Bel Air Carpet v. Korey Homes Bldg Grp ( 2021 )


Menu:
  • Bel Air Carpet, Inc. v. Korey Homes Building Group, LLC, et al.
    No. 1006, Sept. Term, 2019
    Opinion by Leahy, J.
    Negligence > Duty of Care > Economic Loss Doctrine
    Maryland has adopted the economic loss doctrine, which generally precludes tort liability
    for “negligence that causes purely economic harm in the absence of privity, physical injury,
    or risk of physical injury.” Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl,
    LLP, 
    451 Md. 600
    , 611 (2017).
    Negligence > Duty of Care > Economic Loss Doctrine > Intimate Nexus
    “Where the failure to exercise due care creates a risk of economic loss only, courts have
    generally required an intimate nexus between the parties as a condition to the imposition
    of tort liability.” UBS Fin. Servs., Inc. v. Thompson, 
    217 Md. App. 500
    , 525 (2014)
    (quoting 100 Inv. Ltd. P’ship v. Columbia Town Ctr. Title Co., 
    430 Md. 197
    , 214 (2013)).
    “This intimate nexus is satisfied by contractual privity or its equivalent.” Jacques v. First
    Nat’l Bank of Md., 
    307 Md. 527
    , 534-35 (1986).
    Negligence > Duty of Care > Economic Loss Doctrine > Intimate Nexus
    In concluding our survey of the intimate nexus test, we quote Judge Adkins’s observation
    about the level of conduct linking the plaintiff to the defendant that is required to establish
    an intimate nexus:
    These cases illustrate that regardless of whether we apply the Credit
    Alliance/Walpert test, our privity-equivalent analysis in economic loss cases
    looks for linking conduct—enough to show the defendant knew or should
    have known of the plaintiff's reliance. This means, of course, that context is
    critical.
    Balfour Beatty, 451 Md. at 620-21.
    Negligence > Duty of Care > Economic Loss Doctrine > Intimate Nexus >
    Construction Industry > Lender
    We conclude that Maryland law does not recognize a general duty on the homeowner’s
    lender to ensure that the general contractor on a home construction project pays all of its
    subcontractors for work completed when the lender disburses funds to the general
    contractor, and where there is no privity of contract or intimate nexus between the lender
    and the subcontractors. The public policy of Maryland and other states disfavor imposing
    such a general duty of care on home construction lenders. As we note above, it would be
    “manifestly unfair” to make lenders the “insurer of the subcontractors’ interests” by
    imposing a general duty on lenders to ensure that general contractors properly pay
    unknown subcontractors for their work. See Richard F. Kline, Inc. v. Signet
    Bank/Maryland, 
    102 Md. App. 727
    , 733 (1995).
    Negligence > Duty of Care > Economic Loss Doctrine > Intimate Nexus > Pleading
    Requirements
    We hold that Bel Air Carpet has failed to allege a cognizable duty of care owed to it by
    Hamilton Bank because Bel Air Carpet does not allege privity or any equivalent intimate
    nexus in the complaint. The complaint does not allege the necessary “linking conduct”
    between the parties to justify Bel Air Carpet’s reliance that Hamilton Bank would ensure
    that its borrower’s funds were paid to Bel Air Carpet.
    Negligence > Duty of Care > Economic Loss Doctrine > Intimate Nexus > Pleading
    Requirements
    As our review of our cases requiring an intimate nexus highlights, the plaintiff must allege
    “linking conduct” sufficient to “show the defendant knew or should have known of the
    plaintiff’s reliance.” Balfour Beatty, 451 Md. at 620-21. Nowhere in the complaint does
    Bel Air Carpet allege that Hamilton Bank made a specific promise or representation to
    perform an obligation for Bel Air Carpet’s benefit or that Hamilton Bank knew that Bel
    Air Carpet was relying on it. Bel Air Carpet seeks to cure this defect by asserting a broad-
    based standard in the construction industry. Unfortunately for Bel Air Carpet, neither
    Maryland nor most other states recognize such a broad-based duty of care that requires a
    lender to ensure that subcontractors and suppliers are paid.
    Negligence > Duty of Care
    Although it may be foreseeable that Hamilton Bank’s failure to request mechanic’s lien
    releases or inspect the properties could harm Bel Air Carpet, unless Hamilton Bank owes
    Bel Air Carpet a duty, Hamilton Bank cannot be liable to Bel Air Carpet in negligence.
    Ashburn v. Anne Arundel Co., 
    306 Md. 617
    , 628 (1986) (“[T]here is no duty to control a
    third person’s conduct so as to prevent personal harm to another, unless a ‘special
    relationship’ exists either between the actor and the third person or between the actor and
    the person injured.”).
    Circuit Court for Harford County
    Case No. C-12-CV-19-000151
    REPORTED
    IN THE COURT OF SPECIAL APPEALS
    OF MARYLAND
    No. 1006
    September Term, 2019
    ______________________________________
    BEL AIR CARPET, INC.
    v.
    KOREY HOMES BUILDING GROUP, LLC,
    ET AL.
    ______________________________________
    Kehoe,
    Nazarian,
    Leahy,
    JJ.
    ______________________________________
    Opinion by Leahy, J.
    ______________________________________
    Filed: January 28, 2021
    Pursuant to Maryland Uniform Electronic Legal
    Materials Act
    (§§ 10-1601 et seq. of the State Government Article) this document is authentic.
    2021-04-30 15:00-04:00
    Suzanne C. Johnson, Clerk
    The underlying lawsuit was brought by a subcontractor in the construction industry
    left unpaid at the end of a construction project.1 Appellant Bel Air Carpet, Inc. (“Bel Air
    Carpet”) was one of the last subcontractors to complete work on a series of new homes
    built by Korey Home Building Group, LLC (“Korey Homes”), a custom home builder with
    its principal place of business in Harford County. Bel Air Carpet filed a negligence action
    to recover damages in the Circuit Court for Harford County against Korey Homes and
    several other defendants. This appeal concerns just one of the defendants in that action—
    appellee Hamilton Bank.2
    The trial court granted Hamilton Bank’s motion to dismiss the single count of
    negligence against it on the ground that the complaint failed to state a claim because Bel
    Air Carpet failed to allege any contractual relationship or intimate nexus between it and
    Hamilton Bank to establish a duty of care. Upon a consent motion, the circuit court
    certified its order as final and appealable under Maryland Rule 2-602(b).
    1
    Maryland has been grappling with the problem of unpaid contractors on
    construction projects since the time it became the seventh state to ratify the U.S.
    Constitution in 1788. The General Assembly enacted the first mechanic’s lien law in the
    United States in December 1791 to encourage the building of Washington, D.C. by
    granting contractors the ability to obtain a lien on property to ensure payment for their work
    on a project. 1791 Md. Laws Ch. 45, § 10.
    2
    After the litigation was commenced, Orrstown Financial Services, Inc., the holding
    company for Orrstown Bank, acquired Hamilton Bancorp, Inc., which operated Hamilton
    Bank. Hamilton Bank is now known as Orrstown Bank. To avoid confusion, as the parties
    adopt in their briefs, we will continue to refer to the successor entity as Hamilton Bank.
    Bel Air Carpet presents two questions for our review,3 which we have recast as
    follows:
    I.             Did the circuit court err in dismissing the negligence count against Hamilton
    Bank by finding, as a matter of law, that Hamilton Bank did not owe a duty of
    care to Bel Air Carpet?
    II.            Did the circuit court err or abuse its discretion in dismissing the negligence count
    against Hamilton Bank prior to discovery?
    Bel Air Carpet urges that we hold that Hamilton Bank owed a duty of care to the
    subcontractors of Korey Homes to ensure they were paid under the theory that Hamilton
    Bank should have required mechanics lien releases from all subcontractors and conducted
    independent inspections of the work. Maryland law does not support the imposition of
    such a duty, and we cannot step beyond the statutes and cases that the Maryland General
    Assembly and our Courts have established to create one. We further note that, because the
    existence of a duty is a legal determination, the circuit court did not abuse its discretion in
    dismissing the negligence count prior to discovery. Consequently, we affirm the judgment
    of the circuit court.
    3
    The questions presented in Bel Air Carpet’s opening brief are:
    “1.         Whether a construction lender owes a duty of care to a subcontractor
    where that bank releases funds to a general contractor, a portion of
    which belongs to the subcontractor, without requiring lien releases
    from subcontractors or conducting inspections to ensure the work on
    the custom home had been completed, which are both standard
    lending industry practices and a contractual condition precedent to
    releasing the funds to the general contractor?
