Manekin Construction v. Dept. of Gen. Servs. , 233 Md. App. 156 ( 2017 )


Menu:
  •                REPORTED
    IN THE COURT OF SPECIAL APPEALS
    OF MARYLAND
    No. 600
    September Term, 2016
    ______________________________________
    MANEKIN CONSTRUCTION, INC.
    v.
    MARYLAND DEPARTMENT OF GENERAL
    SERVICES
    ______________________________________
    Woodward, C.J.
    Berger,
    Kenney, James A., III
    (Senior Judge, Specially Assigned),
    JJ.
    ______________________________________
    Opinion by Berger, J.
    ______________________________________
    Filed: June 28, 2017
    This appeal arises from the circuit court’s order affirming the decision of the
    Maryland Board of Contract Appeals (the “Board”) to grant summary decision in favor of
    the Department of General Services of Maryland (“DGS”), appellee. On June 9, 2010,
    appellant Manekin Construction, LLC (“Manekin”) was awarded a contract with DGS to
    construct a two-story barrack and a one-story garage for the Maryland State Police in
    Hagerstown, Maryland. The contract price totaled more than eight million dollars and was
    subject to mutually agreed upon Proposed Change Orders (“PCOs”). As we discuss in
    detail below, Manekin submitted PCO No. 68 to DGS requesting additional compensation
    during the construction of the project. After the project was complete, Manekin submitted
    a “Request for Equitable Settlement” on March 18, 2013. After DGS’s procurement officer
    denied Manekin’s claim for compensation, Manekin appealed to the Board. On September
    17, 2016, during a hearing on the merits of the claim, the Board stopped the proceedings
    and granted DGS’s Third Motion for Summary Decision. The Circuit Court for Howard
    County affirmed the Board’s decision. This appeal followed.
    The primary issue we must decide on appeal is whether the Board erred when it
    stopped the evidentiary hearing and granted summary decision in favor of DGS. More
    specifically, we must decide whether the Board improperly made findings of fact on
    disputed issues, including whether Manekin knew or should have known that DGS disputed
    or rejected Manekin’s request for compensation detailed in PCO No. 68. For the reasons
    explained below, we hold that the Board erred in its decision to grant summary decision in
    favor of DGS.
    BACKGROUND AND PROCEDURAL HISTORY
    Construction of the barrack and garage took place from June 21, 2010 until the
    project was substantially complete on or around July 26, 2012. Approximately every two
    weeks throughout the construction process, Manekin and DGS officials held meetings
    (“Progress Meetings”) to discuss Manekin’s progress and other issues.               During
    performance of the construction, Manekin encountered certain difficulties that it attributed
    to delays caused by DGS (among other reasons) and submitted numerous PCOs, thereby
    requesting additional compensation. On November 2, 2011, Manekin notified DGS of the
    “cumulative impact and ripple effect of” certain factors. On December 7, 2011, Manekin
    submitted PCO No. 68, requesting compensation for the “additional time, and associated
    general conditions costs resulting from changes” discussed in the November 2, 2011 letter.
    A letter attached to PCO No. 68 detailed the changes requested, including the five “impact
    factors” that affected the cost of the project. Manekin and DGS discussed PCO No. 68 at
    three Progress Meetings, during which the issue was designated as “void” in the minutes
    for Progress Meetings and in the “PCO Log.”
    After the completion of the project, on or around March 18, 2013, Manekin sent a
    “Request for Equitable Settlement” to DGS requesting compensation for additional time
    caused by the same five impact factors as outlined in PCO No. 68. DGS denied the request
    in a letter dated April 3, 2013. DGS indicated in its letter, “if you wish to further pursue
    this matter, you may do so in accordance with COMAR [Code of Maryland Regulations]
    21.10.04 and the Contract Documents, General Conditions, Section 6.13, ‘Disputes and
    Contract Claims.’” On April 10, 2013, Manekin submitted its notice of claim, and on
    2
    April 29, 2013, submitted its formal claim to the procurement officer. The procurement
    officer denied Manekin’s claim on November 12, 2013, finding that the notice of claim
    was not submitted within thirty days of when Manekin knew or should have known of the
    basis of a claim. Manekin timely appealed to the Board.
    On September 17, 2016, the Board stopped the proceedings and granted DGS’s
    pending Third Motion for Summary Decision, finding that Manekin knew of the basis of
    its claim by no later than March 1, 2012, which was more than thirty days before Manekin
    submitted its notice of claim. On September 21, 2015, the Board issued a written order.
    Manekin filed a petition for judicial review in the Circuit Court for Howard County. After
    a hearing on April 21, 2016, the circuit court affirmed the Board’s grant of summary
    decision in a written opinion issued on April 27, 2016.
    DGS Contract & Relevant COMAR Provisions
    The “Department of General Services General Conditions for Construction
    Contracts (Revised March 2007)” contains the conditions of the contract between DGS and
    Manekin. As required, the contract incorporates the language of COMAR 21.07.02.05-1. 1
    Under a section of the contract entitled “6.13 Disputes and Contract Claims (COMAR
    21.07.02.05-1),” the contract provides that it is “subject to the provisions of State Finance
    1
    Similarly, COMAR 21.10.04.02 provides the following:
    Unless a lesser period is prescribed by law or by contract, a
    contractor shall file a written notice of a claim relating to a
    contract with the appropriate procurement officer within 30
    days after the basis for the claim is known or should have been
    known, whichever is earlier.
    3
    and Procurement Article, Title 15, Subtitle 2, Annotated Code of Maryland, and COMAR
    21.10.” The following are other pertinent provisions incorporated in the contract from
    COMAR 21.07.02.05-1:
    B.     Except as otherwise provided in this contract or by law,
    all disputes arising under or as a result of a breach of this
    contract that are not disposed of by mutual agreement shall be
    resolved in accordance with this clause.
    C.     As used herein, claim means a written demand or
    assertion by one of the parties seeking, as a legal right, the
    payment of money, adjustment or interpretation of contract
    terms, or other relief, arising under or relating to this contract.
    A voucher, invoice, or request for payment that is not in dispute
    when submitted is not a claim under this clause. However, if
    the submission subsequently is not acted upon in a reasonable
    time, or is disputed as to liability or amount, it may be
    converted to a claim for the purpose of this clause.
