Russell Black v. Bureau of Parks and Lands , 2022 ME 58 ( 2022 )


Menu:
  • MAINE SUPREME JUDICIAL COURT                                                   Reporter of Decisions
    Decision: 
    2022 ME 58
    Docket:   BCD-21-257
    Argued:   May 10, 2022
    Decided:  November 29, 2022
    Panel:       STANFILL, C.J., JABAR and HORTON, JJ., CLIFFORD, A.R.J. and HUMPHREY, A.R.J.*
    RUSSELL BLACK et al.
    v.
    BUREAU OF PARKS AND LANDS et al.
    PER CURIAM
    [¶1] NECEC Transmission LLC, Central Maine Power Co. (collectively,
    CMP1), and the Bureau of Parks and Lands appeal from a judgment of the
    Business and Consumer Docket (Murphy, J.) entered in favor of the plaintiffs2
    (collectively Black), vacating the Bureau’s lease of public reserved land to CMP
    for construction of a high-capacity transmission line. Black cross-appeals from
    * Justice Humphrey sat at oral argument and participated in the initial conference while he was
    an Associate Justice and, as directed and assigned by the Chief Justice, is now participating in this
    appeal as an Active Retired Justice.
    1 As did the trial court, we refer to defendant-appellants Central Maine Power Co. and NECEC
    Transmission LLC collectively as “CMP” for the sake of consistency with prior orders in this case.
    2   The plaintiff-appellees are Senator Russell Black, Senator Richard A. Bennett, former Senator
    Thomas B. Saviello, former Representative Kent Ackley, former Representative Seth Berry,
    Representative Chad Grignon, former Representative Denise Harlow, Representative Margaret
    O’Neil, Representative William Pluecker, Edwin Buzzell, Greg Caruso, Charlene Cummings, Robert
    Haynes o/b/o Old Canada Road National Scenic Byway, Cathy Johnson, Ron Joseph, John R. Nicholas
    Jr., George A. Smith, Clifford Stevens, Todd Towle, and the Natural Resources Council of Maine
    (NRCM).
    2
    the trial court’s decision not to address the substantive question of whether the
    Bureau had the constitutional authority to lease the public reserved land. Black
    later moved to dismiss all appeals on the ground that a citizen’s initiative, which
    purported to retroactively require approval of leases like the ones at issue here
    by a vote of two-thirds of all members elected to each House of the Legislature,
    rendered the appeals moot.
    [¶2] The broad questions we answer are, in order, (1) whether the
    United States Constitution permits a citizens’ initiative to retroactively
    invalidate the lease at issue; (2) what procedure, if any, the public-lands
    provision of the Maine Constitution and its implementing statutes required the
    Bureau to follow before leasing the public reserved lands; and (3) whether the
    Bureau’s lease of the public reserved lands exceeded the Bureau’s
    constitutional or statutory leasing authority.
    [¶3] We determine that this case is justiciable, vacate the judgment
    rendered for Black, and remand for entry of judgment in favor of the Bureau
    and CMP.
    3
    I. BACKGROUND
    A.    Constitutional and Statutory Background
    [¶4] Public reserved lands existed before Maine was a state. “At the close
    of the Revolutionary War, the Commonwealth of Massachusetts owned . . . vast
    amounts of land, including most of what is now the state of Maine.” Lee M.
    Schepps, Maine’s Public Lots: The Emergence of a Public Trust, 
    26 Me. L. Rev. 217
    , 219 (1974). When Maine became a state in 1820, it came to own that land
    through the agreement that granted it independence—the Articles of
    Separation. Id. at 220-21.
    [¶5] Beginning in the 1970s, public concern about the sale of public lands
    to private persons or entities precipitated efforts to preserve public lands for
    future generations. The culmination of these efforts was a 1993 amendment to
    the Maine Constitution:
    State park land, public lots or other real estate held by the State for
    conservation or recreation purposes and designated by legislation
    implementing this section may not be reduced or its uses
    substantially altered except on the vote of 2/3 of all the members
    elected to each House. The proceeds from the sale of such land
    must be used to purchase additional real estate in the same county
    for the same purposes.
    Me. Const. art. IX, § 23. During the several years following the amendment’s
    ratification, the Legislature enacted implementing legislation.          See, e.g.,
    4
    12 M.R.S. §§ 598 to 598-B (2022) (Designated Lands); 12 M.R.S. §§ 1801-1900
    (2022) (establishing the Bureau of Parks and Lands and prescribing its
    authority).
    [¶6] The Designated Lands statutes apply the requirements of article IX,
    section 23 to certain types of public lands held by the Department of Inland
    Fisheries and Wildlife; under the care, custody, control, and management of the
    Bureau; managed by the Baxter State Park Authority; and gifted to the state or
    acquired by referendum. Id. § 598-A(1), (2-A), (4)-(6). It applies to public
    reserved lands and prevents those lands from being reduced or substantially
    altered without two-thirds legislative approval. Id. §§ 598-A, 598-A(2-A)(D),
    1801(8) (defining “public reserved lands”). “‘Reduced’ means a reduction in
    the acreage of an individual parcel.” Id. § 598(4). “‘Substantially altered,’ in the
    use of designated lands, means changed so as to significantly alter physical
    characteristics in a way that frustrates the essential purposes for which that
    land is held by the State.” Id. § 598(5). “The essential purposes of public
    reserved and nonreserved lands are the protection, management and
    improvement of these properties for the multiple use objectives established in
    section 1847.” Id.
    5
    [¶7] In turn, section 1847 declares that it is in the public interest “that
    the public reserved lands be managed under the principles of multiple use to
    produce a sustained yield of products and services by the use of prudent
    business practices and the principles of sound planning and that the public
    reserved lands be managed to demonstrate exemplary land management
    practices, including silviculture, wildlife and recreation management
    practices.” Id. § 1847(1). The statutory definition of “multiple use” includes
    “[t]he harmonious and coordinated management of the various resources
    without impairing the productivity of the land and with consideration being
    given to the relative values of the various resources.” Id. § 1845(1)(D). And
    “‘[s]ustained yield’ means the achievement and maintenance in perpetuity of a
    high-level regular periodic output of the various renewable resources of the
    public reserved lands without impairing the productivity of the land.” Id.
    § 1845(2). The Bureau effectuates these principles through the creation of
    comprehensive management plans and specific action plans. Id. § 1847(2).
    [¶8] “[C]onsistent with the management plans,” and the above statutory
    provisions, the Bureau, through its director, is authorized to “take actions on
    the public reserved lands.” Id. § 1847(3). For example, the Bureau is authorized
    to sell resources on public reserved lands, including timber, grass, wild foods,
    6
    and sand and gravel for use in the construction of public roads, id. § 1848(1),
    and to lease public reserved land for both private and industrial uses, such as
    campsites, mills, or dams, id. § 1852(5), (6). Relevant here, until 2021 the
    Bureau was authorized to lease the right to “[s]et and maintain or use poles,
    electric power transmission and telecommunication transmission facilities,
    roads, bridges and landing strips” on public reserved lands.                                 12 M.R.S.
    § 1852(4)(A) (2021).3
    B.      Project Background and Procedural History
    [¶9] In December 2014, the Bureau leased part of the Johnson Mountain
    and West Forks Plantation4 public reserved lands to CMP, to accommodate a
    small portion of a high-capacity electric transmission line known as the New
    England Clean Energy Connect (the Project). The proposed Project is 145.3
    miles long, with 0.9 miles of the line crossing the leased portion of the Johnson
    3  The law as later amended by the citizens’ initiative expands the language to include
    “transmission lines and facilities” and provides that “[a]ny such . . . transmission lines . . . are deemed
    to substantially alter the uses of the land[,] . . . and a lease or conveyance for the purposes of
    constructing and operating such . . . transmission lines . . . may not be granted without first obtaining
    the vote of 2/3 of all the members elected to each House of the Legislature.” 12 M.R.S.
    § 1852(4)(A)(2022); see I.B. 2021, ch. 1, § 1 (effective Dec. 19, 2021) (emphasis added).
    4 The West Forks Plantation public reserved lands are comprised of four individual lots in the
    Upper Kennebec Region: the Northeast, Northwest, Central, and Southwest lots. The West Forks
    Plantation Northeast lot adjoins with the Johnson Mountain public reserved lands, and is the lot
    described by the parties simply as the “West Forks Plantation” public reserved lands. For
    consistency, we will follow suit.
    7
    Mountain and West Forks Plantation public reserved lands.                           The area
    encompassed by the lease amounts to 2.6% of the combined 1,241 acres of the
    Johnson Mountain and West Forks Plantation public reserved lands.
    [¶10] In 2020, CMP and the Bureau realized that the 2014 lease violated
    a Maine statute because the Bureau had leased the public reserved land before
    the Maine Public Utilities Commission had granted a Certificate of Public
    Convenience and Necessity (CPCN) authorizing CMP to proceed with the
    Project. See 35-A M.R.S. § 3132(13) (2022) (barring any lease of public land for
    the purpose of constructing a transmission line unless a CPCN has been issued).
    The CPCN was not obtained until 2019. On June 23, 2020, the Bureau and CMP
    executed a new lease for the same public lands but with an increase in the base
    annual payment paid by CMP.5 Other alterations included a change in the lease
    title from “Transmission Line Lease” to “Amended and Restated Transmission
    Line Lease” and the addition of a reference to the 2019 CPCN. Because the
    2020 lease explicitly states that it supersedes the 2014 lease and that the 2014
    5  Pursuant to the 2014 lease, CMP was to make annual payments, with the first payment due on
    the date of execution of the lease, “adjusted each year in accordance with the increase in the
    Consumer Price Index.” A 2015 lease amendment increased the base annual payment from $1,400
    to $3,680, and the 2020 lease further increased the base annual payment to $65,000.
    8
    lease is terminated and of no further effect, our focus on review is on the 2020
    lease.
    [¶11] On the same day that the 2020 lease was executed, Black filed a
    three-count complaint in Superior Court challenging the 2014 lease as ultra
    vires because the lease would reduce or substantially alter public reserved
    lands and therefore had to be approved by a two-thirds vote of the Legislature.
    Black filed an amended complaint—the operative pleading—on July 17, 2020.
    The amended complaint sought (1) a declaration that the 2020 lease was also
    ultra vires; (2) an injunction to prevent construction of the Project; and
    (3) alternatively, judicial review of the Bureau’s leasing decision, see M.R.
    Civ. P. 80C. The case was transferred to the Business and Consumer Docket
    (Murphy, J.) on August 25, 2020.
    [¶12] The Bureau and CMP each moved to dismiss the counts for
    declaratory judgment and injunctive relief, arguing that they were duplicative
    of the Rule 80C count; and CMP’s motion also requested that the count for
    judicial review pursuant to M.R. Civ. P. 80C be dismissed for plaintiffs’ lack of
    standing. While those motions were pending, the trial court ordered the
    Bureau to file the administrative record, which it did. The record contained a
    memorandum dated September 24, 2020 (Findings Memo), included “to
    9
    facilitate judicial review,” that purportedly memorializes the Bureau’s
    determination that the 2020 lease would not reduce or substantially alter the
    uses of the Johnson Mountain and West Forks Plantation public reserved
    lands.6
    [¶13] In orders issued on October 30 and December 21, 2020, the trial
    court denied CMP’s motion to dismiss the 80C appeal for lack of standing and
    the Bureau’s and CMP’s motions to dismiss the counts for declaratory judgment
    and injunctive relief. In response to an argument made by the Bureau that, if
    successful, would have been potentially dispositive of the case, the trial court
    then issued an order, on March 17, 2021, holding that utility leases granted by
    6 An introductory paragraph of the Findings Memo states that the “memorandum provides
    background detail and context and memorializes actions, considerations, and legal interpretations
    by [the Bureau] related to the [Project] utility corridor lease . . . . The lease was originally signed in
    December 2014 (2014 Lease) and was amended and restated in June 2020 (2020 Amended and
    Restated Lease). In preparing this memorandum, the Bureau consulted with former Bureau Director
    Willard Harris and former Director of Operations Tom Morrison for additional detail and context
    regarding the Bureau’s memorialized actions, considerations, and legal interpretations with respect
    to the 2014 Lease and review process.” According to the memorandum, the Johnson Mountain and
    West Forks Plantation public reserved lands have limited ecological or recreational value. Their
    dominant use is timber management. The timber on the lots was harvested in 1986-1987 and
    2006-2007, with the next harvest scheduled to occur in 2026-2027. The abutting properties were
    also historically managed as commercial timberlands. An existing transmission line corridor for the
    so-called Jackman Tie Line straddles the border between the two lots and is three miles long and
    100 feet wide. The memorandum states that, although the Bureau did not reduce the determination
    to writing, the Bureau, before granting each lease, first determined that the Project does not
    substantially alter the Johnson Mountain and West Forks Plantation public reserved lands because
    the primary use of the property is timber harvesting (and the leases require that the Bureau be paid
    the value of the trees cut for the corridor) and because the presence of the Jackman Tie Line indicates
    that these lots are a reasonable place for another transmission corridor.
    10
    the Bureau “are not categorically exempt from application of Article IX,
    Section 23 of the Maine Constitution.”
    [¶14] The trial court next addressed, in an order entered April 21, 2021,
    the parties’ motions regarding the factual record. The trial court struck from
    the record the Findings Memo proffered by the Bureau. Finding that nothing in