    2.      Did the lower court err when it dismissed Bel Air Carpet’s claim for
    negligence prior to discovery?”
    2
    BACKGROUND4
    Bel Air Carpet sells and installs flooring materials, including carpet, hardwood
    flooring and ceramic tile. As stated in Bel Air Carpet’s complaint, “[f]rom on or about
    March 28, 2018 through July 14, 2018, [Bel Air Carpet] and Korey Homes entered into a
    contract whereby [Bel Air Carpet] provided materials and labor for the installation of
    flooring and wall materials to all of Korey Homes’ private custom home contracts based
    upon building specifications provided by Korey Homes[.]” In total, Korey Homes placed
    orders to Bel Air Carpet to provide labor and material to install flooring at twelve different
    custom homes in Harford and Baltimore Counties. In return, Korey Homes “agreed to pay
    [Bel Air Carpet] out of the sums obtained either directly from the homeowners or through
    draws issued from the buyers’ lenders, the collective sum of three-hundred thirteen
    thousand, nine-hundred dollars and fifty-two cents ($313,900.52) for all materials and
    labor.”
    Hamilton Bank financed seven of the twelve custom homes for which Bel Air
    Carpet supplied and installed flooring and related materials. Bel Air Carpet provided
    invoices to Korey Homes for its work on the seven homes financed by Hamilton Bank.
    These invoices totaled $171,167.29.
    4
    As this appeal is from the grant of a motion to dismiss the negligence count for
    failure to state a claim upon which relief can be granted, the evidentiary background will
    “assume the truth of all well-pleaded facts and allegations in the complaint.” Lloyd v. Gen.
    Motors Corp., 
    397 Md. 108
    , 121 (2007) (citing Morris v. Osmose Wood Preserving, 
    340 Md. 519
    , 531 (1995)).
    3
    Bel Air Carpet avers that it “provided all of the requested materials and labor” and
    “completed the work” for the twelve homes “in a good and workmanlike fashion.”
    Despite submitting invoices for this work, Korey Homes never paid Bel Air Carpet.
    Mechanic’s Liens
    In an attempt to recover its losses, Bel Air Carpet “retained [] counsel to protect its
    rights utilizing the Maryland Mechanic’s Lien Statute in order to obtain payment of its
    outstanding invoices.” In response, Korey Homes held a meeting on September 28, 2018
    with approximately twenty subcontractors and informed them that Korey Homes had no
    funds to pay the amounts owed. However, Korey Homes also assured the subcontractors
    that it would contact each subcontractor to devise a plan to pay their invoices, although
    most invoices would need to be reduced. Korey Homes “implored the subcontractors in
    attendance to continue to work on Korey Homes’ contracts and to refrain from filing
    mechanic’s liens because the subcontractors, including [Bel Air Carpet], would receive
    ‘pennies on the dollar’ from the homeowners and because it was not the buyers’ fault that
    Korey Homes did not pay the subcontractors[.]” Less than a week later, “on or about
    October 2, 2018, Korey Homes shuttered its doors and never communicated further with
    [Bel Air Carpet].”
    Complaint
    On February 15, 2019, Bel Air Carpet filed a seven-count complaint in the Circuit
    Court for Harford County against Korey Homes, the individual members of Korey
    Homes—Korey and Stacy Smith, and Hamilton Bank. The first six counts of the complaint
    included a breach of contract claim against Korey Homes and a variety of counts against
    4
    both Korey Homes and Korey and Stacy Smith: trover and conversion; constructive fraud
    and breach of fiduciary duty; intentional misrepresentation (fraud and deceit); violation of
    the Maryland Construction Trust Statute; and violation of the Maryland Custom Home
    Protection Act. The seventh count asserted a negligence claim against Hamilton Bank.
    In its complaint, Bel Air Carpet alleged the following pertinent facts concerning
    Hamilton Bank under the heading “Facts”:
    • Korey Homes and Hamilton Bank had a relationship in which Hamilton
    Bank ignored most, if not all, standard financial practices in disbursing
    construction loan funds to Korey Homes on behalf of its borrowers. For
    example, Hamilton Bank did not require Korey Homes, Korey [Smith],
    or Stacy [Smith] . . . to obtain Mechanic’s Lien Releases from its
    subcontractors before Hamilton Bank would issue draws to Korey Homes
    despite Hamilton Bank’s explicit requirement that releases were a
    condition precedent to Korey Homes receiving draws. Hamilton Bank
    never required Korey Homes to furnish requisition orders prior to
    disbursement, which was also a condition precedent to Hamilton Bank
    issuing draws. Indeed, Hamilton did not require Korey Homes to show
    any evidence that Korey Homes completed its work or paid its
    subcontractors before Hamilton released additional funds to Korey
    Homes.
    • In contrast to Hamilton Bank, other lenders required Korey Homes to
    obtain and forward Mechanic’s Lien Releases before releasing draws.
    • Hamilton Bank issued wires of its borrowers’ funds based only [on] a
    phone call from Korey [Smith], without additional documentation from
    Korey Homes.
    • Hamilton Bank wired hundreds of thousands of dollars to Korey Homes,
    some of which [Bel Air Carpet] had earned and was entitled to, into Korey
    Homes’ operating account without obtaining any accountability from
    Korey Homes that Korey Homes used that money to pay its
    subcontractors.
    In its negligence count against Hamilton Bank, Bel Air Carpet asserted that
    “Hamilton Bank owed a duty of care to [Bel Air Carpet] to ensure that the funds it disbursed
    5
    to Korey Homes w[ere], in fact, paid to [Bel Air Carpet].” Hamilton Bank breached its
    duty to Bel Air Carpet “by failing to obtain Mechanic’s Lien Releases . . . for work
    performed and materials provided to its borrowers’ custom homes,” which was “standard
    industry practice.” Bel Air Carpet claimed that their “losses proximately resulted from
    Hamilton Bank’s breach of its duty of care.”
    Motion to Dismiss
    On March 19, 2019, Hamilton Bank filed a motion to dismiss in the circuit court.
    In its memorandum in support of this motion, Hamilton Bank argued that Bel Air Carpet
    could not “prevail on its negligence claim against Hamilton Bank as a matter of law
    because Hamilton Bank had no obligation to ensure that Korey Homes paid subcontractors
    such as Bel Air [Carpet].”
    Invoking the economic loss rule as articulated in Jacques v. First National Bank of
    Maryland, 
    307 Md. 527
    , 534 (1986), Hamilton Bank asserted that “[i]t is well-settled that,
    ‘[w]here the failure to exercise due care creates a risk of economic loss only, courts have
    generally required an intimate nexus between the parties as a condition to the imposition
    of tort liability.’” According to Hamilton Bank, due to the intimate nexus requirement,
    “courts have generally concluded that a lender does not owe a duty of care to non-
    customers such as Bel Air [Carpet].” Hamilton Bank averred that it did not have a contract
    with Bel Air Carpet and that Bel Air Carpet failed to allege “the existence of any
    relationship between itself and Hamilton Bank, let alone a close relationship of the type
    that could give rise to an ‘intimate nexus.’” (Emphasis in original.) Relying on Richard
    F. Kline, Inc. v. Signet Bank/Maryland, 
    102 Md. App. 727
    , 735 (1995) and related cases
    6
    from other jurisdictions, Hamilton Bank argued that courts “uniformly hold[] that a
    construction lender does not owe any duty to a subcontractor, including a duty to ensure
    that the subcontractor is paid by the contractor that hired it.”
    Finally, Hamilton Bank asserted that, even if it owed a duty of care to Bel Air
    Carpet, the failure to obtain mechanics’ lien releases would not breach that duty or ensure
    that the subcontractors would have been paid. Rather, “[w]hether or not subcontractors
    were ultimately paid depended solely upon whether Korey Homes paid them, either from
    its own funds or from the proceeds of the draws advanced to it by Hamilton Bank on behalf
    of the [borrowers].”
    In its opposition, filed April 17, 2019, Bel Air Carpet argued that Kline was
    “inapposite to the facts of this case,” because the “Court opined that Signet owed no duty
    to Kline based on the facts of that case and within the context of unjust enrichment.” Bel
    Air Carpet asserted that it “brought a claim of negligence against Hamilton Bank for failing
    to ensure that its borrower’s funds were utilized by the general contractor for their express
    intended purpose – to pay the subcontractors.”