    D.    Within 30 days after Contractor knows or should have
    known of the basis for a claim relating to this contract,
    Contractor shall file a written notice of claim with the
    procurement officer.
    * * *
    F.     The claim shall set forth all the facts surrounding the
    controversy. Contractor, at the discretion of the procurement
    officer, may be afforded an opportunity to be heard and to
    offer evidence in support of the claim.
    PCO No. 68
    On December 7, 2011, Manekin submitted PCO No. 68 providing two methods for
    calculating the amount of compensation it asserted to be due for the five impact factors
    discussed in PCO No. 68 -- a “Change Order Analysis” and a “Measured Mile Approach.”
    Manekin notes in the PCO that, although these two methods produced two different time
    4
    calculations, they were intended to provide a basis for further negotiations. Manekin relied
    on its “General Requirements Costs” of $1,315.00 per day, as provided in the original
    contract with DGS, and requested 96 days of “Contract Time Extension” plus other
    expenses, for a total of $128,134.00. Within the PCO, however, Manekin “reserve[d] the
    right to request compensation for all direct and indirect costs attributable to this delay
    impact.” At the end of PCO No. 68, Manekin added, “We believe our calculations to be
    reasonable and an appropriate representation of the impacts to Manekin on this project.
    However, we are willing to meet and negotiate an acceptable compromise without this
    matter escalating to another level.” Thereafter, the parties’ representatives discussed PCO
    No. 68 at multiple Progress Meetings.
    PCO Log
    The PCO Log is a record of all PCOs as well as each PCO’s status. The status of
    each PCO is indicated in the “Remarks/Days” column. Some of these status designations
    include “VOID,” “REJECTED,” “CREDIT,” and various phrases such as “No charge
    VOID,” “Located in PCO #13 VOID,” or “G.C. agrees to amt.” Additionally, in the date
    column, either the date of the action is indicated or, if the PCO’s status is “VOID,” only
    the word “VOID” is listed in place of the date. A column labeled “PCO AMT.” lists the
    amount requested for each PCO, and a column labeled “DGS EST.” lists the amount to be
    added to the total amount due to Manekin. For any item designated as “VOID,” the “DGS
    EST.” is either blank or has a value of “$0.00.” At the end of the PCO Log, the total “DGS
    EST.” indicated is $1,232,918.00.
    5
    For PCO No. 68, which is described as “Time Extension Request to justify new
    schedule,” the table indicates a “PCO AMT.” of $128,134.00, and the term “VOID” is
    included under the “REMARKS/DAYS” column and in the date column. For comparison
    purposes, PCO No. 22 (“Soil Fill Material Phase #1), which had a “PCO AMT.” of
    $117,642.00, is recorded as “REJECTED” in the “REMARKS/DAYS” column. PCO No.
    70 (“Revise Membrane @ Phse Chimney Caps”), on the other hand, is listed as “No charge
    VOID” and no amount was added to the total.
    Progress Meetings
    The record before the Board contained the minutes for each relevant Progress
    Meeting, including Progress Meetings 37, 38, and 39. The minutes for each Progress
    Meeting include the names of persons attending, who would receive a copy of the minutes,
    a synopsis of the progress of the project as of that date, and notes of the topics discussed at
    the meeting. The minutes from Progress Meeting 37, held on January 5, 2012, include a
    section entitled “Time Extension PCO Discussion” containing eighteen points of
    discussion. The relevant portion of the minutes from Progress Meeting 37 includes the
    following:
    14.    J. Rohrbach tentatively said that with correct back-up:
    a. PCO 63 -- 6 days
    b. PCO 68 -- VOID
    c. PCO 73 -- 10 days
    15. Dan Sharpe offered March 1, 2012 and leave open on
    compensational [sic]. 2
    2
    As we discuss infra, whether the notation indicated that Manekin had committed
    to providing the fragnets by March 1, 2012 was not established at the evidentiary hearing
    as an undisputed fact.
    6
    * * *
    18. Tentative Schedule:
    -- February 15, 2012 -- Develop ‘work list’
    -- March 1, 2012 -- Substantial Completion Punch List
    and begin Barrack move
    -- Within 60 days (May 1, 2012) the following items will
    be placed on punch list and complete:
    - Abatement
    - Demo
    - Landscape
    - Paving
    - Fuel System
    The revised minutes for Progress Meeting 38, which was held on January 19, 2012,
    reference the need for “fragnets” for PCO No. 68. A fragnet is a detailed analysis of how
    particular factors impacted the construction project, such as when and how the contractor
    lost scheduled time. The minutes indicate that the parties continued to discuss PCO No.
    68., referenced by the following notation:
    VOIDED AA. PCO 068 -- Rock extension is not approved
    to April 14, 2012.
    Day after Jan. 27, 2012 Liquidated Damages
    will be accessed [sic].
    Fragnets must be submitted and part of the
    time extension.
    01-05-12 VOIDED.
    Finally, the minutes from Progress Meeting 39, held on February 2, 2012, included
    the same notations under points 14, 15, and 18 as the minutes from Progress Meeting 37,
    with the addition of the following notes added to point 18:
    01-19-12      52 days currently being allowed for extension.
    02-02-12      Substantial Complete is now May 1st (Added
    131 days)
    7
    Hearing Before the Board and the Board’s Decision
    In a letter dated August 7, 2015 from Board Member Dana Dembrow, the Board
    notified the parties of the trial date for Manekin’s appeal of the procurement officer’s denial
    of its claim. The brief letter included the following:
    As you know, there are three (3) Motions pending for Partial
    Summary Decision in this matter, which is currently scheduled
    for trial on September 14, 2015.
    Counsel understand that the pending Motions must be based on
    factual matters as to which there is no genuine dispute, and that
    all factual inferences must be resolved in favor of the adverse
    party at this point in the proceeding.
    At the present time, the Board does not anticipate making any
    decision on the pending Motions until after evidence is
    presented at trial. Of course, counsel are also free to renew
    Motions during the course of trial as evidence is adduced.
    We hope this correspondence is useful to your trial preparation.
