Building Inspector of Palmer v. Palmer Motorsports Park, LLC. ( 2023 )


Menu:
  • NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule
    23.0, as appearing in 
    97 Mass. App. Ct. 1017
     (2020) (formerly known as rule 1:28,
    as amended by 
    73 Mass. App. Ct. 1001
     [2009]), are primarily directed to the parties
    and, therefore, may not fully address the facts of the case or the panel's
    decisional rationale. Moreover, such decisions are not circulated to the entire
    court and, therefore, represent only the views of the panel that decided the case.
    A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25,
    2008, may be cited for its persuasive value but, because of the limitations noted
    above, not as binding precedent. See Chace v. Curran, 
    71 Mass. App. Ct. 258
    , 260
    n.4 (2008).
    COMMONWEALTH OF MASSACHUSETTS
    APPEALS COURT
    22-P-173
    BUILDING INSPECTOR OF PALMER1
    vs.
    PALMER MOTORSPORTS PARK, LLC.
    MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
    The defendant corporation, Palmer Motorsports Park, LLC
    (PMP), appeals from a judgment of civil contempt.              After a
    trial, a Land Court judge found that PMP had failed to comply
    with an order included in a judgment dated January 14, 2020.                 On
    appeal, PMP asserts that the judge's order was ambiguous and,
    even if the order was clear and unequivocal, PMP's noncompliance
    should be excused under the doctrine of impossibility.               We
    affirm.
    "[A] civil contempt finding [must] be supported by clear
    and convincing evidence of disobedience of a clear and
    unequivocal command."       Birchall, petitioner, 
    454 Mass. 837
    , 853
    1 Bonita J. Weeks, the named plaintiff, was sued in her capacity
    as building inspector and zoning enforcement officer of the Town
    of Palmer.
    (2009).   The order at issue, reproduced in the margin,2 was clear
    and unequivocal.   It required PMP, "by no later than 45 days
    from the entry of this Judgment," to take two actions:     (a) to
    implement certain noise mitigation measures and (b) to provide
    the town with "actual noise readings" from certain locations so
    the town could assess the efficacy of the mitigation measures.
    We discern no ambiguity in the language of the order concerning
    the timing of the two actions required of PMP.   Plainly, both
    were to occur within forty-five days.   PMP's reading of the
    order -- that the forty-five day deadline applied only to
    implementation of the mitigation measures, and that there was no
    clear time constraint on its obligation to provide noise
    readings "following" implementation -- is a strained and
    unnatural interpretation of the order's clear command.     "[A]
    2 "[T]he Court . . . ORDERS PMP, by no later than 45 days from
    the entry of this Judgment, to (a) implement proper mitigation
    measures so as to remedy all of the noise conditions that the
    evidence at the trial of this matter and/or the study of the
    Palmer Motorsports Park (the 'Park') prepared by Resource
    Systems Group, Inc., dated November 1, 2018 shows are not in
    compliance with Condition #10 [of a Special Permit issued in
    December 2007]; and (b) following PMP's implementation of such
    measures, provide to the Planning Board of the Town of Palmer,
    for professional review at PMP's expense, actual noise readings
    from the same locations as the 'original study' described in
    Condition #10. In order to fulfill the requirements of
    subparagraph (b) . . . , such actual noise readings and
    corresponding data must be in such form as to allow a
    professional acoustical engineer engaged by the Board to
    determine whether noise from the Park, after PMP's
    implementation of mitigation measures, meets the requirements of
    Condition #10."
    2
    party's self-serving characterization of a provision as
    'ambiguous' does not make it so."    Stabile v. Stabile, 
    55 Mass. App. Ct. 724
    , 726-727 (2002).
    Although the order clearly required PMP to implement the
    noise mitigation measures and to provide the required data
    within forty-five days of January 14, 2020, that is, by February
    28, 2020,3 PMP argues that it was impossible to comply with the