    the record demonstrated that the determinations in the Findings Memo were
    made contemporaneously with the execution of the leases, the trial court
    concluded that it was barred from considering any post hoc material (i.e., any
    determination made by the Bureau after the execution of the lease). The trial
    court also denied the Bureau’s alternative motion to remand the matter so that
    it could make factual findings anew after accepting public comments, including
    from the plaintiffs here. From this order the Bureau and CMP appealed. This
    Court (Gorman, J.) dismissed that appeal as interlocutory in a June 8, 2021,
    order.
    [¶15] After the parties filed motions for judgment on the declaratory
    judgment count and briefs on the Rule 80C issues, the trial court issued a final
    judgment on August 10, 2021. It granted Black a declaratory judgment, held
    that Black had waived the request for injunctive relief, and reversed the
    Bureau’s decision to lease the public reserved land. As to the declaratory
    11
    judgment, the trial court held that the Bureau must make a determination of
    whether the leases would result in a reduction or substantial alteration to the
    public reserved lands by applying the statutory definitions of those terms when
    deciding whether to lease the lands.7 The trial court then held that “the Maine
    Constitution requires that any such determination must be made pursuant to a
    public administrative process” and indicated that the Bureau needed to follow
    the process required for an adjudicatory proceeding. Cf. 5 M.R.S. § 9051-A
    (2022) (providing notice requirements for environmental agency adjudicatory
    hearings).
    [¶16] Addressing the Rule 80C claim next, the trial court found “no
    competent evidence supporting [the Bureau’s] assertion that it made the
    requisite public, pre-execution findings that the 2020 lease would not reduce
    or substantially alter the uses of the lands.” It declined the Bureau’s request to
    remand without vacating the lease, in part because it could not, “as a matter of
    separation of powers,” create an administrative process for the Bureau.
    7 In so holding, the trial court rejected the Bureau’s argument that management plans prepared
    pursuant to 12 M.R.S. § 1847(2) (2022) suffice for a determination regarding substantial alteration.
    These plans require the Bureau director to, among other things, “compile and maintain an adequate
    inventory of the public reserved lands, including not only the timber on those lands but also the other
    multiple use values for which the public reserved lands are managed.” Id.
    12
    [¶17] The Bureau and CMP timely appealed three days later, and Black
    cross-appealed. See M.R. App. P. 2A, 2B(c)(1), 2C(a)(1)-(2). On August 24,
    2021, Black moved to lift the automatic stay pending the appeal. See M.R.
    Civ. P. 62(g); M.R. App. P. 10. After agreement of all the parties at a conference,
    this Court (Jabar, J.) ordered CMP “to refrain from all construction activities,
    including vegetation removal” on the leased lands pursuant to M.R. Civ. P. 62(g).
    [¶18] On November 2, 2021, the people of Maine voted to approve an
    initiated bill (the Initiative) that changed the law governing the permitting of
    electric transmission lines and restricting where they can be constructed.8 I.B.
    2021, ch. 1, §§ 1-6 (effective Dec. 19, 2021).9 The legislation enacted by the
    Initiative requires that all “high-impact electric transmission lines” receive
    legislative approval in addition to a CPCN and bans outright such lines from “the
    8 On November 2, 2021, fifty-nine percent of Maine voters approved the Initiative, which took
    effect on December 19, 2021, and effectively halted the Project. I.B. 2021, ch. 1, §§ 1-6; see NECEC
    Transmission LLC v. Bureau of Parks and Lands, 
    2022 ME 48
    , ¶¶ 18-23, 
    281 A.3d 618
    . The effective
    date of the Initiative was approximately four months after the trial court issued its final judgment.
    The trial court, therefore, analyzed the relevant law as it existed before the Initiative took effect. See
    12 M.R.S. § 1852(4) (2021).
    9Bills introduced through the initiative process are assigned I.B. (“Initiated Bill”) designations.
    See Maine State Legislature, Votes on Initiated Bills, https://legislature.maine.gov/lawlibrary/votes-
    on-initiated-bills-1910/9204/ (last visited Aug. 30, 2022). An initiative is a type of referendum that
    allows voters to propose to the Legislature any bill, resolve, or resolution. Me. Const. art. IV, pt. 3,
    § 18. The Secretary of State must verify the validity of the requisite number of signatures on the
    petition. See id. § 18(2); 21-A M.R.S. § 905(1) (2022). The Legislature may then pass that law as
    submitted or refer the initiated measure to the people for a referendum vote. Me. Const. art. IV, pt. 3,
    § 18(2)-(3).
    13
    Upper Kennebec Region,” both retroactively to September 16, 2020. Id. §§ 2-6.
    Relevant here, the Initiative also amends the statutes authorizing the Bureau to
    lease public reserved land for construction of transmission lines by requiring
    that such leases first receive two-thirds legislative approval. Id. § 1. That
    provision applies retroactively to September 16, 2014, and therefore would
    govern the 2014 lease as well as the 2020 lease. Id. On December 23, 2021,
    Black moved to dismiss all pending appeals as moot in light of the Initiative.
    After the Bureau moved to enlarge the time to respond to Black’s motion, this
    Court (Horton, J.), ordered that the motion to dismiss would be considered with
    the merits of the appeal, and the Bureau and CMP filed oppositions to the
    motion shortly thereafter. See M.R. App. P. 4(d), 10.
    II. DISCUSSION
    [¶19]   Before turning to the merits of the appeal, we address the
    threshold issues of jurisdiction and standing, and also the issue of the
    retroactive application of section 1 of the Initiative to both the 2020 lease and
    its 2014 predecessor. We determine that the Superior Court had jurisdiction
    pursuant to the Maine Administrative Procedure Act and Rule 80C of the Maine
    Rules of Civil Procedure, that certain plaintiffs have standing to bring the claims
    14
    presented, and that section 1 of the Initiative cannot constitutionally apply to
    the 2020 lease or its 2014 predecessor.
    [¶20] We then address Black’s contention that article IX, section 23 of
    the Maine Constitution and the Designated Lands statutes required the Bureau
    to make a formal determination, before granting the 2014 lease and the 2020
    lease, that neither lease would reduce or substantially alter public lands. We
    conclude that the Bureau’s grant of leases of public reserved lands were not
    adjudicatory acts because the Legislature had granted the Bureau broad
    authority to grant leases that did not reduce or substantially alter public
    reserved lands, without requiring any formal findings, notice, hearing, or other
    administrative or adjudicative process. Therefore, we conclude that, by the
    very act of granting the leases, the Bureau determined that the leases were
    within its constitutional and statutory authority.
    [¶21] We further conclude that, because the Bureau’s lease of public
    reserved land is a contractual act limited only by the Legislature’s broad grant
    of leasing authority to the Bureau, the grant of the 2020 lease is reviewable only
    to determine whether the Bureau exceeded its statutory or constitutional
    authority and therefore acted ultra vires. Lastly, based on the undisputed facts
    regarding the nature, location, uses, and extent of the 2020 lease and the public
    15
    reserved lands it concerns, we conclude that the 2020 lease does not cause the
    public reserved lands, of which it concerns a very small portion, to be
    “substantially altered” for purposes of the Maine Constitution and the
    Designated Lands statutes. Me. Const. art. IX, § 23; 12 M.R.S. § 598(5). Because
    the 2020 lease concerns the same portion of the same public reserved lands as
    the 2014 lease, our conclusion necessarily applies to both.
    A.    Jurisdiction
    [¶22] The parties disagree about the basis of jurisdiction both in the trial
    court and here. The Bureau and CMP maintained, in their motions to dismiss
    Black’s ultra vires claim in Count 1 and the injunction claim in Count 2 of the
    first amended complaint, that jurisdiction exists solely under Rule 80C, and
    they repeat the argument here, citing to our decision in Fair Elections Portland
    v. City of Portland, 
    2021 ME 32
    , ¶¶ 19, 21 n.7, 
    252 A.3d 504
    —precedent in
    which we approved the dismissal of independent claims as duplicative of a
    Rule 80B appeal. Black responds that the purpose of Count 1 was to seek “a
    declaratory judgment that signing the 2014 and 2020 leases without first
    obtaining a two-thirds vote of each House violated Article IX, Section 23 and
    was therefore ultra vires.” Neither argument is wrong, and our decision in Sold,
    Inc. v. Town of Gorham helps explain why. 
    2005 ME 24
    , 
    868 A.2d 172
    .
    16
    [¶23]   In Sold, seven subdivision developers brought a declaratory
    judgment action—not a Rule 80B appeal—challenging certain impact fee
    requirements in the conditional approvals the town planning board had
    granted. Id. ¶¶ 1, 3. We held that their appeal was barred by the exclusivity
    provisions of Rule 80B because the actions appealed from were not outside the
    planning board’s authority and could not be the basis for an ultra vires claim:
    All of the subdivisions at issue in this action were approved, subject
    to a condition requiring payment of the impact fee. There is no
    dispute that none of the conditional approvals given to the
    plaintiffs’ subdivision applications were challenged within the
    thirty-day period required by M.R. Civ. P. 80B(b). When the time to
    file an appeal expired, the conditional approvals, including the
    impact fee requirements, became final, and were not subject to
    challenge.
    A declaratory judgment action cannot be used to create a
    cause of action that does not otherwise exist. A declaratory
    judgment action may only be brought to resolve a justiciable
    controversy. Thus, a declaratory judgment action cannot be used
    to revive a cause of action that is otherwise barred by the passage
    of time. The declaratory judgment law, 14 M.R.S.A. §§ 5951-5963
    (2003), does not provide a self-help device for parties who have
    failed to timely appeal a municipal administrative decision to gain
    an extension or revival of the time to appeal and reopen a decision
    that has otherwise become final.
    The plaintiffs assert that they may appeal by a declaratory
    judgment action, after the normal time period for appeal has
    expired, if the challenged action of the municipality is ultra vires as
    being beyond the lawful statutory or constitutional authority of the
    Town to act. If the plaintiffs’ view of the law is correct, then there
    would be, in effect, no time limit to appeal any action of a municipal
    17
    government—or the state government for that matter—that is
    alleged to be inconsistent with a statutory or constitutional
    requirement. Our law does not countenance such a wholesale
    deviation from explicit provisions requiring timely appeals to
    promote finality of administrative actions.
    Subject to equitable defenses including laches, a
    governmental action may be challenged at any time, as ultra vires,
    when the action itself is beyond the jurisdiction or authority of the
    administrative body to act. Thus, municipal or state actions may be
    collaterally attacked as outside the jurisdiction or authority of an
    agency, when it is claimed that the ordinance or statute under
    which the administrative agency purported to act was
    unconstitutional on its face, thus rendering the administrative
    action beyond the lawful authority of the challenged agency.
    Here, there is no dispute that the Planning Board had
    authority to consider, approve, and attach conditions to approvals
    of subdivisions. Plaintiffs only challenge one condition of the
    subdivision approval as inconsistent with statutory and
    constitutional requirements. Such challenges are the essence of
    matters that must be brought pursuant to Rule 80B to question
    whether the particular action of a municipal administrative agency
    is consistent with the requirements of law.
    Id. ¶¶ 9-13 (citations omitted).
    [¶24] Our decision in Sold illustrates the principle that ultra vires claims
    constitute a narrow exception to the Rule 80B (and Rule 80C) exclusivity rule,
    but only if Rule 80B (or Rule 80C) review is unavailable. Applied to this case,
    that principle leads us to conclude that Black’s declaratory judgment count
    applies only to the 2014 lease and is duplicative as to the 2020 lease. His appeal
    of the 2020 lease met the Rule 80C time limits, and Rule 80C, along with the
    18
    Maine Administrative Procedure Act, authorizes a reviewing court to entertain
    claims that an agency decision is “[i]n excess of the statutory authority of the
    agency.” 5 M.R.S. § 11007(4)(C)(2) (2022). That the 2014 lease was terminated
    by the 2020 lease raises a mootness issue as to Black’s declaratory judgment
    count, but because the ultra vires issue is the same as to both leases, an
    invalidation of the 2020 lease on ultra vires grounds would likewise invalidate
    the 2014 lease, were it still in effect, rather than resurrecting it. Moreover, the
    trial court’s ruling that the Bureau was required to make a “substantial
    alteration” determination and conduct an administrative process before
    granting the leases is reviewable here only under Rule 80C and the Maine
    Administrative Procedure Act because the ruling focused on the procedure for
    granting the leases, not on the Bureau’s substantive authority to grant them. In
    sum, Rule 80C allows us to consider both of Black’s challenges to the leases—
    the Bureau’s failure to meet alleged procedural requirements and the Bureau’s
    alleged ultra vires action—and we deem Black’s Rule 80C appeal as to the
    2020 lease to be the appropriate focus of our review.
    B.    Standard of Review
    [¶25] “When we consider a judgment of the Superior Court, reviewing a
    decision of a state administrative agency pursuant to M.R. Civ. P. 80C, we follow
    19
    the standards of review governing administrative appeals. Thus, when the trial
    court has acted in an intermediate appellate capacity, we review directly the
    original decision of the fact-finding agency, without deference to the ruling on
    the intermediate appeal by the court from which the appeal is taken.” Anderson
    v. Me. Pub. Emps. Ret. Sys., 
    2009 ME 134
    , ¶ 2, 
    985 A.2d 501
    . “Statutory
    construction is a question of law, and, therefore, we review [the agency’s
    statutory interpretation] de novo.” Med. Mut. Ins. Co. of Me. v. Bureau of Ins.,
    
