Bickford's Family Restaurants, Inc. v. Waltham Ventures, LLC. ( 2023 )


Menu:
  • NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule
    23.0, as appearing in 
    97 Mass. App. Ct. 1017
     (2020) (formerly known as rule 1:28,
    as amended by 
    73 Mass. App. Ct. 1001
     [2009]), are primarily directed to the parties
    and, therefore, may not fully address the facts of the case or the panel's
    decisional rationale. Moreover, such decisions are not circulated to the entire
    court and, therefore, represent only the views of the panel that decided the case.
    A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25,
    2008, may be cited for its persuasive value but, because of the limitations noted
    above, not as binding precedent. See Chace v. Curran, 
    71 Mass. App. Ct. 258
    , 260
    n.4 (2008).
    §§ COMMONWEALTH OF MASSACHUSETTS
    APPEALS COURT
    22-P-6
    BICKFORD'S FAMILY RESTAURANTS, INC.
    vs.
    WALTHAM VENTURES, LLC.
    MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
    This case arises from a real estate contract dispute.               The
    plaintiff, Bickford's Family Restaurants, Inc., which operated a
    restaurant in Waltham, assigned the purchase option in its
    commercial lease1 to the defendant, Waltham Ventures, LLC.                In
    addition to other consideration, the defendant agreed to a
    deferred payment2 in the amount of $200,000, less credits,
    subject to conditions discussed infra.           Three years later, after
    an inquiry by the plaintiff regarding status of the deferred
    payment, the defendant stated its belief that, per the terms of
    the parties' written agreement (contract), it did not owe the
    1 The original lease was between the plaintiff and an entity
    named DPS Waltham Development, LLC, which is not a party to this
    appeal.
    2 The deferred payment was, at times, referred to as a "kicker"
    payment.
    deferred payment because it had refinanced a loan secured by the
    property without netting any funds in excess of the payoff
    balance.   The plaintiff sued, seeking enforcement of the
    deferred payment clause and damages under G. L. c. 93A.        A
    Superior Court judge granted summary judgment in favor of the
    plaintiff on the breach of contract claim and permitted the
    c. 93A claim to proceed to trial.     After a bench trial, a
    different Superior Court judge found for the defendant on the
    c. 93A claim and ordered the plaintiff to pay fees and costs.
    Both parties cross-appealed.    Discerning no error, we affirm.
    Discussion.    1.   Summary judgment.   On appeal, the
    defendant argues that the motion judge should not have granted
    summary judgment to the plaintiff as to the breach of contract
    claim because (1) the language of the contract unambiguously
    supported the defendant's position and (2) summary judgment was
    inappropriate insofar as the judge had concluded that certain
    provisions of the contract conflict.    We are not persuaded.
    "Our review of a motion judge's decision on summary
    judgment is de novo, because we examine the same record and
    decide the same questions of law."    G4S Tech. LLC v.
    Massachusetts Tech. Park Corp., 
    479 Mass. 721
    , 730 (2018),
    quoting Kiribati Seafood Co. v. Dechert LLP, 
    478 Mass. 111
    , 116
    (2017).    "The standard of review of a grant of summary judgment
    is whether, viewing the evidence in the light most favorable to
    2
    the nonmoving party, all material facts have been established
    and the moving party is entitled to judgment as a matter of
    law."   G4S Tech. LLC, 
    supra,
     quoting Casseus v. Eastern Bus Co.,
    
    478 Mass. 786
    , 792 (2018).
    "A contract is a promise or a set of promises for the
    breach of which the law gives a remedy, or the performance of
    which the law in some way recognizes as a duty."    Sea Breeze
    Estates, LLC v. Jarema, 
    94 Mass. App. Ct. 210
    , 215 (2018),
    quoting I & R Mechanical, Inc. v. Hazelton Mfg. Co., 
    62 Mass. App. Ct. 452
    , 454 (2004).    "When contract language is
    unambiguous, it must be construed according to its plain
    meaning."   Balles v. Babcock Power Inc., 
    476 Mass. 565
    , 571
    (2017).   "To determine whether the language at issue is
    ambiguous, we look both to the contested language and to the
    text of the contract as a whole."    
    Id. at 572
    .