    Bel Air Carpet averred that it set out a prima facie claim for negligence by alleging:
    (1) Hamilton Bank had a duty to ensure that the funds it disbursed were
    utilized for their intended purposes; (2) [] Hamilton Bank breached its duty
    to [Bel Air Carpet] by failing to obtain mechanic’s lien releases, as expressly
    required by Hamilton Bank and in compliance with standard industry
    practices, before issuing draw payments to [] Korey Homes; and (3) [] this
    breach of duty proximately caused damages in excess of $150,000.00.
    Bel Air Carpet conceded there was no contractual privity between it and Hamilton Bank
    but averred that it had “adequately pled ‘its equivalent.’” Specifically, relying on Walpert,
    7
    Smullian & Blumental, P.A. v. Katz, 
    361 Md. 645
     (2000) and Iglesias v. Pentagon Title &
    Escrow, LLC, 
    206 Md. App. 624
     (2012), Bel Air Carpet claimed that, because Hamilton
    Bank had an obligation to “ensure that its borrowers’ funds were properly utilized,” the
    bank “knew or should have known that Bel Air [Carpet] was likely to take some action
    based on what Hamilton Bank said or did.” Bel Air Carpet asserted that public policy
    requires Hamilton Bank to be held liable because “[f]ollowing their own rules and industry
    standards would have minimized losses by everyone involved, including the
    subcontractors, and would have instilled trust that everyone’s money was protected.”
    In reply, Hamilton Bank contended that the complaint “contains no allegations
    establishing the existence of an ‘intimate nexus’ . . . sufficient to constitute the ‘equivalent’
    of contractual privity.” Hamilton Bank noted that the complaint did not allege that it was
    aware that Bel Air Carpet was one of Korey Homes’ subcontractors and asserted that the
    complaint “demonstrate[d] that Bel Air [Carpet] was a complete stranger whose existence
    was completely unknown to Hamilton Bank.”
    Hamilton Bank stated that it was “simply a conduit for monies owed by its
    borrowers to Korey Homes,” and lambasted Bel Air Carpet’s failure to cite legal authority
    for the proposition that a lender owes a duty to ensure that a general contractor uses
    disbursed funds to pay its subcontractors. According to Hamilton Bank, no such authority
    exists, and Bel Air Carpet’s negligence claim was not supported by public policy.
    Specifically, relying on Kline, 102 Md. App. at 733, and cases from other jurisdictions,
    Hamilton Bank averred that “imposing a duty on construction lenders . . . to police the use
    8
    of funds disbursed to third parties” would “chill construction lending” and make the lender
    an “insurer of the subcontractors’ interests.”
    On June 25, 2019, the circuit court held a hearing on Hamilton Bank’s motion to
    dismiss. Counsel for the bank argued the points in the memoranda, adding that “in effect,
    the bank and Bel Air Carpet and all the other subcontractors are complete strangers.”
    Although counsel pointed out that “there’s really no case directly on point in Maryland,”
    he cited Kline for the proposition that “[y]ou can’t have a duty arising out of a relationship
    where the parties don’t know each other and haven’t had any prior dealings.”
    Counsel for Bel Air Carpet asserted that it “would be premature to dismiss [Bel Air
    Carpet’s] claims,” because discovery “would allow [Bel Air Carpet] and this [c]ourt to
    more appropriately respond to Hamilton Bank’s contentions that no duty exists between it
    and Bel Air Carpet.” The judge then questioned:
    Well, what do you expect, though, to find in those documents? Aren’t they
    just typical loan documents that the homeowners have gone to the bank . . .
    in order to get the funds to build these homes? So, how would they know
    what subcontractors Korey Homes intend[ed] to use? How would the bank
    know that? Why would that be in any of the loan documents?
    Counsel replied that the “loan documents w[ould] set forth the rules by which Hamilton
    Bank is going to issue the money . . . to Korey Homes intended for subcontractors.”
    Further, counsel asserted that the cases cited by Hamilton Bank “turned on the loan
    agreement,” which further supported Bel Air Carpet’s contention that the motion was
    premature. Counsel then asserted that “by not following their own rules[,] [Hamilton
    Bank] harmed Bel Air Carpet to the tune of more than $150,000.” Referencing back to
    Walpert and Iglesias, counsel submitted that while Hamilton Bank “may not have known
    9
    specifically that Bel Air Carpet was a subcontractor providing the work,” it “knew a
    subcontractor like Bel Air Carpet could be harmed by their failure to follow the rules and
    the common practices of the industry.” Finally, counsel argued that, had Hamilton Bank
    required mechanic’s lien releases, any failure to pay subcontractors would have been
    caught earlier.
    On rebuttal, counsel for Hamilton Bank asserted:
    [T]he bank’s duty and the reason why the bank has progress payments and
    sends inspectors out before each draw and inspects to make sure the work is
    done is because that home is the bank’s collateral, and the bank wants to
    make sure if it’s [disbursing] $100,000 that $100,000 worth of work’s been
    done. Once the work’s been done and the money is [disbursed], then the
    bank and the homeowner are protected because the value is in the ground.
    Counsel for Hamilton Bank avowed that Bel Air Carpet’s “theory of recovery makes zero
    sense” because Bel Air Carpet admits that the work was completed, and “Korey Homes
    was paid for the carpet that was put in the house.” The problem, counsel concluded, was
    “Korey Homes didn’t turn around and pay Bel Air Carpet under its contract.”
    In response to a question from the court whether Hamilton Bank should have gotten
    a mechanic’s lien release, counsel averred, pursuant to the Maryland Custom Home Statute,
    “the subcontractor cannot get a mechanic’s lien against a custom home unless the owner is
    in default under the contract with the builder and has not paid the builder. . . . So, once the
    homeowner has paid the contractor. . . ., there is no liability. . . .The subcontractor, Bel Air
    Carpet, in this case, has to look to Korey Homes.”
    Ruling from the bench, the judge granted the motion to dismiss, explaining:
    In this case, on a motion to dismiss, the [c]ourt is required to assume
    the truth of all of the well-pleaded facts within the complaint and the attached
    10
    exhibits and any reasonable inferences that may be drawn from that, and in
    the light most favorable to the nonmoving party in this case, . . . the plaintiff
    here in this case.
    [O]n a claim for negligence, one really critical element is that the
    plaintiff must show some duty on the part of the defendants to the plaintiffs,
    in this case, Hamilton Bank, having a duty to the plaintiff, Bel Air Carpet,
    Incorporated. Even if this case gets to trial, even if after discovery, I don’t
    see how the plaintiff can do that.
    In this case, just to use [counsel for Hamilton Bank’s] words, the bank
    is just a conduit for the funds. But there is no special relationship, no nexus
    that establishes a duty between the bank and [Bel Air Carpet] in this case.
    And I agree that when I read the Custom Home Statute there’s nothing that
    requires a mechanics lien or that permits a mechanics lien to be filed in this
    case or submitted in this case.
    So, there has to be some sort of contractual privity, and there’s none
    between these two parties in this case. That’s a critical element that
    underpins [Bel Air Carpet’s] complaint in this matter. And without the
    ability to show that nexus, it’s not even a matter of just showing that there is
    some economic benefit that [Hamilton Bank] gained. I think that’s a stretch
    in this case given that based on the contract that they had with the
    homeowners, they’re required to make draws to the contractor, Korey
    Homes, in this case. But there’s nothing, then, that gives the bank some
    special relationship with the contractor’s subcontractor just because they’re
    the ones that have the money, and they’re the ones that have to pay out on it.
    * * *
    And I agree there is no Maryland law on point, but in this case, I think the
    just general negligence law in this matter makes it clear that you have to have
    some duty that’s breached in order for the Court to find that based on the four
    corners of the complaint, any of exhibits, and any of the reasonable
    inferences from that that there is going to be some duty that the bank owed
    to Bel Air Carpet. If that’s the case, then every lender would do so, every
    lender would have that same obligation to every unknown subcontractor in
    this case, and that’s not the intent of the public policy of any of the statutes,
    of any of the case law that requires that there be some duty.
    So, in this case, finding that there is none, I am going to grant the
    motion to dismiss that the defendant, Hamilton Bank, has filed. I’ll sign an
    order [to] that effect.
