Board of Selectmen of Duxbury v. Webster Point Village, LLC. ( 2023 )


Menu:
  • NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule
    23.0, as appearing in 
    97 Mass. App. Ct. 1017
     (2020) (formerly known as rule 1:28,
    as amended by 
    73 Mass. App. Ct. 1001
     [2009]), are primarily directed to the parties
    and, therefore, may not fully address the facts of the case or the panel's
    decisional rationale. Moreover, such decisions are not circulated to the entire
    court and, therefore, represent only the views of the panel that decided the case.
    A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25,
    2008, may be cited for its persuasive value but, because of the limitations noted
    above, not as binding precedent. See Chace v. Curran, 
    71 Mass. App. Ct. 258
    , 260
    n.4 (2008).
    COMMONWEALTH OF MASSACHUSETTS
    APPEALS COURT
    22-P-810
    BOARD OF SELECTMEN OF DUXBURY
    vs.
    WEBSTER POINT VILLAGE, LLC.
    MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
    The town of Duxbury (town), acting by and through its board
    of selectmen (board), brought this action against developer
    Webster Point Village, LLC (WPV), raising breach of contract and
    related claims. 1     A judge of the Superior Court denied WPV's
    special motion to dismiss brought under the "anti-SLAPP"
    statute.    See G. L. c. 231, § 59H.        WPV appeals from the adverse
    ruling on an interlocutory basis under the doctrine of present
    execution.     See Blanchard v. Steward Carney Hosp., Inc., 
    483 Mass. 200
    , 212-213 (2019) (Blanchard II).            We affirm.
    1 The board's complaint contained the following claims and
    requests for equitable relief: declaratory judgment (count 1),
    breach of contract (count 2), breach of the implied covenant of
    good faith and fair dealing (count 3), promissory estoppel
    (count 4), quantum meruit (count 5), and injunctive relief
    (count 6).
    Background.   We recite only so much of the long history of
    this case that is necessary to decide the appeal.   On June 21,
    2006, following a remand from the housing appeals committee
    (HAC), the town's zoning board of appeals (ZBA) issued an
    amended comprehensive permit (2006 amended comprehensive permit)
    to Delphic Associates, LLC (Delphic), WPV's predecessor in
    interest.   The 2006 amended comprehensive permit authorized the
    construction of an affordable housing project, required work to
    commence within one year, and was subject to numerous
    conditions, including a conservation restriction condition (2006
    conservation restriction condition). 2
    Following the lapse of the permit, lengthy litigation
    ensued over Delphic's request to reinstate it, culminating in a
    Superior Court judgment in Delphic's favor.   After the ZBA
    noticed its appeal from the judgment to this court, four parties
    (the board, the ZBA, Delphic, and WPV) entered into a settlement
    2 The ZBA granted the 2006 amended comprehensive permit subject
    to 106 conditions, including condition twelve, which included,
    as herein relevant, the following provisions: "Prior to any
    grading, land disturbance, issuance of any building permit and
    construction of any structure or infrastructure, [Delphic] shall
    execute and cause to be recorded at the Plymouth County Registry
    of Deeds, a Conservation Restriction pursuant to G. L. c. 184,
    s. 31, clearly identifying the land areas noted on the approved
    plans as 'Restricted Area' to be left in their natural
    vegetative state with no provisions for site alteration. . . .
    The Conservation Restriction required by this paragraph shall be
    deemed an independent condition and requirement from that or
    those required by the Commonwealth's Natural Heritage and
    Endangered Species Act."
    2
    agreement and mutual release (2012 settlement agreement) whereby
    Delphic and WPV agreed not to request modifications of certain
    conditions. 3
    Further proceedings required by the 2012 settlement
    agreement, see note 3, supra, were held before the ZBA, which
    issued a modified comprehensive permit (2015 modified
    comprehensive permit) to WPV in August 2015 in light of the
    number of modifications requested and changed circumstances. 4
    Like the 2006 amended comprehensive permit, the 2015 modified
    3 The 2012 settlement agreement provided, as herein relevant,
    that "for good and valuable consideration, the sufficiency of
    which is hereby acknowledged, the undersigned Parties agree
    . . . [that] the [ZBA] shall . . . withdraw the Appeal . . .