    Hearings before the Board were held on September 14, 16, and 17, 2016. The only
    witness to testify before the Board ended the proceedings by granting DGS’s motion for
    summary decision was Daniel Sharpe, Vice President and Project Manager for Manekin.
    Sharpe testified regarding when he became aware that DGS had denied the request
    contained in PCO No. 68. The following colloquy between the Presiding Member of the
    Board and counsel for DGS ensued:
    PRESIDING MEMBER DEMBROW: . . . Now, frankly, . . .
    there’s nothing in this affidavit that says what Mr. Rohrbach
    intended by the word void or voided. And that’s the crux of
    the issue. [ . . . ] We’re still trying to figure out what was meant
    by void. So hopefully we’ll get to that point. [ . . . ] [Y]ou’ve
    made a very effective point that the State told the Appellant
    this PCO 68 was void. Okay.
    8
    [COUNSEL FOR DGS]: Mr. Dembrow, . . . I gave you a
    Daniel Webster’s Dictionary definition of the word void.       [
    . . . ] You’re not going to get anything more from the State. We
    just -- we use English words . . . . And [counsel for Manekin]
    will agree with me, the word void isn’t defined anywhere in the
    contract.
    PRESIDING MEMBER DEMBROW: . . . I’ve been waiting
    to hear from Mr. Rohrbach. In this affidavit he . . . reiterates
    that he uses the word void. It seems odd that he doesn’t say
    PCO 68 was rejected. What it says is it was void. And it further
    says that it was void with the opportunity to submit or the
    request and requirements to submit fragnets. And Mr. Sharpe,
    if we can [direct] your attention to the progress meeting on
    January 5, 2012 . . . that’s where the progress meeting reports
    say, quote, Dan Sharpe offered March 1, 2012 and leave
    discussion open on compensational. Whatever that means . . . .
    Counsel for DGS returned to questioning Sharpe and asked whether his belief “in
    his mind” that the issue in PCO No. 68 was left open had been documented. After Sharpe
    pointed to the Progress Meeting minutes notation “leave open on compensational [sic],”
    Presiding Member Dembrow added the following:
    PRESIDING MEMBER DEMBROW: I think he has . . . I
    think that the progress meeting notes are consistent with what
    he said. He’s saying that he asked for the compensation to be
    left open, and the minutes of the progress meeting say leave
    discussion open.
    Thereafter, Presiding Member Dembrow interrupted cross-examination to ask a
    question directed at counsel for DGS:
    PRESIDING MEMBER DEMBROW: . . . Mr. Rohrbach is
    not going to testify, is that correct?
    [COUNSEL FOR DGS]: I haven’t made that decision yet, sir.
    9
    PRESIDING MEMBER DEMBROW: I’m curious to know
    why it says in the affidavit that he never told anyone that they
    could wait until a later date, but all the notes reflect that they’re
    asking for fragnets. They’re requiring fragnets. They want
    proof that it’s on the critical path. Obviously there was an
    anticipation that [Manekin was] going to submit something or
    [DGS] wouldn’t have required and requested it. And . . . that’s
    sort of a mystery at this point. [ . . . ] [H]e voided and asked
    for fragnets. That’s the dilemma. That’s the dichotomy.
    [COUNSEL FOR DGS]: No, no, no, that’s not what his . . . if
    you . . . Mr. Dembrow, it says that he repeatedly had questions
    -- conversations with Chris Mento where Dan Sharpe was not
    present and he repeatedly said this is what I need, and they
    never came forward. [ . . . ]
    PRESIDING MEMBER DEMBROW: That makes your claim
    clearer. I’m sure [counsel for Manekin] has a different point
    of view. We’re going to hear evidence about that. [ . . . ]
    I interjected. I’m putting the State on fair notice where we
    need, where at least I need clarification. And that goes to the
    question of what they meant when they said voided give us
    fragnets. We’re trying to get to that, and the parties have
    opposite points of view. So let’s just try to go through the . . .
    evidence as we should with the next, with another question of
    Mr. Sharpe.
    * * *
    [Redirect by counsel for Manekin]
    Q.      . . . Your request for payment . . . for ripple effects, was
    that in dispute at the time you submitted it?
    A.     No.
    Q.     Was PCO 68 in dispute at the time you submitted it?
    A.     No.
    10
    Chairman Collins interjected during redirect with additional questions directed at
    Sharpe, which were focused primarily on why Sharpe had not filed a claim after PCO No.
    68 was marked “VOID.”
    A.     . . . I didn’t feel that I had any claim or anything at the
    time when I was going through these things initially ‘cause we
    were trying to work through them.
    * * *
    CHAIRMAN COLLINS: . . . Because you thought in your
    mind we can do it all at the end. When in reality the general
    conditions said you had to do it within 30 days of when you
    should have known. [ . . . ] That’s the trouble I’m having as a
    Board Member here --
    A.     But Mr. Collins, what I would like to answer back --
    CHAIRMAN COLLINS: Yeah, [p]lease do.
    A.      -- is I really . . . didn’t know . . . I had a dispute going
    on. I was asked to try to produce a fragnet which I worked
    vigorously to try to do, and I was -- because I never could really
    produce that fragnet that stated all these different things, that’s
    the reason why I felt that . . . I wasn’t like in a . . . claim mode
    or this major dispute mode ‘cause I was still trying to figure a
    way to produce the evidence or the backup that the State was
    asking for. [ . . .]
    CHAIRMAN COLLINS: Yeah, but even though you knew,
    you knew that it was gone.
    A. Well, it wasn’t . . . really gone.
    CHAIRMAN COLLINS: Well, yeah, it was really gone. Mr.
    Mento acknowledged it was really gone, and so did Mr.
    Rohrbach in this deposition say it was really gone. What he
    did say, so we are going to void this, and you can come back
    later. This is null and void. This is gone. But you know if you
    can produce that fragnet down the road show me another PCO.
    11
    Well when someone says that to me . . . you got to say to
    yourself at that point, there’s a potential claim.
    [By counsel for Manekin]
    Q. . . . [The] question to you is was there a dispute that had
    arisen during this process that you could file a notice of claim?
