Central Ceilings, Inc. v. Suffolk Construction Co., Inc. ( 2017 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    15-P-1117                                              Appeals Court
    CENTRAL CEILINGS, INC.      vs. SUFFOLK CONSTRUCTION COMPANY, INC.
    & others.1
    No. 15-P-1117.
    Suffolk.      October 7, 2016. - March 29, 2017.
    Present:    Agnes, Maldonado, & Desmond, JJ.
    Contract, Construction contract, Subcontractor, Damages.
    Damages, Breach of contract, Attorney's fees. Practice,
    Civil, Attorney's fees, Discovery.
    Civil action commenced in the Superior Court Department on
    October 3, 2006.
    The case was heard by S. Jane Haggerty, J.; an award of
    attorney's fees was entered by her; and a motion for
    reconsideration was considered by Judith Fabricant, J.
    Joel Lewin (John P. Connelly also present) for the
    defendants.
    Paul R. Mordarski (Thomas J. Fullam also present) for the
    plaintiff.
    DESMOND, J.       After a jury-waived trial, a Superior Court
    judge entered judgment awarding the plaintiff, Central Ceilings,
    1
    Fidelity and Deposit Company of Maryland, Safeco Insurance
    Company of America, and XL Specialty Insurance Company.
    2
    Inc. (Central), $321,315 on its breach of contract claim for
    damages for loss of productivity incurred while acting as a
    subcontractor for defendant Suffolk Construction Company, Inc.
    (Suffolk), on a large construction project.    This case is before
    us on cross appeals.
    Suffolk challenges the judgment,2 claiming, inter alia, that
    Central's claim was barred by the "no-damages-for-delay" clause
    in the subcontract between the parties, and that the judge erred
    in ruling that Central had established its claim for damages by
    the "total cost" method.   Suffolk further challenges the judge's
    award of $471,682 in attorney's fees to Central, claiming that
    it was wrongfully denied discovery and a hearing prior to the
    entry of that award.
    On its cross appeal, Central challenges the judge's holding
    that the "pay-if-paid" clause in the subcontract barred it from
    recovering $82,538 from Suffolk for unpaid change order requests
    (CORs).   For the reasons set forth herein, the judgment on the
    merits entered on December 20, 2013, and the amended judgment
    for attorney's fees entered on September 9, 2014, are affirmed.
    1.   Background.   First, we set forth the basic material
    facts, drawing extensively from the trial judge's thoughtful and
    2
    While this appeal is brought on behalf of all defendants,
    other than Suffolk, the defendants are sureties and not
    principal actors in the underlying events.
    3
    thorough findings of fact, rulings of law, and decision.   The
    Massachusetts State College Building Authority (MSCBA) hired
    Suffolk to serve as general contractor on the construction of
    three interconnected dormitories at what is now known as
    Westfield State University (the project).   As the dormitories
    were to be ready for occupancy by students arriving for the fall
    semester in 2005, the contract between the MSCBA and Suffolk
    (the general contract) provided for a substantial completion
    date of July 1, 2005.   As an incentive for Suffolk to finish on
    time, the general contract further provided that Suffolk could
    either earn a $200,000 bonus for completing the project on time
    or pay significant liquidated damages if it was not.3
    Central submitted a bid to serve as the subcontractor for
    installing, among other things, the exterior heavy metal gauge
    framing and sheathing, interior light gauge framing, drywall,
    and hollow metal door frames.   Critical to Central's estimate
    and ability to timely complete its work was the "flow" of the
    project, with each aspect of its work following in sequence,
    floor by floor, exterior to interior, building by building.
    3
    The liquidated damages clause provided for payment of
    $30,000 for each week beyond July 15, 2005, up to September 2,
    2005; $25,000 per additional day from September 3, 2005 to
    October 2, 2005; and a $810,000 lump sum payment for failure to
    complete the project by October 3, 2005.
    4
    Suffolk accepted Central's bid, and the parties entered into a
    subcontract in the original amount of $3,606,476.
