Celco Construction Corp. v. Town of Avon ( 2015 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    13-P-1880                                               Appeals Court
    CELCO CONSTRUCTION CORP.     vs.   TOWN OF AVON.
    No. 13-P-1880.
    Norfolk.        October 8, 2014. - March 2, 2015.
    Present:    Green, Rubin, & Agnes, JJ.
    Contract, Public works, Bidding for contract, Municipality,
    Modification, Promissory estoppel. Public Works, Bidding
    procedure, Extra work. Municipal Corporations, Contracts,
    Estoppel.
    Civil action commenced in the Superior Court Department on
    October 22, 2010.
    The case was heard by Patrick F. Brady, J., on a motion for
    summary judgment.
    Raymond S. Ewer for the plaintiff.
    Doris R. MacKenzie Ehrens for the defendant.
    GREEN, J.     In its successful bid to perform work for the
    defendant town of Avon (town) on a water main extension project,
    the plaintiff, Celco Construction Corp. (Celco), assigned a unit
    price of $0.01 as its charge to excavate each cubic yard of rock
    from the project site.       That price was substantially lower than
    2
    Celco's actual cost to remove each cubic yard of rock; Celco
    constructed its bid based on its belief that the amount of rock
    actually on site would be considerably less than the unverified
    estimate indicated in the contract bid documents, so that its
    low unit price would give it a competitive advantage when
    compared to other bidders who assigned a unit price to rock
    removal that more closely approximated the actual cost.1    When
    the amount of rock turned out to exceed the estimate by more
    than 1,500 cubic yards, Celco sought an "equitable adjustment"
    in the contract price to recover its increased costs for rock
    removal.    See G. L. c. 30, § 39N.   The town refused Celco's
    request, Celco filed a complaint in the Superior Court, and a
    judge of that court allowed the town's motion for summary
    judgment.   Celco appealed, and we now affirm the judgment.
    Background.    We summarize the undisputed facts appearing in
    the summary judgment record relevant to Celco's claim of
    entitlement to an equitable adjustment in the contract price.2
    In 2008, the town solicited bids to perform work on a project
    for the installation of water mains and associated
    reconstruction of roadways disturbed during such installation.
    1
    To make up the difference between its bid price and its
    cost to remove the amount of rock it estimated to be on the
    site, Celco increased the unit prices it assigned to various
    other components of the work.
    2
    We reserve additional facts relevant to Celco's claim of
    promissory estoppel for our discussion of that issue.
    3
    Celco submitted a bid and was awarded the contract.     Celco's bid
    included unit prices for various elements of the work including,
    as relevant to its claim for equitable adjustment, a specified
    unit price of $0.01 per cubic yard for excavation and disposal
    of rock from the project site.3    Next to the line item for that
    element of the work, under the heading "Estimated Quantity," the
    bid documents specified "1000* cu. yd."     A legend at the bottom
    of the page explained that the asterisk denoted an
    "[i]ndeterminate quantity assumed for comparison of bids."4
    Celco and the town entered into a contract for the work on April
    6, 2009.
    During its performance of the work, Celco discovered that
    the quantity of rock requiring removal substantially exceeded
    the 1,000 cubic yards estimated in the bid documents for
    purposes of bid comparison.     On August 11, 2009, Celco requested
    an increase in its contract unit price for rock removal from
    $0.01 to $220 per cubic yard.     On November 16, 2009, describing
    the additional rock as a "change in the conditions depicted by
    3
    Celco was not alone in submitting a "penny bid" for rock
    removal; thirteen other bidders similarly submitted penny bids
    for that line item. Several other bidders, however, submitted
    bids that specified unit prices ranging from $40 to $125 per
    cubic yard for rock excavation and removal. We note that
    Celco's bid submission also assigned a $0.01 unit price to a
    variety of other line items, none of which is the subject of
    dispute between the parties.
    4
    Several other line items included the same denotation
    regarding the specified estimate.
    4
    the plans and specifications," Celco again requested an increase
    in the unit price, this time to $190 per cubic yard.    On January
    13, 2010, the town denied Celco's request for an adjustment to
    the unit price.    Eventually, Celco removed a total of 2,524
    cubic yards of rock from the project site.
    In support of its claim for an "equitable adjustment" to
    the contract price, Celco asserts that its performance of the
    work was made more difficult by the additional rock.
    Specifically, Celco claimed that it lost "150 feet per day of
    production," because average production in earth without rock
    was 300 feet per day, compared to only 150 feet per day with
    rock.    However, Celco submitted no evidence suggesting that the
    character of the rock discovered on site was different, or that
    the actual unit cost to remove it was greater, by reason of the
    increased amount or any other concealed condition.
    Following the town's denial of its request for adjustment
    to the contract price, Celco commenced an action in the Superior
    Court.    A judge of that court allowed the town's motion for
    summary judgment, and this appeal followed.
    Discussion.     Under G. L. c. 30, § 39N, inserted by
