Arruda v. Newport Construction Corporation ( 2023 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    22-P-716                                              Appeals Court
    JOAN ARRUDA     vs.   NEWPORT CONSTRUCTION CORPORATION.
    No. 22-P-716.
    Middlesex.       February 14, 2023. – July 21, 2023.
    Present:       Henry, Shin, & Hodgens, JJ.
    Negligence, Duty to prevent harm, Causation. Way, Public:
    defect. Practice, Civil, Summary judgment.
    Civil action commenced in the Superior Court Department on
    April 23, 2018.
    The case was heard by Christopher K. Barry-Smith, J., on a
    motion for summary judgment.
    Robert I. Feinberg (Colleen M. Santora also present) for
    the plaintiff.
    Steven C. Kennedy for the defendant.
    HODGENS, J.     While walking into a crosswalk with her
    granddaughter at dusk, the plaintiff caught her foot on a
    protruding granite block, fell, and sustained injuries.       This
    granite block formed part of a decorative margin for the
    crosswalk and should have been flush with the surrounding
    2
    roadway, but the defendant construction contractor caused the
    margin to protrude above the roadway by one-half inch.     The
    defendant intended to repair the defect months later when
    applying the final course of asphalt but provided no warning to
    pedestrians at the time of the incident.    After the plaintiff
    filed a complaint alleging negligence, a Superior Court judge
    allowed the defendant's motion for summary judgment and
    concluded that the one-half inch defect was "too minor or
    insubstantial" to support a negligence claim.    We vacate the
    judgment and remand for further proceedings.
    Background.     We summarize the facts in the light most
    favorable to the plaintiff, Joan Arruda, as the party opposing
    summary judgment.    See FBT Everett Realty, LLC v. Massachusetts
    Gaming Comm'n, 
    489 Mass. 702
    , 704 (2022).   See Mass. R. Civ.
    P. 56 (c), as amended, 
    436 Mass. 1404
     (2002).    Newport
    Construction Corporation (Newport), the defendant construction
    contractor, reconstructed four streets in Cambridge, including
    Thorndike Street.    Prior to September 8, 2017, Newport excavated
    the existing asphalt roadway and cobblestone base of Thorndike
    Street, laid a new gravel base, and covered the base with a
    "binder" course of asphalt.    This binder course left a one-
    quarter to one-half inch difference in elevation between the
    granite margin of the crosswalk and the roadway surface.    A
    passenger in a vehicle would "barely feel" the protrusion when
    3
    driving over the crosswalk and approaching the stop sign at the
    intersection.   Newport planned to apply in the spring a final
    course of asphalt that would make the roadway surface flush with
    the protruding granite margin of the crosswalk.
    At about 6 P.M., on September 8, 2017, Arruda walked
    through Cambridge with her granddaughter to attend a
    neighborhood festival.   As they diagonally crossed Thorndike
    Street into the crosswalk, Arruda caught her foot on the
    protruding granite margin, fell, and sustained injuries.    At the
    time of the incident, the granite protrusion was not highlighted
    by any traffic cones, warning signs, or paint.
    Arruda filed a complaint in the Superior Court and claimed
    that Newport negligently maintained the roadway and walkway and
    failed to provide a warning of the defect.     A Superior Court
    judge allowed Newport's motion for summary judgment.    The judge
    concluded, "In the context of resurfacing a street, that one-
    half inch difference in elevation is sufficiently small that a
    reasonable person -- namely, the street contractor -- would not
    anticipate injury and guard against it."
    Discussion.   "Ordinarily, 'summary judgment is not an
    appropriate means to resolve negligence cases, because usually
    the question of negligence is one of fact.'"     Doe v. Boston Med.
    Ctr. Corp., 
    88 Mass. App. Ct. 289
    , 291 (2015), quoting Roderick
    v. Brandy Hill Co., 
    36 Mass. App. Ct. 948
    , 949 (1994).     A viable
    4
    negligence claim consists of four elements:    "[(1)] [the]
    defendant owes a duty of reasonable care to the plaintiff,
    [(2)] the defendant committed a breach of that duty, [(3)] the
    plaintiff suffered damage, and [(4)] a causal relationship
    existed between the breach of duty and the damage."     Heath-
    Latson v. Styller, 
    487 Mass. 581
    , 584 (2021).     While the
    existence of a duty is a question of law, the remaining elements
    are considered "to be the special province of the jury."        Jupin
    v. Kask, 
    447 Mass. 141
    , 146 (2006).     "[A] party moving for
    summary judgment in a case in which the opposing party will have
    the burden of proof at trial is entitled to summary judgment if
    he demonstrates . . . that the party opposing the motion has no
    reasonable expectation of proving an essential element of that
    party's case."    Kourouvacilis v. General Motors Corp., 
    410 Mass. 706
    , 716 (1991).    We review the judge's summary judgment
    decision "de novo."     Kennedy v. Abramson, 
    100 Mass. App. Ct. 775
    , 777 (2022).
