Sheehan v. Modern Continental/Healy , 62 Mass. App. Ct. 937 ( 2005 )


Menu:
  • *938We agree with the subcontractor that the contractor was not entitled to summary judgment. Indemnity agreements in construction contracts are subject to G. L. c. 149, § 29C, as appearing in St. 1986, c. 557, § 135, which renders void any provision requiring a subcontractor to indemnify another for injury “not caused by the subcontractor, or its employees, agents or subcontractors.” Here, the parties’ indemnity agreement purports to require the subcontractor to indemnify the contractor for claims and expenses attributable to injury “caused or alleged to be caused in whole or in part by any negligent act or omission of the [subcontractor” (emphasis supplied). However, the language “alleged to be caused” exceeds what is permissible under G. L. c. 149, § 29C. A contractor may not base a claim for indemnity upon mere allegations of the subcontractor’s responsibility, because to do so could result in indemnification for injury or damage “not caused by the subcontractor.” The judge therefore erred in finding that the indemnification clause did not violate G. L. c. 149,

    § 29C, and that it can be triggered by an allegation in the contractor’s complaint.

    The indemnity provision does not fail as a whole, because the offending portion may be excised.2 Under what remains, the contractor may be indemnified, but only if it is established that a negligent act or omission of the subcontractor “caused” the injury in question.3 Because there remained disputed issues of fact as to whether any negligence of the subcontractor played a role in causing Sheehan’s injuries, summary judgment on the contractor’s claim for indemnity was not appropriate.

    Nor was it appropriate for the judge to order, as provided in the judgment, that the subcontractor immediately assume the contractor’s defense and reimburse the contractor for its past defense costs. It is true that the subcontract contained separate language which required the subcontractor to defend the contractor from claims arising out of the performance of the subcontract. Such language may be enforceable even when a related indemnity provision runs afoul of G. L. c. 149, § 29C. See Herson v. New Boston Garden Corp., 40 Mass. App. Ct. 779, 786-787 (1996). In this case, however, there was no basis for imposing upon the subcontractor an immediate duty to defend. Sheehan alleged nothing in his complaint to suggest the subcontractor’s involvement in his injuries. See Miley v. Johnson & Johnson Orthopaedics, Inc., 41 Mass. App. Ct. 30, 34 (1996). Nor did the summary judgment record establish, as a matter of undisputed fact, any extrinsic basis for triggering the subcontractor’s duty to defend. Mere allegations in the contractor’s third-party complaint were not sufficient to give rise to a defense obligation on the part of the subcontractor.

    Richard W. Jensen for K.C. Electric Company, Inc. John F. Leahy, Jr., for Modem Continental/Healy.

    The judgment is reversed and the case remanded for further proceedings consistent with this opinion.

    So ordered.

    The indemnity agreement contains a “savings” clause limiting its scope “[t]o the fullest extent permitted by law.” This language permits its enforcement to the extent permitted by G. L. c. 149, § 29C. See Callahan v. A.J. Welch Equip. Corp., 36 Mass. App. Ct. 608, 611 (1994).

    Although the statutory phrase “caused by” has been held to include conduct that does not necessarily involve negligence, this indemnity agreement specifies negligence, and it is that standard that applies. See Erland Constr. Co. v. Park Steel Corp., 41 Mass. App. Ct. 919, 920 (1996).

Document Info

Docket Number: No. 03-P-1507

Citation Numbers: 62 Mass. App. Ct. 937

Filed Date: 1/20/2005

Precedential Status: Precedential

Modified Date: 6/25/2022