    A. Not at the time . . .
    Q. Why not?
    A. Because we didn’t receive any official thing. Except I
    understand the conversations that were had, but we were still
    having basically ongoing meetings, ongoing discussions about
    a lot of different things on the project, and I didn’t get, until I
    got that letter slammed back at me[,] that was when I realized
    I didn’t really have a --
    Q. Which letter?
    A. . . . It was a letter that came back from the State which was
    from DGS that basically denied . . . everything. . . .
    Q. . . . Mr. Collins’ point was that you knew that there was at
    least that PCO 68 was void. [ . . .]
    A. Well it didn’t mean to me it was off the table. It meant to
    me that I still had to come back, . . . and once I produced the
    additional backup that I could bring that thing back up.
    Near the conclusion of Sharpe’s testimony, the Board stopped the proceedings and
    granted DGS’s Third Motion for Summary Decision.              Presiding Member Dembrow
    provided the following rationale for the Board’s Decision:
    Okay. At this time there will not be a need for recross-
    examination because the Board has unanimously determined to
    grant the State’s Motion for Partial Summary Judgment
    Number 3. After listening carefully to the testimony of Mr.
    Sharpe, who is the Vice President of the Appellant
    Construction Company, Manekin, and the Project Manager on
    12
    this job, it is clear that even giving the Appellant the benefit of
    all doubt the ripple effect claim was first raised to the State by
    correspondence November 2, 2011. It was formally submitted
    as a proposed change order on December 7, 2011. And the
    very next day the State indicated to Appellant that that PCO
    was, quote, void, end quote. Now that was clear in the mind of
    some of the Members of the Board that that meant reject. But
    giving Appellant the benefit of all doubt, because there is a bit
    of a nuance in that DGS also noted on that voiding of that PCO
    that they wanted fragnets. The Board notes that the last
    request, and there are a couple of them at least, that the State
    made of the Appellant to submit the fragnets needed to support
    PCO 68, the last reference to fragnet was made on January 19,
    2012.
    There was a progress meeting on February 2, 2012, and in the
    minutes of that progress meeting, the minutes being dated
    February 7, 2012, there is reference that Mr. Sharp[e] stated or
    at least the minutes state, quote, Dan Sharpe offered March 1,
    2012 and leave discussion open on compensational, period.
    That’s certainly not an example of the greatest grammar
    because it’s somewhat difficult to know what that even means.
    But it does appear beyond a shadow of a doubt that on February
    2, 2012, when PCO 68 was marked void there was no reference
    to fragnets at that point. There had not been a reference for the
    need for further documentation by way of fragnets since
    January 19, 2012. At least as of February [2nd] Mr. Sharpe
    was saying we’ll do this by March 1, 2012.
    [COMAR 21.10.04.02] says . . . a contractor shall file a written
    notice of a claim relating to a contract with the appropriate
    procurement officer within 30 days after the basis for the claim
    is known or should have been known. It appears that the basis
    of the claim was initially known back in November of 2011. It
    certainly was known as of February 2012. But this claim was
    not filed until a year later. So even if we give the . . . Appellant
    the benefit of all doubt and give them [until] March 1, 2012, as
    the trigger date for the beginning of that 30-day statute of
    limitations, we’re still a year late. And the Board is directed
    by [COMAR 21.10.04.02C], quote, a notice of a claim or a
    claim that is not filed within the time prescribed shall be
    dismissed. Emphasis on the word shall.
    13
    Fair or unfair, that [is] what the regulation requires. [. . .] The
    Board has no choice but to not address the substantive merits
    of a claim that is filed a year late. And the Board concludes
    that that is the correct categorization of this appeal. Therefore,
    it will be dismissed at this time without the necessity of further
    testimony.
    Presiding Member Dembrow confirmed that the other Board Members concurred in the
    decision before adding the following:
    We wanted to hear testimony from Mr. Sharpe and give the
    Appellant the benefit of all doubt. We are comfortable that
    we’ve done that now. So this was not a decision made in haste,
    but one that we’ve been thinking about for a long time. And
    the testimony . . . confirmed the view of some of the Board
    Members a long time ago.
    The Circuit Court’s Affirmance of the Board’s Decision
    On April 27, 2016, the Circuit Court for Howard County affirmed the Board’s
    decision to grant summary decision. The written opinion of the circuit court provides, in
    pertinent part:
    The parties’ first dispute is over the standard of review to be
    applied by the Circuit Court in reviewing the decision of an
    administrative agency. . . . Specifically, Manekin argues that
    the VOID notation indicated it was to provide more
    documentation or information, and that it’s right to appeal did
    not attach until its more formal claim letter was denied 14
    months later. [ . . . ]
    DGS reminds the Court that because of the MSBCA members’
    familiarity with the subject matter, state procurement law, and
    expertise in that area, the appellate decisions and statutes allow
    the Court a very limited scope of review. [ . . . ]
    When the Court is reviewing a final decision of an
    administrative agency, the Court determines the legality of the
    decision and whether there was “substantial evidence” from
    the record as a whole to support the decision. [ . . . ]
    14
    Case law is clear that the Circuit Court[] is not to make findings
    of fact. That function is entirely within the realm of the agency,
    as is determining the inferences to be drawn from those facts.
    [ . . . ] Even though the final decision was reached by way of
    a ruling on a motion for summary decision, and not as the result
    of a contested hearing, the analysis is the same. . . . The Court
    must determine if the findings of fact are supported in the
    record by substantial evidence, and if so, whether the decision
    of the agency was legally correct.
    (Citations omitted).
    After articulating this standard of review, 3 the circuit court analyzed the Board’s
    decision and characterized the Board’s findings regarding notice as a “finding of fact.”
    The [Board] made a finding of fact that Manekin was on notice
    of DGS’s denial of its requests under PCO 68 by the end of
    February 2012 when Presiding Member Dana Dembrow
    stated, “It appears that the basis of the claim was initially
    known back in November of 2011. It certainly was known as
    of February 2012. But this claim was not filed until a year
    later. So even if we give the [] Appellant the benefit of all
    doubt and give them [until] March 1, 2012, as the trigger date
    for the beginning of that 30-day statute of limitations, we’re
    still a year late.” [ . . . ] This finding of fact was supported in
    the record by the Progress Meeting Notes for January 5, 2012,
    January 19, 2012, and February 2, 2012 which were received
    as evidence at the [Board] hearing. Reasoning minds
    examining this evidence could reasonably reach the conclusion
    that Manekin was on notice (knew or should have known) that
    DGS denied its claim for costs under PCO 68 by the end of
    February 2012. Inferences were resolved in Manekin’s favor
    when the Presiding Member gave Manekin until March 1,
    2012.