    Newport has not demonstrated that Arruda has no reasonable
    expectation of proving an essential element of her negligence
    case.     The record shows that Newport was a contractor in the
    process of reconstructing Thorndike Street.    As a matter of law,
    Newport owed a duty of care to pedestrians, like Arruda, who
    walked across that street and encountered the construction
    defect.    See Meyer v. Veolia Energy N. Am., 
    482 Mass. 208
    , 209
    5
    (2019) (contractor that "created a particular defect" in roadway
    subject to negligence claim of injured bicyclist); Seltzer v.
    Amesbury & S. Gas Co., 
    188 Mass. 242
    , 244 (1905) (liability was
    based on contractor's act of "digging a pit and leaving it
    insufficiently or improperly filled, thus creating an
    obstruction to public travel").   Viewed in a light most
    favorable to Arruda, the record also contained factual support
    for the remaining elements of her negligence claim.   Newport
    knew about the protruding "lip" of the granite margin and
    planned to eliminate it in the spring through the application of
    a final course of asphalt that would make the roadway surface
    flush with the granite.   At the time of the incident, the
    granite protrusion lacked any traffic cones, warning signs, or
    paint.   As Newport's construction manager put it, he believed
    paint was not necessary because the protrusion was "not in a
    pedestrian path of travel."   Arruda and her granddaughter
    diagonally crossed Thorndike Street into the crosswalk where
    Arruda caught her foot on the protruding granite margin, fell,
    and sustained injuries.   Jurors need to sift through these facts
    and weigh the evidence to decide whether Newport's conduct
    amounted to a breach of its duty of care and caused the injury
    to Arruda.   See Regan v. John J. Amara & Sons Co., 
    348 Mass. 734
    , 737 (1965) ("jury could have found that [contractor] knew
    or ought to have known of the defective condition of the street
    6
    and was negligent in failing to take adequate precautions");
    Scholl v. New England Power Serv. Co., 
    340 Mass. 267
    , 270 (1960)
    (jury question presented where contractor "fail[ed] to warn
    travellers of the excavation" in city street).
    Contrary to Newport's claim, the height of the defect,
    standing alone, is not determinative of the negligence claim as
    a matter of law.   Newport contends that the half-inch protrusion
    of the granite margin above the binder layer of asphalt was "too
    minor or insubstantial to support a negligence claim."    Rather
    than focusing exclusively on the height of the protrusion, the
    "necessary inquiry is whether the defect is so minor or
    insubstantial that a reasonable person would not have
    anticipated injury and guarded against it."   Doherty v. Belmont,
    
    396 Mass. 271
    , 275 (1985).   This broader inquiry, under the
    reasonable person standard, focuses not just on the height of
    the defect but also on its origin, location, and duration.
    Properly focused, the inquiry shows that Newport's application
    of the binder course of asphalt to the roadway surface left the
    protrusion (or "lip") of the granite margin along the edge of
    the crosswalk.   According to the construction manager, a final
    layer of asphalt could have been applied over the binder layer
    "the next day," but "the scope of the project" called for
    leaving the protrusion in place for a "longer duration" until
    the spring.   In the interim, the protrusion lacked any warning
    7
    of its unfinished, defective condition at the time of Arruda's
    injury.    Based on the record here, a jury could conclude that
    Newport was aware,1 or should have been aware, of the defect and
    should have anticipated a potential injury, but "nonetheless
    failed to take steps to eliminate this risk" through adequate
    warnings or other remedial action.    
    Id.
       Whether such a
    conclusion should ultimately be drawn is a factual question
    within "the special province of the jury."    Jupin, 
    447 Mass. at 146
    .
    Newport's creation of the protruding granite margin and
    knowledge of the defect distinguish this case from those in
    which liability cannot be imposed for insignificant conditions.
    See Pastrick v. S.S. Kresge Co., 
    288 Mass. 194
    , 195, 197 (1934)
    ("no defect and no unusual danger" where "sum of the width and
    height in the stairway in question gave 'an abnormally high
    cadence' to the pacing of an ordinary person"); Rosenthal v.