    11
    On June 25, the circuit court entered a written order granting Hamilton Bank’s
    motion and dismissing the negligence count “WITH PREJUDICE AND WITHOUT
    LEAVE TO AMEND for failure to state a claim against Hamilton Bank upon which relief
    can be granted.” On July 26, the parties filed a consent motion to certify the circuit court’s
    order as a final and appealable judgment pursuant to Maryland Rule 2-602(b).5 On July
    29, the circuit court granted the consent motion, finding “that there is no just reason for
    delay,” and ordered that the order granting the motion to dismiss “is hereby determined to
    be a final judgment as to [Bel Air Carpet’s] claims against Hamilton Bank pursuant to
    Maryland Rule 2-602(b).”6 Bel Air Carpet then noted a timely appeal on August 7, 2019.
    STANDARD OF REVIEW
    Under Maryland Rule 2-322(b)(2), a defendant may seek a dismissal of a complaint
    if it fails “to state a claim upon which relief can be granted[.]” While generally confining
    its analysis to the “four corners of the complaint and its incorporated supporting exhibits,
    5
    We have previously explained: “It is this Court’s duty to examine a circuit court’s
    certification decision under Maryland Rule 2-602.” Shofer v. Stuart Hack Co., 
    107 Md. App. 585
    , 591 (1996). Because the order is dispositive of Bel Air Carpet’s entire claim
    against Hamilton Bank, certification was proper. See Snowden v. Balt. Gas & Elec. Co.,
    
    300 Md. 555
    , 563 (1984) (Authorization is “limited to orders which, by their nature, have
    a characteristic of finality. Such orders must be completely dispositive of an entire claim
    or party.”).
    6
    Following the certification of the order as final and appealable, on July 30, 2019,
    Korey and Stacy Smith filed a suggestion of bankruptcy in the circuit court, indicating that
    they had filed for bankruptcy protection in the United States Bankruptcy Court for the
    District of South Carolina under Chapter 7 of the United States Bankruptcy Code.
    Consequently, pursuant to 11 U.S.C. § 362, further proceedings involving the Smiths were
    stayed.
    12
    if any,” the trial court may grant a motion “only if the allegations and permissible
    inferences, if true, would not afford relief to the plaintiff, i.e., the allegations do not state a
    cause of action for which relief may be granted.” Floyd v. Mayor of Balt., 
    463 Md. 226
    ,
    241 (2019) (quoting State Ctr., LLC v. Lexington Charles Ltd. P’ship, 
    438 Md. 451
    , 496–
    97 (2014)).7
    We “review[] the grant of a motion to dismiss for legal correctness.” Rounds v.
    Maryland-Nat. Capital Park & Planning Comm’n, 
    441 Md. 621
    , 635 (2015) (citing Patton
    v. Wells Fargo Fin. Md., Inc., 
    437 Md. 83
    , 95 (2014)). “In conducting this review, we
    assume the facts and allegations in the complaint, and any inferences that may be drawn
    from them, are true and view them in a light most favorable to the non-moving party.”
    Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 
    451 Md. 600
    , 609
    (2017) (citation omitted).
    We review the denial of discovery for an abuse of discretion and will only conclude
    that the circuit court abused its discretion “‘where no reasonable person would take the
    view adopted by the [trial] court [ ]’ . . . or when the court acts ‘without reference to any
    guiding principles,’ and the ruling under consideration is ‘clearly against the logic and
    7
    Bel Air Carpet argues that it “properly relied upon Hamilton Bank’s draw
    schedule,” an exhibit to its memorandum, in opposing Hamilton Bank’s motion to dismiss,
    and that the court considered the exhibits in dismissing the negligence count. These
    documents are not relevant for our review. The circuit court judge ruled on the motion to
    dismiss and limited herself, as she explained, to “the well-pleaded facts within the
    complaint and the attached exhibits.” Consequently, the circuit court correctly “confine[d]
    [her] review . . . to the four corners of the complaint and its incorporating supporting
    exhibits, if any.” Rounds v. Maryland-Nat. Capital Park & Planning Comm’n, 
    441 Md. 621
    , 636 (2015).
    effect of facts and inferences before the court[ ]’ . . . or when the ruling is ‘violative of fact
    and logic.’” Moser v. Heffington, 
    465 Md. 381
    , 400 (2019) (quoting Wilson v. Crane, 
    385 Md. 185
    , 198 (2005)).
    DISCUSSION
    I.
    Negligence
    A. Parties’ Contentions
    Bel Air Carpet contends that it “set forth sufficient facts to form the basis of a prima
    facie negligence claim against Hamilton Bank and adequately pled the equivalent of
    contractual privity[.]” Specifically, relying on Walpert, Smullian & Blumental, P.A. v.
    Katz, 
    361 Md. 645
     (2000) and Iglesias v. Pentagon Title & Escrow, LLC, 
    206 Md. App. 624
     (2012), Bel Air Carpet avers that, because Hamilton Bank failed to follow “banking
    industry standards” and its own rules concerning how draws would be issued, it breached
    a duty to Bel Air Carpet. According to Bel Air Carpet, “had Hamilton Bank followed its
    own rules it would have ‘control[led] the risk to which [it was] exposed’ by simply
    obtaining mechanic’s lien releases for all of the previous work completed under successor
    draws and/or issuing dual-payee checks to ensure its borrowers signed off and thereby
    knew what work was being paid.”
    Further, Bel Air Carpet argues that public policy “requires that construction lenders
    like Hamilton Bank be held accountable for their negligence” for two reasons. First, “it
    seems nonsensical for construction lenders . . . to set out the non-negotiable and steadfast
    rules of how it will hold and disburse funds from trust that belong to borrowers and
    14
    subcontractors, subsequently act in bad faith by violating those very rules, and then claim
    that it has no liability to anyone.” Second, “[f]ollowing their own rules and industry
    standards would have minimized losses by everyone involved, including the
    subcontractors, and would have instilled trust that everyone’s money was protected.”
    To the contrary, Hamilton Bank asserts that “Bel Air Carpet cannot maintain a
    negligence claim against [it] because no contractual privity or its equivalent existed
    between Bel Air Carpet and Hamilton Bank.” Hamilton Bank contends that the complaint
    “demonstrates that Bel Air Carpet was a complete stranger” and that “Hamilton Bank’s
    only duty was to remit to Korey Homes the funds that [its] borrowers directed[.]” Relying
    on Richard F. Kline, Inc. v. Signet Bank/Maryland, 
    102 Md. App. 727
    , 735 (1995) and
    related cases from other jurisdictions, Hamilton Bank avers that “a construction lender does
    not owe a duty to ensure that subcontractors working on a job that the lender is financing
    are paid for their work.” Hamilton Bank urges that Bel Air Carpet’s negligence claim is
    not supported by public policy. Citing Kline, 102 Md. App. at 733, and other cases,
    Hamilton Bank contends that the imposition of a duty to “police the funds disbursed to
    third parties” would “clearly chill construction lending.”
    In its reply, Bel Air Carpet directs us to an Ohio statute, which, Bel Air Carpet
    mistakenly asserts, “codifies a duty between a construction lender and a subcontractor,
    even where there is no direct contract between the parties.”
    15
    B. Foundational Elements
    To sustain a cause of action for negligence in Maryland, a plaintiff must allege: (1)
    the defendant was under a duty to protect the plaintiff from harm; (2) a breach of that duty;
    (3) a causal relationship between the breach and the harm; and 4) the damages suffered.
    Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 
    451 Md. 600
    , 611
    (2017); 100 Inv. Ltd. P’ship v. Columbia Town Ctr. Title Co., 
    430 Md. 197
    , 213 (2013);
    Walpert, Smullian & Blumenthal, P.A. v. Katz, 
    361 Md. 645
    , 655 (2000) (citing Jacques v.
    First Nat’l Bank of Md., 
    307 Md. 527
    , 531 (1986)). “Absent a duty of care, there can be
    no liability in negligence.” Walpert, 
    361 Md. at 655
    .
    Maryland has adopted Prosser and Keeton’s characterization of “duty” as “an
    obligation, to which the law will give recognition and effect, to conform to a particular
    standard of conduct toward another.” 100 Inv. Ltd. P’ship, 430 Md. at 213 (quoting W.
    PAGE KEETON, ET AL., PROSSER AND KEETON ON THE LAW OF TORTS § 53 (5th ed. 1984)).
