LUCIUS HILL & Another v. CONSERVATION COMMISSION OF FALMOUTH. ( 2023 )


Menu:
  • NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule
    23.0, as appearing in 
    97 Mass. App. Ct. 1017
     (2020) (formerly known as rule 1:28,
    as amended by 
    73 Mass. App. Ct. 1001
     [2009]), are primarily directed to the parties
    and, therefore, may not fully address the facts of the case or the panel's
    decisional rationale. Moreover, such decisions are not circulated to the entire
    court and, therefore, represent only the views of the panel that decided the case.
    A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25,
    2008, may be cited for its persuasive value but, because of the limitations noted
    above, not as binding precedent. See Chace v. Curran, 
    71 Mass. App. Ct. 258
    , 260
    n.4 (2008).
    COMMONWEALTH OF MASSACHUSETTS
    APPEALS COURT
    22-P-581
    LUCIUS HILL & another 1
    vs.
    CONSERVATION COMMISSION OF FALMOUTH.
    MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
    The plaintiffs, Lucius and Wendy Hill, appeal from the
    judgment of a Superior Court judge upholding the decision of the
    conservation commission of Falmouth (commission) denying an
    application for an order of conditions for construction of a new
    walkway leading to an existing dock in West Falmouth harbor.                 We
    affirm.
    In addition to the Wetlands Protection Act, G. L. c. 131,
    § 40 (WPA), the town of Falmouth regulates wetlands through a
    local wetlands protection bylaw, chapter 235 of the town's code
    (wetlands bylaw), and the commission's Falmouth wetland
    regulations (FWR).       The plaintiffs submitted a notice of intent
    under the WPA, wetlands bylaw, and the FWR, seeking permission
    1   Wendy Hill.
    to construct an elevated walkway to reach their existing
    licensed concrete ramp and float. 2   Section 10.16 (h) of the FWR
    provides "general requirements" and "prohibitions" applicable to
    all docks and piers.   Section 10.16 (h) (1) provides that:
    "No new docks or piers or extension of an existing dock or
    pier may be constructed in any portion of [a] FEMA
    designated velocity zone (V-Zone) unless the applicant
    demonstrates that there will be public benefit from the
    project. The Commission shall weigh the potential
    likelihood of damage and harm that any such dock or pier
    would cause during a storm event with the public benefit
    demonstrated by the applicant in determining whether the
    project should be allowed."
    While the record does not reveal a specific finding, the
    commission and the parties have all treated the location of the
    proposed walkway as being in a velocity zone, and the plaintiffs
    do not suggest otherwise on appeal.
    After providing proper notice, the commission conducted a
    public hearing over several days.     At one of the first hearing
    dates, some of the members inquired about revegetating the
    existing walking path after the elevated walkway is installed.
    The plaintiffs responded with a letter from a landscape design
    company recommending the planting of 200 salt marsh plugs to
    facilitate restoration.   At the next hearing, the plaintiffs'
    representative informed the commission that the plaintiffs would
    2 According to the commission's meeting minutes, currently there
    is a grass path leading to a solid stone and concrete dock,
    which is surrounded by knee-high water at times.
    2
    install salt marsh material as recommended by the landscape
    design company.    Before the commission voted, it was noted that
    the plan proposed an expansion of a dock in a velocity zone and
    that planting plugs was recommended to enhance the salt marsh
    after construction of the walkway.    Indeed, one of the members
    of the commission noted prior to the vote that "[i]t will be a
    better environment because the salt marsh will fill in.      It's
    better for Falmouth to have the project than not to have it."
    Another member commented, however, that "[t]here is value of the
    salt marsh and the value of the velocity zone.    The structure
    should be prohibited because of the damage that will be done
    when the structure is ripped out in a storm and does harm to the
    resources."
    On February 24, 2021, a motion was made to grant the order
    of conditions.    The commission voted, but the vote failed to
    carry a majority of the commission, and therefore, the
    application was considered denied.    On February 26, 2021, the
    commission issued a written decision signed by a majority
    explaining its reasons for denying the application.    The
    decision set forth the commission's finding that the proposed
    walkway is an "extension" of the existing dock and explained