    Thereafter, the circuit court affirmed the Board’s determination finding that DGS
    was entitled to summary decision as a matter of law.
    3
    We note, preliminarily, that the circuit court relied upon an incorrect standard of
    review, as we discuss in further detail below.
    15
    DISCUSSION
    I.     Judicial Review of an Agency’s Conclusions of Law
    The Court of Appeals has explained that we “look[] through the circuit court’s . . .
    decision[], although applying the same standards of review, and evaluate[] the decision of
    the agency.” People’s Counsel for Baltimore Cnty. v. Surina, 
    400 Md. 662
    , 681 (2007). In
    other words, we “review[] the agency’s decision, not the circuit court’s decision.” Long
    Green Valley Ass’n v. Prigel Family Creamery, 
    206 Md. App. 264
    , 273 (2012) (citation
    omitted). We review questions of law de novo. See Assateague Coastkeeper v. Md. Dep’t
    of the Env’t, 
    200 Md. App. 665
    , 690 (2011).
    We note that “[a]n administrative agency’s interpretation of a statute that the agency
    administers should ordinarily be given considerable weight by reviewing courts,” Piney
    Orchard Cmty. 
    Ass’n, 231 Md. App. at 92
    (citation omitted); however, we owe no
    deference to an agency’s erroneous conclusions of law. See Bd. of Cnty. Comm’rs for St.
    Mary’s Cnty. v. S. Res. Mgmt., Inc., 
    154 Md. App. 10
    , 34 (2003) (citations omitted)
    (“[W]here an administrative agency renders a decision based on an error of law, we owe
    the agency’s decision no deference.”). “In contrast to administrative findings of fact,
    questions of law, including the proper construction of a statute, are subject to more plenary
    review by the courts.” Md. Office of People’s Counsel v. Md. Pub. Serv. Comm’n, 
    226 Md. App. 483
    , 501 (2016) (quoting Office of People’s Counsel v. Md. Pub. Serv. Comm’n,
    
    355 Md. 1
    , 14 (1999)).
    Although we “review[] the agency’s decision, not the circuit court’s decision,”
    Long Green 
    Valley, supra
    , 206 Md. App. at 273, we note that the circuit court’s recitation
    16
    of the “substantial evidence” standard of review as the appropriate review of an
    administrative agency’s summary decision was incorrect. The circuit court noted that the
    Board’s “finding of fact that Manekin was on notice of DGS’s denial of its requests under
    PCO 68 by the end of February 2012 . . . . March 1, 2012 at the latest” was supported by
    “substantial evidence.” Further, the circuit court found the Board’s finding of March 1,
    2012 as an “inference[] . . . resolved in Manekin’s favor.” The circuit court, therefore,
    erred in determining whether there was substantial evidence in the record to support the
    Board’s findings of fact. That error compounded the Board’s error in making findings of
    fact on disputed issues prior to the conclusion of Manekin’s presentation of evidence on
    the issue. Although DGS attempts to provide us with support for the circuit court’s review
    and argues that “this Court should apply a more deferential ‘substantial evidence’ standard
    of review,” we reject this assertion. The correct standard of review, at both the circuit court
    level as well as for this Court, is whether the Board’s decision to grant summary decision
    in favor of DGS was correct as a matter of law. See Eng’g Mgmt. Servs. v. State Highway
    Admin., 
    375 Md. 211
    , 228-29 (2003) (citations omitted) (“The standard for appellate
    review of a summary judgment is whether it is “legally correct. [ . . . ] This is the same
    standard of review we apply to the question of the legal correctness of an administrative
    agency’s decision.”). Because the Board made its decision on a motion for summary
    decision, we examine whether the Board’s decision was correct as a matter of law.
    17
    II.   Summary Decision Standard & State Procurement Contract Framework
    Critically, only when there is no genuine dispute of material fact may the Board
    determine whether a party is entitled to summary decision as a matter of law. COMAR
    21.10.05.06D provides the following:
    (1) A party may move for summary decision on any
    appropriate issue in the case.
    (2) The Appeals Board may grant a proposed or final summary
    decision if the Appeals Board finds that:
    (a) After resolving all inferences in favor of the party
    against whom the motion is asserted, there is no genuine
    issue of material fact; and
    (b) A party is entitled to prevail as a matter of law. [4]
    The Board’s two-step process in deciding a motion for summary decision begins with the
    determination of whether there is any “genuine issue of material fact.”              COMAR
    21.10.05.06D(2)(a). If the moving party is unable to demonstrate that no material fact is
    in dispute, the analysis ends and summary decision is not appropriate. Only “[a]fter
    resolving all inferences in favor of the party against whom the motion is asserted” and
    finding that “there is no genuine issue of material fact” should the Board determine whether
    the moving “party is entitled to prevail as a matter of law.” COMAR 21.10.05.06D(2). 5
    4
    This standard for summary decision in administrative decisions provided by
    COMAR 21.10.05.06D is similar to the standard for summary judgment, as provided by
    Maryland Rule 2-501(a): “Any party may file a written motion for summary judgment on
    all or part of an action on the ground that there is no genuine dispute as to any material fact
    and that the party is entitled to judgment as a matter of law.”
    5
    The Board itself acknowledged these criteria in its letter of August 7, 2015,
    reminding the parties that “the pending Motions must be based on factual matters as to
    18
    Put differently, the Board is not authorized to make findings of fact on material issues that
    remain in dispute. To the extent the court considers a disputed fact, the court must view
    that fact in favor of the nonmoving party and determine whether the moving party is
    entitled to summary decision.