    From the outset, however, the project was plagued by
    problems as Suffolk failed to carry out many of its obligations,
    including:   failing to coordinate the work of other "trades,"
    such as the steel erector and window installer, whose work
    necessarily had to be completed before Central could complete
    its own; failing to establish proper elevation, column, and
    control lines, from which Central worked to construct the
    building in accordance with the plans; failing to provide for
    the timely and properly coordinated delivery of the hollow metal
    door frames to be installed by Central; and failing to ensure
    that the buildings were weather-tight and properly heated, both
    of which were essential to Central's ability to, among other
    things, carry out the temperature-sensitive tasks related to the
    installation of the gypsum wall board.4
    As Central encountered each obstacle and awaited
    resolution, its workers, who had taken their tools and the
    4
    In addition, due to design defects, over 500 "requests for
    information" (RFIs) were submitted to the architect over the
    life of the project, with over 200 from Central alone. An RFI
    is generated when a contractor or subcontractor encounters an
    issue that is either inconsistent with, or not clearly addressed
    by, the plans. The RFI seeks clarification and/or direction
    from the architect, who responds with a "supplemental
    information" (ASI) and often a sketch. The architect issued
    over 200 ASIs on the project. The volume of RFIs and ASIs was
    not only unusual for a project of this size, but of any size.
    5
    necessary supplies and mobilized in a specific area to carry out
    a specific task, were repeatedly forced to break down and
    remobilize to a different area to carry out a different task.
    Then, once the obstacle had been overcome, Central's workers
    would have to do a "go back," remobilizing and completing the
    original task.   Meanwhile, Central's project manager and other
    supervisory personnel were forced to spend an inordinate amount
    of time coordinating all of the changes and filling out related
    paperwork.   The problems also resulted in Central's workers
    being forced to work in the same space and at the same time as
    other subcontractors, an inefficient situation commonly referred
    to in the industry as the "stacking of trades."
    Given the substantial completion date, and the financial
    incentives and disincentives related thereto, Suffolk advised
    Central that no time extensions would be granted on the project.
    As a result, while the start dates for various aspects of
    Central's subcontract work were consistently pushed back due to
    the myriad of issues caused by Suffolk's breaches, the
    completion dates remained the same and the time within which
    Central had to perform was constantly "compressed."     When
    Central complained, Suffolk told it to simply assign additional
    manpower to keep the project on track, which is what Central was
    forced to do.    As such, even though the project was
    substantially completed on time, to the financial benefit of
    6
    Suffolk, the "flow" and productivity that Central had reasonably
    counted on when calculating its bid for the project suffered
    significantly.
    Central brought this suit for breach of contract and
    quantum meruit claiming that Suffolk had not adequately managed
    and coordinated the project, and that these deficiencies
    resulted in damages for loss of productivity in the amount of
    $321,315 and $82,538 in unpaid CORs.5   The judge specifically
    found that Suffolk had breached the contract "(1) by failing to
    coordinate erection of the steel; (2) by incorrectly
    establishing the elevation, column, and control lines of
    Building 2; (3) by failing to order the [hollow metal door
    frames] and to coordinate delivery of the window and curtain
    walls in a timely manner; (4) by failing to provide the
    necessary climate for the interior work on the Project; and (5)
    by making errors in design that affected the plumbing, the
    heights and dimensions throughout the Project, the fan coil
    units in each room, the shaft walls, the curtain walls, and the
    pour stops."
    At trial, Central sought to establish its damages due to
    this loss of productivity through the expert testimony of
    5
    The judge did not allow recovery for the unpaid CORs
    which, as earlier noted, is the subject of Central's cross
    appeal.
    7
    Richard Broglino, an individual with substantial experience in
    the construction industry.      Broglino opined that Central's loss
    was best quantified through the impact it had on "manpower."       To
    that end, he first reviewed Central's original estimate for
    labor costs of $1,657,000 and determined that it was reasonably
    accurate.     He then subtracted that figure, as well as amounts
    that Central had already recovered for labor through change
    orders, from the $2,310,526 in actual labor costs Central
    incurred on the project, resulting in a net loss of $321,315 in
    labor productivity.    The judge determined Broglino's testimony
    was credible and awarded that amount to Central on its claims
    for breach of contract.6
    2.   Standard of review.     On appeal from a jury-waived
    trial, we review the trial judge's findings of fact for clear
    error and review de novo her rulings on questions of law.        Trace
    Constr., Inc. v. Dana Barros Sports Complex, LLC, 
    459 Mass. 346
    ,
    351 (2011).
