Intershell International Corp. v. Great Eastern Marine Service, Inc. ( 2024 )


Menu:
  • NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule
    23.0, as appearing in 
    97 Mass. App. Ct. 1017
     (2020) (formerly known as rule 1:28,
    as amended by 
    73 Mass. App. Ct. 1001
     [2009]), are primarily directed to the parties
    and, therefore, may not fully address the facts of the case or the panel's
    decisional rationale. Moreover, such decisions are not circulated to the entire
    court and, therefore, represent only the views of the panel that decided the case.
    A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25,
    2008, may be cited for its persuasive value but, because of the limitations noted
    above, not as binding precedent. See Chace v. Curran, 
    71 Mass. App. Ct. 258
    , 260
    n.4 (2008).
    COMMONWEALTH OF MASSACHUSETTS
    APPEALS COURT
    23-P-1117
    INTERSHELL INTERNATIONAL CORP.
    vs.
    GREAT EASTERN MARINE SERVICE, INC.
    MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
    This action concerns a contract for the defendant, Great
    Eastern Marine Service, Inc. (GEM), to construct a pier for the
    plaintiff, Intershell International Corp. (Intershell).               The
    parties dispute whether the agreement included a condition
    precedent that GEM would obtain a building permit such that
    construction would be complete before June 1, 2020.              GEM did not
    obtain a building permit in time to do so (through no fault of
    either party), and Intershell then brought this action in which
    both parties alleged, among other claims and counterclaims, that
    the other breached their agreement.           After a bench trial, a
    judge of the Superior Court concluded that the agreement did
    contain an unfulfilled condition precedent and, as a result, the
    contract was unenforceable.     The judge ordered GEM to return the
    $100,000 that Intershell previously had paid GEM, less $5,000
    that GEM expended in preparation to complete the work.
    The parties cross-appealed from the judgment.     GEM argues
    that the judge's findings that the contract contained a
    condition precedent and that Intershell's $100,000 payment
    constituted a refundable deposit were clear error.     Intershell
    counters that it was entitled to prejudgment interest on the
    amount it received under the judgment.     We vacate so much of the
    judgment as declined to award prejudgment interest and remand
    for reconsideration.1   We otherwise affirm.
    Background.   We set forth the undisputed facts as well as
    those found by the judge after trial.     We reserve certain facts
    for our later discussion.
    Intershell is a commercial fishing business and GEM is a
    marine construction business.     Howard Monte Rome is Intershell's
    general manager.   Kenneth Taliadoros (Kenneth) is GEM's owner
    and president, and Kenneth's son, Jonathan Taliadoros
    (Jonathan), is an engineer for GEM.2
    1 Although the judgment itself does not include the order to
    return the deposit, we treat that order as subsumed in the final
    judgment that entered on April 6, 2023.
    2 Because Kenneth and Jonathan share a last name, we refer
    to them by their first names.
    2
    1.    The bid and the contract.   In December 2019, Intershell
    sought bids to construct a new pier (project) on its property in
    the city of Gloucester (city).3    Intershell wanted the project
    completed by June 1, 2020,4 which was the start of its busy
    season.     To that end, Rome and Kenneth, who were acquainted
    because of the parties' previous business dealings over the
    years, met at the property to discuss the project.     At that
    meeting, Rome gave Kenneth copies of certain documents including
    an amended order of conditions (OOC) that Intershell had
    obtained for the project from the city's conservation
    commission.
    On January 10, GEM sent a written bid for the project in
    the amount of $357,500 to Intershell.     The bid provided that
    "[u]nless specifically modified in the attached
    quotation/proposal, payment terms require [one-third] upon
    acceptance, [one-third] upon [fifty percent] completion and
    [one-third] upon [one hundred percent] completion."     In the e-
    mail message accompanying the bid, Kenneth stated that the
    "quote includes [GEM] pulling the building permit for the
    project."     Notwithstanding that representation, the bid
    specified that "[a]ll permits are by owner."
    3 My Management Group, LLC, an Intershell affiliate, is the
    record owner of the property.
    4   Unless otherwise specified, all events took place in 2020.
    3
    On January 25, Rome, Kenneth, and Jonathan met to discuss
    GEM's bid.     During that meeting, the parties agreed to the terms
    set forth in GEM's bid with the following three oral
    modifications:     (1) Intershell's first payment to GEM would be
    in the amount of $100,000 rather than one-third of the bid price
    ($117,975); (2) GEM was responsible for obtaining the building
    permit for the project; and (3) the project had to be completed,
    and GEM's equipment and barge removed from the site by June 1.
    The parties signed the bid and Intershell provided GEM with
    $100,000.    Of the three bids that Intershell received for the
    project, GEM's bid was the highest.     However, Intershell
    selected GEM's bid because GEM was the only bidder prepared to
    complete the project by June 1.
    2.   Building permit and GEM's preparation work.     On
    February 19, Kenneth submitted the building permit application
    to the city.     Kenneth believed that the city would quickly issue
    the building permit because Intershell already obtained several
    environmental-related permits, including the OOC.    On February
    22, GEM brought a barge and other equipment to the job site.        At
    that time, Kenneth informed Rome that he had not yet received
    the building permit.     A few days later, Jonathan and another GEM
    employee performed some preparation work on the job site,
    including removing debris and preparing to demolish and remove a
    4
    concrete slab.   GEM spent between $5,000 and $6,000 to complete
    this work.
    On February 27, Kenneth contacted the city's building
    department to inquire about the status of the permit application
    and learned that the conservation commission was "holding up"
    approval of the application.     Kenneth then contacted the
    conservation commission and was told that the permit application
    had to be denied because the OOC previously obtained by
    Intershell was not valid.    Kenneth immediately told Rome and, in
    turn, Rome took prompt action to obtain a new OOC.
    Rome kept Kenneth apprised of the status of the OOC, but
    its issuance was delayed by the conservation commission.      When