    “To determine whether a duty exists in a particular context, we examine: (1) ‘the nature of
    the harm likely to result from a failure to exercise due care,’ and (2) ‘the relationship that
    exists between the parties.’” Id. at 213-14 (citing Jacques, 
    307 Md. at 534
    ). The Court of
    Appeals has discerned:
    an inverse correlation exists between the nature of the risk on one hand, and
    the relationship of the parties on the other. As the magnitude of the risk
    increases, the requirement of privity is relaxed—thus justifying the
    imposition of a duty in favor of a large class of persons where the risk is of
    death or personal injury. Conversely, as the magnitude of the risk decreases,
    a closer relationship between the parties must be shown to support a tort duty.
    16
    Jacques, 
    307 Md. at 537
    . “In essence, the determination of whether an actionable duty
    exists represents a policy question of whether the specific plaintiff is entitled to protection
    from the acts of the defendant.” Blondell v. Littlepage, 
    413 Md. 96
    , 120 (2010). “Whether
    a legal duty exists between parties is a question of law to be decided by the court.” 100
    Inv. Ltd. P’ship, 430 Md. at 211. Accordingly, the determination of a legal duty is
    particularly “an appropriate issue to be disposed of on motion for dismissal.” Iglesias v.
    Pentagon Title & Escrow, 
    206 Md. App. 624
    , 644 (2012) (quoting Bobo v. State, 
    346 Md. 706
    , 716 (1997)).
    C. Duty, the Economic Loss Doctrine, and the Intimate Nexus
    Maryland has adopted the economic loss doctrine, which generally precludes tort
    liability for “negligence that causes purely economic harm in the absence of privity,
    physical injury, or risk of physical injury.” Balfour Beatty, 451 Md. at 611. “Where the
    failure to exercise due care creates a risk of economic loss only, courts have generally
    required an intimate nexus between the parties as a condition to the imposition of tort
    liability.” UBS Fin. Servs., Inc. v. Thompson, 
    217 Md. App. 500
    , 525 (2014) (quoting 100
    Inv. Ltd. P’ship, 430 Md. at 214). “This intimate nexus is satisfied by contractual privity
    or its equivalent.” Jacques, 
    307 Md. at 534-35
    . The Court of Appeals summarized the
    rationale of the intimate nexus requirement in Walpert:
    [T]he rationale underlying the requirement of privity or its equivalent as a
    condition of liability for negligent conduct, including negligent
    misrepresentations, resulting in economic damages emerges: to avoid
    “liability in an indeterminate amount for an indeterminate time to an
    indeterminate class.” Stated differently, the reason for the requirement is to
    limit the defendant’s risk exposure to an actually foreseeable extent, thus
    permitting a defendant to control the risk to which the defendant is exposed.
    17
    
    361 Md. at 671
     (citation omitted).
    Our appellate courts have, on many occasions, considered whether an “intimate
    nexus” presents a relationship sufficiently close to support a duty of care. Specifically, as
    we have noted, “[t]he intimate nexus analysis has been applied in Maryland to permit
    recovery of economic loss in suits between: a bank and its client, see Jacques, 
    307 Md. at 534-35
    ; a title company and a purchaser of real property, see 100 Inv. Ltd. P’ship v.
    Columbia Town Center Title Co., 
    430 Md. 197
    , 225 (2013); and an accounting firm and a
    third-party investor, see Walpert, 
    361 Md. at 693-94
    .” Balfour Beatty Infrastructure, Inc.
    v. Rummel Klepper & Kahl, LLP, 
    226 Md. App. 420
    , 447 (2016). In addition, our Courts
    have analyzed whether an intimate nexus existed in other scenarios, including in the
    context of a bank and a non-customer. Chi. Title Ins. Co. v. Allfirst Bank, 
    394 Md. 270
    ,
    300 (2006).
    The Court of Appeals first adopted the intimate nexus test in Jacques, 
    307 Md. at 534-37
    . As a result, the Court held that a bank owed its customers a duty of reasonable
    care in the processing of a loan application where the bank expressly agreed to process the
    customers’ application, received consideration for processing it, and agreed to “lock in” a
    specific interest rate, which was clearly “intended to entice the customer to deal with the
    offering bank.” 
    Id. at 528, 537-38
    . The customers in Jacques entered into a residential
    sales contract to purchase a house with a contingency that the customers obtain outside
    financing or forfeit a $10,000 deposit. 
    Id. at 531
    . The customers then submitted an
    application for a loan from a bank in accordance with the terms of the contract. 
    Id. at 529
    .
    18
    The bank agreed to process the loan, in exchange for $144 for the appraisal and credit
    report, and to lock in the interest rate for ninety days. 
    Id.
     The bank determined that its
    customers qualified for an amount significantly less than necessary to complete the sale.
    
    Id. at 530
    . While the customers qualified for a much larger loan from a second lender,
    interest rates had escalated in the interim, and the customers were faced with the dilemma
    of whether to settle with the first bank at a lower interest rate and secure other loans to
    make up the difference or secure the loan from the second bank. 
    Id.
     The customers
    proceeded to settlement with the first bank and then filed suit. 
    Id.
    In finding that there was an intimate nexus between the bank and the customers, the
    Court explained that the customers were “particularly vulnerable and dependent on the
    Bank’s exercise of due care.” 
    Id. at 540
    . Specifically, “[i]n accepting the loan application
    for processing, the [b]ank had knowledge that [its customers] would be legally obligated
    to either proceed to settlement with the loan . . . or forfeit their deposit . . . and lose any
    benefit of their bargain.” 
    Id.
     Accordingly, the bank’s duty emanated from both its
    relationship with the customer and the bank’s knowledge that the customer relied on its
    services. 
    Id. at 540-41
    . The Court further recognized the “public nature” of banking and
    held that “[t]he recognition of a tort duty of reasonable care under the circumstances
    presented in this case is . . . consistent with the policy of this State” and “reasonable in light
    of the nature of the banking industry and its relation to public welfare.” 
    Id. at 543
    .
    The Jacques Court discussed two leading cases from New York, both authored by
    Justice Cardozo. In Glanzer v. Shepard, the Court of Appeals of New York held that “a
    public weigher of beans was liable to the buyer of the beans for negligence in the weighing,
    19
    notwithstanding that the weigher had been engaged and paid only by the seller.” 
    135 N.E. 275
    , 276-77 (1922). Because the weigher held himself out as skilled and careful, the
    “assumption of the task of weighing was the assumption of a duty to weigh carefully for
    the benefit of all whose conduct was to be governed[.]” 
    Id. at 276
    . Conversely, in
    Ultramares Corp. v. Touche, the Court held that accountants who carelessly prepared a
    balance sheet did not have the requisite nexus to a third-party corporation who made loans
    in reliance on the balance sheet to impose a duty of care. 
    174 N.E. 441
    , 447-48 (N.Y.
    1931). In contrast to the weigher of beans, the accountant had no relationship with the
    third-party. While the accountants were generally on notice that third parties might rely
    on their reports, “[t]he range of transactions in which a certificate of audit might be
    expected to play a part was as indefinite and wide as the possibilities of the business that
    was mirrored in the summary[.]” 
    Id. at 442
    .
    In Walpert, our Court of Appeals held that the legal equivalent of privity to support
    a negligence claim existed between an accountant and a third party where, assuming the
    truth of certain facts for purposes of summary judgment, the accountant had knowledge
    that the third party would rely on that accountant’s financial statement. 
    361 Md. at 692
    -
    94. The Court adopted the three-prong test for “privity equivalent” from Credit Alliance
    Corp. v. Arthur Anderson, 
    483 N.E.2d 110
    , 118 (N.Y. 1985), which required the plaintiff
    to “establish: (1) the accountants must have been aware that the financial reports were to
    be used for a particular purpose or purposes; (2) in the furtherance of which a known party
    or parties was intended to rely; and (3) there must have been some conduct on the part of
    the accountants linking to that party or parties, which evinces the accountants’
    20
    understanding of that party or parties’ reliance.” Walpert, 
    361 Md. at 674
    . In adopting the
    Credit Alliance test, our Court of Appeals concluded that this three-part test would “limit[]
    the unpredictable and unlimited nature of economic damages.” 
    Id. at 675
    . The Court then
    determined that applying the test “to the facts sub judice produces a clear result[.]” 
    Id. at 693
    . The Court focused on the accountant’s knowledge of the third party’s reliance. 
    Id. at 693-94
    . Specifically, the Court noted that the accountant had met with the third party on
    “several occasions” and met with him to discuss [a business’s] financial condition in order
    for the [third party] to determine whether to ‘lend money[.]’” 