    2005 ME 12
    , ¶ 5, 
    866 A.2d 117
    .
    C.    Standing
    [¶26] We review standing de novo as a question of law and may raise the
    issue sua sponte; therefore we are not bound by the trial court’s conclusion.
    Blanchard v. Town of Bar Harbor, 
    2019 ME 168
    , ¶ 8, 
    221 A.3d 554
    . The plaintiffs
    bear the burden of establishing standing, which is determined based on the
    circumstances that existed when the complaint was filed. Bank of Am., N.A. v.
    Greenleaf, 
    2014 ME 89
    , ¶ 7, 
    96 A.3d 700
    ; Conservation L. Found. v. Town of
    Lincolnville, No. AP-00-3, 
    2001 Me. Super. LEXIS 26
    , at *21 (Feb. 28, 2001)
    (citing Sims v. State of Florida, 
    862 F.2d 1449
    , 1458 (11th Cir. 1989)).
    [¶27] In Maine, standing is prudential, not constitutional. Roop v. City of
    Belfast, 
    2007 ME 32
    , ¶ 7, 
    915 A.2d 966
    . Thus, this Court may “limit access to
    20
    the courts to those best suited to assert a particular claim.” 
    Id.
     (quotation marks
    omitted). “Just what particular interest or injury is required for standing
    purposes and the source of that requirement—whether statutory- or common
    law-based—varies based on the type of claims being alleged.” Greenleaf, 
    2014 ME 89
    , ¶ 7, 
    96 A.3d 700
    . Our standing analysis in Fitzgerald v. Baxter State Park
    Authority is applicable because the plaintiffs in Fitzgerald, like those here,
    asserted that a state agency entrusted with management of public lands had
    acted in excess of its authority. 
    385 A.2d 189
    , 194, 196-97 (Me. 1978). In
    Fitzgerald, we decided that users of the public land in question had standing to
    challenge the agency’s action. 
    Id. at 196-97
    .
    [¶28] CMP contends that none of the plaintiffs here “claim standing
    based on traditional property rights or a nexus to [the Bureau’s leasing]
    decision,” further noting that “most of these plaintiffs have not alleged any use
    of either the leased land itself or the broader public lots in Johnson Mountain
    Township or West Forks Plantation.” To the contrary, at least three of the
    individual plaintiffs have sufficiently demonstrated standing. Specifically, the
    first amended complaint alleges that plaintiffs Edwin Buzzell, Clifford Stevens,
    and Todd Towle own and operate outdoor recreation and guiding businesses
    that “operate[] in and around the public reserved lands” subject to the lease,
    21
    and that they have hunted and fished in the area as well. Although these
    plaintiffs allege no specific harm beyond the transmission line’s mere visibility,
    their history of use of the public reserved lands, occupied in part by the area
    encompassed in the original and subsequent leases, is sufficient to confer
    standing. See 
    id. at 196-97
    .
    [¶29] We further hold that NRCM has associational standing. “An
    association has standing to bring suit on behalf of its members when its
    members would otherwise have standing to sue in their own right, the interests
    at stake are germane to the organization’s purpose, and neither the claim
    asserted nor the relief requested requires the participation of individual
    members in the lawsuit.” Friends of the Earth, Inc. v. Laidlaw Env’t Servs. (TOC),
    Inc., 
    528 U.S. 167
    , 181 (2000); see also Conservation L. Found., 
    2001 Me. Super. LEXIS 26
    , at *18-19.
    [¶30] NRCM satisfies each part of this test. First, Towle and Buzzell are
    members of NRCM and otherwise have standing to sue individually. Second,
    NRCM is an environmental advocacy group whose “mission is ‘protecting,
    conserving, and restoring Maine’s environment.’” The claims at issue seek the
    invalidation of a lease of public reserved lands and are undoubtedly germane
    to NRCM’s environmental conservation mission.
    22
    [¶31] We have never determined whether individual members of the
    Legislature have standing to challenge agency action. See Me. Senate v. Sec’y of
    State, 
    2018 ME 52
    , ¶¶ 13, 25, 
    183 A.3d 749
     (assuming without deciding that the
    Maine Senate had standing to seek “declaratory and injunctive relief to halt the
    implementation of ranked-choice voting”); see also Carson v. Comm’r of the Dep’t
    of Health & Hum. Servs., No. AP-18-48, 
    2019 Me. Super. LEXIS 170
    , at *3, 5-6
    (June 27, 2019) (declining to determine whether a state senator had standing
    to bring a Rule 80C petition because other petitioners had standing). Because
    we have determined that other plaintiffs have standing to pursue these claims,
    we need not resolve this question here.
    D.    Retroactive Application of the Initiative to the 2020 Lease
    [¶32] After the Initiative went into effect, Black moved to dismiss this
    pending appeal on mootness grounds, contending that the enactment of the
    Initiative invalidated the 2020 lease as a matter of law and therefore obviated
    the need to review the trial court’s judgment. We do not address the merits of
    moot cases absent exceptional circumstances, so before continuing our analysis
    we need to consider the effect of the Initiative upon the justiciability of this case.
    See Mainers for Fair Bear Hunting v. Dep’t of Inland Fisheries & Wildlife, 
    2016 ME 57
    , ¶ 7, 
    136 A.3d 714
    .       Black contends that application of the new law
    23
    (1) invalidates the lease between the Bureau and CMP; (2) creates the
    argued-for public process regarding substantial alteration determinations by
    requiring legislative approval of high-impact transmission line leases; and
    (3) eliminates the need for this Court to determine if the Project substantially
    alters the public reserved lands at issue because the legislation makes that
    determination by fiat. Whether section 1 of the Initiative moots this appeal, as
    Black contends, depends on whether the Initiative applies retroactively to the
    2020 lease.
    1.      Retroactive Application Generally
    [¶33] We begin our discussion of the Initiative by noting that “[t]he same
    constitutional limitations on legislative authority apply to citizen-initiated
    legislation as apply to the enactments of the Legislature,” although
    “citizen-initiated legislation enjoys a heavy presumption of constitutionality
    and should be construed liberally.” NECEC Transmission LLC v. Bureau of Parks
    and Lands, 
    2022 ME 48
    , ¶ 35, 
    281 A.3d 618
     (quotation marks omitted).
    Section 1 of the Initiative amended 12 M.R.S. § 1852(4) to require two-thirds
    legislative approval before the Bureau may grant “a lease or conveyance for the
    24
    purpose of constructing and operating . . . transmission lines and facilities” and
    makes the amendment retroactive to September 16, 2014. I.B. 2021, ch. 1, § 1.10
    [¶34] A new statute enacted by citizen initiative or by the Legislature can
    apply retroactively if (1) the statute is intended to apply retroactively and
    (2) retroactive application does not violate any provisions of the Maine
    Constitution. MacImage of Me., LLC v. Androscoggin County., 
    2012 ME 44
    , ¶¶ 21,
    23, 
    40 A.3d 975
    ; State v. L.V.I. Grp., 
    1997 ME 25
    , ¶ 9, 
    690 A.2d 960
     (“If the
    Legislature intends a retroactive application, the statute must be so applied
    unless the Legislature is prohibited from regulating conduct in the intended
    10   Section 1 provides for the statute, as amended, to state in full:
    4. Lease of public reserved land for utilities and rights-of-way. The
    bureau may lease the right, for a term not exceeding 25 years, to:
    A. Set and maintain or use poles, electric power transmission and
    telecommunication transmission lines and facilities, roads, bridges, and landing
    strips;
    B. Lay and maintain or use pipelines and railroad tracks; and
    C. Establish and maintain or use other rights-of-way.
    Any such poles, transmission lines and facilities, landing strips, pipelines and railroad
    tracks under this subsection are deemed to substantially alter the uses of the land
    within the meaning of the Constitution of Maine, Article IX, Section 23, and a lease or
    conveyance for the purpose of constructing and operating such poles, transmission
    lines, and facilities, landing strips, pipelines and railroad tracks under this subsection
    may not be granted without first obtaining the vote of 2/3 of all the members elected
    to each House of the Legislature.
    Notwithstanding Title 1, section 302 or any other provision of law to the contrary,
    this subsection applies retroactively to September 16, 2014.
    12 M.R.S. § 1852(4) (2022); see I.B. 2021, ch. 1, § 1.
    25
    manner, and such a limitation upon the Legislature’s power can only arise from
    the United States Constitution or the Maine Constitution.” (quotation marks
    omitted)). Cf. Opinion of the Justices, 
    103 Me. 506
    , 508, 
    69 A. 627
     (1907)
    (“[L]aws and regulations are to be held valid unless there can be pointed out
    some provision in the State or United States Constitution which clearly
    prohibits them.”).
    [¶35] The analysis of the first prong of the MacImage retroactivity test is
    plain: section 1 explicitly states that the law applies retroactively to
    September 16, 2014. I.B. 2021, ch. 1, § 1. The second prong requires a more
    extensive analysis.         Black’s motion to dismiss contends that retroactive
    application of section 1 of the Initiative to the 2020 lease does not violate the
    Contract Clause or the Due Process Clause of either the United States
    Constitution or the Maine Constitution. We disagree and hold that retroactive
    application of section 1 of the Initiative violates the Contract Clause of the
    United States Constitution,11 and, therefore, need not reach Black’s argument
    regarding the Due Process Clause’s vested rights doctrine.
    11 CMP and the Bureau have raised no independent argument specific to the Maine Constitution’s
    Contract Clause. We have never stated whether the Contract Clause of the Maine Constitution is
    coextensive with that of the U.S. Constitution. Because the issue is not briefed, this case is not the
    forum to decide that question. See State v. Chan, 
    2020 ME 91
    , ¶ 18 n.10, 
    236 A.3d 471
    .
    26
    2.     Section 1 of the Initiative and the Contract Clause
    [¶36] The federal constitution’s Contract Clause limits the enactment of
    laws impairing the obligation of contracts. See U.S. Const. art. 1, § 10, cl. 1. Its
    general purpose is “to encourage trade and credit by promoting confidence in
    the stability of contractual obligations” by “limit[ing] the power of the States to
    modify their own contracts as well as to regulate those between private
    parties.”   U.S. Tr. Co. v. New Jersey, 
    431 U.S. 1
    , 15, 17 (1977); see also
    Rediscovering the Contract Clause, 
    97 Harv. L. Rev. 1414
    , 1429 (1984) (“[T]he
    reasons motivating legislators to impair contractual obligations must relate to
    a diffuse public interest rather than merely to narrow factional ends. . . .
    Moreover, the imperative that government accommodate private expectations
    by acting only pursuant to rules fixed and announced beforehand demands that
    the legislature’s discretion to repudiate the state’s own obligations be strictly
    constrained.” (footnotes and quotation marks omitted)).            This limitation
    applies not only to state legislatures but also to voters, who “may no more
    violate the Constitution by enacting a ballot measure than a legislative body
    may do so by enacting legislation.” Citizens Against Rent Control/Coal. for Fair
    Hous. v. City of Berkeley, 
    454 U.S. 290
    , 295 (1981).
    27
    [¶37]    “Yet the Contract Clause does not prohibit the States from
    repealing or amending statutes generally, or from enacting legislation with
    retroactive effects.” U.S. Tr. Co., 
    431 U.S. at 17
    . We therefore must determine if
    a particular exercise of legislative power justifies the impairment of a contract.
    