    it became clear that the new OOC would not issue in time for GEM
    to obtain a building permit and complete the project by June 1,
    Intershell took the position that the contract was null and void
    and offered to cover GEM's costs thus far.     GEM continued to
    offer to complete the project once the permit issued.
    In April, Rome directed Kenneth to remove its barge and
    equipment, and GEM did so.     In May, Rome requested that Kenneth
    return Intershell's $100,000 and stated that the parties could
    discuss GEM performing the work in the coming fall or winter.
    GEM continued to offer to perform under the agreement once the
    permit was obtained.   That same month, Rome suggested that GEM
    provide a new bid consistent with the lower bid prices that it
    5
    previously received (between $220,000 and $265,000) because the
    parties' agreement was "no longer valid" and Intershell was not
    willing to pay "the premium" price for the project given that
    the June 1 deadline could not be met.       In June, Rome notified
    Kenneth that Intershell received the OOC and was ready "to make
    a plan for the work."   Kenneth responded that the parties'
    attorneys should have further discussions.       Intershell later
    awarded the project to another company for $219,000.
    3.   The judge's findings.    In August, Intershell brought an
    action for breach of contract and violation of G. L. c. 93A.5
    GEM brought counterclaims for breach of contract, breach of the
    covenant of good faith and fair dealing, and violation of G. L.
    c. 93A.   The matter proceeded to a jury-waived trial where Rome,
    Kenneth, and Jonathan testified.       After hearing the parties'
    evidence, the judge allowed each party's motion for involuntary
    dismissal of the other's c. 93A claim.
    Following the trial, the judge entered written findings on
    the parties' breach of contract claims and GEM's breach of the
    covenant of good faith and fair dealing claim, the relevant
    portions of which are summarized as follows.       The judge found
    that the parties entered into a valid contact that required GEM
    5 Intershell also brought a fraud claim that was dismissed
    prior to trial. The parties make no argument about that claim
    on appeal.
    6
    to complete the project, and to remove its equipment and barge
    by June 1.    The requirement that GEM obtain a building permit to
    complete the work by June 1 was a condition precedent to the
    parties' performance under the contract.     Because that condition
    could not be met through no fault of the parties, the contract
    was unenforceable and neither party was in breach.     Intershell
    also did not breach the implied covenant of good faith and fair
    dealing because Intershell acted in good faith and made
    expeditious attempts to obtain a new OOC.
    As to the $100,000 that Intershell paid to GEM, the judge
    found that payment was a deposit that must be returned.
    Nonetheless, the judge found that GEM was entitled to be paid
    for the services it rendered under the doctrine of quantum
    meruit and that the fair and reasonable value of the work
    performed by GEM in preparation for the project was $5,000.      In
    light of these findings, the judge ordered that GEM return
    $95,000 of the deposit to Intershell.     The judge further ordered
    that "[n]o party is entitled to recover interest (because no
    monetary judgment shall enter) or their costs."     Judgment then
    entered and this cross appeal followed.
    Discussion.    "We review a judge's findings of fact under
    the clearly erroneous standard and his conclusions of law de
    novo."   Casavant v. Norwegian Cruise Line Ltd., 
    460 Mass. 500
    ,
    503 (2011).
    7
    1.   Condition precedent.    GEM first argues that the judge's
    finding that the contract included a condition precedent was
    clear error.   "A condition precedent defines an event which must
    occur before a contract becomes effective or before an
    obligation to perform arises under the contract."     Massachusetts
    Mun. Wholesale Elec. Co. v. Danvers, 
    411 Mass. 39
    , 45 (1991)
    (Massachusetts Mun.).   A condition precedent may be expressly
    created by the parties, usually through the use of "[e]mphatic
    words" in the contract (citation omitted).     Id. at 46.     A
    condition precedent also may be implied in fact if "the intent
    of the parties to create one is clearly manifested in the
    contract as a whole."    Id.   See Restatement (Second) of
    Contracts § 226 comments a and c (1981); 8 T. Murray, Corbin on
    Contracts § 30.10 (rev. ed. 2018).
    "Where, as here, the terms of an oral agreement are in
    dispute, the finder of fact determines the terms of any
    agreement 'from the conversation of the parties and their
    conduct'" (citation omitted).    Twin Fires Inv., LLC v. Morgan
    Stanley Dean Witter & Co., 
    445 Mass. 411
    , 420 (2005).        "Where
    the dispute concerns a condition precedent, 'a court looks to
    the parties' intent to determine whether they have created a
    condition precedent.    To ascertain intent, a court considers the
    words used by the parties, the agreement taken as a whole, and
    surrounding facts and circumstances'" (citation omitted).         
    Id.
    8
    Here, the judge made explicit findings that at the time
    they entered into the agreement, the parties clearly understood
    and agreed to the following.    First, that the work on the
    project could not be performed until GEM secured the building
    permit from the city.    Second, that the project must be
    completed, and GEM's barge and equipment must be removed from
    the job site by June 1, as this deadline was an essential and
    material term of the parties' agreement.    Although those terms
    were not reduced to writing, the judge's finding that the
    parties orally agreed to these terms was adequately supported by
    Rome's testimony at trial and the parties' written
    communications in evidence.6
    The judge properly considered this evidence when
    determining that the parties intended the contract to contain a
    condition precedent.    This was not clear error.   See Tilo
    Roofing Co. v. Pellerin, 
    331 Mass. 743
    , 746 (1954) (parties
    orally agreed to condition precedent that written agreement not
    effective until defendants satisfied as to quality of
    plaintiff's work).     See also Twin Fires Inv., LLC, 
    445 Mass. at
    6 The judge did not credit Kenneth's testimony that the June
    1 deadline was not firm and that GEM could complete the work in
    the fall. On that point, the judge instead credited Rome's
    testimony and other evidence to the contrary, and we defer to
    the judge's findings on that point. See Twin Fires Inv., LLC,
    
