Frederick Olson v. Town of Yarmouth , 2018 ME 27 ( 2018 )


Menu:
  • MAINE	SUPREME	JUDICIAL	COURT	                                       Reporter	of	Decisions
    Decision:	 
    2018 ME 27
    Docket:	   Cum-17-274
    Argued:	   December	13,	2017
    Decided:	  February	22,	2018
    Panel:	    SAUFLEY,	C.J.,	and	ALEXANDER,	MEAD,	GORMAN,	JABAR,	HJELM,	and	HUMPHREY,	JJ.
    FREDERICK	OLSON	et	al.
    v.
    TOWN	OF	YARMOUTH	et	al.
    HUMPHREY,	J.
    [¶1]	 	 Frederick	 Olson	 and	 Leora	 Rabin	 appeal	 from	 a	 judgment	 of	 the
    Superior	 Court	 (Cumberland	 County,	 Warren,	 J.)	 affirming,	 pursuant	 to	 M.R.
    Civ.	P.	 80B,	 the	 Town	 of	 Yarmouth	 Planning	 Board’s	 approval	 of	 a	 site	 plan
    application	by	Portland	Cellular	Partnership,	d/b/a	Verizon	Wireless	(Verizon),
    to	install	wireless	communication	equipment	on	a	tower	and	site	owned	by	the
    Yarmouth	Water	District.		Olson	and	Rabin	argue	that	Verizon’s	application	did
    not	 comply	 with	 Yarmouth’s	 Zoning	 Ordinance	 because	 (1)	 the	 Yarmouth
    Water	District	site	was	subject	to	a	presumption	of	unsuitability	that	Verizon
    failed	to	overcome,	and	(2)	Verizon	did	not	present	sufficient	evidence	that	it
    investigated	other	technically	feasible	sites.		Because	the	Board	did	not	err	by
    2
    concluding	that	Verizon’s	application	complied	with	the	relevant	provisions	of
    the	Zoning	Ordinance,	we	affirm	the	judgment.
    I.		BACKGROUND
    [¶2]	 	 In	 2001,	 Sprint	 Spectrum	 L.P.	 (Sprint)	 submitted	 a	 site	 plan
    application	to	the	 Town	of	Yarmouth	in	which	it	applied	to	install	a	wireless
    communication	antenna	array	on	a	water	tower	owned	by	the	Yarmouth	Water
    District	and	to	install	equipment	cabinets	on	the	ground	near	the	tower.		The
    Planning	Board	denied	the	application	because	it	did	not	meet	zoning	and	site
    plan	ordinance	standards.		In	April	2016,	Verizon	applied	to	the	Planning	Board
    for	a	similar	use	at	the	same	site.
    [¶3]		At	a	public	meeting	on	May	25,	2016,	the	Planning	Board	reviewed
    Verizon’s	plan.		The	Planning	Board	and	neighboring	residents,	including	Olson
    and	Rabin,	questioned	the	location	of	the	equipment	enclosure	and	the	related
    visual,	noise,	and	health	effects	on	the	neighborhood.		Olson’s	property	abuts
    the	Yarmouth	Water	District	site,	and	Rabin	resides	within	500	feet	of	the	site.
    Verizon	represented	that	it	would	examine	other	sites	and	look	at	the	gaps	in
    3
    coverage	that	led	to	the	selection	of	this	location.		The	Planning	Board	did	a	site
    walk	on	June	15,	2016.
    [¶4]		On	July	20,	2016,	Verizon	submitted	its	final	site	plan	application	to
    install	equipment	on	the	Yarmouth	Water	District	site.		Verizon	asserted	in	its
    application	that,	by	installing	the	equipment	on	the	Yarmouth	 Water	 District
    site,	 Verizon	 would	 “be	 able	 to	 fill	 the	 substantial	 coverage	 gap	 that	 it	 now
    experiences,	 and	 provide	 improved	 coverage	 and	 capacity	 to	 residents,
    businesses,	and	traffic	corridors	within	sections	of	Yarmouth	that	are	currently
    located	within	deficient	service	areas	of	Verizon	Wireless’[s]	network.”
    [¶5]	 	 The	 Town	 of	 Yarmouth	 Director	 of	 Planning	 and	 Development
    (Director)	submitted	a	report	to	the	Planning	Board	on	September	 23,	2016.