    Id. at 17, 21-22
    .
    [¶38] To do so, we use a three-step analysis: first, we determine if a
    legislative act results in a substantial impairment of a contractual relationship;
    if it does, we next identify the legislative purpose of that impairing act; then, we
    determine if that purpose justifies the alteration of the contracting parties’
    rights and responsibilities. Kittery Retail Ventures, LLC v. Town of Kittery, 
    2004 ME 65
    , ¶ 38, 
    856 A.2d 1183
    ; see also Energy Rsrvs. Grp., Inc. v. Kan. Power & Light
    Co., 
    459 U.S. 400
    , 411-13 (1983).
    [¶39] Under the first step, we ask “whether there is a contractual
    relationship, whether a change in law impairs that contractual relationship, and
    whether the impairment is substantial.” Kittery Retail, 
    2004 ME 65
    , ¶ 38, 
    856 A.2d 1183
     (quotation marks omitted). To determine the degree of impairment,
    we consider several factors, including whether the subject matter of the
    contract is already regulated, whether the additional regulation was
    foreseeable, and whether the change in law affects the contract itself, as
    28
    opposed to the underlying subject matter. Id. ¶¶ 39-41. We may also consider
    the value of the contract and the extent to which the impairing law undermined
    the parties’ contractual expectations. See U.S. Tr. Co., 
    431 U.S. at 18-21
    .
    [¶40] If a legislative act substantially impairs a contract, we next identify
    the legislative purpose of the impairing act. See Kittery Retail, 
    2004 ME 65
    , ¶ 38,
    