    III.   The Board Erred In Granting DGS’s Third Motion for Summary Decision.
    We have explained that contract claims arising out of state procurement contracts
    are subject to statutorily-prescribed administrative procedures. See McLean Contracting
    Co. v. Md. Transp. Auth., 
    70 Md. App. 514
    , 523-24 (1987). The mandatory claims process
    is set forth in Maryland Code (2009, 2015 Repl. Vol.), State Finance & Procurement
    Article (SFP), Title 15 and COMAR 21.10. COMAR 21.07.02.05-1D provides, “[w]ithin
    30 days after contractor knows or should have known of the basis for a claim relating to
    this contract, contractor shall file a written notice of claim with the procurement officer.”
    Further, “[a] notice of claim or a claim that is not filed within the time prescribed in
    Regulation .02 of this chapter shall be dismissed.” COMAR 21.10.04.02C.
    A.     Knowledge Of A Basis For Submitting A “Request for Payment” That
    Is Not In Dispute When Submitted Does Not Establish Knowledge Of “A
    Basis For A Claim.”
    To determine whether Manekin failed to comply with the timing requirements, the
    Board was required to consider whether Manekin “[knew] or should have known of the
    basis for a claim” more than thirty days before it submitted its notice of claim to the
    which there is no genuine dispute, and that all factual inferences must be resolved in favor
    of the adverse party at this point in the proceeding.” Thereafter, the letter provides that the
    parties should prepare for trial accordingly.
    19
    procurement officer on April 10, 2013. See COMAR 21.07.02.05-1D. To apply this
    provision correctly, therefore, the Board was required to make a finding of fact, accurately
    identifying “a basis for a claim” pursuant to COMAR 21.07.02.05-1. A “claim” is defined
    in the following provision:
    As used herein, claim means a written demand or assertion by
    one of the parties seeking, as a legal right, the payment of
    money, adjustment or interpretation of contract terms, or other
    relief, arising under or relating to this contract. A voucher,
    invoice, or request for payment that is not in dispute when
    submitted is not a claim under this clause. However, if the
    submission subsequently is not acted upon in a reasonable
    time, or is disputed as to liability or amount, it may be
    converted to a claim for the purpose of
    this clause.
    COMAR 21.07.02.05-1C (emphasis added).
    Pursuant to COMAR 21.07.02.05-1C, a contractor’s knowledge of the basis for
    “request[ing] payment that is not in dispute when submitted” is not the same as having
    knowledge of the basis of a “claim.” Manekin’s submission of a PCO, therefore, is not
    dispositive evidence of having knowledge of the basis for a claim. Once a request for
    payment is disputed, however, a claim arises. The thirty-day limitations period under
    COMAR 21.07.02.05-1D would begin, therefore, once the contractor knows or should
    have known of a dispute or denial of its request.
    As we have 
    explained supra
    , although we attribute some weight to an agency’s
    expertise and its interpretation of a statute that it administers, we review questions of law
    de novo. See Assateague 
    Coastkeeper, supra
    , 200 Md. App. at 690. Here, however, the
    Board in its decision provided no interpretation of COMAR 21.07.02.05-1. Indeed, in
    20
    explaining the Board’s decision, Presiding Member Dembrow stated, “[i]t appears that the
    basis of the claim was initially known back in November of 2011,” referring to the date
    that Manekin first raised the issues contained in PCO No. 68 in a letter to DGS prior to
    submitting PCO No. 68. It is not clear, therefore, whether the Board equated having
    knowledge of a basis for submitting a request for payment that was not in dispute when
    submitted with a “basis for a claim.”
    Although the Board’s prior interpretations of a statute do not create mandatory
    authority for this Court, we note that the Board’s application of the timing provisions in
    COMAR 21.07.02.05-1 in this case is inconsistent with the Board’s own interpretations in
    some of its prior decisions. For example, in Info. Sys. & Networks Corp., MSBCA No.
    2225 (March 4, 2004), the Board found that the thirty-day limitations period began upon
    the appellant’s receipt of the procurement officer’s letter denying the appellant’s change
    order request (i.e. a “PCO”). On January 22, 1999, after the parties had contemplated an
    increase to the contract ceiling during weekly progress meetings, the appellant submitted a
    formal request for a change order. Thereafter, the appellant sent the agency two follow-up
    requests for a decision on its January 22, 1999 request and did not receive a response until
    the procurement officer’s July 23, 1999 denial letter. The Board concluded that the thirty-
    day limitations period did not begin until the appellant received the procurement officer’s
    denial letter. 
    Id. at 13.
    In its written decision, the Board reached the following conclusions:
    Until [the procurement officer’s] letter of July 23, 1999
    rejecting Appellant’s change order request, Appellant had no
    reason to believe that its change order was in dispute.
    Appellant timely filed a notice of claim and claim regarding
    the Procurement Officer’s . . . July 23, 1999 rejection of its
    21
    change order request, which was confrontational and put
    Appellant on notice that it must file a claim.
    
    Id. Similarly, in
    David A. Bramble, Inc., MSBCA No. 2823 (July 5, 2013), the Board
    found that the contractor’s notice of claim was not timely because the contractor admitted
    that he had actual notice of the agency’s rejection of his proposal more than thirty days
    before filing a notice of claim. In Syscom, Inc., MSBCA No. 2268 (July 5, 2002), the
    Board found that a dispute triggering the limitations period did not arise prior to the
    procurement officer’s decision that the agency’s additional reporting directives to the
    contractor were within the scope of the underlying contract. 
    Id. at 8.
    Notably, in that case,
    the contractor had previously sent a letter to the agency, refusing to carry out the directives
    without an approved change order. 
    Id. at 2.
    In these decisions, the Board’s findings are consistent with our interpretation in this
    case of COMAR 21.07.02.05-1C and D -- that the thirty-day limitations period begins
    when the contractor has notice that the agency disputes the contractor’s request. In
    determining whether Manekin complied with the timing requirements, the Board was
    charged with deciding whether Manekin had notice from DGS that DGS disputed or denied
    its request contained in PCO No. 68 more than thirty days before Manekin filed its notice
    of claim.
    22
    B.     The Board Made Findings of Fact on Disputed Issues by Determining
    the Meaning of “Void” and that Manekin was to Provide Additional
    Information by March 1, 2012.