    445 Mass. at 421
     (judge's findings resolving disputes over
    content of oral conversations entitled to deference).
    9
    421 (where parties' intent must be deduced from conflicting
    testimony, "we accord particular deference to the judge's
    findings").    Moreover, where that condition precedent was
    unfulfilled through no fault of the parties, the judge correctly
    concluded that the contract was unenforceable and thus neither
    party was in breach.7    See Massachusetts Mun., 411 Mass. at 45.
    2.   Order to return deposit.   a.   Deposit.   GEM next argues
    that it was entitled to keep the $100,000 paid by Intershell at
    the January 25 meeting because it was a nonrefundable
    installment payment and not a deposit.      In support, GEM points
    to written bid that sets forth "payment terms," which required
    the first of the three payments to be made on acceptance of the
    bid.
    As an initial matter, we note that the bid discusses
    "payment terms" but not deposits or installments.        Regardless,
    the judge found that the parties orally agreed to modify the
    payment terms at the January 25 meeting by reducing the amount
    due on acceptance.    More importantly, the judge made a specific
    For the same reasons, GEM's claim that Intershell breached
    7
    the covenant of good faith and fair dealing fails, see Uno
    Restaurants, Inc. v. Boston Kenmore Realty Corp., 
    441 Mass. 376
    ,
    385 (2004) (implied covenant of good faith and fair dealing does
    not "create rights and duties not otherwise provided for in the
    existing contractual relationship"), as does its related claim
    for a violation of G. L. c. 93A.
    10
    finding that the parties intended for the payment made at the
    January 25 meeting to be treated as a deposit.
    Conflicting evidence was presented on the nature of the
    payment, but there was ample evidence to support the judge's
    finding of a deposit.   For example, ten days before the January
    25 meeting, Rome informed Kenneth via text message, "I will go
    ahead with your offer and will be ready with a deposit early
    next week."   Kenneth did not contest Rome's characterization of
    the deposit and simply responded, "Great I'll plan on seeing you
    next week."   Moreover, Rome testified that the parties
    negotiated "a requirement of [a] deposit for $100,000."        The
    nature of the payment turned on the parties' intent and we defer
    to the judge's finding on this point.     See Twin Fires Inv., LLC,
    