    [and] [u]pon dismissal of this appeal and subject to any future
    appeals this Amended Comprehensive Permit shall become final."
    As part of the settlement, the parties agreed that "Delphic
    and/or WPV . . . shall not request modification from the [ZBA]
    or from the HAC of . . . [sixty-nine conditions of the 2006
    amended comprehensive permit, including the 2006 conservation
    restriction condition]." The agreement stated that it was
    "negotiated in good faith and constitutes a fair and reasonable
    resolution of the Parties' dispute." The parties also agreed
    that Delphic and/or WPV would submit a request for modification
    of the 2006 amended comprehensive permit to bring it in line
    with the requirements of Zoning Bd. of Appeals of Amesbury v.
    Housing Appeals Comm., 
    457 Mass. 748
     (2010).
    4 In its decision, the ZBA stated that the 2015 modified
    comprehensive permit superseded the 2006 amended comprehensive
    permit and an earlier comprehensive permit and that those
    "previous permits shall have no further force or effect." The
    ZBA further stated that the 2012 settlement agreement "shall
    remain in full force and effect except as specifically
    superseded by [the] Modified Comprehensive Permit" and that
    "[n]othing in [the] Modified Comprehensive Permit waives the
    [ZBA's] argument that other conditions that WPV agreed not to
    modify in that [settlement] [a]greement remain non-modifiable."
    3
    comprehensive permit required WPV, as a condition of building,
    to record a conservation restriction (2015 conservation
    restriction condition).   The language of that condition was
    substantially similar to the 2006 conservation restriction
    condition.
    In November 2020, WPV asked the HAC to eliminate the 2015
    conservation restriction condition, claiming that the condition
    could not be satisfied, that the 2012 settlement agreement was
    void insofar as it prohibited WPV from requesting modifications
    of certain conditions, and that, moreover, the 2012 settlement
    agreement did not prohibit WPV from requesting that the board or
    the HAC modify the 2015 conservation restriction condition.    In
    March 2021, the board notified WPV that its request to the HAC
    violated the 2012 settlement agreement.   After the HAC
    determined that WPV's request was not properly before it, WPV
    asked the ZBA to eliminate the 2015 conservation restriction
    condition as an "insubstantial change" to the 2015 modified
    comprehensive permit.   Shortly before the ZBA denied the
    request, the board filed this action; WPV responded with a
    special motion to dismiss.   Applying the burden-shifting,
    augmented Duracraft framework, see Reichenbach v. Haydock, 
    92 Mass. App. Ct. 567
    , 572 (2017), a judge denied the motion,
    concluding that (1) WPV failed to meet its stage one burden and
    4
    (2) even if WPV met its burden, the board prevailed at the
    second stage.
    Discussion.   We consider de novo WPV's showing at the first
    stage but review for abuse of discretion or error of law the
    motion judge's ruling concerning the board's showing at the
    second stage.    See Reichenbach, 92 Mass. App. Ct. at 572 (de
    novo first stage); Blanchard v. Steward Carney Hosp., Inc., 
    477 Mass. 141
    , 160 (2017) (Blanchard I).    At the first stage of the
    framework, the moving party and alleged target of a SLAPP suit
    (here, WPV) bears the burden of establishing "through pleadings
    and affidavits that the claims against it are based on the
    petitioning activities alone and have no substantial basis other
    than or in addition to the petitioning activities" (quotations
    and citation omitted).    Blanchard I, supra at 147.