    The	Director	detailed	how	Verizon’s	application	complied	with	individual	site
    plan	 and	 zoning	 standards	 and	 concluded	 that	 the	 project	 conformed	 to	 the
    Town’s	 comprehensive	 plan	 and	 submission	 requirements.	 	 As	 to	 the
    Ordinance’s	 requirement	 that	 Verizon	 investigate	 other	 technically	 feasible
    sites,	he	concluded	that	Verizon	had	“described	[its]	site	selection	process,”	and
    the	 Yarmouth	 Water	 District	 site	 allows	 “the	 antenna	 to	 be	 located	 on	 an
    existing	 water	 tower	 which	 avoids	 the	 need	 to	 construct	 a	 new	 tower.”	 	 The
    4
    Director	 recommended	 that	 the	 Planning	 Board	 approve	 the	 application	 if
    Verizon	accepted	the	conditions	that	he	proposed	in	his	report.
    [¶6]		The	Director’s	report	included	the	2001	letter	denying	Sprint’s	site
    plan	application	and	the	Planning	Board’s	findings	on	Sprint’s	application.		The
    2001	Planning	Board	report	stated	that	“[t]he	size	and	configuration	of	the	lot
    on	which	the	water	tower	is	located	and	upon	which	equipment	is	located	is	too
    small	 in	 area	 and	 too	 narrow	 in	 width	 and	 therefore	 too	 constrained	 for
    ‘adverse	impacts’	of	the	proposed	equipment	installation	on	the	ground	to	be
    adequately	minimized,	per	[Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(1)],	in
    the	residential	context	and	close	proximity	to	adjacent	and	nearby	residences
    involved.”1
    [¶7]		On	September	28,	2016,	the	Planning	Board	considered	Verizon’s
    final	site	plan	application	at	a	public	meeting.		The	Planning	Board	asked	about
    alternative	 sites	 that	 Verizon	 had	 considered,	 and	 a	 Verizon	 representative
    explained	that	it	looked	at	the	gaps	in	its	area	of	coverage	and	then	looked	for
    sites	that	could	fill	the	gaps	with	a	minimal	impact	on	the	Town.		The	Verizon
    1		The	2001	Planning	Board’s	written	findings	included	a	section	entitled	“Presumption	of	inability
    to	 accommodate	 similar	 equipment”	 that	 was	 stricken	 by	 hand.	 	 Because	 the	 record	 is	 devoid	 of
    evidence	 concerning	 the	 rationale	 for	 removing	 this	 language	 and	 we	 review	 the	 Ordinance’s
    provision	creating	a	presumption	of	unsuitability	de	novo,	see	Osprey	Family	Tr.	v.	Town	of	Owls	Head,
    
    2016 ME 89
    ,	¶	9,	
    141 A.3d 1114
    ,	we	accord	no	weight	to	this	section	of	the	Planning	Board’s	findings.
    5
    representative	 told	 the	 Planning	 Board	 that	 Verizon’s	 “[g]oal	 at	 this	 site	 has
    been	to	.	.	.	comply	with	the	primary	goal	of	the	Town’s	wireless	ordinance,	and
    that	is	to	avoid	the	need	for	new	towers.”		Verizon’s	search	revealed	that	the
    Yarmouth	Water	District	site	was	the	only	appropriate	location	because	other
    buildings	 in	 the	 area	 were	 not	 tall	 enough	 and	 a	 Central	 Maine	 Power	 pole
    would	not	fill	the	coverage	gap	and	posed	administrative	hurdles.		The	Planning
    Board	 unanimously	 gave	 conditional	 approval	 to	 Verizon’s	 application	 after
    finding	 that	 the	 plan	 conformed	 to	 the	 Site	 Plan	 Review	 Ordinance.	 	 The
    Planning	Board	issued	a	written	approval	letter	on	October	7,	2016.
    [¶8]	 	 On	 November	 8,	 2016,	 Olson	 and	 Rabin,	 who	 both	 appeared	 and
    commented	at	the	Planning	Board	meetings,	filed	a	complaint	and	petition	for
    review	 of	 final	 municipal	 action	 pursuant	 to	 M.R.	 Civ.	 P.	 80B	 in	 the	 Superior
    Court.2	 	 Verizon	 intervened	 in	 the	 action.	 	 The	 court	 affirmed	 the	 Planning
    Board’s	decision	on	June	1,	2017.