    445 Mass. at 421
    .   See also Rood v. Newberg, 
    48 Mass. App. Ct. 185
    , 191 (1999) ("If the trial judge makes one of several
    possible choices of what facts are supported by the evidence,
    the judge's choice is not clearly erroneous" [citation
    omitted]).
    b.   Cost of GEM's preparation work.     GEM next argues that
    the judge committed clear error by disregarding its evidence of
    the costs for its preparation work.     However, the judge's
    finding that "the value of the labor and materials to GEM for
    bringing the barge and equipment to the job site, and for
    performing the preparation work was approximately $5,000 to
    11
    $6,000," was amply supported by Jonathan's own testimony.
    Jonathan testified as to the work that GEM completed between
    February and April.    When asked if he had "any estimate as to
    the costs incurred for that period of time," Jonathan responded,
    "I think in the tune of, direct out-of-pocket cost, for those
    specific items, was probably 5 or $6,000."
    Although GEM also sought to recover additional costs from
    Intershell (including $50,000 for the two-month period that
    equipment owned by GEM was at the project site and $20,000 for
    business overhead), the evidence on these costs consisted only
    of brief testimony from Jonathan and a single-page spreadsheet
    that Jonathan created in preparation for GEM's bid on the
    project.    The judge did not commit clear error in rejecting that
    minimal evidence of GEM's additional costs and instead
    determining that $5,000 constituted a fair and reasonable value
    for the services rendered.
    c.     Prejudgment interest.   Intershell's sole argument on
    cross appeal is that it was entitled to prejudgment interest
    under G. L. c. 231, §§ 6C and 6H.       GEM counters that no such
    interest is permitted because the judge's order to return the
    deposit did not constitute a damages award.
    In relevant part, G. L. c. 231, § 6C, provides as follows:
    "In all actions based on contractual obligations, upon a
    verdict, finding or order for judgment for pecuniary
    damages, interest shall be added by the clerk of the court
    12
    to the amount of damages, at the contract rate, if
    established, or at the rate of twelve per cent per annum
    from the date of the breach or demand."
    The statute also applies to quantum meruit damages.       See Peabody
    N.E., Inc. v. Marshfield, 
    426 Mass. 436
    , 444-446 (1998).         "[T]he
    policy underlying G. L. c. 231, § 6C, is that '[p]rejudgment
    interest serves to compensate [a party] for the loss of use of
    money wrongfully withheld'" (citation omitted).     Henry v.
    Morris, 
    62 Mass. App. Ct. 714
    , 717-718 (2004).8
    We turn then to whether the statute applies to the judge's
    order for the return of Intershell's deposit.     The circumstances
    here are analogous to those in National Starch & Chem. Co. v.
    Greenberg, 
    61 Mass. App. Ct. 906
    , 906 (2004) (National Starch),
    which pertained to an agreement for the sale of commercial
    property.    The agreement allowed the seller to retain the
    buyer's deposit as liquidated damages if the buyer breached the
    agreement.    See 
    id.
       The agreement also included a mortgage
    contingency clause that provided that the agreement was "void
    without recourse to the parties" and the buyer was entitled to
    return of her deposit if the buyer provided timely written
    notice that she was unable to obtain financing.     
    Id.
        The
    8 "General Laws c. 231, § 6H, is a 'catch-all interest
    provision,' that 'reflects the Legislature's intent that
    prejudgment interest always be added to an award of compensatory
    damages'" (citations omitted). Governo Law Firm LLC v.
    Bergeron, 
    487 Mass. 188
    , 198–199 (2021).
    13
    parties disputed whether they agreed to extend the deadline to
    comply with mortgage contingency clause, but ultimately the
    buyer did not obtain financing.     See id. at 906-907.      Both
    parties requested the deposit from the escrow agent and the
    agent refused to release the funds to either party.       See id at
    907.     The seller then brought an action to recover the deposit
    on grounds that the buyer was in breach.     See id.   The court
    concluded to the contrary, finding that the agreement was "void
    without recourse" because the buyer timely exercised her right
    under the mortgage contingency clause.     Id.   The court ordered
    the deposit to be returned to the buyer and awarded prejudgment
    interest under G. L. c. 231, §§ 6C and 6H.       National Starch,
    
