R.M. Packer Co., Inc. v. Marmik, LLC , 88 Mass. App. Ct. 654 ( 2015 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    14-P-1638                                           Appeals Court
    R.M. PACKER CO., INC.   vs.   MARMIK, LLC & others.1
    No. 14-P-1638.
    Dukes.    September 2, 2015. - November 25, 2015.
    Present:   Meade, Wolohojian, & Milkey, JJ.
    Massachusetts Oil and Hazardous Material Release Prevention Act.
    Hazardous Materials. Damages, Hazardous waste
    contamination, Attorney's fees. Contribution. Practice,
    Civil, Attorney's fees, Costs, Findings by judge.
    Department of Environmental Protection.
    Civil action commenced in the Superior Court Department on
    May 8, 2009.
    The case was heard by Gary A. Nickerson, J., and a motion
    for attorney's fees and costs was heard by him.
    John D. Curran for the plaintiff.
    Marilyn H. Vukota for Vineyard Port Hole, Inc.
    1
    Wallace Realty Trust; TP Panancy LLC; Vineyard Markets,
    Inc.; and the Vineyard Port Hole, Inc. Vineyard Port Hole, Inc.
    is a closely held Massachusetts corporation, owned by Terrence
    P. McCarthy, doing business as Dockside Marina (Dockside).
    2
    WOLOHOJIAN, J.   At issue is whether R.M. Packer Co.
    (Packer) was properly found liable for attorney's fees and costs
    under G. L. c. 21E, § 4A(f), after it unsuccessfully sought
    contribution from the defendants for costs to clean up an oil
    spill.   In three circumstances, the statute requires that
    reasonable attorney's fees and costs be awarded against a
    plaintiff who has sued seeking contribution for environmental
    clean-up costs.   Those three circumstances are
    "[i]f the court finds that (1) the plaintiff did not
    participate in negotiations or dispute resolution in good
    faith; (2) the plaintiff had no reasonable basis for
    asserting that the defendant was liable, or (3) the
    plaintiff's position with respect to the amount of the
    defendant's liability pursuant to the provisions of this
    chapter was unreasonable."
    G. L. c. 21E, § 4A(f), inserted by St. 1992, c. 133, § 294.
    Here, after a bench trial, a judge found that Packer had no
    reasonable basis for asserting its claim against the defendant
    Dockside at the time it filed suit, and accordingly awarded fees
    and costs under § 4A(f)(2).   The judge reached this conclusion
    despite the fact that, before Packer filed its complaint, the
    Department of Environmental Protection (DEP) had issued a notice
    of responsibility to Dockside, stating that it had reason to
    believe that Dockside was a "[p]otentially [r]esponsible
    [p]erson."
    Packer argues that DEP's position vis à vis Dockside's
    potential responsibility provided a reasonable basis upon which
    3
    Packer could sue Dockside for contribution.   Hence, Packer
    argues, the judge erred in awarding fees and costs under
    § 4A(f)(2).   We do not need to reach this issue because, on the
    facts found by the judge (and not challenged on appeal), the
    award was independently proper under § 4A(f)(3).   We accordingly
    affirm the award on that basis.
    Background.2   Packer was in the business of selling and
    delivering petroleum-based products on Martha's Vineyard.3
    Before the events at issue in this case, Packer had owned a
    piece of commercial property located at 27 Lake Avenue in Oak
    Bluffs, where a gas station was located.   In 1998, Packer
    2
    The facts are drawn from the trial judge's clear and
    detailed written findings. Where, as here, a judge acts as the
    trier of fact, his or her factual findings must be accepted on
    appeal unless shown to be clearly erroneous. See Mass.R.Civ.P.