    856 A.2d 1183
    ; Energy Rsrvs. Grp., Inc., 
    459 U.S. at 411-12
    ; U.S. Tr. Co., 
    431 U.S. at 21-22
    . As long as the State has not contracted away an essential attribute of
    sovereignty,12 a public-purpose justification for a contractual impairment is
    required, to “guarantee[] that the State is exercising its police power, rather
    than providing a benefit to special interests.” Energy Rsrvs. Grp., Inc., 
    459 U.S. at 412
    ; see U.S. Tr. Co., 
    431 U.S. at 23
    . “We look to the plain language of a statute
    to discern the real purpose of the legislation.”                       Am. Republic Ins. Co. v.
    Superintendent of Ins., 
    647 A.2d 1195
    , 1197 (Me. 1994) (quotation marks
    omitted). We do so “to reconcile the strictures of the Contract Clause with the
    essential attributes of sovereign power necessarily reserved by the States to
    safeguard the welfare of their citizens.” U.S. Tr. Co., 
    431 U.S. at 21
     (quotation
    12If the impaired contract purports to bargain away an aspect of state sovereignty, the focus
    turns to “the State’s power to create irrevocable contract rights in the first place, rather than [to] an
    inquiry into the purpose or reasonableness of the subsequent impairment.” U.S. Tr. Co. v. New Jersey,
    
    431 U.S. 1
    , 23 (1977). No party contends that the 2020 lease implicates a matter of state sovereignty.
    29
    marks and citation omitted). An impairing law “must have a significant and
    legitimate public purpose behind [it], such as the remedying of a broad and
    general social or economic problem.” Energy Rsrvs. Grp., Inc., 
    459 U.S. at 411-12
    (citation omitted).
    [¶41]    Lastly, once we have identified the legislative purpose, we
    determine whether that purpose justifies the alteration of the contracting
    parties’ rights and responsibilities. See Energy Rsrvs. Grp., Inc, 
    459 U.S. at 412
    ;
    Kittery Retail, 
    2004 ME 65
    , ¶ 38, 
    856 A.2d 1183
    ; see also U.S. Tr. Co., 
    431 U.S. at 22
     (“Legislation adjusting the rights and responsibilities of contracting parties
    must be upon reasonable conditions and of a character appropriate to the
    public purpose justifying its adoption.”). We will defer to the Legislature’s
    judgment as to the necessity and reasonableness of economic or social
    regulation, unless, as here, the State is a contracting party. See Kittery Retail,
    