    Id. at 694
    . The accountant
    “knew that the [third parties] had relied on information supplied by [the accountant] in
    deciding to lend monies to, or securing loans” for the accountant’s client. 
    Id. at 693
    .
    Accordingly, a dispute of material fact precluded the grant of summary judgment. 
    Id. at 694
    .
    Applying the privity equivalent test again six years later in Chicago Title Insurance
    Co. v. Allfirst Bank, the Court of Appeals found an intimate nexus between a third-party
    title company and drawer of a check and the depository bank. 
    394 Md. at 297-98
    . There,
    a title company sought to clear two deeds of trust, securing a loan and a line of credit, on a
    customer’s house as part of a refinancing. 
    Id. at 277-78
    . After receiving a check from the
    title company, the bank correctly closed the loan. 
    Id.
     After settlement, the title company
    sent the customer a check, payable to the bank, with a letter instructing the bank to use
    those funds to close the line of credit. 
    Id. at 278
    . The customer brought the check to the
    bank to deposit but did not include the instruction letter. 
    Id.
     Instead of applying the funds
    to the outstanding balance to clear the line of credit, the bank credited the customer’s
    21
    individual account. 
    Id. at 278
    . When the customer defaulted on his loan, the bank sought
    to foreclose. 
    Id. at 279
    . Consequently, the title company learned that the funds had been
    misapplied and the original mortgage had never been released. 
    Id.
    The Court of Appeals held that the equivalent of privity existed between the bank
    and title company. 
    Id. at 297-98
    . Specifically, the Court of Appeals determined that the
    bank should have known the title company was relying on the bank to properly apply the
    funds. 
    Id. at 297-98
    . The Court noted that the bank was already aware of the title company,
    having received and processed the first check to close the loan. 
    Id. at 298
    . Not only had
    the bank provided the title company with a payoff amount to close the line of credit, its
    president testified that, when presented with a check payable to the bank without further
    instruction, the bank manager “should make inquiries to the presenter on ‘how they wanted
    to use the funds.’” 
    Id. at 297-98
    . The Court emphasized that its holding “[did] not impose
    liability on [the bank] to an indeterminate class of people for an indeterminate time, but
    rather, addresses a specific entity, [the title company], for this specific transaction.” 
    Id. at 299-300
    . Chicago Title is the only decision in which the Court of Appeals recognized an
    intimate nexus between a bank and a non-customer because the facts in that case
    demonstrated the “intimate” relationship necessary to establish a “privity equivalent.”
    The antipodal outcome was reached in Iglesias where the circuit court granted
    summary judgment on a negligence claim because the plaintiff had not alleged “facts
    demonstrating any relationship between herself and [the defendant bank], much less a
    relationship sufficiently intimate to justify the imposition of a tort duty.” 206 Md. App. at
    656. There, a loan officer engaged in a fraudulent scheme in which he and others forged
    22
    notarized powers of attorney to purchase two properties in Iglesias’s name. Id. at 627-28.
    After Iglesias discovered the fraud, she sued several parties involved with the real estate
    settlement, including a negligence action against Pentagon, the title company that
    conducted the real estate settlements. Id. at 628. The circuit court granted summary
    judgment in favor of Pentagon, finding that the company did not owe a duty to Iglesias.
    Id. at 629.
    On appeal to this Court, Iglesias argued that the circuit court erred in finding that
    Pentagon did not owe her a duty of care to look beyond the facially valid, but fraudulent,
    powers of attorney used in the real estate transactions. Id. at 656. Because Pentagon
    provided professional services, Pentagon had a duty to ascertain whether Iglesias was an
    actual party to the transaction. Id. at 658-59. Iglesias argued both that she was in direct
    contractual privity as well as the equivalent of contractual privity with Pentagon on two
    grounds: first, based on Pentagon’s mistaken belief that she was a party to the transaction;
    and, second, because “red flags” put Pentagon on notice that the powers of attorney were
    fraudulent, creating a duty on Pentagon’s part to investigate whether she was a victim of
    identity fraud. Id. at 659.
    We held that the circuit court did not err in granting summary judgment. Id. at 656.
    We concluded that Iglesias was not in contractual privity with Pentagon and that her
    argument was self-defeating. Id. We reasoned:
    Iglesias cannot argue, on the one hand, that Pentagon owed her a duty to
    detect that she was not a true party to the transaction and, on the other hand,
    that she was in privity with Pentagon because she “paid” for its services out
    of funds borrowed fraudulently in her name.
    23
    Id.
    Turning to Iglesias’s alternative argument, we determined that Pentagon’s mistaken
    belief was insufficient to create the privity-equivalent, in part, because the relationship
    between Iglesias’s imposter and the Pentagon was too attenuated. Id. at 660. We ruled
    that the “red flags” would be material only “if they served to put Pentagon on notice that
    Iglesias likely was the victim of identity fraud, thus enlightening Pentagon to the fact that
    she would be relying upon it to protect her interests.” Id. at 663 (citation omitted). The
    “red flags” in that case were insufficient to create privity. In sum, we concluded, “none of
    the facts Iglesias point[ed] to were sufficiently unusual to put Pentagon on notice that a
    fraud was being committed and that Iglesias was relying upon it to protect her from the
    fraud.” Id. at 664.
    In Balfour Beatty, both this Court and the Court of Appeals held that “in the absence
    of contractual privity, physical injury, or risk of physical injury, design professionals in
    large government construction projects do not owe a tort duty to those who bid for and
    contract with a government entity.” 451 Md. at 604; see also Balfour Beatty, 226 Md. App.
    at 427 (same). There, the City of Baltimore contracted with an engineer to design upgrades
    to a water treatment plant. 451 Md. at 605. The City accepted a contractor’s bid to
    complete the work required by the engineer’s design. Id. During the construction, the
    contractor “encountered leaking and other problems, which resulted in delays and cost
    overruns.” Id. at 606. The contractor filed a three-count complaint for professional
    negligence, negligent misrepresentation, and a claim under Restatement (Second) of Torts
    § 552 against the engineer to recover damages for its loss. Id. The engineer filed a motion
    24
    to dismiss for failure to state a claim because “without privity between the parties, no
    legally cognizable tort duty ran from Engineer to Contractor that would permit recovery of
    purely economic losses.” Id. at 607. After oral argument, the circuit court granted the
    engineer’s motion because of the lack of privity, and we affirmed. Id. at 608. The Court
    of Appeals then granted certiorari to consider, among other things, whether “the economic
    loss doctrine bar[s] a general contractor’s professional negligence claim against a design
    professional on a government construction project under the privity-equivalent analysis of
    the intimate nexus test[.]” Id.
    After reviewing the evolution of the economic loss doctrine and the intimate nexus
    test, the Court of Appeals “decline[d] to extend the privity-equivalent intimate nexus test
    to design professionals on government construction projects.” Id. at 627. Central to the
    Court’s decision was the “complex web of contracts that typically undergird a public
    construction project,” which offers contractors “sufficient opportunity to protect
    themselves (and anticipate their liability) in negotiating these contracts.” Id. at 626. “In
    the context of larger construction projects, . . . parties typically rely on a network of
    contracts to allocate their risks, duties, and remedies . . . and do have the opportunity to
    bargain and define their rights and remedies, or to decline to enter into the contractual
    relationship if they are not satisfied with it.” Id. (quoting BRW, Inc. v. Dufficy & Sons,
    Inc., 
    99 P.3d 66
    , 72 (Colo. 2004)). Further, the Court was “mindful that government
    contracts have a special consideration—the public purse. Imposing a tort duty on design
    professionals will likely correlate with an increase in project costs and with a corresponding
    rise in price for government entities.” 
    Id. at 626-27
    . Accordingly, the “complex web of
    25
    contractual arrangements” in public construction projects “predominates” and precludes
    “injecting a tort duty” against the public interest. 
    Id. at 630
    .
    In concluding our survey of the intimate nexus test, we quote Judge Adkins’s
    observation about the level of conduct linking the plaintiff to the defendant that is required
    to establish an intimate nexus:
    These cases illustrate that regardless of whether we apply the Credit
    Alliance/Walpert test, our privity-equivalent analysis in economic loss cases
    looks for linking conduct—enough to show the defendant knew or should
    have known of the plaintiff’s reliance. This means, of course, that context is
    critical.