    [¶9]		Olson	and	Rabin	filed	a	timely	appeal.		See	M.R.	Civ.	P.	80B(n);	M.R.
    App.	P.	2(b)(3)	(Tower	2016).3
    2	 	 Pursuant	 to	 Yarmouth,	 Me.,	 Site	 Plan	 Review	 Ordinance,	 art.	 I(F)(3)	 (June	 2017),	 site	 plan
    decisions	of	the	Planning	Board	are	appealed	to	the	Superior	Court	in	Cumberland	County.
    3		This	appeal	was	commenced	before	September	1,	2017,	and	therefore	the	restyled	Maine	Rules
    of	Appellate	Procedure	do	not	apply.		See	M.R.	App.	P.	1.
    6
    II.		DISCUSSION
    [¶10]		Olson	and	Rabin	raise	two	issues	on	appeal.		First,	they	argue	that
    the	 Planning	 Board	 erred	 in	 its	 approval	 of	 Verizon’s	 site	 plan	 application
    because,	pursuant	to	article	II(Z)(4)(a)(3)	(Sept.	2016)	of	the	Yarmouth	Zoning
    Ordinance,	 the	 Yarmouth	 Water	 District	 site	 was	 presumed	 to	 be	 unsuitable
    and	Verizon	failed	to	overcome	that	presumption.		Second,	they	contend	that
    there	was	not	substantial	evidence	in	the	record	to	support	the	Board’s	finding
    that	 Verizon	 investigated	 other	 technically	 feasible	 sites,	 as	 required	 by
    Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(9)(c)	(Sept.	2016).
    [¶11]	 	 “We	 review	 the	 Planning	 Board’s	 approval	 of	 the	 [site	 plan
    application]	 directly	 for	 error	 of	 law,	 abuse	 of	 discretion	 or	 findings	 not
    supported	by	substantial	evidence	in	the	record.”		Osprey	Family	Tr.	v.	Town	of
    Owls	 Head,	 
    2016 ME 89
    ,	 ¶	 9,	 
    141 A.3d 1114
     (quotation	 marks	 omitted).
    “Substantial	 evidence	 exists	 when	 a	 reasonable	 mind	 would	 rely	 on	 that
    evidence	as	sufficient	support	for	a	conclusion.”		
    Id. (quotation marks
    omitted).
    “Although	 interpretation	 of	 an	 ordinance	 is	 a	 question	 of	 law,	 we	 accord
    substantial	 deference	 to	 the	 Planning	 Board’s	 characterizations	 and
    fact-findings	as	to	what	meets	ordinance	standards.”		Bizier	v.	Town	of	Turner,
    
    2011 ME 116
    ,	¶	8,	
    32 A.3d 1048
    (quotation	marks	omitted).		When	interpreting
    7
    an	 ordinance	 de	 novo,	 “we	 first	 evaluate	 the	 plain	 meaning	 of	 the	 Ordinance
    and,	if	the	meaning	is	clear,	[we]	need	not	look	beyond	the	words	themselves.
    We	 construe	 the	 terms	 of	 an	 ordinance	 reasonably,	 considering	 its	 purposes
    and	structure	and	to	avoid	absurd	or	illogical	results.”		Fryeburg	Tr.	v.	Town	of
    Fryeburg,	
    2016 ME 174
    ,	¶	5,	
    151 A.3d 933
    (citation	omitted)	(quotation	marks
    omitted).		Olson	and	Rabin	bear	the	burden	of	persuasion	on	appeal	because
    they	seek	to	vacate	the	Planning	Board’s	decision.		See	Bizier,	
    2011 ME 116
    ,	¶	8,
    
    32 A.3d 1048
    .
    A.	   Application	of	the	Presumption	of	Unsuitability
    [¶12]	 	 We	 first	 consider	 Olson	 and	 Rabin’s	 argument	 that,	 pursuant	 to
    article	 II(Z)(4)(a)(3)	 of	 the	 Ordinance,	 the	 Planning	 Board’s	 2001	 denial	 of
    Sprint’s	 application	 to	 install	 a	 wireless	 communication	 antenna	 array	 and
    associated	equipment	cabinets	on	the	Yarmouth	Water	District	site	created	a
    rebuttable	presumption	that	the	site	was	unsuitable	to	accommodate	Verizon’s
    proposal.