    2004 ME 65
    , ¶ 38, 
    856 A.2d 1183
     (stating that no deference is owed if “the State
    . . . is a contracting party”); see also U.S. Tr. Co., 
    431 U.S. at 25-26
     (“[A]n
    impairment may be constitutional if it is reasonable and necessary to serve an
    important public purpose.      In applying this standard, however, complete
    deference to a legislative assessment of reasonableness and necessity is not
    appropriate [when] the State’s self-interest is at stake.”).
    30
    [¶42] We now apply these principles to the instant case. The contractual
    relationship at issue is defined in the 2020 lease. Before the enactment of
    section 1 of the Initiative, the Bureau had been delegated the authority to freely
    lease public reserved land to “[s]et and maintain” transmission lines, so long as
    the term of the lease did not exceed twenty-five years. 12 M.R.S. § 1852(4)
    (2021). Section 1 retroactively stripped the Bureau of that authority. See I.B.
    2021, ch. 1, § 1. This impairs the lease between the Bureau and CMP for two
    reasons. First, Section 1 essentially invalidates the lease as ultra vires—beyond
    the Bureau’s authority.     Such an invalidation disrupts the longstanding
    contractual expectations between the Bureau and CMP. It results in the total
    destruction of the parties’ contractual expectations and is therefore a
    substantial impairment. See U.S. Tr. Co., 
    431 U.S. at 26-27
    .
    [¶43] Second, the new rule at the heart of Section 1 of the Initiative—
    that the Bureau is retroactively stripped of an authority it possessed at the time
    of the granting of both the 2014 and 2020 leases—was not foreseeable when
    the leases were granted. The management of public reserved lands and the
    construction and operation of electric transmission lines are regulated
    activities, and therefore any regulations modifying the parties’ rights and
    responsibilities under the lease should be reasonably foreseeable. On this
    31
    point, Black contends that a lease provision which states that CMP “shall be in
    compliance with all Federal, State and local statutes, ordinances, rules and
    regulations, now or hereinafter enacted” is evidence that “the written
    instrument underlying [the contractual] relationship expressly contemplates”
    retroactive legislation. Although it may have been reasonably foreseeable that
    future legislation would affect the lease, it would be unreasonable to suggest
    that it was foreseeable, at the time of the execution of the lease (June 23, 2020),
    that a citizens’ initiative (approved by voters on November 2, 2021) with a
    retroactivity provision dating back seven years would completely invalidate the
    lease.
    [¶44] Having determined that Section 1 of the Initiative substantially
    impairs the lease between the Bureau and CMP, we next identify the legislative
    purpose of that part of the referendum, looking to the Initiative’s plain language
    to do so. Section 1 is a relatively short provision, and its text reveals no clear
    purpose. The legal effect of the amendment is legislative oversight of actions
    the Bureau had previously been authorized to take. Black asserts that the
    purpose of the legislation is “additional environmental protections and
    legislative oversight.” We assume, without deciding, that this is the Initiative’s
    32
    legislative purpose.13 Because the State is a party to the impaired contract, the
    underlying legislative purpose is not entitled to the usual deference. Black
    argues that full deference should still apply here because, although the State is
    a party to the lease, it derives no “financial benefit” from the impairment. But
    the limitation on a state’s ability to impair, through retroactive legislation, a
    contract to which it is a party applies regardless of whether the impairment
    benefits the State financially. “[A] State is not completely free to consider
    impairing the obligations of its own contracts on a par with other policy
    alternatives. Similarly, a State is not free to impose a drastic impairment when
    an evident and more moderate course would serve its purposes equally well.” U.S.
    Tr. Co., 
    431 U.S. at 30-31
     (emphasis added). There clearly was a more moderate
    course available here that would have promoted the alleged goals of
    13The stated purpose of the Initiative is not specifically to prevent the Project from being built.
    But see NECEC Transmission LLC v. Bureau of Parks & Lands, No. BCD-CIV-2021-00058, 2021 Me. Bus.
    & Consumer LEXIS 2, at *19 (Dec. 16, 2021) (“Proponents of the Initiative included a political action
    committee, ‘No CMP Corridor,’ which repeatedly stated that the purpose of the Initiative was to stop
    the Project.”). Project opponents tried that direct approach in a 2020 initiative that impermissibly
    targeted the PUC’s authorization for this Project. Avangrid Networks, Inc. v. Sec’y of State, 
    2020 ME 109
    , ¶ 35, 
    237 A.3d 882
    . The State has a long-standing, multifaceted permitting process through
    which several state agencies and impacted local governments authorize electric transmission lines.
    The 2021 Initiative did not purport to reverse a particular decision from a state agency or
    commission, as the first initiative did. But the 2021 Initiative’s language affected no agency subject
    to the Designated Lands statutes other than the Bureau; affected no activity allowed on designated
    lands other than the construction of transmission lines and other linear projects on public reserved
    lands; and made section 1 retroactive to September 16, 2014—a date that appears to have relevance
    only because it predates the execution of the 2014 lease. Opponents have swapped a targeted
    directive in the first initiative for a nominally nontargeted retroactive mandate in the one before us
    now.
    33
    environmental protection and legislative oversight—to make the statutory
    change prospective only and require legislative approval for all future
    transmission line leases on public lands. Of course, if the true purpose of the
    Initiative was to stop the Project, that more moderate course would not have
    been sufficient.
    [¶45] Finally, we must determine whether the need for additional
    legislative oversight justifies the alteration of the contracting parties’ rights and
    responsibilities. In making that determination, we must consider the state’s
    authority to enter into the agreement in the first instance. See U.S. Tr. Co., 
    431 U.S. at 21-24
    .
    [¶46] Black has offered no reason why the Initiative’s purpose to
    increase legislative oversight and environmental protection of public reserved
    lands justifies the invalidation of the parties’ lease and every other lease that
    the Bureau has granted since 2014 for projects within the scope of section 1 of
    the Initiative. No emergency gave rise to section 1 of the Initiative, nor does it
    remedy any broad and general social or economic problem. Over the years, the
    Bureau has granted hundreds of leases and licenses of public reserved lands.
    The Bureau granted all these leases and licenses without engaging in any
    rulemaking or other public administrative process. Through the Initiative, the
    34
    legislative power has reached back in time to destroy at least one lease and to
    put the validity of hundreds more into question, all without any showing of
    necessity for such drastic action.
    [¶47] Based on the lack of any “significant and legitimate” countervailing
    public purpose to justify the voiding of the 2020 lease, we conclude that the
    Contract Clause does not permit the impairment caused by section 1 of the
    Initiative. See Energy Rsrvs. Grp., Inc, 
    459 U.S. at 411-12
    ; see U.S. Tr. Co., 
    431 U.S. at 26-27
    ; Me. Const. art. 1, § 11. Accordingly, the 2020 lease was not voided by
    the Initiative, and CMP’s and the Bureau’s appeals remain justiciable. Black’s
    motion to dismiss these appeals as moot is therefore denied. As a result, in
    addressing the remaining issues, we apply the law as it was prior to the
    Initiative, codified at 12 M.R.S. § 1852(4) (2021).
    E.    Requirements Applicable to the Bureau’s Granting of Leases of
    Public Reserved Lands
    [¶48] We now address Black’s contention and the trial court’s ruling that
    article IX, section 23 of the Maine Constitution and the Designated Lands
    statutes required the Bureau to follow a “public administrative process” before
    granting the 2020 lease.
    35
    1.     The Bureau’s Leasing Authority Generally
    [¶49] Prior to the ratification of article IX, section 23, public reserved
    lands could be leased and were managed under multiple-use principles by the
    Bureau’s predecessor agency. See P.L. 1987, ch. 737, pt. B, § 2 (effective Mar. 1,
    1989) (codified at 12 M.R.S.A. § 585(1), (2)(A), (4) (Supp. 1988)). That agency
    realized these management objectives through the creation of comprehensive
    management plans and specific action plans, and it was authorized to lease
    public reserved lands for electric power transmission for up to a
    twenty-five-year term if that action was consistent with the management plans
    for the leased area. P.L. 1987, ch. 737, pt. B, § 2 (effective Mar. 1, 1989) (codified
    at 12 M.R.S.A. § 585(3), (4)(C) (Supp. 1988)).
    [¶50] The ratification of article IX, section 23 in 1993 did not directly
    amend this statutory scheme, but the Legislature could no longer delegate to
    executive agencies, including the Bureau, the authority to reduce or
    substantially alter the use of designated lands. Furthermore, as the trial court
    described, the constitutional amendment “[took] back from the executive
    branch authority previously delegated to it by the Legislature. . . . [W]hat was
    taken back was the final say as to whether public reserved lands could be sold,
    and—pertinent here—whether the uses of the public lands could be
    36
    ‘substantially altered.’”   In other words, the executive branch was still
    authorized to grant utility leases, but only if those leases did not reduce or
    substantially alter the uses of designated land.
    [¶51] After the passage of the constitutional amendment, the Legislature
    enacted implementing legislation, the Designated Lands statutes, in which it
    defined the term “substantially altered.” See 12 M.R.S. § 598(5).
    “Substantially altered,” in the use of designated lands, means
    changed so as to significantly alter physical characteristics in a way
    that frustrates the essential purposes for which that land is held by
    the State.
    Id. None of the parties argues that the Legislature’s definition does not comport
    with the letter and intent of the constitutional term, so we accept the
    Legislature’s definition for purposes of this analysis. There are two issues that
    must be resolved when applying this definition: (1) whether a change in use
    significantly alters the physical characteristics of the land and, if so, (2) whether
    that alteration frustrates the essential purposes for which the land is held.
    See id.
    [¶52]    The Bureau argues that the Legislature’s statutory scheme
    reflected the Legislature’s view that no utility lease could ever be deemed to
    result in a substantial alteration of the use of public reserved land—even if, for
    example, a combination of utility leases occupied the entirety of a tract of public
    37
    reserved land. We cannot logically assume that the Legislature ever endorsed
    this view. The essential purpose of public reserved lands is multiple-use
    management that achieves a sustained yield of products and services. Id.
    §§ 598(5), 1847(1); see also id. § 1845(1)(D).       Multiple-use management
    requires the Bureau to catalog the various resources of a particular public lot;
    to develop a management plan that “provide[s] for the demonstration of
    appropriate management practices that will enhance the timber, wildlife,
    recreation, economic and other values of the lands,” id. § 1847(2); and to
    manage that lot in such a way that no single purpose frustrates the others and
    impairs the land’s productivity, see id. § 1845(1)(D), (2). Considering this
    management scheme together with the requirements imposed by article IX,
    section 23, a lease could so significantly alter the physical characteristics of a
    public lot that it would result, practically speaking, in the Bureau managing the
    land for that purpose at the expense of all others. See id. § 1847(1)-(2). Thus,
    the Legislature’s continued delegation of authority to grant utility leases on
    public reserved lands did not mean that the Legislature deemed that any such
    lease could never result in a “substantial alteration” of use. Instead, the
    statutory scheme requires the Bureau to decide on a case-by-case basis
    38
    whether it has authority to lease public reserved land for utility transmission
    lines.
    2.   The Bureau’s Authority to Grant the 2020 Lease Without Any
    Formal Administrative Process
    [¶53] In this case, our conclusion that the Bureau did not have blanket
    authority to grant a lease for a utility transmission line without determining for
    itself whether the lease would substantially alter public reserved lands does
    not mean that the Legislature required the Bureau to make that determination
    pursuant to any particular administrative process. Neither article IX, section 23
    of the Maine Constitution, nor any statute, nor any decision by this Court,
    explicitly requires the Bureau to make a determination regarding substantial
    alteration pursuant to a public administrative process before granting a utility
    lease on public reserved lands. See Me. Const. art. IX, § 23; 12 M.R.S. §§ 598 to
    598-B, 1852(4)(A) (2022); 12 M.R.S. § 1852(4)(A) (2021).
    [¶54] Indeed, the Bureau’s general authority to “take actions on the
    public reserved lands,” including granting leases, could hardly be more broad
    and sweeping: “The director may take actions on the public reserved lands
    consistent with the management plans for those lands and upon any terms and
    conditions and for any consideration the director considers reasonable.”
    12 M.R.S. § 1847(3) (emphasis added). The delegation of leasing authority
    39
    specific to leases for utility transmission lines was equally broad prior to the
    passage of the Initiative. See 12 M.R.S. § 1852(4) (2021).
    [¶55]   The Legislature clearly could have constrained the Bureau’s
    authority to grant leases of public reserved lands in the manner that it has done
    for other agency action, such as leasing submerged public lands. See 12 M.R.S.
    § 6072 (2022).     The Legislature has required the Department of Marine
    Resources (DMR) to follow an adjudicatory-type process pursuant to the Maine
    Administrative Procedure Act in granting aquaculture leases. Id. § 6072(6)
    (“Prior to granting [an aquaculture] lease, the commissioner shall hold a
    hearing. The hearing shall be an adjudicatory proceeding and shall be held in
    the manner provided under the Maine Administrative Procedure Act . . . .”); see
    also 12 M.R.S. § 6001(13). Because the aquaculture lease statute designates the
    lease procedure as adjudicatory, the statute requires notice and a written
    decision and requires DMR to promulgate the rules under which it will exercise
    its leasing authority. See id. §§ 6072(6)(B) (“Under the provisions of Title 5,
    section 9052, the leasing procedure must require notice to the general public.”),
    6072(7-A) (“In evaluating the proposed lease, the commissioner shall take into
    consideration the number and density of aquaculture leases in an area and may
    grant the lease if the proposed lease meets the following conditions as defined
    40
    by rule.”), 6072(10)(B) (requiring the Department to provide notice of the
    granting of a lease to riparian owners, intervenors, and the municipality in
    which the lease was granted). In the same manner, the Legislature has required
    the Bureau to provide notice, receive comment, and hold hearings in other
    public lands contexts. See, e.g., id. §§ 1814-A (easements across rail tracks),
    1837(2) (sale of nonreserved public lands).
    [¶56] Although there are such requirements now, at the time of these
    leases there was no similar set of requirements for the Bureau’s granting of
    leases for public reserved lands.14 See Me. Const. art. IX, § 23; 12 M.R.S. §§ 598
    14During the spring of 2022, the Maine Legislature passed L.D. 1075, An Act to Protect Public
    Lands, which requires the Bureau to adopt rules for determining whether a proposed activity will
    reduce or substantially alter the use of designated lands under the Bureau’s jurisdiction, but the law
    was not in effect at the time of the execution of the 2020 lease. See P.L. 2021, ch. 654 (effective Aug. 8,
    2022); L.D. 1075 (130th Legis. 2022); Comm. Amend. A to L.D. 1075, No. S-493 (130th Legis. 2022).
    This new law enacted 12 M.R.S. § 598-C, which provides, in full:
    §598-C. Process for determination of reduction or substantially altered use of
    designated land
    The Department of Agriculture, Conservation and Forestry, Bureau of Parks
    and Lands shall adopt rules to establish an objective evaluation process for
    determining if a proposed activity on land designated under this chapter and under
    the jurisdiction of the bureau would cause the land to be reduced or the uses of the
    land to be substantially altered. In adopting the rules, the bureau shall observe the
    requirements relating to designated lands in the Constitution of Maine, Article IX,
    Section 23 and ensure proper exercise of the bureau’s public trust responsibility.
    These rules must also include provisions for public notice and comment before
    authorizing any such activity and for determining the appropriate instrument to be
    used to authorize that activity, including but not limited to whether an easement,
    lease, license or other instrument should be used. Rules adopted pursuant to this
    section are major substantive rules as defined in Title 5, chapter 375, subchapter 2-A.
    41
    to 598–B (2022); 12 M.R.S. § 1852(4) (2021); cf. 12 M.R.S. §§ 1814–A(1), (4),
    1837(2), 1847(2), 1851(3), (4) (2022).
    [¶57] More fundamentally, a government agency’s execution of a lease
    of government property, including land, is neither adjudicatory nor otherwise
    subject to a formal administrative process unless the legislative delegation of
    leasing authority to an agency requires otherwise, as in the case of aquaculture
    leases. See, e.g., Ala. Aircraft Indus. v. United States, 
    82 Fed. Cl. 757
    , 773 n.14
    (2008) (“Decisions by contracting officers are not adjudicatory decisions to be
    made on the record after a hearing.         Nor are they formal rulemakings.”
    (quotation marks omitted)); Sierra Club v. Comm’r of the Dep’t of Envtl. Mgmt.,
    