    Balfour Beatty, 451 Md. at 620-21.
    D. Construction Lenders and Duty
    Returning to our threshold consideration, we have found no reported decision in
    Maryland that squarely answers whether a lender owes a duty to ensure that a subcontractor
    receives payment from its disbursements to the general contractor absent any contractual
    obligation to do so. Further, our courts have not yet had the opportunity to apply the
    “privity equivalent” test in a negligence action against a lender for economic damages
    resulting from an alleged failure to ensure that subcontractors are paid for their work.
    Richard F. Kline, Inc. v. Signet Bank/Maryland, 
    102 Md. App. 727
     (1995),
    represents perhaps the clearest enunciation from our courts of a lender’s duty to a
    subcontractor.   In Kline, we addressed, as a matter of first impression, whether “a
    construction lender was unjustly enriched where the subcontractor was unable to obtain a
    mechanic’s lien or seek damages for breach of contract because the general contractor was
    in bankruptcy.” 
    Id. at 731
    . The subcontractor averred that the lender knew that the
    26
    developer, the lender’s borrower, had defaulted on the project but, instead of informing the
    subcontractors, paid none of the subcontractors and increased the value of its collateral. 
    Id. at 729
    . After setting out the elements of unjust enrichment, this Court summarized that a
    “party seeking recovery under the doctrine of unjust enrichment ‘must demonstrate that the
    [third party] has in fact been benefitted[.]’” 
    Id. at 733
     (citing Meehan v. Cheltenham
    Township, 
    189 A.2d 593
    , 595 (1963)). Further, we noted that “in the absence of some
    misleading by the third party, the mere failure of performance by one of the contracting
    parties does not give rise to a right of restitution against the third party.” 
    Id.
     (quoting
    Meehan, 189 A.2d at 596). Consequently, we recognized that “it would be ‘manifestly
    unfair’ for a court to make the construction mortgage lender an ‘insurer of the
    subcontractors’ interests.”’ Id. at 733 (citing D.A. Hill Co. v. CleveTrust Realty, 
    573 A.2d 1005
    , 1010 (Pa. 1990)).
    The subcontractor contended that the lender “had a duty to notify [subcontractor]
    that [developer] had defaulted on the loan.” 
    Id. at 734
    . We saw “no such duty,” 
    id.,
     and
    explained:
    If a project has not been completed, and the construction lender has not fully
    disbursed funds for the work completed, an unpaid subcontractor may not
    support its claim for payment from those funds merely by asserting that the
    construction lender failed in its duty to notify the subcontractor of a default,
    because no such duty exists. To require otherwise, would no doubt make it
    more difficult for developers to obtain construction loans.
    
    Id. at 734-35
    . To prevail on its unjust enrichment claim, the subcontractor would have to
    “show that it was in some way induced by the construction lender.” 
    Id. at 735
    . Although
    the cause of action in Kline was unjust enrichment, as opposed to negligence, the case is
    27
    instructive insofar as it considers the duty of care by a lender to a party with whom it does
    not have a direct relationship. See also Eisenberg v. Wachovia Bank, N.A., 
    301 F.3d 220
    ,
    225 (4th Cir. 2002) (“Courts in numerous jurisdictions have held that a bank does not owe
    a duty of care to a noncustomer with whom the bank has no direct relationship.”)
    (interpreting North Carolina law and collecting cases).
    Appellate decisions from other states that have reached this issue have broadly
    determined that a lender providing a construction loan owes no duty to an unpaid
    subcontractor absent the lender’s express promise or assurance of payment. For example,
    in Peterson v. First Clayton Bank & Trust Co., a materialman sued a construction lender
    for disbursing loan proceeds to the builder without first verifying that subcontractors and
    materialmen had been paid. 
    447 S.E.2d 63
    , 64 (Ga. App. 1994). The builder failed to pay
    subcontractors and suppliers, liens accrued on the property, and the bank foreclosed. 
    Id. at 65
    . After the trial court granted summary judgment, the materialman appealed. 
    Id.
     On
    appeal, the Court of Appeals of Georgia, noting that “the question of duty is for the court,”
    found that no duty existed to ensure that suppliers were paid before disbursing funds to the
    builder:
    Given that the [bank’s] primary role is to protect its interest in the secured
    property, we find no basis for imposing upon the lender the duties of the
    owner and general contractor to pay for labor and materials supplied to the
    project. Absent clear evidence that the [bank] either expressly agreed to
    undertake this obligation or actively participated in the monitoring of
    payments made during the construction, the creation of such a burden would
    discourage lending.
    
    Id. at 68
    .
    28
    In Resolution Trust Corp. v. BVS Development, Inc., the United States Court of
    Appeals for the Ninth Circuit considered whether a construction lender owed a duty to a
    subordinated seller. 
    42 F.3d 1206
    , 1214-15 (9th Cir. 1994). In affirming the grant of
    summary judgment, the Court held:
    The duty of a lender to supervise the use of loan funds arises only from a
    written agreement to do so, or perhaps from the knowledge that the seller is
    relying on such monitoring and the lender does not disclaim such reliance or
    the lender actively undertakes such a role. Because there is no duty on the
    bank implied in law, and because the written agreements disclaim any
    implied duty, the appellants’ arguments must fail.
    Id.; see also Koppers Co. v. Garling & Langlois, 
    594 F.2d 1094
    , 1100 (6th Cir. 1979)
    (“[T]here is strong authority in other jurisdictions against making construction lenders
    (and, we suppose, their disbursing agents) the absolute insurers of subcontractors’ risks.”)
    (collecting cases); United Plumbing & Heating Co. v. AmSouth Bank, 
    30 So.3d 343
    , 348
    (Miss. Ct. App. 2009) (“We hold [subcontractor’s] negligence claim invalid as a matter of
    law. We find no contract, statute, or law that would establish that [lender] had a duty to
    (1) pay money to a party it was not obligated to pay; (2) investigate or contradict a valid
    request made by its client[]; or (3) adhere to its own dispute resolution policies when
    [subcontractor] was neither a client nor a party to any valid contract involving [lender].”).
    This principle is also found in leading scholarly publications. See 2 LAW OF REAL
    ESTATE FINANCING § 14:23 (database updated November 2020) (“Ordinarily the
    construction lender has no duty of care to ensure that the disbursements correspond to work
    completed or that subcontractors and suppliers (as potential lienholders) are paid by the
    contractor.”); Paul A. Sandars III, Theories of Lender Liability on Construction Projects,
    29
    CONSTR. LAWYER, 44 (Am. Bar Ass’n, Fall 2005) (“Generally, construction lenders that
    restrict their involvement to financing will not be found liable under a lender liability
    theory.”).
    Bel Air Carpet refers us, in contrast to the weight of the foregoing authorities, only
    to Section 1311.011 of the Revised Code of Ohio, which concerns the operation of
    mechanic’s liens. This section provides, in pertinent part:
    (4) No lending institution shall make any payment to any original contractor
    until the original contractor has given the lending institution the original
    contractor’s affidavit stating:
    (a) That the original contractor has paid in full for all labor and work
    performed and for all materials furnished by the original contractor and all
    subcontractors, material suppliers, and laborers prior to the date of the
    closing of the purchase or during and prior to the payment period, except
    such unpaid claims as the original contractor specifically sets forth and
    identifies both by claimant and by amount claimed;
    (b) That no claims exist other than those claims set forth and identified
    in the affidavit required by division (B)(4) of this section.
    (5) When making any payment under the home construction contract or on
    behalf of the owner or part owner under a home purchase contract, the
    lending institution may accept the affidavit of the original contractor required
    by division (B)(4) of this section and act in reliance upon it, unless it appears
    to be fraudulent on its face. The lending institution is not financially liable to
    the owner, part owner, purchaser, lessee, or any other person for any
    payments, except for gross negligence or fraud committed by the lending
    institution in making any payment to the original contractor.
    After receipt of a written notice of a claim of a right to a mechanic’s
    lien by a lending institution, failure of the lending institution to obtain a lien
    release from the subcontractor, material supplier, or laborer who serves
    notice of such claim is prima-facie evidence of gross negligence.