    In addition to finding that Manekin knew of the issues raised in PCO No. 68 as early
    as November 2, 2011, the Board found, alternatively, that Manekin should have known
    that DGS disputed the request contained in PCO No. 68 by February 2012. In so doing,
    the Board relied primarily on notations in the PCO Log and Progress Meeting minutes to
    make at least two improper findings of fact prior to a full hearing on the merits. Critically,
    both of these factual conclusions were determinative in its decision.
    First, the Board relied, in part, upon the fact that PCO No. 68 was designated as
    “VOID” in the PCO Log to conclude that Manekin knew or should have known of the basis
    of a claim by December of 2011, and “certainly . . . as of February 2012.” Presiding
    Member Dembrow explained the Board’s reliance on the “VOID” notation in the following
    portion of the Board’s decision:
    [I]t is clear that even giving the Appellant the benefit of all
    doubt the ripple effect claim was first raised to the State by
    correspondence November 2, 2011. It was formally submitted
    as a proposed change order on December 7, 2011. And the
    very next day the State indicated to Appellant that the PCO
    was, quote, void, end quote. Now that was clear in the mind of
    some of the Members of the Board that that meant reject. [ . . . ]
    * * *
    It appears that the basis of the claim was initially known back
    in November of 2011. It certainly was known as of February
    2012. But this claim was not filed until a year later.
    At various points during the evidentiary hearing, however, Presiding Member
    Dembrow emphasized the need for additional clarification. Presiding Member Dembrow
    23
    found the term “void” particularly troubling in relation to the undisputed fact that the
    minutes from Progress Meetings 37 and 39 reference a comment by Sharpe to “leave
    discussion open on compensational [sic],” which the Board acknowledged is difficult to
    interpret. Further, in addition to the term “void,” the PCO Log included the term “rejected”
    as the status for other PCOs. Presiding Member Dembrow pointed out that Rohrbach
    admitted during his deposition that there was a difference between the terms “void” and
    “rejected, explaining that “void” meant “you can come back later.” During the evidentiary
    hearing, Presiding Member Dembrow stated to counsel for DGS, “I’ve been waiting to hear
    from Mr. Rohrbach. In this affidavit he . . . reiterates that he uses the word void. It seems
    odd that he doesn’t say PCO 68 was rejected.” He later added, “Now, frankly, . . . there’s
    nothing in this affidavit that says what Mr. Rohrbach intended by the word void . . . .”
    Thereafter, Presiding Member Dembrow informed counsel for DGS, “I’m putting the State
    on fair notice where we need, where at least I need clarification. And that goes to the
    question of what they meant when they said voided give us fragnets. We’re trying to get
    to that, and the parties have opposite points of view.” As Presiding Member Dembrow
    stated, “[T]hat’s the crux of the issue. [ . . . ] We’re still trying to figure out what was meant
    by void.”
    The only evidence presented at trial that was relevant to the meaning of the term
    “void,” however, was Sharpe’s testimony concerning his understanding of the term.
    Sharpe testified that he interpreted “void” to mean that the issue would be left open to raise
    again at a later date, and in this case, not until Manekin had compiled and submitted the
    information requested. Further, Sharpe testified that he was not aware that DGS disputed
    24
    Manekin’s request until DGS denied Manekin’s “Request for Equitable Settlement” on
    March 18, 2013.
    The blurring of the line between a hearing on the motion for summary decision and
    the evidentiary hearing, during which testimony had already begun, presents procedural
    challenges. Without hearing Rohrbach’s testimony on the merits of the claim, certain
    Board Members found his deposition testimony and affidavit convincing enough to draw
    conclusions of fact regarding the meaning of the “void” notation. For instance, Chairman
    Collins stated to Sharpe during his cross-examination, “Mr. Rohrbach in this deposition
    [said PCO No. 68] was . . . gone.” Chairman Collins paraphrased his understanding of
    Rohrbach’s deposition testimony, in which Rohrbach explained his interpretation of the
    meaning of “void,” in the following way: “[W]e are going to void this, and you can come
    back later. This is null and void. This is gone. But you know if you can produce that
    fragnet down the road show me another PCO.” Based, in part, on Rohrbach’s explanation,
    Chairman Collins added that Manekin should have known there was a dispute. This factual
    finding, however, was not permitted at this stage of the proceeding. The parties disputed
    the meaning of the term “void,” which was not defined in relevant statutes or the parties’
    contract. The Board erred, on a motion for summary decision, in determining whether the
    notation of “void” indicated that Manekin knew or should have known that DGS had
    rejected PCO No. 68, and thus, that the basis of a claim had arisen more than thirty days
    before Manekin submitted its notice of claim.
    The Board further erred in finding that Manekin had committed to providing the
    fragnets for PCO No. 68 by March 1, 2012. The Board reached this finding based on a
    25
    vague notation contained in the minutes from Progress Meeting 39 held on February 2,
    2012. 6 Presiding Member Dembrow stated as follows:
    [I]n the minutes being dated February 7, 2012,[7] there is [a]
    reference that Mr. Sharpe stated or at least the minutes state,
    quote, Dan Sharpe offered March 1, 2012 and leave discussion
    open on compensational, period. . . . [I]t’s somewhat difficult
    to know what that even means. [ . . . ] [But] [t]here had not
    been a reference for the need for further documentation by way
    of fragnets since January 19, 2012. At least as of February 2nd,
    Mr. Sharpe was saying we’ll do this by March 1, 2012.
    * * *
    So even if we give the, the Appellant the benefit of all doubt
    and give them [until] March 1, 2012[] as the trigger date for
    the beginning of that 30-day statute of limitations, we’re still
    a year late.
    During the hearing, however, the Board raised questions regarding why DGS
    continued to ask for fragnets while designating PCO No. 68 as void. Indeed, Presiding
    Member Dembrow acknowledged during Sharpe’s testimony that, although Rohrbach
    stated in his affidavit that he did not tell Manekin that they could later return to PCO No. 68,
    the minutes reflect that DGS had continued to ask for fragnets while simultaneously
    marking it as “void.” Presiding Member Dembrow stated, “They’re requiring fragnets.