    3.   Suffolk's appeal.     a.   "No-damages-for-delay" clause.
    Suffolk first argues that the award of damages, which was based
    on Central's claim of loss of productivity, contravened the
    following provision in the subcontract, often generically
    6
    Having ruled for Central on its contract claims, the judge
    entered judgment for Suffolk and the surety defendants on
    Central's alternative quantum meruit claims.
    8
    referred to in the construction industry as a "no-damages-for-
    delay" clause:
    "The Subcontractor agrees that it shall have no claim for
    money damages or additional compensation for delay no
    matter how caused, but for any delay or increase in the
    time required for performance of this Subcontract not due
    to the fault of the Subcontractor, the Subcontractor shall
    be entitled only to an extension of time for performance of
    its Work. Written notice of all claims for any extension
    of time shall be submitted to Contractor within ten (10)
    days of the date when Subcontractor knows (or should know)
    of the event which causes such delay, or such claim shall
    be considered waived by Subcontractor."
    In Massachusetts, such a provision is, as a general proposition,
    enforceable.     See, e.g., Worcester v. Granger Bros., 
    19 Mass. App. Ct. 379
    , 388 (1985); B.J. Harland Elec. Co. v. Granger
    Bros., 
    24 Mass. App. Ct. 506
    , 509 (1987).7    Here both parties
    agree, and the judge determined, that the clause is unambiguous.
    We concur.   Consequently, the no-damages-for-delay clause at
    issue here must be interpreted and applied on its own terms.
    See Siebe, Inc. v. Louis M. Gerson Co., 
    74 Mass. App. Ct. 544
    ,
    550 (2009) (parole or extrinsic evidence not admissible to
    contradict or modify an unambiguous contract).     It was on the
    basis of that clause's plain language that the judge ruled, for
    7
    At the same time, courts in various jurisdictions have
    recognized a number of exceptions to the enforceability of such
    clauses. See Tricon Kent Co. v. Lafarge N. Am., 
    186 P.3d 155
    ,
    160 (Colo. Ct. App. 2008) (noting that recognized exceptions
    include instances of fraud, misrepresentation, bad faith, and
    "active interference").
    9
    two independent reasons, that it did not bar Central's claim.
    Suffolk now challenges both reasons.
    i.    Deprivation of remedy.    The judge first determined the
    no-damages-for-delay clause inapplicable because, even if
    Central could be deemed to be seeking damages "for delay,"
    Suffolk had deprived Central of its only remedy under that
    clause by refusing to grant requested extensions of time for
    performance.    Suffolk argues that this finding was clearly
    erroneous because there was no evidence that Central ever
    requested extensions of time.     This argument fails for at least
    two reasons.
    First, we need not consider this argument because Suffolk,
    by its own admission, never raised it in the trial court.      See
    R.W. Granger & Sons, Inc. v. J & S Insulation, Inc., 
    435 Mass. 66
    , 73-74 (2001) (an argument raised for the first time on
    appeal need not be considered).     Suffolk, in response, argues
    that it had no reason to make the argument earlier because the
    issue of extensions of time arose only after the judge issued
    her decision.    That suggestion, however, is belied by the
    record.   Central's project manager testified that Suffolk had
    made clear that no extensions of time would be granted, and
    Central emphasized that point in its requests for findings of
    fact and rulings of law.    The issue of the availability of time
    extensions, therefore, was a live issue at trial, and Suffolk
    10
    was required to raise any related arguments it had in that forum
    to preserve them for appeal.8   This it failed to do.