    Here, we agree with the motion judge that the language of
    paragraph 22 of the contract unambiguously supports summary
    judgment in the plaintiff's favor.    Paragraph 22 of the contract
    states in full:
    "Upon the earlier of (a) the third anniversary of the
    Closing, or (b) the occurrence of a Capital Transaction,
    Buyer shall pay Seller the Deferred Payment in the amount
    of Two Hundred Thousand Dollars ($200,000.00), less credits
    due to Buyer for (x) one-half (1/2) of the first six Non-
    refundable Option Payments made hereunder, and (y) any
    payments made by Buyer on account of Seller's failure to
    perform its obligations hereunder, including the Lease. As
    used herein, the term "Capital Transaction" shall mean the
    3
    Buyer's sale of all, or substantially all of its interest
    in the Property, either directly or [through] a transfer of
    a membership interest in Buyer or a financing transaction
    resulting in the recording of a mortgage or other security
    instrument against the Property after completion of the
    initial construction of the Project[], where such financing
    transaction pays Buyer a net amount of $1,000,000.00 or
    more over the payoff balance of the existing mortgage. If
    the net amount received by Buyer is less th[a]n
    $1,000,000.00 then the Deferred Payment amount required to
    be paid at the time of the financing transaction shall be
    reduced proportionately by the ratio of net amount received
    by Buyer divided by $1,000,000. This obligation shall
    survive the closing."
    The plain language of this paragraph indicates that, given
    the parties' agreement that no sale of the property has occurred
    and that three years have passed since the defendant closed on
    the property, the defendant must show, at a minimum, a genuine
    issue of material fact regarding whether a new mortgage or
    security had been recorded against the property in order to
    avoid summary judgment on the claim of breach of contract.    See
    Sea Breeze Estates, LLC, 94 Mass. App. Ct. at 215.   It has
    failed to do so.   See id. at 216-218 (summary judgment
    appropriate where party fails to show genuine issue of material
    fact regarding contract terms).
    Paragraph 22 defines a "capital transaction" as, inter
    alia, "a financing transaction resulting in the recording of a
    mortgage or other security instrument."   The undisputed record
    reflects that the defendant's April 10, 2014 agreement with RBS
    Citizens, N.A., titled "Amendment to Construction Mortgage,
    4
    Assignment of Leases and Security Agreement and Other Loan
    Documents," was an amendment of the existing mortgage between
    those parties, rather than a new mortgage.   Indeed, the
    defendant concedes as much in its brief.   Because the amendment
    did not result in the recording of a new mortgage or other
    security instrument, it was not a capital transaction as defined
    by paragraph 22.   Therefore, the defendant's failure to generate
    any additional funds through the refinancing and amendment of
    its existing mortgage did not eliminate its obligation to make
    the deferred payment.
    The defendant further argues that summary judgment was
    improper because the judge concluded that certain provisions of
    paragraph 22 in the contract conflict and there was a factual
    dispute as to the evidence necessary to harmonize that conflict.
    We are not convinced.   See G4S Tech. LLC, 
    479 Mass. at 730
    .
    Assuming without deciding that any conflict in the plain meaning
    of the contract language exists, such a conflict only deals with
    the extent to which the payment would be reduced in the event
    that a capital transaction occurred.3   The plain language of the
    contract, however, shows that a capital transaction did not
    occur, meaning that any reduction of payment in the event of
    such an occurrence is immaterial to the grant or denial of a
    3 The defendant has not explicitly identified any other conflict
    in its brief before this panel.
    5
    motion for summary judgment. See Balles, 
    476 Mass. at 571
    .      See
    also G4S Tech. LLC, 
    479 Mass. at 730
    .
    2.   Chapter 93A.   On cross appeal, the plaintiff argues
    that the trial judge's findings do not support his decision to
    award judgment to the defendant on the c. 93A claim.    We
    disagree.
    "General Laws c. 93A, § 11, prohibits unfair or deceptive
    acts or practices among those engaged in trade or commerce."
    Diamond Crystal Brands, Inc. v. Backleaf, LLC, 
    60 Mass. App. Ct. 502
    , 506-507 (2004), citing Anthony's Pier Four, Inc. v. HBC
    Assocs., 411 Mass 451, 474 (1991).    "Not every breach of
    contract constitutes a violation of G. L. c. 93A, but a knowing
    violation of contractual obligations for the purpose of securing
    unwarranted benefits does" (citation omitted).    Diamond Crystal
    Brands, Inc., 
    supra at 507
    .    "Courts must consider whether the
    nature, purpose, and effect of the challenged conduct is
    coercive or extortionate."    
    Id.,
     citing Massachusetts Employers
    Ins. Exch. v. Propac-Mass, Inc., 
    420 Mass. 39
    , 42-43 (1995).
    "The standard of review is well established.     The findings
    of fact of the judge are accepted unless they are clearly
    erroneous.   We review the judge's legal conclusions de novo"
    (citation omitted).   T.W. Nickerson, Inc. v. Fleet Nat'l Bank,
    
    456 Mass. 562
    , 569 (2010).    "In an action alleging violations of
    G. L. c. 93A, 'whether a particular set of acts, in their
    6
    factual setting, is unfair or deceptive is a question of fact.'"