    6
    The circuit court’s review of the Board’s decision supports our finding that the
    Board made findings of fact that were material to the Board’s decision to grant summary
    decision in favor of DGS. Indeed, we agree with the circuit court that “[t]he [Board] made
    a finding of fact that Manekin was on notice of DGS’s denial of its requests under PCO 68
    by the end of February 2012,” because Manekin had not produced the requested fragnets.
    7
    The minutes for Progress Meeting 39 were finalized on February 7, 2012.
    26
    They want this information. [ . . . ] Obviously there was anticipation that they were going
    to submit something or they wouldn’t have . . . requested it.”
    The Board’s conclusion that Manekin’s Vice President had offered March 1, 2012
    as the deadline by which Manekin would provide the fragnets involves a finding of fact on
    a disputed issue. The Board acknowledged during the proceedings that the notation “Dan
    Sharpe offered March 1, 2012 and leave discussion open on compensational [sic]” required
    further clarification. Manekin did not concede that the parties had discussed a particular
    deadline for Manekin’s submission of the fragnets for PCO No. 68. Instead, Sharpe
    explained during his testimony only that he had requested that the parties leave the issue
    open. 8 Additionally, other notations within the minutes for Progress Meeting 39, under
    the same points of discussion, refer to “March 1, 2012” in relation to the notation
    “Substantial Completion Punch List and begin Barrack move.” In other words, whether the
    notation indicated that Sharpe had agreed to a March 1, 2012 deadline to produce fragnets
    for PCO No. 68 was not a permissible finding at this stage of the proceedings.
    Furthermore, although March 1, 2012 is later than the other dates considered by the
    Board as potentially starting the limitations period, the finding that the thirty-day period
    began on March 1, 2012 was not sufficient to “resolv[e] all inferences in favor of the party
    against whom the motion is asserted.” COMAR 21.10.05.06.D(2)(a). Manekin argued
    that the limitations period did not begin until April 3, 2013, when DGS denied Manekin’s
    8
    Additionally, when the notation was raised during the cross-examination,
    Presiding Member Dembrow agreed that Sharpe’s testimony -- that he had requested the
    parties keep the issue of PCO No. 68 open -- was consistent with his own interpretation of
    the meeting minutes.
    27
    “Request for Equitable Settlement.” The Board inferred that Manekin was required to
    provide fragnets by March 1, 2012, and therefore, that Manekin knew or should have
    known of a dispute on that date. This inference was not permitted since the relevant
    COMAR provision directed the Board to resolve all inferences at this stage of the
    proceeding in favor of Manekin. Based on the Board’s determination of March 1, 2012 “as
    the trigger date for the beginning of [the thirty-day] statute of limitations,” however, the
    Board concluded that Manekin had submitted its notice of claim more than a year late. The
    Board’s conclusion that Sharpe was required to provide the fragnets for PCO No. 68 by
    March 1, 2012 was, therefore, an improper finding of fact at this stage of the proceeding.
    The point at which the thirty-day limitations period began, as the Board has
    indicated in several prior decisions 
    noted supra
    , is the moment Manekin knew or should
    have known that DGS rejected or denied the request contained in PCO No. 68. The point
    in time when Manekin should have known of a denial of its request involves a disputed
    material fact, which the Board was not authorized to resolve via summary decision. The
    Board’s task was, first, to determine if there existed any “issue[s] of material fact,” after
    resolving all reasonable inferences in favor of Manekin. The Board, therefore, was required
    to hear the merits of the case and apply the appropriate meaning of “a basis for a claim”
    under COMAR 21.07.02.05-1 in its final determination.
    The Board erred by terminating the proceedings after hearing from only one of
    Manekin’s witnesses. The Presiding Member of the Board stated:
    At this time there will not be a need for recross-examination
    because the Board has unanimously determined to grant the
    State’s Motion for Partial Summary [Decision] Number 3.
    28
    After listening carefully to the testimony of Mr. Sharpe, . . . it
    is clear that even giving the Appellant the benefit of all doubt
    the . . . claim was first raised to the State by correspondence
    November 2, 2011.
    Presiding Member Dembrow concluded, “We wanted to hear testimony from Mr. Sharpe
    and give [him] the benefit of all doubt. We are comfortable that we’ve done that now.”
    Presiding Member Dembrow added that “the testimony . . . confirmed the view of some of
    the Board Members a long time ago.” Sharpe made no explicit concession during his
    testimony, however, that was dispositive on the issue of when Manekin knew or should
    have known that DGS disputed Manekin’s request for additional compensation contained
    in PCO No. 68.
    The Board’s error in this case stems, primarily, from its failure to adhere to
    procedural processes. The standards for summary decision as opposed to a merits hearing
    are fundamentally different. The Board should not consider a motion for summary decision
    during an evidentiary hearing, unless the rules expressly provide for it. The only evidence
    presented at the evidentiary hearing at the time the Board stopped the proceedings was
    testimony that served to confirm that the parties disputed a material fact.        The Board,
    however, made findings of fact on those disputed issues and then granted summary
    decision. In doing so, the Board blurred the line between determining whether a disputed
    fact existed and making findings of fact based on the evidence presented at the evidentiary
    hearing. The Board’s consideration of whether to grant summary decision during the
    proceedings on the merits creates confusion and, as shown here, increases the chance for
    error by both the Board and the circuit court.
    29
    Accordingly, we hold that the Board erred in its decision to terminate the
    proceedings and grant summary decision in favor of DGS. We, therefore, remand to the
    Board to decide, after hearing all of the evidence, when DGS communicated a dispute or
    denial of PCO No. 68 to Manekin such that it knew or should have known that it was
    required to submit a notice of claim to DGS within 30 days.
    JUDGMENT OF THE CIRCUIT COURT FOR
    HOWARD     COUNTY    REVERSED. CASE
    REMANDED TO THE BOARD OF CONTRACT
    APPEALS FOR FURTHER PROCEEDINGS
    CONSISTENT WITH THIS OPINION. COSTS
    TO BE PAID BY APPELLEE.
    30
    

Document Info

Docket Number: 0600-16

Citation Numbers: 163 A.3d 214, 233 Md. App. 156

Judges: Berger

Filed Date: 6/28/2017

Precedential Status: Precedential

Modified Date: 1/12/2023