Aggregate Industries - Northeast Region, Inc. v. Hugo Key and Sons, Inc. , 90 Mass. App. Ct. 146 ( 2016 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    15-P-916                                              Appeals Court
    AGGREGATE INDUSTRIES - NORTHEAST REGION, INC.      vs.   HUGO KEY AND
    SONS, INC., & another.1
    No. 15-P-916.
    Essex.       April 13, 2016. - September 1, 2016.
    Present:   Wolohojian, Kinder, & Neyman, JJ.
    Contract, Construction contract, Offer and acceptance,
    Performance and breach, Public works. Damages, Quantum
    meruit, Public Works Contract. Bond, Public works. Public
    Works, Payment bond. Consumer Protection Act,
    Businessman's claim, Unfair or deceptive act. Practice,
    Civil, Attorney's fees.
    Civil action commenced in the Superior Court Department on
    October 31, 2011.
    The case was heard by Timothy Q. Feeley, J., and a motion
    for a new trial was considered by him.
    Cole M. Young for the plaintiffs.
    William T. Harrington for the defendants.
    WOLOHOJIAN, J.      The plaintiff subcontractor, Aggregate
    Industries - Northeast Region, Inc. (Aggregate), contracted with
    1
    Argonaut Insurance Company, which is not participating in
    this appeal.
    2
    the defendant general contractor, Hugo Key and Sons, Inc. (Hugo
    Key), for the supply of material and labor for a public works
    construction project in Salem.   A dispute arose about payment,
    and Aggregate filed a complaint in the Superior Court asserting
    contract and quantum meruit claims under G. L. c. 149, § 29, the
    Commonwealth's bond statute for publicly funded construction
    projects, and violations of G. L. c. 93A (c. 93A).   Following a
    jury-waived trial, judgment entered in favor of Hugo Key on all
    counts of the complaint, with the exception of a discreet
    quantum meruit award, not under the bond statute, in favor of
    Aggregate.   Judgment also entered in favor of Hugo Key on a
    c. 93A counterclaim.   Aggregate appeals, claiming the judge
    erred in his application of contract principles and in his
    analysis of the statutes at issue.   We affirm in part, and
    reverse in part.
    Background.    We summarize the facts as found by the judge,
    supplemented by undisputed information from the record.     In
    2011, Hugo Key and Salem entered into a contract for the
    construction of the Salem Wharf project.   The contract was
    secured by a payment bond in the amount of $1,336,925, furnished
    by the defendant Argonaut Insurance Company (Argonaut).     Hugo
    Key, in turn, solicited bids from subcontractors for the portion
    of the project that required bituminous concrete pavement work.
    On or about January 14, 2011, Aggregate submitted an estimate
    3
    for the pavement work, which included two provisions relevant to
    the present dispute.   The first stated:    "Grader Service:
    $400.00/HR."   The second was an escalation clause, which
    provided for additional per ton charges for bituminous concrete
    if the base price of liquid asphalt2 increased.3    Aggregate
    submitted two revised estimates in May, 2011.     Hugo Key did not
    sign or accept any of the estimates, and its representative,
    Sandy Key, informed the Aggregate salesman, Vincent Venturo,
    "that Hugo Key would not deal with Aggregate if the agreement
    included an escalation clause for liquid asphalt."
    Having reached no agreement, Hugo Key sent Aggregate a
    purchase order dated May 17, 2011, that included the revised
    estimate, but was silent as to grader service and the escalation
    clause.   Venturo signed the purchase order and returned it by
    fax with a handwritten notation attempting to incorporate the
    escalation clause into the agreement.4     In response, Sandy Key
    2
    Bituminous concrete paving material is a mixture of
    asphalt, crushed rock aggregate, and mineral filler.
    3
    The estimate provided: "Prices quoted are based on the
    current FOB refinery prices on liquid asphalt. Such quoted
    prices are not guaranteed by the major oil companies and are
    subject to sudden adjustment during the term of the agreement.
    The base price of liquid asphalt for this quote is [$]460.00.
    Any change in the price of liquid asphalt will require an extra
    charge of $0.06 per ton for every $1.00 per ton increase in the
    price of liquid asphalt."
    4
    The notation stated:   "As Per Estimate #14536-2011 Terms &
    Conditions."
    4
    immediately rejected the term; the trial judge found that "Sandy
    Key told Venturo, and Venturo knew, that if Aggregate insisted
    on the escalation clause, Hugo Key would not give Aggregate the
    pavement work."   Sandy Key then prepared a new purchase order
    dated May 23, 2011, removing Venturo's handwritten addition and
    adding "Purchase order based on liquid asphalt price of $460.00
    per ton" for the express purpose of excluding the escalation
    clause.   With the approval of his manager, Venturo signed and
    accepted the purchase order and work commenced.     During the
    paving project, Hugo Key determined that it required grading
    services from Aggregate, which Aggregate performed, and then
    billed at the price, quoted on the original estimate, of $400
    per hour.
    After completion of the project, by invoice dated July 6,
    2011, Aggregate billed Hugo Key $89,989.90.     Of that sum,