    Second, even if we do consider Suffolk's argument, it fails
    independently.   Not only was there evidence at trial that
    Suffolk had made clear that no extensions of time would be
    granted on the project, that evidence was undisputed.      Thus,
    even though there was no evidence that Central requested
    extensions of time in writing, the judge's ruling was not
    clearly erroneous.   See Demoulas v. Demoulas Super Mkts., Inc.,
    
    424 Mass. 501
    , 509 (1997) (finding is only "clearly erroneous"
    if "reviewing court on the entire evidence is left with the
    definite and firm conviction that a mistake has been
    committed").   As noted above, Central's project manager
    testified that Suffolk had communicated that no extensions of
    time would be granted.   Suffolk did not dispute that evidence.
    The evidence further established that Suffolk was financially
    incentivized to avoid extensions of time by both the bonus
    available to it for completing the project on schedule and the
    liquidated damages it faced for failing to do so.   In short, the
    8
    Inexplicably, Suffolk states that it is not arguing that
    Central, even if seeking damages covered by the no-damages-for-
    delay clause, first has to establish that it requested and was
    denied extensions of time. Suffolk's argument, therefore, seems
    circular in nature (i.e., the judge erred in finding that
    Central had satisfied a condition precedent that Suffolk
    concedes did not need to be satisfied).
    11
    only reasonable inference that could be drawn from the evidence
    was that the possibility of extensions had been foreclosed by
    Suffolk.   As such, we see no basis for disturbing the judge's
    resulting conclusion that Suffolk had committed a material
    breach by depriving Central of its sole contractual remedy,
    thereby precluding Suffolk from invoking the no-damages-for-
    delay clause as a bar to Central's claim for damages.    See Ward
    v. American Mut. Liab. Ins. Co., 
    15 Mass. App. Ct. 98
    , 100
    (1983) (a material breach by one party precludes it from
    demanding performance by the other).9
    ii.   Nature of damages.   The judge also determined that the
    no-damages-for-delay clause did not apply because Central was,
    in fact, not seeking damages "for delay."      Suffolk now suggests
    that finding was in error because Central was seeking damages
    "caused by delays."   The suggestion, however, misapprehends both
    the language of the no-damages-for-delay clause at issue and the
    judge's ruling, which applied that language.
    9
    Suffolk suggests the judge erred by favorably comparing
    this case to Farina Bros. v. Commonwealth, 
    357 Mass. 131
    , 138
    (1970), because the fact finder in that case found that the
    defendant acted in an unreasonable, arbitrary, and capricious
    manner in denying the plaintiff-contractor extensions of time.
    The judge's discussion of Farina, however, was not essential to
    her finding. Moreover, it was implicit in her ruling, and the
    record here supports a finding, that Suffolk, motivated by its
    own financial interests, acted in an unreasonable, arbitrary,
    and/or capricious manner by seeking to enforce a provision with
    a limited remedy, while simultaneously imposing a blanket
    prohibition against the remedy in that provision.
    12
    As the judge noted, courts have uniformly held that no-
    damages-for-delay clauses must be strictly construed due to the
    harsh effects they impose.    See, e.g., United States Steel Corp.
    v. Missouri Pac. R.R. Co., 
    668 F.2d 435
    , 438 (8th Cir. 1982);
    John E. Green Plumbing & Heating Co. v. Turner Constr. Co., 
    742 F.2d 965
    , 966 (6th Cir. 1984) (John E. Green Plumbing); Tricon
    Kent Co. v. Lafarge N. Am., 
    186 P.3d 155
    , 159 (Colo. App. Ct.
    2008).   The clause here provides, in pertinent part, that
    Central "shall have no claim for money damages or additional
    compensation for delay no matter how caused, but for any delay
    or increase in the time required for performance of this
    Subcontract not due to the fault of the Subcontractor, the
    Subcontractor shall be entitled only to an extension of time for
    performance of its Work"   (emphasis   added).   Strictly construing
    this language, the judge found that Central was not seeking
    damages because it had been delayed, but, rather, because it had
    been forced to increase its workforce due to the compression of
    the schedule occasioned by Suffolk's breaches of its
    obligations.   As the judge further stated, "Suffolk's breaches
    did not affect Central's ability to complete its work on time
    . . . but, rather, with its ability to complete its work on
    budget."