    Ohio Rev. Code Ann. § 1311.011 (West). Bel Air Carpet asserts that this provision protects
    subcontractors; however, the Supreme Court of Ohio has clarified that a lending institution
    30
    owes a duty to the homeowner, not the subtrades. Thompson Elec., Inc. v. Bank One,
    Akron, N.A., 
    525 N.E.2d 761
    , 770 (Ohio 1988) (“[W]hile a lending institution may owe a
    duty to a homeowner to obtain affidavits before disbursing funds from a construction loan,
    no such duty extends to subtrades.”). Moreover, if we take Bel Air Carpet’s argument at
    face value, it is requesting that we impose a broad-based common law duty of care on
    lenders in Maryland, predicated on a mechanic’s lien statute in Ohio.8
    We conclude that Maryland law does not recognize a general duty on the
    homeowner’s lender to ensure that the general contractor on a home construction project
    pays all of its subcontractors for work completed when the lender disburses funds to the
    general contractor, and where there is no privity of contract or intimate nexus between the
    lender and the subcontractors. The public policy of Maryland and other states disfavor
    imposing such a general duty of care on home construction lenders. As we note above, it
    would be “manifestly unfair” to make lenders the “insurer of the subcontractors’ interests”
    by imposing a general duty on lenders to ensure that general contractors properly pay
    unknown subcontractors for their work. See Kline, 102 Md. App. at 733.
    8
    Pursuant to Maryland Code (1974, 2015 Repl. Vol., 2018 Supp.), Real Property
    Article, § 9-104(f)(3), “the lien of the subcontractor against a single family dwelling being
    erected on the land of the owner for his own residence shall not exceed the amount by
    which the owner is indebted under the contract at the time the notice is given.” Bel Air
    Carpet failed to demonstrate how it could have successfully asserted a mechanic’s lien
    when each homeowner had already paid the entire purchase price for the construction
    project to Korey Homes, nor did Bel Air Carpet identify any statutory, regulatory or
    contractual requirement on Hamilton Bank to request mechanics lien releases to ensure
    subcontractors and suppliers were paid.
    31
    E. Analysis
    Applying the foregoing precepts, we hold that Bel Air Carpet has failed to allege a
    cognizable duty of care owed to it by Hamilton Bank because Bel Air Carpet does not
    allege privity or any equivalent intimate nexus in the complaint. The complaint does not
    allege the necessary “linking conduct” between the parties to justify Bel Air Carpet’s
    reliance that Hamilton Bank would ensure that its borrower’s funds were paid to Bel Air
    Carpet.9 Bel Air Carpet concedes that “contractual privity does not exist between Bel Air
    Carpet and Hamilton Bank” and recognizes that it must “adequately ple[a]d ‘its equivalent’
    to allege the requisite duty of care.”
    According to Bel Air Carpet’s complaint, the duty allegedly owed to Bel Air Carpet
    derived from a relationship between Hamilton Bank and Korey Homes, whereby Hamilton
    Bank “ignored most, if not all, standard financial practices in disbursing construction loan
    funds to Korey Homes on behalf of its borrowers[.]” To be sure, missing from Bel Air
    Carpet’s complaint, is the allegation of any relationship between Hamilton Bank and Bel
    Air Carpet.
    As our review of our cases requiring an intimate nexus highlights, the plaintiff must
    allege “linking conduct” sufficient to “show the defendant knew or should have known of
    the plaintiff’s reliance.” Balfour Beatty, 451 Md. at 620-21. Nowhere in the complaint
    does Bel Air Carpet allege that Hamilton Bank made a specific promise or representation
    9
    In reaching this holding, we do not foreclose the possibility that a contractor,
    subcontractor, supplier, or similar entity could allege a specific factual scenario that would
    demonstrate an intimate nexus with a lender.
    32
    to perform an obligation for Bel Air Carpet’s benefit or that Hamilton Bank knew that Bel
    Air Carpet was relying on it. Bel Air Carpet seeks to cure this defect by asserting a broad-
    based standard in the construction industry. Unfortunately for Bel Air Carpet, neither
    Maryland nor most other states recognize such a broad-based duty of care that requires a
    lender to ensure that subcontractors and suppliers are paid. Perhaps this is an issue the
    General Assembly may want to address, but we decline to adopt such a broad duty of care
    to lenders in the construction industry as a matter of law. 100 Inv. Ltd. P’ship, 430 Md. at
    211. As the Court of Appeals, quoting an article relied on in an Indiana case, explained in
    Balfour Beatty:
    Perhaps more than any other industry, the construction industry is vitally
    enmeshed in our economy and dependent on settled expectations. The parties
    involved in a construction project rely on intricate, highly sophisticated
    contracts to define the relative rights and responsibilities of the many persons
    whose efforts are required—owner, architect, engineer, general contractor,
    subcontractor, materials supplier—and to allocate among them the risk of
    problems, delays, extra costs, unforeseen site conditions, and defects.
    Imposition of tort duties that cut across those contractual lines disrupts and
    frustrates the parties’ contractual allocation of risk and permits the
    circumvention of a carefully negotiated contractual balance among owner,
    builder, and design professional.
    451 Md. at 626 (quoting Indianapolis-Marion Cnty. Pub. Library v. Charlier Clark &
    Linard, P.C., 
    929 N.E.2d 722
    , 737 (Ind. 2010)).
    If we were to adopt Bel Air Carpet’s theory, we would alter the delicate contractual
    balance in the construction industry and the privity requirement of the economic loss
    doctrine. We would render Hamilton Bank the “insurer of the subcontractors’ interest”—
    a concern we enunciated in Kline. 102 Md. App. at 733. Even assuming that there is a
    standard in the industry that a bank require mechanic’s lien releases, Bel Air Carpet has
    33
    not alleged how or why a duty of care should be imposed upon Hamilton Bank for its
    benefit. Peterson, 447 S.E.2d at 68. Although it may be foreseeable that Hamilton Bank’s
    failure to request mechanic’s lien releases or inspect the properties could harm Bel Air
    Carpet, unless Hamilton Bank owes Bel Air Carpet a duty, Hamilton Bank cannot be liable
    to Bel Air Carpet in negligence. Ashburn v. Anne Arundel Co., 
    306 Md. 617
    , 628 (1986)
    (“[T]here is no duty to control a third person’s conduct so as to prevent personal harm to
    another, unless a ‘special relationship’ exists either between the actor and the third person
    or between the actor and the person injured.”).
    II.
    Denial of Discovery
    Bel Air Carpet claims that the circuit court erred in dismissing the negligence claim
    before the parties had engaged in discovery. Specifically, Bel Air Carpet claims it “was
    deprived of an opportunity to produce evidence that could better establish the elements of
    the relationship between it and Hamilton Bank[.]”
    Bel Air Carpet’s contention is without merit. Because the circuit court’s ruling that
    Hamilton Bank did not owe a duty of care to Bel Air Carpet was a legal determination,
    discovery could not have saved the deficiency in Bel Air Carpet’s complaint. 100 Inv. Ltd.
    P’ship, 430 Md. at 211. Further, the circuit court judge limited herself to the four corners
    of the complaint and the accompanying exhibits in ruling on the motion to dismiss.
    34
    Rounds, 441 Md. at 636. Correspondingly, any discovery could not have overcome Bel
    Air Carpet’s failure to plead the requisite duty of care in its complaint. 10
    JUDGMENT OF THE CIRCUIT COURT
    FOR HARFORD COUNTY AFFIRMED;
    COSTS TO BE PAID BY APPELLEE.
    10
    At oral argument, counsel for Hamilton Bank asserted that two letters from
    Hamilton Bank’s counsel, attached to Bel Air Carpet’s opposition to the motion to dismiss,
    were not included in the record. In the first letter, Hamilton Bank confirmed that it wired
    the final draw on one of the projects to Korey Homes; and, in the second, Hamilton Bank
    advised its borrowers that “Korey Homes may not have used some of the monies that were
    advanced to it under your loan to pay subcontractors who should have been paid from the
    proceeds of those advances.” While these documents undoubtedly are in the record, as we
    have explained, the circuit court properly declined to consider them in ruling on the motion
    to dismiss.
    Furthermore, we clarify that this opinion does not offer any countenance to
    Hamilton Bank’s representation at oral argument that a homeowner would be unconcerned
    about whether subcontractors and suppliers who contributed to the construction of their
    home received payment for their services. Counsel for Hamilton Bank provided no
    authority for this sweeping assertion, and, on this point, there was certainly no evidence in
    the record.
    35
    The correction notice(s) for this opinion(s) can be found here:
    https://mdcourts.gov/sites/default/files/import/appellate/correctionnotices/cosa/1006s19cn.pdf