    [¶13]		Article	II(Z)(4)(a)(3)	states:
    Once	 the	 Planning	 Board	 has	 determined	 that
    telecommunications	equipment	proposed	by	the	applicant	cannot
    be	accommodated	on	an	existing	or	approved	tower	or	Alternative
    Tower	 Structure,	 each	 tower	 or	 Alternative	 Tower	 Structure	 so
    found	is	presumed	unable	to	accommodate	similar	equipment	that
    may	be	proposed	in	the	future	unless	the	Board	determines,	after
    8
    additional	 information	 is	 provided,	 that	 new	 technology	 or	 other
    considerations	 enables	 the	 existing	 or	 approved	 tower	 or
    Alternative	Tower	Structure	to	accommodate	the	equipment.
    Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(4)(a)(3).
    [¶14]	 	 Olson	 and	 Rabin	 argue	 that	 Yarmouth,	 Me.,	 Zoning	 Ordinance,
    art.	II(Z)(4)	 (Sept.	 2016)4	 broadly	 addresses	 co-location	 requirements	 and	 is
    4		Article	II(Z)(4)	provides:
    4.		Co-location	requirements
    a.	 On	existing	towers:
    (1)	 Applicants	for	site	plan	review	for	a	new	wireless	communication	tower
    must	send	written	notice	by	pre-paid	first	class	United	States	mail	to	all
    other	such	tower	and	Alternative	Tower	Structure	owners	and	licensed
    wireless	communication	providers	in	the	Town	utilizing	exi[s]ting	towers
    and	 Alternative	 Tower	 Structures	 and	 to	 owners	 of	 such	 towers	 and
    Alternative	 Tower	 Structures	 within	 a	 1	 mile	 search	 radius	 of	 the
    proposed	tower,	stating	their	siting	needs	and/or	colocation	capabilities.
    Evidence	 that	 this	 notice	 requirement	 has	 been	 fulfilled	 shall	 be
    submitted	 to	 the	 Planning	 Board	and	shall	include	a	 name	 and	 address
    list,	copy	of	the	notice	which	was	sent,	and	a	statement,	under	oath,	that
    the	notices	were	sent	as	required.	An	application	for	a	new	tower	must
    include	 evidence	 that	 existing	 or	 previously	 approved	 towers	 and
    Alternative	 Tower	 Structures	 within	 the	 Town	 and	 search	 area	 cannot
    accommodate	 the	 communications	 equipment	 (antennas,	 cables,	 etc.)
    planned	for	the	proposed	tower.	Such	evidence	would	be	documentation
    from	a	qualified	and	licensed	professional	engineer	that:
    (a.) Planned	necessary	equipment	would	exceed	the	structural	capacity
    of	existing	and	approved	towers	and	Alternative	Tower	Structures,
    considering	 the	 existing	 and	 planned	 use	 of	 those	 towers	 and
    Alternative	Tower	Structures,	and	the	existing	and	approved	towers
    cannot	 be	 reinforced	 to	 accommodate	 planned	 or	 equivalent
    equipment	at	a	reasonable	cost;
    (b.) Planned	 equipment	 will	 cause	 electromagnetic	 frequency
    interference	 with	 other	 existing	 or	 planned	 equipment	 for	 that
    tower	or	Alternative	Tower	Structure,	and	the	interference	cannot
    be	prevented	at	a	reasonable	cost;
    9
    not	limited	to	applicants	seeking	to	construct	a	new	tower.		They	contend	that
    although	 article	 II(Z)(4)(a)(1)	 applies	 only	 to	 new-tower-construction
    applicants,	 article	 II(Z)(4)(a)(3)	 applies	 both	 to	 new-tower-construction
    (c.)   Existing	or	approved	towers	and	Alternative	Tower	Structures	do
    not	have	space	on	which	planned	equipment	can	be	placed	so	it	can
    function	 effectively	 and	 at	 least	 in	 parity	 with	 other	 similar
    equipment	in	place	or	approved;	or
    (d.) Other	 documented	 reasons	 that	 make	 it	 technically	 or	 financially
    unfeasible	 to	 place	 the	 equipment	 planned	 by	 the	 applicant	 on
    existing	and	approved	towers	and	Alternative	Tower	Structures.
    (2)	 Shared	 use	 shall	 be	 conditioned	 on	 the	 applicant’s	 agreement	 to	 pay	 a
    reasonable	fee	and	costs	of	adapting	existing	facilities	to	the	proposed	use.