    that no extension of a dock is allowed in the velocity zone
    unless the applicant demonstrates a public benefit, and the
    3
    plaintiffs did not demonstrate how there will be a public
    benefit from the proposed project.
    The plaintiffs filed a certiorari appeal pursuant to G. L.
    c. 249, § 4, in the Superior Court.     On cross motions for
    judgment on the pleadings, the judge granted the commission's
    motion, affirming the commission's decision and dismissing the
    appeal.    This appeal followed.
    Discussion.   "In a review under certiorari, the court is
    limited to correcting 'substantial errors of law apparent on the
    record adversely affecting material rights'" (citation omitted).
    FIC Homes of Blackstone, Inc. v. Conservation Comm'n of
    Blackstone, 
    41 Mass. App. Ct. 681
    , 684 (1996).     We review a
    decision allowing a motion for judgment on the pleadings de
    novo.   Delapa v. Conservation Comm'n of Falmouth, 
    93 Mass. App. Ct. 729
    , 733 (2018).    "In an action in the nature of certiorari
    challenging a wetlands permit decision made by a conservation
    commission pursuant to a local by-law, our review is limited at
    most to whether the commission's decision is supported by
    substantial evidence in the administrative record, whether the
    commission's action was arbitrary and capricious, and whether
    the commission committed an abuse of discretion or other error
    of law."    Id. at 733-734.   With these principles in mind, we
    address the plaintiffs' arguments.
    4
    1.   Sufficiency of the vote.   The plaintiffs first argue
    that when the commission's vote to grant the order of conditions
    did not pass, the commission erred in treating it as a vote to
    deny the order of conditions, and that the proper procedure
    would have been to conduct a second vote specifically on the
    question whether to deny the order of conditions.    They point to
    several sections of the wetlands bylaw and the FWR, none of
    which require two votes in the circumstances presented.    Cf.
    McElderry v. Planning Bd. of Nantucket, 
    431 Mass. 722
    , 722, 727
    (2000) (in absence of affirmative vote by majority of quorum,
    plan disapproved).
    First, the plaintiffs point to § 10.05 (9) (b) of the FWR,
    which discusses "substantive denials" and provides that the
    commission "may deny permission for any activity within areas
    under its jurisdiction if, in its judgment, such denial is
    necessary to protect the Resource area values identified in the
    Bylaw."   It further provides that "[t]he written decision will
    include the reasons for the denial, citing Resource area values
    protected, and relevant regulations.    The written decision will
    be signed by a majority of the Commission."    Contrary to the
    plaintiffs' contention, all of these requirements were met, as
    reflected in the written decision.
    In addition, the plaintiffs point to § 235-7 (B) of the
    wetlands bylaw, which requires that in denying a request for a
    5
    permit, "[d]ue consideration shall be given to any demonstrated
    hardship on the applicant by reason of denial, as presented at
    the public hearing," and argue that because there was no second
    vote, the commission did not consider any "hardship" that the
    plaintiffs would suffer if their application were denied.    The
    FWR defines "hardship" specifically:
    "Hardship means the application of Chapter 235 of the Code
    of Falmouth to a particular piece of property, evaluated in
    its totality, owing to the unique characteristics of the
    property, that is unduly oppressive, arbitrary or
    confiscatory and would involve substantial economic loss to
    the Applicant because of the literal enforcement of the
    Bylaw provided that the Conditions and characteristics of
    the property are not the result of the actions of the
    Applicant, or owner, or their agents, predecessors,
    successors or assignees."
    Nothing in the record suggests that the plaintiffs presented
    evidence at the hearing of a hardship within the foregoing
    definition.   And, in their brief, they point only to their need
    to wade through water to reach their existing dock -- which
    evidence was before the commission when it voted.   The
    commission cannot be faulted for failing to explicitly weigh the
    hardship on the plaintiffs when the plaintiffs presented no
    evidence of harm that would meet the definition of "hardship,"
    or any evidence that they would suffer from a "substantial
    economic loss" because of the application of the wetlands bylaw.
    The plaintiffs also argue that § 10.05 (2) of the FWR was
    violated because the decision was drafted after the vote and the
    6
    commission did not vote on the specific reasons for denial while