    791 N.E.2d 325
    , 332-33 (Mass. 2003) (agency’s approval of lease modification
    was an exercise of legislatively delegated authority, not an adjudication); Flores
    v. Bd. of Land & Nat. Res., 
    424 P.3d 469
    , 479-483 (Haw. 2018) (agency not
    required to hold hearing on whether to consent to a sublease); see also Haverhill
    Manor, Inc. v. Comm’r of Pub. Welfare, 
    330 N.E.2d 180
    , 190 (1975) (“The APA
    provisions applicable to adjudicatory proceedings are . . . inapposite, since in
    the instant circumstances a hearing is not required by constitutional right or by
    any provision of the General Laws.” (citations and quotation marks omitted)).
    42
    [¶58] At the time the 2020 lease was granted, there was nothing
    requiring the Bureau to promulgate rules for granting leases of public reserved
    lands. When the Bureau granted the lease, it was authorized to grant leases of
    public reserved land for transmission lines on any terms it deemed reasonable,
    so long as the leases did not reduce or substantially alter public reserved lands.
    [¶59] Our conclusion that the Bureau was not required to issue findings
    or conduct any other “public administrative process” when it granted the
    2020 lease does not preclude review of the leasing decision pursuant to
    Rule 80C and the Maine Administrative Procedure Act. The agency decisions
    reviewable under the Maine Administrative Procedure Act are not limited to
    the adjudicatory proceedings and decisions for which hearings and findings are
    required. See Davric Me. Corp. v. Me. Harness Racing Comm’n, 
    1999 ME 99
    , ¶ 11,
    