    order because no "high-sound" events were scheduled during the
    off-season months of January and February.     Moreover, PMP's
    ability to schedule an event to generate the required noise
    level data was further hampered by the outbreak of the COVID-19
    pandemic.4
    It was not until July 16, 2020, that PMP held the first
    event that would generate the required data.    PMP contracted
    with an entity called Cross-Spectrum Acoustics (CSA) to take the
    noise readings.   Because of equipment problems, CSA was unable
    to gather data from two of the four required monitoring
    locations.   PMP held a second event on August 8, 2020, at which
    CSA obtained data from all four required locations.    PMP did not
    provide the partial July 18 noise readings or the complete
    3 In fact, PMP had already complied with the first part of the
    order before it was issued. Its only remaining obligation was
    to provide noise readings by February 28, 2020.
    4 "On March 10, 2020, the Governor declared a state of emergency
    throughout the Commonwealth in response to the spread of COVID-
    19." Christie v. Commonwealth, 
    484 Mass. 397
    , 398 (2020).
    3
    August 8 readings to the town.   On September 22, 2020, exactly
    forty-five days after the August 8 event, the plaintiff filed
    the contempt complaint.
    "Noncompliance with a court order may be excused where
    compliance becomes impossible, but the burden of proving
    impossibility lies with the alleged contemnor."   Commonwealth v.
    One 1987 Ford Econoline Van, 
    413 Mass. 407
    , 412 (1992).     The
    judge rejected PMP's impossibility argument.   He found that
    PMP's inability to comply with the judgment ended with the event
    held on July 16, but that PMP withheld the partial data from
    that event.   The judge also found that PMP did not produce the
    data from the August 8 event until after it received the
    contempt complaint.   The judge concluded, "Even if the 45-day
    clock started on July 16, 2020 (a generous reading of the
    Judgment), PMP was obligated either to provide to the Town
    testing data by August 31, 2020, or seek modification of the
    Judgment."
    We review the judge's underlying conclusions of law de
    novo, the findings of fact for clear error, and the ultimate
    finding of contempt for abuse of discretion.   See Martinez v.
    Lynn Hous. Auth., 
    94 Mass. App. Ct. 702
    , 705 (2019); Commercial
    Wharf E. Condominium Ass'n v. Boston Boat Basin, LLC, 
    93 Mass. App. Ct. 523
    , 532 (2018).   We discern no basis to disturb the
    contempt judgment.
    4
    PMP argues that it was unable to provide the noise readings
    to the town because the data was in the hands of its contractor,
    CSA.   Perhaps, as PMP argues, the plaintiff did not introduce
    any evidence to contradict the track owner's testimony that he
    mailed the noise readings to the town as soon as he received
    them from CSA.   But the burden was on PMP to show that it was
    "reasonably diligent and energetic in attempting to accomplish
    what was ordered" (citations omitted).    One 1987 Ford Econoline
    Van, 
    413 Mass. at 412
    .   PMP presented no evidence that the data
    it was required, by court order, to produce to the town was
    somehow inaccessible, or that PMP was at all diligent or
    energetic in pressing CSA to provide that data.
    Finally, there is no merit to PMP's claim that the
    plaintiff was required to show willful or intentional
    disobedience.    See United Factory Outlet, Inc. v. Jay's Stores,
    Inc., 
    361 Mass. 35
    , 37 (1972) (to hold corporation in civil
    contempt "it is not necessary to show that there was wilful
    disobedience or intention to violate the order.    It is enough to
    establish that persons acting for the corporation were
    responsible for acts or inaction which in fact constituted a
    5
    violation").
    Judgment of contempt
    affirmed.
    By the Court (Rubin,
    Massing & D'Angelo, JJ.5),
    Clerk
    Entered:    February 17, 2023.
    5   The panelists are listed in order of seniority.
    6
    

Document Info

Docket Number: 22-P-0173

Filed Date: 2/17/2023

Precedential Status: Non-Precedential

Modified Date: 2/22/2023