    they were at the meeting.    Section 10.05 (2) requires only that
    any action taken by the commission pursuant to "Chapter 235 of
    the Code of Falmouth" "is to be taken by more than half the
    members present at a meeting of at least a quorum."    It does not
    require that the drafting of a written decision occur during the
    meeting.    Where the written decision was signed by more than
    half of the members that were present at the public meeting on
    the plaintiffs' proposal, the regulation was satisfied.
    Finally, the plaintiffs argue that a second vote was
    required because it may not have passed and then the commission
    might have failed to act on the application within twenty-one
    days of the application and lost its jurisdiction to enforce the
    local bylaw and regulations.    See Oyster Creek Preservation,
    Inc. v. Conservation Comm'n of Harwich, 
    449 Mass. 859
    , 866
    (2007).    That outcome, however, is belied by the written
    decision denying the application that was signed by a majority
    of the commission.    In short, the requirement of a written order
    explaining the reasons for the denial eliminates the scenario
    the plaintiffs have contemplated.
    2.    Walkway is an extension of the existing dock.   The
    plaintiffs next contend that the commission's conclusion that
    the proposed walkway is an "extension" of the existing dock is
    based on an erroneous interpretation of the regulations.     As
    7
    noted above, § 10.16 (h) prohibits new structures in the
    velocity zone (in the absence of a public benefit) and applies
    to "new docks or piers or extension[s] of an existing dock or
    pier."     A "dock" is defined in § 10.04 as "the entire structure
    of any Pier, wharf, walkway, bulkhead or float, and any part
    thereof including pilings, ramps, walkways, float and/or tie-off
    pilings."
    The plaintiffs speculate that the prohibition on extensions
    of existing docks is only for "seaward extensions," not to the
    addition of a walkway landward of an existing dock.     Velocity
    zones are defined in the FWR as "those portions of land subject
    to coastal storm flowage which are coastal high hazard areas or
    areas of special flood hazard extending from the inland limit
    within the one-hundred-year floodplain seaward supporting waves
    greater than three feet in height."     By its very definition,
    velocity zones include property that may be inland from the
    dock.     The distinction offered by the plaintiffs is not made in
    the bylaw and we decline to add language to it.     Where the
    plaintiffs do not suggest that the proposed walkway will not be
    in a velocity zone, we discern no reason to conclude that
    § 10.16 (h) does not apply to it.
    3.    Public benefit.   The commission concluded that the
    plaintiffs did not demonstrate how there would be a public
    benefit from the proposed project.     On appeal, the plaintiffs
    8
    contend that there will be a public benefit because the project
    will restore some salt marsh.   They contend that salt marsh
    provides public benefits and assists in controlling storm
    damage, and that the commission should have weighed these
    benefits with the risks of harm from the walkway.
    The meeting minutes reveals that the commission considered
    the planned wetlands restoration and, indeed, reveals that the
    commission members disagreed as to whether the restoration
    offset the potential harm from the elevated walkway.   It was the
    commission's job to determine whether a public benefit would
    arise, and the majority concluded that there was no public
    benefit.   We cannot substitute our judgment on this issue.    See
    Croteau v. Planning Bd. of Hopkinton, 
    40 Mass. App. Ct. 922
    , 924
    (1996) ("The determination of public benefit involves a
    'considerable area of discretion' and it is 'the board's
    evaluation . . ., not the judges, which is controlling'"
    [citation omitted]).   Cf. Wine v. Planning Bd. of Newburyport,
    
    74 Mass. App. Ct. 521
    , 527 (2009) (burden of showing board erred
    in denying waiver because denial was not in public interest
    "nearly insupportable" [citation omitted]).   Where the
    commission concluded that there was no public benefit, the
    plaintiffs' argument that the commission did not weigh the
    public benefit against the likelihood of harm is unavailing.
    9
    Discerning no abuse of discretion or other error of law, we
    affirm the judgment.
    Judgment affirmed.
    By the Court (Sullivan,
    Desmond & Singh, JJ. 3),
    Clerk
    Entered:    August 2, 2023.
    3   The panelists are listed in order of seniority.
    10
    

Document Info

Docket Number: 22-P-0581

Filed Date: 8/2/2023

Precedential Status: Non-Precedential

Modified Date: 8/2/2023