the parties' intent,
    we consistently have applied the ordinary rules of
    interpretation of easements to easements taken by eminent
    domain, see General Hosp. Corp., 
    423 Mass. at 764-765
    , and
    MassDOT has not proffered any reason for us to revisit that
    view.
    Here, whereas the purpose of the 1991 taking was to
    relocate railroad rights of way and Conrail's facilities, the
    2018 taking provides, "[f]or the avoidance of doubt," that it
    encompasses the 1991 purpose, but that it also includes "all
    lawful railroad purposes within the Commonwealth."
    Specifically, the 2018 taking states that it encompasses,
    "without limitation," testing, calibration, and storage of any
    type of railroad vehicle, and the associated uses such as
    parking that are necessary to those primary uses.
    18
    The Red Line test track project, which falls within this
    language, is a new and different project from the original
    relocation of Conrail's railroad track and facilities.   It
    involves an additional 6,000 square foot building, a different
    type of railroad car, and a considerably larger portion of the
    burdened land than did the single track originally constructed
    by Conrail pursuant to the 1991 easement.   Indeed, the 2018
    taking permits the easement holder to use the "Remainder
    Railroad Easement Area" -- i.e., the entirety of the burdened
    land, not just the right of way taken up by the relocated
    Conrail track -– for "all lawful railroad purposes within the
    Commonwealth."   Thus, the easement holder now may engage in any
    "railroad purposes," anytime and anywhere on the burdened land.
    Consequently, the 2018 easement makes it virtually impossible
    for the fee holder to build anywhere else on the burdened land,
    because the owner of the fee can never know whether or when the
    easement holder might seek to exercise its rights on that part
    of the burdened land.
    MassDOT raises a number of arguments as to why the 1991
    easement is just as sweeping in extent as the 2018 easement.
    These arguments are unpersuasive.   If the purpose of the 1991
    easement was to relocate Conrail's right of way and facilities
    to support construction of the haul road, and if the location of
    the easement became fixed once Conrail completed that process,
    19
    then clearly the 1991 easement did not authorize the very
    different and larger Red Line test track project nearly thirty
    years later.     In particular, MassDOT contends that the provision
    in the 1991 taking that the easement "shall be used for railroad
    purposes only" broadly authorizes use of the 1991 easement for
    any railroad purpose in the future, including the Red Line test
    track project.     That provision, however, is plainly a
    restriction on the use of the 1991 easement; it prohibits
    Conrail or a successor from using the easement for something
    other than railroad purposes.     As such, it remains subordinate
    to the over-all governing purpose of the 1991 easement, namely,
    the relocation of Conrail's right of way and facilities to
    support construction of the haul road.      The provision does not
    supersede that overarching governing purpose so as to expand the
    scope of the easement to include any future railroad purpose.
    As discussed, an easement taken by eminent domain must be
    construed in light of the "circumstances surrounding the
    taking."   General Hosp. Corp., 
    423 Mass. at 764
    .     In that case,
    for example, DPW had granted the Massachusetts Transit Authority
    (MTA) (the predecessor of the MBTA) the right to maintain its
    existing transit lines running through a DPW highway layout.
    
    Id. at 761
    .    The right to maintain included the right to
    "construct, reconstruct, maintain, repair, and operate [the]
    structures."     
    Id.
       Because the MTA's only structures within the
    20
    layout at that time were elevated tracks, no reasonable
    interpretation of the language of the easement granted the MTA
    the right to build an underground parking garage.      Similarly,
    here, the phrase "for railroad purposes only" in the 1991 taking
    should not be viewed out of context as authorizing the Red Line
    test track project nearly thirty years later, when clearly the
    purpose of the 1991 taking was to facilitate the relocation of
    Conrail's facilities.
    e.   Use of like kind.     MassDOT further argues, relying on
    Leroy v. Worcester St. Ry., 
    287 Mass. 1
    , 10-15 (1934), that the
    use of the easement for a test track and a building to hold new
    subway cars was permissible under the 1991 taking because the
    new use did not differ in kind from the original railroad use
    set forth in the 1991 taking.     In Leroy, the court held that an
    easement that had been taken for operation of a steam railway
    properly could be used for a motor bus, applying the principle
    that an easement taken for one public purpose may be used for a
    "public use of a like kind."     Leroy, supra at 13.   In either
    event, the court reasoned, "the essential purpose was to . . .
    transport members of the public."     Id. at 12.