    $11,400 was for "grader rental" and $10,064.50 was for "liquid
    asphalt escalation."    Having received no payment, on October 31,
    2011, Aggregate commenced the present action.     The complaint
    alleges claims for breach of contract and quantum meruit, with
    payment under the bond statute, G. L. c. 149, § 29, and
    violations of c. 93A for the wrongful withholding of the funds
    due.   Shortly after the complaint was filed, by check dated
    November 8, 2011, Hugo Key paid Aggregate $68,525.40, the sum
    not in dispute, and indicated a willingness to pay a reasonable
    5
    fee for the grader rental.5      Aggregate refused the offer of
    payment, and Hugo Key filed a counterclaim alleging violations
    of c. 93A.
    Following a one-day bench trial, the judge issued his
    written findings of fact and conclusions of law.      He concluded
    that the contract formed between Aggregate and Hugo Key did not
    incorporate the escalation clause or the grader rental fee, but
    that Aggregate was entitled to the fair and reasonable sum of
    $7,125 on its quantum meruit claim for grader rental.
    Nevertheless, the judge dismissed the portions of the complaint
    seeking recovery under G. L. c. 149, § 29, reasoning that
    "[f]airness would be the victim if this court permitted
    Aggregate to recover under the bond, with its right to
    attorneys' fees, on a quantum meruit claim that Hugo Key was
    ready, willing, and able to resolve at the fair and reasonable
    value of the services provided at or about the time this action
    was commenced."      As for the competing c. 93A claims, the judge
    found in favor of Hugo Key, on the ground that Aggregate
    commenced the present litigation as a form of extortion, by
    means of the attorney's fee provision of G. L. c. 149, § 29, to
    force Hugo Key to pay for the escalation clause that it knew was
    not a part of the contract.      Rather than awarding damages on the
    5
    Key testified that $220 per hour would be a reasonable
    fee.
    6
    c. 93A judgment, however, the judge withheld the prejudgment and
    postjudgment interest on Aggregate's $7,125 quantum meruit
    award.   Aggregate moved for a new trial, which the judge denied
    without a hearing.    On Hugo Key's motion for c. 93A attorney's
    fees and costs, the judge awarded a total of $67,319.
    Discussion.      We review the trial judge's findings of fact,
    including all reasonable inferences that are supported by the
    evidence, for clear error.      See Twin Fires Inv., LLC v. Morgan
    Stanley Dean Witter & Co., 
    445 Mass. 411
    , 420 (2005);
    Mass.R.Civ.P. 52(a), as amended, 
    423 Mass. 1402
    (1996).      The
    judge's conclusions of law are reviewed de novo.     Martin v.
    Simmons Properties, LLC, 
    467 Mass. 1
    , 8 (2014).
    1.    Breach of contract.    Based on the undisputed evidence
    of Sandy Key and Venturo's ongoing verbal and written
    negotiations, offers, and counter offers, the judge reasonably
    concluded that no binding contract was formed until Venturo
    accepted, on behalf of Aggregate, Sandy Key's final May 23,
    2011, purchase order.     Looking at the same evidence, the judge
    also reasonably concluded that the escalation and grader rental
    terms had been rejected and were not to be read into the final
    agreement.   In other words, the parties expressed no mutual
    intention to bind themselves until the acceptance of the terms
    7
    limited to the May 23, 2011, purchase order.6    See Situation
    Mgmt. Sys., Inc. v. Malouf, Inc., 
    430 Mass. 875
    , 878 (2000).       As
    Hugo Key paid the agreed upon amount due under the final terms
    of the agreement, no breach of contract occurred.     Count I of
    the complaint, alleging nonpayment under the invoice, was
    properly dismissed.
    2.   Application of G. L. c. 149, § 29.    Aggregate claims
    that once the judge determined that it was owed damages on its
    quantum meruit claim for the grader rental, the provisions of
    G. L. c. 149, § 29, including an award of attorney's fees, must
    apply to the claim, as all of the requirements of the statute
    had been satisfied.   We agree.
    The bond statute, G. L. c. 149, § 29, which is an outgrowth
    of the mechanic's lien statutes, requires that general
    contractors obtain "security in favor of those furnishing labor
    and materials in the construction or repair of public structures
    and other public works, . . . as there can be no lien upon
    public buildings or other public works."   Massachusetts Gas &
    Elec. Light Supply Co. v. Rugo Constr. Co., 
    321 Mass. 20
    , 22
    (1947) (citation omitted).   Because the purpose of the statute
    6
    As the judge noted, the result is the same under the
    Uniform Commercial Code, as Hugo Key had expressly rejected the
    two estimates offered, and, thus, there was no "definite and
    seasonable expression of acceptance" of a contract including the
    disputed terms. G. L. c. 106, § 2-207, inserted by St. 1957,
    c. 765, § 1. See generally Commerce & Indus. Ins. Co. v. Bayer
    Corp., 
    433 Mass. 388
    , 392-393 (2001).
    8
    is remedial in nature, it is to be construed liberally in favor
    of providing such security to subcontractors and materialmen.
    City Rentals, LLC v. BBC Co., 
    79 Mass. App. Ct. 559
    , 564 (2011).