    52(a), as amended, 
    423 Mass. 1402
    (1996). Packer does not argue
    that any of the judge's subsidiary findings are clearly
    erroneous. Moreover, the findings are in essence unreviewable
    because the trial transcript was not included in the appellate
    record. Mass.R.A.P. 16(a)(4), as amended, 
    367 Mass. 921
    (1975),
    & 18(a), as amended, 
    425 Mass. 1602
    (1997). See Kunen v. First
    Agric. Natl. Bank of Berkshire County, 
    6 Mass. App. Ct. 684
    ,
    689-691 (1978); Cameron v. Carelli, 
    39 Mass. App. Ct. 81
    , 83-84
    (1995); Buddy's Inc. v. Saugus, 
    62 Mass. App. Ct. 256
    , 264
    (2004).
    3
    Ralph M. Packer, Jr. was the company's chief executive
    officer; Packer employees, Scott Bailey and Mark Leith, were
    deliverymen.
    4
    installed underground fuel4 storage tanks behind the station.
    Tank one was for diesel fuel; tank two was for gasoline.
    Two piers stretched into Oak Bluffs Harbor nearby.     On one
    of those piers, Dockside owned and operated pumps that dispensed
    fuel to motor boats.    Dockside's pumps were connected to tanks
    one and two, and Dockside purchased the fuel it needed for its
    operations from Packer, who delivered it to, and stored it in,
    those two tanks.
    In 2000, as part of a larger business deal, Packer sold the
    property, including the tanks, to Marmik, LLC (Marmik), an
    unrelated firm.    As a result, Marmik inherited Dockside as what
    the parties call a "pass-through" customer; after the
    transaction, Dockside continued to purchase fuel from Packer
    (paying Packer directly), and Packer continued to deliver it to
    tanks one and two.     However, those tanks were now owned and
    maintained by Marmik,5 and Dockside paid Marmik a per gallon
    handling charge for this arrangement.6
    4
    When we refer to "fuel" in this opinion, we do so
    colloquially where it makes no difference whether the substance
    referred to is diesel fuel or gasoline.
    5
    Dockside neither leased the tanks nor exercised (or
    assumed) exclusive or shared control of the tanks. Dockside was
    not responsible for maintenance or repairs to the tanks.
    Further, it had no duty to monitor the fitness of the tanks.
    6
    Dockside also entered into an indemnification agreement
    with Marmik, agreeing to indemnify Marmik from "acts or
    5
    Marmik adapted the property to meet its business needs.
    Among other changes, it added a nine-foot fence enclosing the
    area where the tanks were buried.   In this same area, Marmik had
    installed a concrete base with layers of sand on top, which was
    customized to serve as an outdoor seating area for a restaurant
    on an abutting parcel.   These changes to the site made it
    difficult for Packer's deliverymen to use the pole method to
    check the fuel levels before filling the tanks.   The pole method
    entails lowering a measuring pole through the direct fill cap of
    the tank to measure the level of the tank's contents.   The pole
    method is a customary and reliable method of measuring the level
    of a tank's contents and allows the deliveryman to determine how
    much fuel can be added to the tank without risking a spill.
    While Packer's deliverymen had on occasion used the pole
    method to measure the fuel levels, they usually relied instead
    on a remote electronic sensory system known as a veeder root
    system (VRS), which Packer had put in place when the tanks were
    added to the site.   With the aid of sensors inside each tank,
    the VRS measured and recorded each tank's fuel capacity on a
    running tape (akin to a sales register printout); thus, the VRS
    recorded the volume of fuel in a tank and its ullage, i.e., the
    number of gallons that could be added.   The VRS terminal was
    omissions" of Dockside and its agents.   This agreement, however,
    does not appear to be implicated here.
    6
    housed in a nearby convenience store and available when the
    store was open for business.