    The Red Line test track project, however, is not a public
    use of a like kind.     The 1991 easement provided Conrail the
    right to relocate its operations, which proved to be a single
    track.   In contrast, the Red Line test track project involves
    21
    not only a test track, but also a large new building, parking,
    and another track.
    f.   Doctrine of practical location.    MassDOT also contends
    that because the 1991 easement covered the entirety of the
    12,510 square foot area set forth in the 1991 taking, the use of
    the entire burdened area for the Red Line test track was
    permissible.     We disagree.
    The 1991 taking states at the outset of the relevant
    passage that "[e]asements are hereby taken in [three] parcels[,
    including] 60-E-RR-1, . . . for the relocation of the facilities
    of [Conrail]."    Contrary to MassDOT's contention, this language
    does not "clearly and unambiguously" establish that those
    easements were intended to cover the entirety of each parcel.
    Rather, the language merely refers to an easement in some
    portion of each enumerated parcel.
    Under the 1991 easement, Conrail was free to relocate its
    operations wherever it chose within the scope of the easement on
    each parcel.    Once it did so, however, the location of the
    easement became fixed, see Leroy, 
    287 Mass. at 14
    ; Naumkeag
    Steam Cotton Co. v. American Glue Co., 
    244 Mass. 506
    , 508
    (1923), and the fee owner was free to develop the remainder of
    the parcel and the air rights, see General Hosp. Corp., 
    423 Mass. at 764
    .    MassDOT's contention that possession of the
    easement continued to give the easement holder complete control
    22
    to construct additional facilities anywhere on the burdened land
    is inconsistent with the fundamental principles limiting the
    dominant estate to the extent reasonably necessary for the
    purpose of the taking, and protecting the right of the fee
    holder to use the easement area to as great an extent as
    possible, see 
    id.,
     as well as with the doctrine of practical
    location, see Naumkeag Steam Cotton Co., supra; Bannon v.
    Angier, 
    2 Allen 128
    , 129 (1861).
    For this reason, we reject, as inapplicable, MassDOT's
    argument that it would have been illegal under Federal law for
    Conrail to "abandon" its rights over the rest of the burdened
    land.    Conrail never possessed a right to occupy the entire
    parcel of burdened land in perpetuity.    Conrail only possessed a
    right to place its tracks and facilities in the place of its
    choosing on the burdened land.7
    We also conclude that the Appeals Court's decision in
    Mugar, which MassDOT cites and upon which the motion judge
    substantially relied, is distinguishable from the present case.
    Mugar involved an action for compensation where the MBTA had
    taken an easement for an "undefined right of access" from
    7 MassDOT also cites Mahan v. Rockport, 
    287 Mass. 34
    , 37
    (1934), for the proposition that rights are not lost by using
    less than the entire area taken, but that case involved a public
    way, which "once duly laid out continues to be such until
    legally discontinued," and "may be discontinued by vote of the
    town and not otherwise."
    23
    surrounding city streets to a parcel containing a subway vent
    shaft near the center of the plaintiffs' parking lot.       Mugar, 28
    Mass. App. Ct. at 443-444.       Because this access easement gave
    the MBTA unlimited rights of passage from the city streets, it
    necessarily prevented the plaintiffs from building anywhere in
    the parking lot.    See id. at 444.    By contrast, here the 1991
    taking included language that limited the scope of the easement
    to the relocation of Conrail's facilities and explicitly allowed
    the fee holder to develop the air rights on the burdened land
    after a twelve-year period.
    We are mindful that, in exercising the power of eminent
    domain in 1991, DPW had the power to choose how it wished to
    articulate the scope of the easement.      If it had intended to
    establish a perpetual right to occupy all of the burdened
    property, then it could have done so unequivocally, but it did
    not.    When the scope and extent of a taking is unclear, we must
    adopt the narrower interpretation of its language, in favor of
    freedom of the land from servitude, as long as it is otherwise
    consistent with applicable legal principles.       See General Hosp.
    Corp., 
    423 Mass. at 764
    .
    g.   Just compensation.   Because the scope of the 2018
    easement exceeded the scope of the 1991 easement, it represented
    an additional taking.     Accordingly, Smiley's claim for damages
    24
    under G. L. c. 79 should not have been dismissed, and, on
    remand, Smiley is entitled to pursue its claim for damages.
    3.   Conclusion.   The summary judgment is reversed.    The
    matter is remanded to the Superior Court for entry of a
    declaratory judgment in favor of Smiley that the 2018 easement
    exceeded the scope of the 1991 easement and, in particular, did
    not encompass a use such as the Red Line test track project, and
    for further proceedings on the compensation Smiley is due
    pursuant to G. L. c. 79, § 14, as a result of the 2018 taking.
    So ordered.