    732 A.2d 289
     (Rule 80C review of state harness racing commission’s
    nonadjudicatory decision to certify election results). The Federal Circuit has
    observed that “the [federal] Administrative Procedure Act does not itself
    require an agency to explain the basis for its decision, unless an adjudication
    required to be made on the record or a formal rulemaking is involved. . . . [but]
    even if the agency is not obligated to provide reasons, a court may nonetheless
    order the agency to provide explanation if such an explanation is required for
    43
    meaningful judicial review.” Impresa Construzioni Geom. Domenico Garufi v.
    United States, 
    238 F.3d 1324
    , 1337-38 (Fed. Cir. 2001); see also Citizens to Pres.
    Overton Park, Inc. v. Volpe, 
    401 U.S. 402
    , 417 (1971) (“[T]he Administrative
    Procedure Act requirements that there be formal findings in certain rulemaking
    and adjudicatory proceedings do not apply to the Secretary’s action here.”)
    [¶60] We conclude that, under the law in effect in 2014 and 2020, the
    Bureau was legislatively authorized to grant leases of utility transmission lines
    on public reserved lands that would not reduce or substantially alter the lands,
    without giving public notice, conducting hearings, adopting findings of fact and
    conclusions of law, or engaging in any of the other attributes of a public
    administrative process.
    [¶61] This delineation of the Bureau’s leasing authority establishes, in
    turn, that the scope of judicial review of the grant of the 2020 lease is limited.
    No formal process was required in connection with the grant of the 2020 lease,
    and we do not review for compliance with nonexistent procedural
    requirements. Instead, our review is limited to deciding whether the Bureau’s
    grant of the 2020 lease was ultra vires because the lease would result in a
    substantial alteration of public reserved land and therefore had to be approved
    by the Legislature. We now turn to that question.
    44
    F.    The Validity of the 2020 Lease in Light of the Bureau’s Leasing
    Authority
    [¶62] Although Black’s brief frames one of the issues as whether the
    leases reduce or substantially alter public reserved lands, the brief does not
    develop any argument that the leases reduce any public reserved lands, and in
    fact notes that “[t]he Bureau concedes that neither a lease nor an easement
    conveys any land and therefore the acreage in both cases remains the same, as
    it must.” See 12 M.R.S. § 598(4) (“‘Reduced’ means a reduction in the acreage
    of an individual parcel or lot of designated land . . . .”). Black’s ultra vires claim
    argues only that the leases “substantially alter,” and not that they reduce, public
    reserved lands.
    [¶63] A threshold question is whether the current record is sufficient to
    enable us to resolve Black’s ultra vires claim. The Bureau’s and CMP’s briefs
    ask us to vacate the judgment and remand for entry of a judgment affirming the
    Bureau’s decision to grant the 2020 lease, and CMP proposes several
    alternatives to that outcome. Black’s brief asks us to affirm the Superior Court’s
    decision vacating the 2020 lease, and alternatively seeks a remand for the trial
    45
    court “to take evidence”15 and decide the constitutional question of the
    Bureau’s authority.
    [¶64] It is important to note that in assessing whether the Bureau’s
    granting of the 2020 lease was ultra vires, we are applying the law as it existed
    at the time the 2020 lease was granted. See 12 M.R.S. § 1852(4) (2021). The
    Initiative and resulting legislation effectively takes away for all future contracts
    and leases the Bureau’s authority to make a determination regarding whether
    a lease would cause a “substantial alteration,” stating that “[a]ny
    . . . transmission lines . . . are deemed to substantially alter the uses of the
    [public] land . . . and a lease or conveyance for the purpose of constructing and
    operating such . . . transmission lines . . . may not be granted without first
    obtaining the vote of 2/3 of all the members elected to each House of the
    Legislature.” I.B. 2021, ch. 1, § 1. We held above that applying the provisions
    of the Initiative to the 2020 lease would substantially impair it and therefore be
    in violation of the Contract Clause. See supra ¶ 47. Accordingly, we apply the
    facts contained in the record to the law in effect prior to the 2020 lease to
    15  Black does not specify what evidence he would proffer on remand. Elsewhere, his brief asserts
    that “never in any proceeding at any level were Plaintiffs allowed to submit evidence, other than
    through existing public documents,” but the docket in this case does not indicate that Black ever filed
    any motion for the taking of additional evidence pursuant to M.R. Civ. P. 80C(e).
    46
    determine whether the 2020 lease results in a substantial alteration of the use
    of the public lands in question. We turn now to that analysis.
    [¶65] As we discussed above, there are two issues that must be resolved
    when making a determination regarding whether a lease would cause a
    “substantial alteration”: (1) whether a change in use significantly alters the
    physical characteristics of the land and, if so, (2) whether that alteration
    frustrates the essential purposes for which the land is held. See 12 M.R.S.
    § 598(5).
    [¶66]   The relevant facts in the administrative record are free of
    ambiguity or dispute. The two tracts of public reserved lands in question—
    Johnson Mountain and West Forks Plantation—occupy a combined area of
    1,241 acres in the Upper Kennebec Region.                    A.R. II0014, II0093; A.R.
    IV0029-38.16 Their physical characteristics include water bodies, wetlands,
    and primarily standing timber. A.R. II0093, II0223-24. There are no unique
    features or protected areas on either tract. A.R. II0015, II0018-19, II0095,
    II0219. Their predominant use has been for timber harvesting every twenty
    years, but there are also recreational facilities and an existing 100-foot-wide,
    16The A.R. citations throughout this section refer to the Administrative Record filed in
    conjunction with this case, which spans seven volumes and hundreds of pages.
    47
    three-mile-long utility transmission line on the tracts. A.R. II0093, II0235-38.
    The essential purposes of the tracts are to support the multiple uses currently
    being made of them consistent with the Bureau’s management plans.
    [¶67] Before agreeing to grant the 2014 lease, the Bureau considered
    locating CMP’s transmission line within the clearing that contains the existing
    line on the tracts, but decided against it because of the adverse environmental
    impacts that it would cause. A.R. III0033. The Bureau also performed field
    work and persuaded CMP to avoid stream crossings and reduce the total area
    covered by the lease. A.R. III0181-82, III0208-10, III0233-38. As granted, the
    2020 lease concerns 32.39 acres, or 2.6% of the combined area of the public
    reserved lands and would accommodate a 0.9-mile-long section of the Project.
    A.R. I0001, I0013; A.R. II0093. Accordingly, the section of the Project on the
    tracts would be wider, but shorter, than the existing transmission line corridor.
    The 2020 lease includes provisions limiting road construction and protecting
    forest resources and vernal pools. A.R. I0004-06.
    [¶68] Construction of a transmission line as permitted by the 2020 lease
    will necessarily result in the significant alteration of the 32.39 acres that it
    actually encompasses, but that alone is not the test. The clause “significantly
    alter[s] physical characteristics in a way that frustrates the essential purposes
    48
    for which that land is held” means that the proposed activity will have that
    major effect either because it will occupy such a large portion of the public
    reserved land or because it will change the physical characteristics of the public
    reserved land well beyond the area that it occupies. Given the uses, physical
    characteristics, and essential purposes of the Johnson Mountain and West
    Forks Plantation tracts, we see no reasonable basis for deciding that a second
    utility transmission line occupying 2.6% of the combined tracts could
    significantly alter the physical characteristics of so much of the remaining
    97.4% that the multiple-use purposes for which the tracts are held would be
    frustrated.
    [¶69] In a Rule 80C appeal we review the agency’s actions directly,
    without deference to the trial court’s decision, and compare them against the
    record evidence to determine whether the agency’s actions were in excess of
    their statutory authority and therefore ultra vires. See Anderson, 
    2009 ME 134
    ,
    ¶ 2, 
    985 A.2d 501
    ; Sold, 
    2005 ME 24
    , ¶ 12, 
    868 A.2d 172
    . Because we conclude
    that the evidence contained in the record is sufficient, we see no reason to
    impose a further burden on the parties’ time and resources by remanding for
    the Bureau to take further evidence. We conclude that the record establishes
    49
    that the Bureau acted within its constitutional and statutory authority in
    granting the 2020 lease.
    The entry is:
    Judgment vacated. Remanded for entry of a
    judgment, consistent with this opinion, for the
    Bureau of Parks and Lands, NECEC Transmission
    LLC, and Central Maine Power Co. on all counts
    of the first amended complaint.
    Aaron M. Frey, Attorney General, Lauren E. Parker, Asst. Atty. Gen. (orally),
    Scott W. Boak, Asst. Atty Gen., and Laura E. Jensen, Asst. Atty. Gen., Office of the
    Attorney General, Augusta, for appellant Bureau of Parks and Lands
    Nolan L. Reichl, Esq. (orally), Jared S. des Rosiers, Esq., and Kyle M. Noonan,
    Esq., Pierce Atwood LLP, Portland, for appellants and cross-appellees Central
    Maine Power Company and NECEC Transmission LLC
    James T. Kilbreth, Esq. (orally), David M. Kallin, Esq., Jeana M. McCormick, Esq.,
    and Sara P. Cressey, Esq., Drummond Woodsum, Portland, for appellees and
    cross-appellants Russell Black, Richard A. Bennett, Thomas B. Saviello, Kent
    Ackley, Seth Berry, Chad Grignon, Denise Harlow, Margaret O’Neil, William
    Pluecker, Edwin Buzzell, Greg Caruso, Charlene Cummings, Robert Haynes
    o/b/o Old Canada Road National Scenic Byway, Cathy Johnson, Ron Joseph,
    John R. Nicholas Jr., George A. Smith, Clifford Stevens, Todd Towle, and the
    Natural Resources Council of Maine
    Timothy C. Woodcock, Esq., and Jonathan A. Pottle, Esq., Eaton Peabody,
    Bangor, for amicus curiae Maine Forest Products Council
    Orlando E. Delogu, amicus curiae pro se
    50
    P. Andrew Hamilton, Esq., and Casey M. Olesen, Esq., Eaton Peabody, Bangor,
    for amicus curiae H.Q. Energy Services (U.S.) Inc.
    Sigmund D. Schutz, Esq., Anthony W. Buxton, Esq., and Jonathan Mermin, Esq.,
    Preti Flaherty Beliveau & Pachios LLP, Portland, for amicus curiae Joshua
    Reynolds
    James G. Monteleone, Esq., Bernstein Shur, Portland, for amici curiae Troy
    Jackson, Ben Chipman, Eloise Vitelli, Craig Hickman, Chloe Maxmin, Scott
    Cyrway, Paul Davis, Patrick Corey, and Jennifer Poirier
    Business and Consumer Docket docket number CV-2020-29
    FOR CLERK REFERENCE ONLY
    

Document Info

Citation Numbers: 2022 ME 58

Filed Date: 11/29/2022

Precedential Status: Precedential

Modified Date: 11/29/2022

Authorities (20)

Impresa Construzioni Geom. Domenico Garufi v. United States , 238 F.3d 1324 ( 2001 )

Haverhill Manor, Inc. v. Commissioner of Public Welfare , 368 Mass. 15 ( 1975 )

Maine Senate v. Secretary of State , 183 A.3d 749 ( 2018 )

Citizens to Preserve Overton Park, Inc. v. Volpe , 91 S. Ct. 814 ( 1971 )

Anderson v. Maine Public Employees Retirement System , 2009 Me. LEXIS 136 ( 2009 )

Friends of the Earth, Inc. v. Laidlaw Environmental ... , 120 S. Ct. 693 ( 2000 )

United States Trust Co. of NY v. New Jersey , 97 S. Ct. 1505 ( 1977 )

NECEC Transmission LLC v. Bureau of Parks and Lands , 2022 ME 48 ( 2022 )

MacImage of Maine, LLC v. Androscoggin County , 2012 Me. LEXIS 42 ( 2012 )

State of Maine v. Wai Chan , 2020 ME 91 ( 2020 )

Alabama Aircraft Industries, Inc. v. United States , 82 Fed. Cl. 757 ( 2008 )

James Blanchard v. Town of Bar Harbor , 2019 ME 168 ( 2019 )

Roop v. City of Belfast , 2007 Me. LEXIS 31 ( 2007 )

Mainers for Fair Bear Hunting v. Department of Inland ... , 2016 Me. LEXIS 57 ( 2016 )

Fair Elections Portland, Inc. v. City of Portland , 2021 ME 32 ( 2021 )

State v. L.V.I. Group , 1997 Me. LEXIS 26 ( 1997 )

Davric Maine Corp. v. Maine Harness Racing Commission , 1999 Me. LEXIS 117 ( 1999 )

Kittery Retail Ventures, LLC v. Town of Kittery , 2004 Me. LEXIS 67 ( 2004 )

Medical Mutual Insurance v. Bureau of Insurance , 2005 Me. LEXIS 14 ( 2005 )

Sold, Inc. v. Town of Gorham , 2005 Me. LEXIS 23 ( 2005 )

View All Authorities »