    According to Suffolk, the judge erred by defining "delay"
    to be limited to "an idle workforce."      The argument, however,
    13
    mischaracterizes the judge's findings.     It appears that she
    found the reasoning of the Court of Appeals for the Sixth
    Circuit in John E. Green Plumbing to be persuasive.     Although
    the plaintiff-contractor did not ultimately prevail in that
    case, the court held that the plaintiff-contractor's claim for
    damages was not barred by the no-damages-for-delay clause
    because it interpreted that specific clause's reference to delay
    damages to mean damages for "the cost of an idle workforce."
    Id. at 966. ("delay means time lost where work cannot be
    performed because essential supplies have not been delivered or
    necessary preliminary work has not been performed") (emphasis
    added).    Ibid.   Notably, the clause in that case, which provided
    that "[s]hould the Contractor be delayed in the commencement,
    prosecution or completion of the work by the act, omission,
    neglect or default of the Manager . . . then the Contractor
    shall be entitled to an extension of time only[,]" was similar
    in focus and scope to the one at issue here.     Id. at 966 n.1
    (emphasis added).     As an initial matter, therefore, the judge's
    favorable consideration of that case was well-grounded.
    Further, the judge here was merely (and properly) interpreting
    the no-damages-for-delay clause at issue.     Her ruling neither
    seeks to impose, nor results in, a new, universally applicable
    definition of "delay."10    In sum, we discern no basis for
    10
    Suffolk suggests the present case is controlled by
    14
    disturbing either her interpretation of the clause at issue or
    her related factual findings.
    b.   "Total cost" claim.   Suffolk next challenges the
    judge's adoption of the "total cost" method for calculating
    damages as advocated by Central's expert, Broglino.11     The total
    cost method "looks to the difference between the amount bid for
    the work and the actual cost of the work."    North Am.
    Mechanical, Inc. v. Walsh Constr. Co., 
    132 F. Supp. 3d 1064
    ,
    1078 (E.D. Wis. 2015), citing Raytheon Co. v. White, 
    305 F.3d 1354
    , 1365 (Fed. Cir. 2002).    Due to several concerns, courts
    have suggested that the method be used only "as a last resort
    . . . , in those extraordinary circumstances where no other way
    to compute damages was feasible and where the trial court
    employed proper safeguards."    Servidone Constr. Corp. v. United
    Reynolds Bros. v. Commonwealth, 
    412 Mass. 1
     (1992), where the
    court, in enforcing a no-damages-for-delay clause, found "no
    significant distinction between the hindrances and interferences
    to which Reynolds point[ed] and the alleged delay in the start
    of the project and delays caused by the work of other
    contractors." 
    Id. at 7-8
    . Regardless of the language it chose
    to describe its damages, however, the plaintiff in Reynolds
    sought to recover for delay, not, as is the case here with
    Central, the expense of having to increase its workforce to
    avoid delay. In addition, the Commonwealth in Reynolds, unlike
    Suffolk here, did not materially breach the no-damages-for-delay
    clause, thereby precluding its own enforcement of that
    provision. The present case, therefore, is distinguishable.
    11
    Suffolk also had a damages expert, but chose not to call
    him as a witness at trial.
    15
    States, 
    931 F.2d 860
    , 861-862 (Fed. Cir. 1991).12   Thus, a
    plaintiff seeking to utilize the method "must prove that (1) the
    nature of the particular losses make it impossible or highly
    impracticable to determine them with a reasonable degree of
    accuracy; (2) the plaintiff's bid or estimate was realistic; (3)
    its actual costs were reasonable; and (4) it was not responsible
    for the added expenses."13   Raytheon Co., 
    305 F.3d at 1366
    (quotation omitted).   Although Suffolk does not challenge per se
    the use of the total cost method, it nonetheless maintains that
    the judge erred in finding that Central satisfied the first and
    fourth elements.   We disagree.