    In furtherance of that purpose, successful claimants under the
    statute are entitled to "reasonable legal fees based upon the
    time spent and the results accomplished."   G. L. c. 149, § 29,
    inserted by St. 1972, c. 774, § 5.   See City Rentals, LLC v. BBC
    Co., supra at 566, quoting from Manganaro Drywall, Inc. v. White
    Constr. Co., 
    372 Mass. 661
    , 664 (1977) ("The fee-shifting
    provision of § 29 'places the expense of litigation on a
    contractor and a surety who decline to pay a rightful claim
    [and] tends to achieve the legislative goal of expeditious
    payments to subcontractors'").
    As relevant here, the requirements to be met and the
    actions to be taken in commencing an action for payment under
    G. L. c. 149, § 29, are straightforward.    The statute provides,
    in pertinent part:
    "In order to obtain the benefit of such bond for any
    amount claimed due and unpaid at any time, any
    claimant having a contractual relationship with the
    contractor principal furnishing the bond, who has not
    been paid in full for any amount claimed due for the
    labor, materials, equipment, appliances or
    transportation included in the paragraph (1) coverage
    within sixty-five days after the due date for same,
    shall have the right to enforce any such claim (a) by
    filing a petition in equity within one year after the
    day on which such claimant last performed the labor or
    furnished the labor, materials, equipment, appliances
    or transportation included in the claim and (b) by
    9
    prosecuting the claim thereafter by trial in the
    superior court to final adjudication and execution for
    the sums justly due the claimant as provided in this
    section."
    G. L. c. 149, § 29, inserted by St. 1972, c. 774, § 5.      If
    successful, "[a] decree in favor of any claimant under this
    section shall include reasonable legal fees based upon the time
    spent and the results accomplished."   
    Ibid. Here, Aggregate plainly
    met the requirements of:    (1)
    filing a petition in equity in the Superior Court; (2) within
    one year of the completion of the work; (3) alleging nonpayment
    within sixty-five days of the invoice for labor and materials
    provided; and (4) prosecuting the claim "to final adjudication
    and execution for the sums justly due the claimant as provided
    in this section."   G. L. c. 149, § 29, inserted by St. 1972,
    c. 774, § 5.   It necessarily follows that, having achieved a
    decree in its favor on its quantum meruit claim, Aggregate is
    entitled to reasonable attorney's fees under the plain and
    compulsory ("shall") language of the statute.   The judge
    accordingly erred in ordering dismissal of the portion of
    Aggregate's complaint alleging recovery under G. L. c. 149,
    § 29, on its quantum meruit claim.7
    7
    The judge placed too much weight on the "petition in
    equity" language of the statute to support his rejection of the
    G. L. c. 149, § 29, claim on fairness grounds. The phrase
    appears to be merely a vestige of the procedural landscape in
    existence at the time the statute was enacted. The bond statute
    10
    3.   Chapter 93A counterclaim.   Aggregate claims that its
    actions in refusing to negotiate with Hugo Key on the grader
    rental fee and the escalation clause, and in later filing suit
    to recover the disputed amount, did not constitute unfair or
    deceptive acts or practices in the course of trade or commerce.
    Again, we agree.
    Chapter 93A, § 11, "bestows a right of action on '[a]ny
    person who engages in the conduct of any trade or commerce and
    who suffers any loss of money or property, real or personal,' as
    a result of the unfair or deceptive act or practice, or unfair
    method of competition, of another person who engaged in trade or
    was enacted in 1904, see St. 1904, c. 349, well before the
    adoption of the rules of civil procedure in Massachusetts in
    1973, which merged the procedure for bringing suits in equity
    and at law. See Nolan & Sartorio, Equitable Remedies § 4.15 (3d
    ed. 2007). Prior to their adoption, separate and distinct
    complaints at law and in equity were required depending on the
    relief sought. See Reporter's Notes to Mass.R.Civ.P. 2, 46
    Mass. Gen. Laws Ann. at 11 (West 2006). In sum, the phrase
    "petition in equity" made sense within the procedural landscape
    of the time, but, in the present day, is best understood simply
    to refer to the commencement of an action under G. L. c. 149,
    § 29.
    Our conclusion in this regard is consistent with the
    history of the same phrase in the mechanic's lien statute, G. L.
    c. 254, § 14, which predates the bond statute at issue here. In
    the mechanic's lien statute, the language was replaced with the
    phrase "civil action commenced" by legislation dated November
    30, 1973, entitled "An Act improving the procedure in civil
    trials and appeals." St. 1973, c. 1114, § 320. See NES Rentals
    v. Maine Drilling & Blasting, Inc., 
    465 Mass. 856
    , 863 (2013).
    "This act derived from 1973 House Doc. No. 7236, a bill intended
    'to conform the General Laws of Massachusetts to the
    Massachusetts rules of civil procedure and the Massachusetts
    rules of appellate procedure.'" 
    Ibid. 11 commerce." Auto
    Flat Car Crushers, Inc. v. Hanover Ins. Co.,
    