    supra.
        As to the interest, the court held that the buyer was
    entitled to prejudgment interest because the seller demanded the
    deposit from the escrow agent at the point in time when the
    agreement was void and that demand "did deprive the buyer of
    funds to which she was then rightfully entitled."      
    Id.
        Cf.
    Henry, 
    62 Mass. App. Ct. at 718
     (prejudgment interest not
    required under National Starch where buyer-plaintiffs did not
    seek return of deposit, only specific performance, and judge
    made no finding that deposit was wrongfully withheld).
    Here, after it became clear that the permit would not issue
    in time for the work to be completed by the June 1 deadline,
    Intershell requested that GEM return its deposit less GEM's
    14
    expenses for the preparation work.      GEM refused to do so and
    took the position that it was "not contractually obligated to
    refund any portion of the first payment due to delays in the
    permit process."   Ultimately, Intershell initiated this action
    to recover the $100,000 deposit.      Although the judge did not
    explicitly find that the deposit was "wrongfully withheld," the
    facts as found suggest that threshold was met for the same
    reasons as in National Starch.
    We recognize that G. L. c. 231, § 6C, sets forth different
    events that trigger the accrual of prejudgment interest -- i.e.,
    the date of breach (of which there was none here), demand, or
    commencement of the action.   When prejudgment interest begins to
    accrue is a question for the fact finder.9     See Aronovitz v.
    Fafard, 
    78 Mass. App. Ct. 1
    , 10 (2010).      Accordingly, we remand
    the case for further consideration on the issue of prejudgment
    interest.
    Conclusion.   We vacate so much of the judgment entered
    April 6, 2023, as declined to award prejudgment interest.        In
    all other respects, the judgment is affirmed.      The case is
    9 GEM argues that a trial judge may adjust an award of
    prejudgment interest if it would "result in a windfall for
    plaintiffs amounting, in essence, to an award of punitive
    damages." Sterilite Corp. v. Continental Cas. Co., 
    397 Mass. 837
    , 841 (1986). See Nissan Autos. of Marlborough, Inc. v.
    Glick, 
    62 Mass. App. Ct. 302
    , 311 (2004). However, the judge
    made no such finding here.
    15
    remanded for reconsideration of prejudgment interest and entry
    of an amended judgment consistent with this memorandum and
    order.
    So ordered.
    By the Court (Meade,
    Englander & Hodgens, JJ.10),
    Clerk
    Entered:   October 4, 2024.
    10   The panelists are listed in order of seniority.
    16
    

Document Info

Docket Number: 23-P-1117

Filed Date: 10/4/2024

Precedential Status: Non-Precedential

Modified Date: 10/4/2024