    H1 Lincoln, Inc. v. South Washington St., LLC, 
    489 Mass. 1
    , 13-
    14 (2022), quoting Casavant v. Norwegian Cruise Line Ltd., 
    460 Mass. 500
    , 503 (2011).   "But whether conduct found to be unfair
    or deceptive 'rises to the level of a chapter 93A violation is a
    question of law.'"   H1 Lincoln, Inc., supra at 14, quoting Baker
    v. Goldman, Sachs & Co., 
    771 F.3d 37
    , 49 (1st Cir. 2014).
    Here, the plaintiff does not contest the trial judge's
    findings of fact.    Instead, it argues that the facts found by
    the judge require a finding that the defendant's actions
    constituted a violation of c. 93A.   We disagree.   Admittedly,
    the trial judge was highly condemnatory of the defendant's
    conduct.   He stated, among other things, that the defendant's
    manager had made "a significant error in understanding the
    contract," that the manager's position on the dispute was
    "extremely weak," that "[h]is interpretation of the contract was
    baseless," that his signing the contract while "not
    understanding a key provision" was "unreasonable" and that
    "[h]is refusal to pay was also unreasonable."    The judge further
    found that "[t]hese unreasonable positions were adopted after
    [the manager] realized his error [in misunderstanding the
    agreement]."   However, the trial judge explicitly rejected the
    plaintiff's request for findings that the manager's actions were
    "extortionate in intent and effect" and that the defendant
    7
    "simply did not want to pay [the plaintiff] and came up with an
    excuse to justify avoiding its contractual obligations."
    Furthermore, the judge found that the manager's "understanding
    of the contractual agreement was that he would not have to pay a
    'kicker' or bonus to the plaintiff if it took him longer than
    three years to make a big profit," and that the manager "entered
    into a written contract contrary to what he thought he was
    agreeing to."
    Taken together, these findings show that, while
    unreasonable, the defendant's behavior was the result of an
    honest disagreement about the terms of the contractual
    obligations.        However incompetent, the defendant's conduct was
    nothing more than the product of genuine misunderstanding as to
    the meaning and effect of paragraph 22.       Without more, we cannot
    conclude that the defendant's conduct constituted a violation of
    c. 93A.     See Diamond Crystal Brands, Inc., 60 Mass. App. Ct. at
    507.
    3.   Fees.    Declining to reverse the trial judge's ruling
    with respect to the c. 93A claim, we further decline to vacate
    the attorney's fees awarded to the defendant for costs incurred
    in its defense of the plaintiff's c. 93A claim.        Under paragraph
    26 (d) of the contract, the "prevailing party" in any litigation
    arising under the agreement "shall be awarded its costs
    including reasonable attorney's fees."       The defendant is the
    8
    "prevailing party" as to the c. 93A claim.4,5   See Northern
    Assocs. v. Kiley, 
    57 Mass. App. Ct. 874
    , 880-881 (2003), quoting
    Bardon Trimount, Inc. v. Guyott, 49 Mass. App Ct. 764, 778-780
    (2000) ("litigant in whose favor judgment enters is 'prevailing
    party'").   We decline to award attorney's fees to either party
    for costs associated with this appeal.
    Judgment affirmed.
    By the Court (Neyman,
    Desmond & Grant, JJ.6),
    Clerk
    Entered:    May 24, 2023.
    4 We are unpersuaded by the plaintiff's argument that it is the
    prevailing party because it succeeded on the "ultimate issue" of
    the breach of contract claim. The underlying suit consisted of
    two separate claims, breach of contract and violation of c. 93A,
    and the defendant prevailed on the latter claim. See Northern
    Assocs., 57 Mass. App. Ct. at 880-881.
    5 We likewise reject the plaintiff's argument that the judge
    erred in finding that the c. 93A claim "arose from the terms of
    the agreement." Where the plaintiff's complaint alleged that
    the defendant violated c. 93A by, inter alia, "refusing to
    tender the deferred payment," "ignoring the plain meaning of
    Paragraph 22 of the Assignment," and ultimately "engag[ing] in
    conduct in disregard of known contractual arrangements," we
    conclude that the c. 93A claim constitutes "any litigation
    arising under the terms of this Agreement" pursuant to paragraph
    26 (d). Contrast Hannon v. Original Gunite Aquatech Pools,
    Inc., 
    385 Mass. 813
    , 828 (1982) (contract provision entitled
    prevailing party to attorney's fees "in an action brought to
    determine or enforce rights under the contract").
    6 The panelists are listed in order of seniority.
    9