    On the evening of Saturday, July 7, 2007, a Dockside
    employee measured the fuel in the tanks using the VRS, which
    recorded fifty-four inches of diesel fuel in tank one and
    eighteen inches of gasoline in tank two.     In turn, according to
    the parties' well-established protocol, the Dockside employee
    reported the readings to Packer, stating (in inches) the height
    of fuel in each tank.     In addition to reporting the fuel levels,
    the Dockside employee ordered gasoline (for tank two) to be
    delivered as early as possible the following morning.     Dockside
    did not order any diesel (for tank one).     On Sunday, at about
    6:00 A.M., Skip Bailey, Packer's employee, accurately recorded
    Dockside's fuel levels (i.e., fifty-four inches of diesel and
    eighteen inches of gasoline) in a company ledger.
    For reasons set out in more detail in the margin,7 Packer
    was delayed in making the delivery and Dockside's owner,
    Terrence McCarthy, became correspondingly agitated that Dockside
    would run out of fuel.8    Ultimately, Leith made the delivery.
    7
    Bailey intended to deliver gasoline to Dockside after a
    delivery via ferry to another customer located on Chappaquiddick
    Island. That delivery was dependent on the tides, and Bailey
    was delayed on Chappaquiddick Island, due to unfavorable
    conditions that prevented the ferry from returning to Edgartown.
    8
    McCarthy left two messages with an outside answering
    service for Packer, indicating that without a prompt delivery
    7
    However, rather than delivering gasoline, he delivered diesel
    fuel.    Moreover, he did not check tank one's capacity, either by
    the pole method or by using the VRS terminal before filling the
    tank.    Nor did he take any other reasonable step to ascertain
    the level of diesel fuel in tank one.9   Instead, Leith attached
    the truck's hose to the remote (indirect) fill spout for tank
    one and proceeded to fill it.    At the moment he began offloading
    diesel fuel, tank one had room for about 273 gallons.    By the
    time Leith stopped force pumping diesel fuel, he had delivered
    1,060 gallons of diesel, the tank had ruptured, the sensor rod
    within the tank had shot through the top of the tank "like a
    rocket," and diesel fuel was gushing from the tank "like a small
    geyser."   The best estimate is that 787 gallons of diesel fuel
    spilled as a result.
    In the aftermath of the spill, the DEP conducted an
    investigation that led it to send a notice to Dockside stating
    that it had reason to believe that Dockside was "a Potentially
    Dockside would run out of fuel. Driving to the site, a Packer
    employee, Mark Leith, telephoned McCarthy, who voiced his urgent
    need for fuel. McCarthy did not refer to "diesel" fuel, either
    in his messages left with the answering service or in
    conversation with Leith. Nor did Leith inform McCarthy that
    diesel, not gasoline, would be delivered that day.
    9
    Leith had delivered 2,000 gallons of diesel fuel the
    previous day which, the trial judge found, should have raised
    doubts in Leith's mind that additional diesel fuel was needed.
    He could have easily resolved any such doubt by walking over to
    the Dockside pumps.
    8
    Responsible Party (a 'PRP') with liability under . . . G. L.
    c. 21E, § 5, for response costs."   A like notice was sent by DEP
    to Packer, indicating that Packer was also a PRP liable under
    the Act for the spill.
    Packer hired an environmental firm to remediate the spill
    and, all told, the clean-up costs came to $300,000, which were
    assumed by Packer's insurance company.   Packer then, pursuant to
    G. L. c. 21E, § 4A, sent demand letters to both Dockside and
    Marmik, demanding that they each contribute eighty percent of
    the remediation costs (which, had the defendants acceded to the
    demand, would have resulted in a significant windfall).
    Packer's demand at no point changed despite the fact that, as
    the trial judge found, "Packer well knew that Dockside was
    blameless in this instance."    The parties did not resolve their
    differences and Packer brought this suit against Dockside, among
    others,10 asserting liability based on common-law (negligence)
    principles as well as certain provisions of G. L. c. 93A and
    G. L. c. 21E, the Massachusetts Oil and Hazardous Material
    Release Prevention Act (Act).   Dockside asserted a counterclaim
    for an award of its attorney's fees and costs under G. L.
    c. 21E, § 4A(f)(1)-(3).
    10
    See note 
    1, supra
    ; the other named defendants are not
    implicated in this appeal.