    As to the first element, Broglino testified that the total
    cost method was, in his opinion, the only method by which one
    could calculate the loss of labor productivity in this case.    He
    testified that he had considered use of the preferred "measured
    mile" method for calculating such damages,14 but that the type of
    12
    No Massachusetts appellate court appears to have
    addressed the use of the total cost method.
    13
    There is also a "modified total cost" method, which is
    simply "the total cost method adjusted for any deficiencies in
    the contractor's proof in satisfying the [four elements]."
    Propellex Corp. v. Brownlee, 
    342 F.3d 1335
    , 1339 (Fed. Cir.
    2003), citing Servidone, 
    931 F.2d. at 861-862
    . The elements are
    the same for both methods. See Raytheon Co., 
    305 F.3d at
    1365-
    1366; Propellex, 
    342 F.3d at 1339
    .
    14
    "A measured mile analysis requires quantifying the time
    it took [the subcontractor] to complete work in areas that were
    'impacted' by conditions that caused it to be inefficient and
    16
    detailed records necessary to do so did not exist, nor would
    Central have been expected to maintain them.    The judge, as
    indicated above, found Broglino's testimony credible, a finding
    to which we defer.   See Demoulas, 424 Mass. at 509 (noting that
    Mass.R.Civ.P. 52[a], 
    365 Mass. 816
     [1974], "requires that 'due
    regard shall be given to the opportunity of the trial court to
    judge of the credibility of the witnesses'").    Nor do we see a
    basis for disturbing her ruling, based on Broglino's testimony,
    that the pervasive nature of Suffolk's breaches made it
    impossible to identify an adequate baseline for assessing
    damages on an event-by-event basis.15
    Meanwhile, the fourth element of the total cost analysis
    attempts to address concerns of causation, requiring a plaintiff
    to remove from the calculation any damages attributable to its
    compare that with the time it took [the subcontractor] to
    complete essentially identical work in areas that were
    'unimpacted' by such conditions." North Am. Mechanical, 132 F.
    Supp. 3d at 1079.
    15
    Suffolk suggests that Central proved it was possible
    when, at Suffolk's suggestion, it initially submitted a request
    for an equitable adjustment, documented ASI by individual ASI.
    At the time, Suffolk and the MSCBA both rejected the request,
    citing a purported lack of supporting documentation or
    information. As an initial matter, therefore, it is telling
    that Suffolk did not reject that request due to the no-damages-
    for-delay clause. In any event, the judge was presented with
    extensive evidence regarding that prior request and impliedly
    found that it failed to adequately capture Central's damages,
    and we see no grounds to conclude that such a finding was
    clearly erroneous.
    17
    own acts or omissions, or those of a third party for whom the
    defendant is not responsible.     See Raytheon Co., 
    305 F.3d at 1366
    .     However, although Suffolk purports to object to the
    judge's findings on the fourth element, as none of the alleged
    deficiencies now cited by Suffolk concerns that element, there
    is no basis for disturbing the judge's ruling in that regard.
    4.     Central's cross appeal.   In addition to seeking damages
    for loss of productivity, Central sought to recover $83,538 from
    Suffolk for unpaid CORs.     The judge rejected that claim,
    determining that Central did not establish that Suffolk had been
    paid for those amounts by the MSCBA, a condition precedent
    contained in what is commonly referred to as the "pay if paid"
    clause of the subcontract.16    While Central suggests that such
    clauses are looked upon with disfavor, it does not maintain that
    the clause is unenforceable.     Instead, it argues that the
    judge's finding was clearly erroneous because (1) some of the
    unpaid CORs were owed directly by Suffolk and not the MSCBA as
    "pass through" expenses and (2) Suffolk had in fact been paid
    16
    The clause provides, in pertinent part:
    "Within ten (10) days after Contractor's receipt of good
    funds from Owner, Contractor shall pay to Subcontractor
    ninety percent (90%) of the value of the Work properly
    performed during the previous month. Receipt of progress
    and/or final payments by the Contractor from the Owner with
    respect to the Work shall be, in each instance, a condition
    precedent to the Subcontractor's rights to receive payment
    from Contractor."