    Central Garage of Lynn, Inc., 
    279 Mass. 574
    , 575 (1932) (shiny
    and smooth condition of stair treads that was "merely as the
    result of wear" did not constitute defect that rendered stairs
    unsafe); Douglas v. Shepard Norwell Co., 
    217 Mass. 127
    , 130
    (1914) (loose carpet and gradual, slight ridge did not
    The construction manager also testified that the
    1
    protruding granite "probably was painted" at some time, but
    likely wore off by the time of the incident.
    8
    constitute defect "which the defendant ought to have
    discovered"); Ware v. Evangelical Baptist Benevolent &
    Missionary Soc'y of Boston, 
    181 Mass. 285
    , 286-287 (1902) (step
    from hallway into adjoining room "cannot be regarded as
    defective"); Jennings v. Tompkins, 
    180 Mass. 302
    , 302-303 (1902)
    ("there is not a defect" from nail protruding 3/16 of inch from
    step due to natural wear).
    The present case is also distinguishable from cases cited
    by Newport involving municipal defendants.   Municipal defendants
    are aided by a statute that limits liability for injuries
    resulting from defects in public ways.   See G. L. c. 84, § 15
    (road-defect statute).   That statute embodies the public policy
    that municipalities "should not be liable for slight or trivial
    imperfections in public ways which might be caused by weather
    conditions or traffic patterns."   Doherty, 
    396 Mass. at 275
    .
    Newport, however, is not a municipality subject to the road-
    defect statute, and the alleged defect here was caused by
    Newport, not weather conditions or traffic patterns.   Contrast
    Galante v. Brockton, 
    305 Mass. 480
    , 481 (1940) (city not liable
    for injury to pedestrian who fell due to "slight sinking and
    tipping of the curb" away from the sidewalk where requirement of
    "perfect alignment would bear heavily upon municipalities");
    Vellante v. Watertown, 
    300 Mass. 207
    , 208 (1938) (town not
    liable for injury to pedestrian who stumbled on tilting sidewalk
    9
    perhaps caused by "freezing and thawing of the ground" where
    "actionable defect would cast an undue burden upon
    municipalities").2
    Newport asks us to extend the road-defect statute and
    standards of limited municipal liability to its own conduct
    because the burden placed on a contractor will inevitably be
    passed along to a municipality through a higher contract price.
    We decline to do so.   The Supreme Judicial Court has limited the
    reach of the road-defect statute, and cases imposing liability
    under it, to "the county, city, town, or person required to
    perform the public duty of maintaining the way and not to a
    private corporation that causes a defect in the way, even where
    the private entity has been authorized by a governmental entity
    to perform a particular function causing a defect in the way."
    Meyer, 
    482 Mass. at 218
    .   Stated another way, the road-defect
    2 Other cases cited by Newport are also inapposite. See
    Swenson v. Boston, 
    317 Mass. 295
    , 295-296 (1944) (city not
    liable for injury to pedestrian who tripped on streetcar rail
    protruding two inches above roadway where actionable defect
    would "cast an undue burden on municipalities"); Rowett v. North
    Adams, 
    288 Mass. 50
    , 50-51 (1934) (city not liable for injury to
    pedestrian who stepped in hole while crossing paved street where
    testimony did not describe the "area, depth, or other features
    of the so-called 'hole'"); Beaumier v. Heath, 
    282 Mass. 312
    ,
    313, 315-316 (1933) (town not liable for injury to vehicle
    passenger caused by hole in cobblestone road where town lacked
    reasonable notice of defect and opportunity to repair); Newton
    v. Worcester, 
    174 Mass. 181
    , 188 (1899) (city not liable for
    injury to pedestrian who fell on brick sidewalk where varying,
    smooth depressions up to two inches did not render sidewalk
    unsafe).
    10
    statute "applies only to those entities that have a public duty
    to maintain the way, not to private parties causing particular
    defects."   
    Id. at 221
    .
    Conclusion.   Summary judgment is sometimes but "rarely"
    warranted in negligence cases, which usually present questions
    of fact for the jury.     Zavras v. Capeway Rovers Motorcycle Club,
    Inc., 
    44 Mass. App. Ct. 17
    , 21 (1997).    This is not such a rare
    case.   The judgment for Newport is vacated, and the matter is
    remanded to the Superior Court for further proceedings
    consistent with this opinion.
    So ordered.