    If the special movant meets its threshold burden, the
    nonmoving party may defeat the motion in one of two ways at the
    second stage of the framework.    Under the first and less
    traveled path, the nonmoving party may prevail by showing, "by a
    preponderance of the evidence, that the special movant's
    petitioning activity was devoid of any reasonable factual or
    legal support and that it caused the nonmoving party actual
    injury."    Cardno ChemRisk, LLC v. Foytlin, 
    476 Mass. 479
    , 484
    (2017).    See Blanchard II, 
    483 Mass. at 204
    , quoting Blanchard
    I, 
    477 Mass. at
    156 n.20 ("[p]roving that the moving party's
    5
    petitioning activity was, in essence, a sham presents a 'high
    bar'").   If, and only if, the nonmoving party fails to make the
    showing required under the first path of this second stage, the
    judge must then consider the nonmovant's showing under the
    second stage's second path.   See 477 Harrison Ave., LLC v. JACE
    Boston, LLC, 
    483 Mass. 514
    , 519 (2019) (Harrison II).      Under
    this second path, the nonmoving party may withstand the special
    motion to dismiss by "demonstrat[ing], such that the motion
    judge may conclude with fair assurance . . . two elements:      (a)
    that its suit was colorable; and (b) that the suit was not
    brought primarily to chill the special movant's . . . legitimate
    exercise of its rights to petition, i.e., that it was not
    retaliatory (quotations and citation omitted).      Blanchard II,
    supra.
    We agree that WPV's conduct in seeking the removal of the
    2015 conservation restriction condition from both the HAC and
    the ZBA was protected petitioning activity, and that the town's
    claims in this action are based on WPV's petitioning activity.
    See G. L. c. 231, § 59H (defining "party's exercise of its right
    of petition" to "mean any written . . . statement . . .
    submitted to a legislative, executive, or judicial body, or any
    other governmental proceeding").       See also Cardno ChemRisk, LLC,
    
    476 Mass. at 484-485
    .   However, to meet its stage one burden,
    WPV was required to show that the board's claims were based
    6
    solely on WPV's petitioning activities.    WPV's motion foundered
    on this requirement.
    It is well established that "[m]any preexisting legal
    relationships may properly limit a party's right to petition,
    including enforceable contracts in which parties waive rights to
    otherwise legitimate petitioning."    Duracraft Corp. v. Holmes
    Prods. Corp., 
    427 Mass. 156
    , 165 (1998).    Here, as part of the
    2012 settlement agreement, WPV waived its future petitioning
    rights with respect to the 2006 and 2015 conservation
    restriction conditions. 5   See 
    id. at 165-166
     ("quintessential
    example of [proper] waiver is a settlement agreement, in which a
    party releases legal claims against an adversary that otherwise
    properly could be prosecuted by petitioning the court").    These
    facts establish that the board had a "substantial basis other
    than or in addition to the petitioning activities" for bringing
    this lawsuit. 6   Blanchard I, 
    477 Mass. at 147
    , quoting Fustolo v.
    5 For reasons that we explain, we are unpersuaded by WPV's
    argument that it did not waive its future petitioning rights
    with respect to the 2015 conservation restriction condition.
    6 Whether the board's claims turn out to be ultimately
    "meritless," as WPV maintains, is a matter beyond the purview of
    the stage one inquiry. See Burley v. Comets Community Youth
    Ctr., Inc., 
    75 Mass. App. Ct. 818
    , 822 (2009) (question for
    judge at stage one concerns "only the nature of the conduct
    alleged by the plaintiff . . . and not the merits of the case").
    See also 477 Harrison Ave., LLC v. JACE Boston, LLC, 
    477 Mass. 162
    , 168 (2017) (Harrison I) ("In assessing the conduct that is
    complained of, a judge considers only the allegations that are
    relevant to the discrete causes of action brought").
    7
    Hollander, 
    455 Mass. 861
    , 865 (2010).    See Harrison II, 
    483 Mass. at 520
     ("claim for breach of contract [or breach of the
    implied covenant of good faith and fair dealing] sometimes may
    present a substantial basis other than the petitioning activity
    itself for purposes of the anti-SLAPP act"); 477 Harrison Ave.,
    LLC v. JACE Boston, LLC, 
    477 Mass. 162
    , 171 (2017) (Harrison I)
    (where plaintiff alleged that defendants filed two false
    insurance claims, substantial nonpetitioning basis for its G. L.
    c. 93A claim existed and thus defendants could not show claim
    was based solely on their petitioning activity); Duracraft
    Corp., 
    supra at 168
     (nondisclosure agreement constituted
    substantial basis for plaintiff's lawsuit other than petitioning
    activity and defeated special motion to dismiss).