    St. 1972, c. 774, § 4, all public construction contracts such as
    the one at issue in the present case must include a provision
    allowing either party to request an equitable adjustment in the
    contract price "[i]f, during the progress of the work, the
    5
    contractor or the awarding authority discovers that the actual
    subsurface or latent physical conditions encountered at the site
    differ substantially or materially from those shown on the plans
    or indicated in the contract documents."
    The purpose of the equitable adjustment provision is to
    remove unknown risks from the competitive bidding process.    The
    contracting authority is thereby able to obtain bid prices
    stripped of amounts incorporated by bidders to cover the risk,
    and bidders are able to bid with the assurance that they will be
    compensated for subsurface or latent site conditions that impose
    greater costs than reflected in the bid documents.    See Glynn v.
    Gloucester, 
    9 Mass. App. Ct. 454
    , 461 n.9 (1980).    According to
    Celco, the presence of 2,524 cubic yards of rock on the project
    site, when the project bid documents estimated only 1,000 cubic
    yards, presents an appropriate occasion for an equitable
    adjustment to compensate it for the increased costs it incurred
    to remove the additional rock.   We disagree.
    As a threshold matter, we observe that the contract bid
    documents did not specify that the site contained only 1,000
    cubic yards of rock; instead, the bid documents expressly
    disclaimed the accuracy of the stated amount, explaining that
    the estimate appeared solely for the purpose of allowing
    comparison of the submitted bids.   As the motion judge observed,
    6
    the contract anticipated rock excavation and disclosed that the
    amount of rock was "indeterminate."
    More importantly, there is nothing in the summary judgment
    record to suggest, and Celco does not contend, that the nature
    of the rock itself, and the means and cost to remove it, differ
    in any way from what was anticipated in the contract documents.
    Particularly in a contract such as the one in the present case,
    in which the contract price is comprised of the aggregate of
    line items for various elements of the work, which in turn are
    based on unit prices for the quantities involved in each line
    item, no equitable adjustment is warranted by reason of a
    variation in the estimated quantities, standing alone, as
    compared to a deviation in the condition or character of the
    physical condition.    See Perini Corp. v. United States, 
    381 F.2d 403
    , 410-411 (1967).     An equitable adjustment is required only
    when the contractor encounters a material difference in the
    "actual subsurface or latent physical conditions . . . at the
    site . . . of such a nature as to cause an increase or decrease
    in the cost . . . of the work."     G. L. c. 30, § 39N, inserted by
    St. 1972, c. 774, § 4.     Had Celco in its bid assigned to rock
    removal a unit price reasonably approximating its estimated cost
    for such removal, instead of assigning the wholly artificial and
    unrealistic value of one penny, it would be in no need of
    adjustment to the contract price.     Put another way, G. L. c. 30,
    7
    § 39N, is designed to protect contractors from unknown and
    unforeseen subsurface conditions, not from the consequences of
    their decisions to bid a unit price for the performance of work
    that is wholly unrelated to their anticipated cost to perform
    the work.   In such circumstances, it defies logic to invoke
    "equity" as a basis for adjustment to the contract price.
    Celco's additional claims of promissory estoppel and
    quantum meruit require only brief discussion.   Construed in the
    light most favorable to Celco, the statements allegedly made by
    the town's water superintendent John Tetreault to the effect
    that "Celco should keep working on the project and this
    additional [rock] issue would be dealt with once the total
    quantity of [rock] excavated was known" were inadequate to give
    rise to an obligation on the part of the town to compensate
    Celco for rock removal at a rate greater than the unit price
    specified in the contract.   As a threshold matter, Celco has
    offered no evidence to suggest that Tetreault had legal
    authority to agree on behalf of the town to compensate Celco for
    rock removal at a rate in excess of that provided in the
    contract.   Moreover, even if Tetreault personally held
    contracting authority as a general matter, the contract at issue
    in the present case was entered into pursuant to a statutorily
    prescribed public bidding process, and "a party cannot evade the
    statutory limitations on a municipality's contracting power by
    8
    rendering services and subsequently seeking recovery based on
    alternative theories."   Baltazar Contractors, Inc. v. Lunenburg,
    
    65 Mass. App. Ct. 718
    , 724 (2006), quoting from Park Drive
    Towing, Inc. v. Revere, 
    442 Mass. 80
    , 83 n.7 (2004).5
    Judgment affirmed.
    5
    We need not consider whether Tetreault's statements were
    sufficiently unambiguous to induce reasonable reliance, see
    Rhode Island Hosp. Trust Natl. Bank v. Varadian, 
    419 Mass. 841
    ,
    848 (1995), or whether Celco's continued performance of its pre-
    existing obligations under the contract might qualify as
    detrimental reliance for purposes of promissory estoppel.
    

Document Info

Docket Number: AC 13-P-1880

Judges: Green, Rubin, Agnes

Filed Date: 3/2/2015

Precedential Status: Precedential

Modified Date: 11/10/2024