    18
    for some of the CORs by the MSCBA.    At trial, however, Central
    only offered the subject CORs and testimony to the effect that
    it had not received payment for them.     The record, therefore, is
    insufficient to substantiate Central's arguments, never mind a
    conclusion that the judge erred in her findings.
    5.   Attorney's fees.   The judge's awarded Central $471,682
    in attorney's fees pursuant to G. L. c. 149,§ 29.     Suffolk
    claims that it was wrongfully denied discovery prior to the
    entry of that award.   "In general, discovery matters are
    committed to the sound discretion of the trial judge [and will
    be upheld] unless the appellant can demonstrate an abuse of
    discretion that resulted in prejudicial error."     Buster v.
    George W. Moore, Inc., 
    438 Mass. 635
    , 653 (2003).     The discovery
    Suffolk sought here focused on whether Central had been billed,
    and had paid, the fees it was seeking to recover.17    The
    reasonableness of an application for attorney's fees, however,
    does not turn on whether the fees requested were billed for
    and/or paid, "but, rather, on what [the attorney's] services
    were objectively worth."     Heller v. Silverbranch Constr. Corp.,
    
    376 Mass. 621
    , 629 (1978).    Given that the discovery requested
    was not essential to the ultimate issue to be decided, it was
    17
    Central sought $622,300 in attorney’s fees and $24,628.94
    in disbursements. The judge reduced the fees by twenty-five
    percent and declined to award any amount for disbursements.
    19
    not an abuse of discretion to deny it.   Additionally, the judge
    was aware of the discovery Suffolk was seeking and that Central
    had not submitted any legal invoices or evidence of payment in
    support of its fee application.   The issue Suffolk sought to
    raise, therefore, was before the court for consideration.
    Consequently, even if the denial of the discovery amounted to an
    abuse of discretion, Suffolk was not prejudiced thereby.
    Suffolk further claims that the judge erred by declining to
    hold a hearing on the fee application.   A party typically is
    entitled to a hearing regarding the reasonableness of an
    attorney's fee request, but only if it requests one.    See
    Manganaro Drywall, Inc. v. White Constr. Co., 
    372 Mass. 661
    , 666
    (1977).   The only reference Suffolk made to a hearing was buried
    in the conclusion of its seventeen-page opposition to the fee
    application, and even that did not amount to a "request" for a
    hearing.18   A hearing, therefore, was not required.   Moreover,
    Suffolk submitted a lengthy opposition to the fee application,
    and the judge's decision awarding the fees reflects that she not
    only considered Suffolk's objections, she adopted some of them.19
    18
    The judge intimated in an order establishing the
    procedure for the fee application that a hearing would be held.
    Nonetheless, Suffolk still should have requested a hearing if it
    intended to insist on one.
    19
    Suffolk filed a motion for reconsideration of both the
    fee award and denial of discovery, which was reviewed and denied
    by a second Superior Court judge due to the trial judge's
    20
    Indeed, Suffolk has not identified any objection that it was
    prevented from raising as a result of the absence of a hearing.
    Accordingly, Suffolk has not established that it was prejudiced
    thereby.20
    Central's entitlement to attorney's fees, which arises from
    G. L. c. 149, § 29, extends to the appellate process. See
    Manganaro Drywall, 372 Mass. at 667.     Central has included a
    request for such fees in its brief.    If the parties cannot agree
    upon an appropriate amount of fees, they shall follow the
    process prescribed in Fabre v. Walton, 
    441 Mass. 9
    , 10–11
    (2004).   Central shall submit its request to this court, with
    supporting materials, within fourteen days of the date of the
    rescript.    Suffolk and the surety defendants shall submit any
    opposition within ten days thereafter.
    Judgment and amended judgment
    for attorney's fees
    affirmed.
    retirement. The second judge found that the trial judge "gave
    full and careful consideration to each of the issues [Suffolk]
    presented." We agree.
    20
    To the extent the parties raise other issues in their
    briefs, they have not been overlooked. "We find nothing in them
    that requires discussion." Commonwealth v. Domanski, 
    332 Mass. 66
    , 78 (1954).