    In fact, in its 2020 modification request to the HAC, WPV
    reserved its rights to bring a lawsuit to have the portions of
    the 2012 settlement agreement that prohibited it from making
    modification requests declared void.    As WPV candidly
    acknowledged to the HAC, the other parties to the 2012
    settlement agreement had the same constitutionally protected
    right to petition the Superior Court to enforce it. 7     Having
    7 WPV stated that it did not "believe it should be WPV's burden,
    or would serve WPV's interests, to bring such an action at this
    point." WPV expressed its hope that the HAC would simply allow
    the changes, and acknowledged that if the HAC did so, some other
    entity, including the ZBA, could then bring a legal claim
    charactering WPV's request "as a breach of contract." WPV's
    8
    taken this position with the HAC and admitted the existence of
    an actual controversy between the parties, it is inconsistent
    for WPV to now argue that the board's lawsuit for breach of
    contract was based solely on WPV's petitioning activities.
    Even assuming for the sake of argument that WPV made the
    required showing at the first stage, the judge neither erred nor
    abused his discretion in concluding that the board established
    both elements required by the second stage second path. 8   First,
    we discern no abuse of discretion in the judge's determination
    that the board's primary breach of contract claim is
    "colorable," which in this context means "worthy of being
    presented to and considered by the court" and "offer[ing] some
    reasonable possibility of a decision in the party's favor"
    (quotations and citations omitted).   Blanchard II, 483 Mass. at
    next sentence foreshadowed this very proceeding: "If the HAC or
    the respective boards believe the terms of [the 2012 settlement
    agreement] effectively prohibit any modification of the [2015
    conservation restriction] condition, then WPV expects that one
    way or another this issue will be decided in Superior Court,
    which has jurisdiction over interpretation and enforcement of
    contracts."
    8 We note that the judge skipped the first analytical path of the
    second stage. See Harrison II, 
    483 Mass. at 519
    . On appeal,
    the board does not purport to meet the "high bar" of the first
    path. Where WPV does not claim error by the judge in this
    regard, nothing turns on the judge's omission. The actual
    injury, if any, sustained by the board from WPV's modification
    requests was a required element of proof for the board with
    respect to the first path, but not for the second path, and
    thus, we need not address it. See id. at 518.
    9
    207-208.   The colorability of the claim is supported by the
    plain language of the 2012 settlement agreement and the
    comprehensive permits.   As part of the 2012 settlement
    agreement, WPV expressly agreed that it would not seek
    modifications of sixty-nine conditions contained in the 2006
    amended comprehensive permit from either the ZBA or the HCA.
    The relevant portions of the 2012 settlement agreement regarding
    the nonmodifiable conditions were not "specifically superseded"
    by the 2015 modified comprehensive permit, see note 4, 
    supra,
    and thus remained in full force and effect, 9 and as the judge
    noted, the substance of the 2006 and 2015 conservation
    restriction conditions was "largely the same."    Notwithstanding
    the previous agreement, in 2020 and 2021, WPV submitted requests
    for the elimination of a covered condition -- to both the HCA
    and the ZBA.
    As for the second element, we discern no abuse of
    discretion in the judge's determination that, based on the
    totality of the circumstances, the board's claims do not amount
    to a SLAPP suit (i.e., brought primarily to chill WPV's
    legitimate petitioning activities). 10   See Blanchard II, 483
    9 Moreover, the 2015 modified comprehensive permit expressly
    preserved the ZBA's rights to insist on WPV's adherence to the
    conditions listed in the 2012 settlement agreement.
    10 To the extent that WPV seizes on a few words in the judge's
    decision to show that the judge did not apply the correct fair
    assurance standard, we find WPV's arguments unpersuasive.
    10
    Mass. at 209-210.    The judge could reasonably have inferred that
    the board, which waived its appellate rights in consideration of
    WPV's promises in the settlement agreement, was aggrieved by
    WPV's subsequent requests to have the 2015 conservation
    restriction condition eliminated, and through this action was
    seeking damages for the harm caused by WPV's legally
    transgressive acts. 11
    Order dated May 25, 2022,
    denying special motion to
    dismiss affirmed.
    By the Court (Wolohojian,
    Singh & Hand, JJ. 12),
    Clerk
    Entered: August 8, 2023.
    11   WPV's request for attorney's fees is denied.
    12   The panelists are listed in order of seniority.
    11