    9
    After an eight day bench trial, the judge issued findings
    of fact and found in favor of Dockside on all of Packer's
    claims.   On Dockside's counterclaim, the judge awarded Dockside
    $66,409.50 in attorney's fees and costs, relying on G. L. c. 21,
    § 4A(f)(2),11 and concluded:   "[w]hen Packer filed its complaint,
    application of the facts to the existing law made it reasonably
    clear that Dockside was not liable under G. L. c. 21E."     The
    only issue before us is the award of fees and costs.12
    Discussion.   General Laws c. 21E is a comprehensive statute
    designed to promote the prompt and efficient cleanup of sites
    contaminated by the release of hazardous materials and to
    provide a legal framework by which response costs are borne by,
    and appropriately allocated among, those responsible.     See
    Commonwealth v. Boston Edison Co., 
    444 Mass. 324
    , 335 (2005);
    Bank v. Thermo Elemental Inc., 
    451 Mass. 638
    , 653 (2008).       Under
    the Act, a person, as defined by § 2, is authorized to undertake
    11
    Section 4A(f)(2) authorizes an award of litigation costs
    and reasonable attorney's fees to a defendant if a court
    concludes that "the plaintiff had no reasonable basis for
    asserting that defendant was liable." And, in connection with
    his ruling, the judge cited Scott v. NG US 1, Inc., 
    450 Mass. 760
    , 773 (2008) ("the question is whether, when the complaint
    was filed, application of the facts to existing law made it
    reasonably clear that the defendant[] [was] not liable under
    G. L. c. 21E").
    12
    Although Packer's notice of appeal states that Packer
    appeals from the judgment, its only argument on appeal is in
    regards to the award of attorney's fees and costs to Dockside
    pursuant to G. L. c. 21E, § 4A(f)(2).
    10
    response actions13 to remediate a contaminated site and is
    entitled to reimbursement "from any other person liable" for the
    release of hazardous materials.    G. L. c. 21E, § 4, third par.,
    as appearing in St. 1992, c. 133, § 293.     If two or more persons
    are liable, then each is liable to the others for their
    equitable share.14   
    Ibid. See Martignetti v.
    Haigh-Farr, Inc.,
    
    425 Mass. 294
    , 308 (1997); Commonwealth v. Boston Edison Co.,
    supra at 338.
    Section 4A of the Act sets out a detailed prelitigation
    process that a person must follow if that person wishes to
    obtain contribution from others who may also have liability for
    environmental clean-up costs.     To begin with, the person seeking
    contribution must send a demand letter specifying (among other
    things) the nature, scope, and cost of the remediation, the
    legal and factual basis for the demand, and the amount of
    contribution or reimbursement being sought.    G. L. c. 21E,
    § 4A(a).   The recipient of such a demand letter is required to
    13
    "Response," as defined by § 2 of the Act, encompasses
    assessment, containment, and removal measures to remediate a
    site. A response action is deemed complete when it achieves a
    "permanent" solution, a result that is attained when a site no
    longer poses a "significant risk" to the public or environment
    for a "foreseeable period of time." G. L. c. 21E, § 3A(g), as
    appearing in St. 1992, c. 133, § 283.
    14
    There is no question in this   case that Packer is liable
    as a "person who . . . caused or is   legally responsible for a
    release . . . of oil . . . from a .   . . site." G. L. c. 21E,
    § 5(a)(5), inserted by St. 1983, c.   7, § 5.
    11
    respond within forty-five days, and may request additional
    documentation.    
    Ibid. Either party may
    request that the dispute
    be submitted to arbitration, mediation, or some other form of
    alternative dispute resolution.     G. L. c. 21E, § 4A(b).   Only
    after this procedure has been followed can suit be filed in
    Superior Court.   G. L. c. 21E, § 4A(c).    The purpose of this
    procedure is to prevent the parties from resorting to litigation
    unless and until they have attempted to resolve the allocation
    and burden of remediation among themselves.