    469 Mass. 813
    , 822 (2014), quoting from G. L. c. 93A, § 11.
    Hugo Key's counterclaim alleges that Aggregate committed
    unfair and deceptive acts by demanding payment under the
    contract and filing suit and continuing to prosecute its claim
    over the disputed amount.   Ordinary contract disputes, or the
    failure to negotiate a settlement in lieu of ligation, however,
    typically fall outside of the reach of the statute.     See
    Duclersaint v. Federal Natl. Mort. Assn., 
    427 Mass. 809
    , 814
    (1998) ("[A] good faith dispute as to whether money is owed, or
    performance of some kind is due, is not the stuff of which a
    c. 93A claim is made"); Morrison v. Toys "R" Us, Inc., Mass.,
    
    441 Mass. 451
    , 457 (2004) (with the exception of insurance
    providers, c. 93A "has never been read so broadly as to
    establish an independent remedy for unfair or deceptive dealings
    in the context of litigation"); Kobayashi v. Orion Ventures,
    Inc., 
    42 Mass. App. Ct. 492
    , 505 (1997) (ordinary contract
    disputes, "without conduct that was unethical, immoral, [or]
    oppressive," are not actionable under c. 93A).     This is so
    because the unfair or deceptive conduct alleged must itself
    arise from trade or commerce, and not tangentially from
    litigation concerning that conduct.     See First Enterprises, Ltd.
    v. Cooper, 
    425 Mass. 344
    , 347 (1997).
    12
    Hugo Key's counterclaim falls squarely in the above
    category.    Even if Aggregate's claims were weak, it was free to
    file suit and litigate them.    To reach the opposite conclusion,
    rather than furthering the purpose of c. 93A by "improv[ing] the
    commercial relationship between consumers and business persons
    and [] encourag[ing] more equitable behavior in the
    marketplace[,] . . .    would expose ordinary defendants (even
    large corporations . . .) to the risk of liability for multiple
    damages and attorney's fees for choosing to go to court rather
    than settling a dispute, on the ground that its litigation
    tactics are perceived, by the opposing side, to be unfair."
    Morrison v. Toys "R" Us, Inc., Mass., supra at 457-458
    (citations omitted).    The counterclaim should have been
    dismissed.
    Conclusion.   The judgment, dated March 10, 2015, is
    affirmed as to counts I and III of Aggregate's complaint and as
    to count II insofar as the judgment awards damages in the amount
    of $7,125 on Aggregate's quantum meruit claim.    The judgment is
    reversed in all other respects.   The case is remanded to the
    Superior Court for entry of judgment in favor of Aggregate, and
    against Hugo Key and Argonaut,8 on Aggregate's G. L. c. 149,
    8
    Under the payment bond contract, Hugo Key and Argonaut are
    "jointly and severally" liable for any sums owed. See John W.
    Egan Co. v. Major Constr. Mgmt. Corp., 46 Mass. App. Ct 643,
    646-647 (1999).
    13
    § 29, claim related to the quantum meruit award, including
    prejudgment and postjudgment interest,9 and an award of
    reasonable attorney's fees and costs.   Judgment shall enter
    dismissing Hugo Key's c. 93A counterclaim, and the judgment,
    dated June 1, 2015, awarding attorney's fees and costs to Hugo
    Key on its c. 93A counterclaim is vacated.
    So ordered.
    9
    See G. L. c. 231, § 6C.
    

Document Info

Docket Number: AC 15-P-916

Citation Numbers: 90 Mass. App. Ct. 146

Judges: Wolohojian, Kinder, Neyman

Filed Date: 9/1/2016

Precedential Status: Precedential

Modified Date: 11/10/2024