    As a further incentive to encourage the parties to take
    reasonable prelitigation positions and to resolve their disputes
    among themselves, the Legislature designed a fee-shifting
    structure that penalizes any party who takes unreasonable
    prelitigation positions regarding liability or cost sharing.        A
    plaintiff is to be awarded its litigation costs and reasonable
    attorney's fees if the court finds that the defendant is liable
    and "(1) failed without reasonable basis to make a timely
    response to a [demand letter], or (2) did not participate in
    negotiations or dispute resolution in good faith, or (3) failed
    without reasonable basis to enter into or carry out an agreement
    to perform or participate in the performance of the response
    action on an equitable basis or pay its equitable share of the
    costs of such response action or of other liability pursuant to
    the provisions of this chapter, where its liability was
    12
    reasonably clear."15   G. L. c. 21E, § 4A(d).   On the other hand,
    "[i]f the court finds that (1) the plaintiff did not participate
    in negotiations or dispute resolution in good faith; (2) the
    plaintiff had no reasonable basis for asserting that the
    defendant was liable, or (3) the plaintiff's position with
    respect to the amount of the defendant's liability pursuant to
    the provisions of this chapter was unreasonable, it shall award
    litigation costs and reasonable attorneys' fees to the
    defendant."    G. L. c. 21E, § 4A(f).   In essence, attorney's fees
    and costs are to be awarded against any person who takes an
    unreasonable prelitigation position regarding the existence or
    extent of another person's liability.
    Here, the judge awarded fees and costs, concluding that
    Packer had "no reasonable basis for asserting that [Dockside]
    was liable."   G. L. c. 21E, § 4A(f)(2).   This conclusion rested
    on the judge's subsidiary findings, including his finding that
    Dockside was wholly blameless for the spill in this case.
    Indeed, the judge found that the spill was caused by Packer's
    employee, who mistakenly delivered diesel fuel to tank one
    without first measuring the level in the tank.    Dockside had not
    15
    In   the absence of one of these conditions, the plaintiff
    shall not   receive attorney's fees and costs even if the court
    finds the   defendant liable for contribution, reimbursement, or
    equitable   contribution. G. L. c. 21E, § 4A(e).
    13
    ordered diesel fuel to be delivered and, moreover, had
    accurately reported the levels in the tanks.
    Although these subsidiary findings are unassailable on
    appeal, they do not dispose of the question whether Packer had a
    reasonable basis for asserting that Dockside was liable for
    purposes of awarding attorney's fees under § 4A(f)(2).16    That
    question turns on whether Packer had a reasonable basis for
    asserting that Dockside fell within one of the five broadly-
    defined categories of persons who may be liable, under
    § 5(a)(1)-(5), "without regard to fault" or causation.     G. L.
    c. 21E, § 5(a), inserted by St. 1983, c. 7, § 5.   If, as Packer
    alleged, Dockside was strictly liable under § 5(a)(1) as an
    "operator of . . . a site from . . . which there . . . has been
    a release . . . of oil," Packer would have had a reasonable
    basis for asserting Dockside's liability.
    Whether a person is an "operator" for purposes of the Act
    depends on whether the person (here, Dockside) had "actual
    control of, and active involvement in, operations at the site.
    16
    What "ultimate legal determination" the facts support is
    a legal question we review de novo. Matter of Jane A., 36 Mass.
    App. Ct. 236, 239 (1994). See Simon v. Weymouth Agric. &
    Industrial Soc., 
    389 Mass. 146
    , 148-149 (1983); VMark Software,
    Inc. v. EMC Corp., 
    37 Mass. App. Ct. 610
    , 617 n.8 (1994)
    ("appellate court may reach its own ultimate conclusions based
    on a trial judge's findings [of fact] and may set aside a trial
    judge's ultimate ruling that is inconsistent with the [trial]
    judge's own subsidiary factual findings").
    14
    This is a fact-specific determination, and the appropriate
    factors to consider will differ according to the nature of the
    enterprise and the relation between the parties involved."
    Martignetti v. Haigh-Farr, 
    Inc., 425 Mass. at 304
    .    The judge's
    conclusion that Dockside was not an "operator" of the site
    rested on the following subsidiary findings.    The judge found
    that Dockside did not own or control the tanks or the land in
    which they sat.   Nor did it have any duty to maintain the tanks.
    The judge found that Dockside had no role in the day-to-day
    operations of the site, and no landlord-tenant relationship
    existed between it and Marmik.   Dockside received no rents or
    profits from the premises and was not involved in a joint
    venture with Marmik.   On the other hand, several of the judge's
    subsidiary findings point the other way.    Dockside had a long-
    standing arrangement (begun with Packer, and continued with
    Marmik) whereby it pumped fuel from the tanks for sale to its
    customers.   Fuel was delivered to, and stored at, the tanks at
    Dockside's instruction and for its use.    Dockside's use of the
    tanks was not casual or intermittent; it was pursuant to a
    formalized business arrangement whereby it paid a fee to Marmik
    in exchange for the use of the tanks.   In addition, after
    investigation, DEP notified Dockside that it (DEP) had reason to
    believe Dockside was potentially liable under the Act.    This
    fact, taken together with those just recited, was certainly a
    15
    strong buttress for Packer's position that Dockside bore
    potential liability as an operator of the site.
    We need not, however, decide whether Packer had no
    reasonable basis for asserting that Dockside was liable as an
    operator such that an award of attorney's fees and costs was
    proper under § 4A(f)(2).   The award was independently proper
    under § 4A(f)(3) given the judge's other findings.   The judge
    stated that "Packer's insistence that Dockside contribute eighty
    percent of the clean up costs . . . when Packer well knew that
    Dockside was blameless in this instance" was alarming.
    Particularly when that demand is considered with the similar one
    made to Marmik (together significantly exceeding the actual cost
    of remediation), and Packer's inflexibility despite its own
    responsibility for the spill, we have no difficulty concluding
    that Packer's "position with respect to the amount of the
    defendant's liability . . . was unreasonable" such that
    attorney's fees and costs could be awarded under § 4A(f)(3).
    Although in other circumstances we might not determine the
    reasonableness of a presuit litigation position for the first
    time on appeal, we do so here for several reasons.   First, the
    issue was raised and fully briefed below.   Dockside's
    counterclaim sought attorney's fees and costs under all three
    subsections of § 4A(f), and its application for attorney's fees
    also pressed all three grounds.   Second, on appeal, Dockside
    16
    again argues that the award was proper under all three
    subsections.    Tellingly, Packer challenges only the award under
    § 4A(f)(2); it does not argue that the award could not rest on
    § 4A(f)(3).    Finally, it is clear that the judge would have made
    the award under § 4A(f)(3) as well as (or in lieu of) § 4A(f)(2)
    had he considered the question.    As the judge noted, had he
    "reached the question of equitable apportionment of the
    [response] costs vis-a-vis Dockside, a finding of zero share
    would have been entered."    It is but a short step from this
    statement, considered together with the judge's subsidiary
    findings concerning Dockside's lack of responsibility for the
    spill and his forceful remarks concerning his "alarm[]" at
    Parker's intransigent demand for an eighty percent contribution
    to conclude that the judge would have found Packer's inflexible
    contribution position unreasonable.
    The judgment dated September 3, 2013, and the order dated
    April 9, 2014, awarding attorney's fees and costs to Dockside
    are affirmed under G. L. c. 21E, § 4A(f)(3).
    So ordered.
    

Document Info

Docket Number: AC 14-P-1638

Citation Numbers: 88 Mass. App. Ct. 654

Judges: Meade, Wolohojian, Milkey

Filed Date: 11/25/2015

Precedential Status: Precedential

Modified Date: 11/10/2024