    (3)	 Once	 the	 Planning	 Board	 has	 determined	 that	 telecommunications
    equipment	 proposed	 by	 the	 applicant	 cannot	 be	 accommodated	 on	 an
    existing	or	approved	tower	or	Alternative	Tower	Structure,	each	tower	or
    Alternative	 Tower	 Structure	 so	 found	 is	 presumed	 unable	 to
    accommodate	 similar	 equipment	 that	 may	 be	 proposed	 in	 the	 future
    unless	 the	 Board	 determines,	 after	 additional	 information	 is	 provided,
    that	 new	 technology	 or	 other	 considerations	 enables	 the	 existing	 or
    approved	 tower	 or	 Alternative	 Tower	 Structure	 to	 accommodate	 the
    equipment.
    (4)	 The	 Planning	 Department	 will	 maintain	 a	 list	 of	 existing	 and	 approved
    towers	and	Alternative	Tower	Structures,	including	name	and	address	of
    owner(s),	within	the	Town	of	Yarmouth.
    b.	 Construction	of	new	towers
    A	proposal	to	construct	a	new	co-located	communication	tower	taller	than	the
    maximum	height	permitted	for	a	single	wireless	communication	service	must
    include	evidence	that	the	tower	can	structurally	support	a	minimum	of	three
    (3)	antenna	arrays	for	each	anticipated	co-locating	entity.	(See	Section	II.Z.3.a
    Tower	Height,	above.)
    Prior	to	the	issuance	of	any	Building	permits	for	a	co-located	tower	in	excess	of
    the	 height	 of	 a	 single	 user	 tower,	 the	 applicant	 will	 submit	 to	 the	 Code
    Enforcement	 Officer	 executed	 agreements	 documenting	 commitments	 to
    co-locate	from	the	number	of	co-locators	approved	by	the	Planning	Board.
    Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(4)	(Sept.	2016).
    10
    applicants	and	to	co-location	applicants	seeking	to	install	similar	equipment	on
    an	existing	structure.		Based	on	this	reading	of	the	Ordinance,	Olson	and	Rabin
    assert	 that	 the	 presumption	 of	 unsuitability	 attaches	 to	 a	 site	 whenever	 the
    Planning	Board	has	determined	that	the	site	is	unsuitable	for	co-location.		Olson
    and	 Rabin	 contend	 that	 the	 Planning	 Board’s	 2001	 determination	 that	 the
    Yarmouth	Water	District	site	was	“too	small	in	area	and	too	narrow	in	width”
    to	accommodate	Sprint’s	proposal	made	the	site	presumptively	unsuitable	for
    any	later	application	to	install	similar	equipment	at	that	site,	and	that	Verizon
    needed	to	rebut	that	presumption	before	its	application	could	be	approved.
    [¶15]	 	 The	 question	 to	 be	 answered	 is	 whether	 the	 presumption	 of
    unsuitability	 attaches	 to	 a	 co-location	 site	 only	 when	 an	 applicant	 initially
    proposes	 to	 construct	 a	 new	 tower,	 or	 whether	 it	 also	 attaches	 when	 the
    applicant’s	initial	proposal	is	to	co-locate	by	installing	equipment	on	that	site.
    If	the	latter,	a	rebuttable	presumption	of	unsuitability	attached	to	the	Yarmouth
    Water	District	site	after	the	Planning	Board	denied	Sprint’s	application	in	2001.
    [¶16]	 	 As	 is	 the	 case	 with	 statutes,	 our	 single	 goal	 in	 interpreting	 an
    ordinance	is	to	give	effect	to	the	Town’s	intent	in	enacting	the	ordinance.		See
    Dickau	v.	Vt.	Mut.	Ins.	Co.,	
    2014 ME 158
    ,	¶	19,	
    107 A.3d 621
    .		We	first	determine
    if	 the	 language	 of	 the	 ordinance	 is	 plain	 and	 unambiguous.	 	 See	 
    id. Our 11
    interpretation	 of	 the	 plain	 language	 is	 guided	 by	 “taking	 into	 account	 the
    subject	matter	and	purposes	of	the	statute,	and	the	consequences	of	a	particular
    interpretation.”	 	 
    Id. ¶ 21.
     	 We	 must	 construe	 the	 terms	 of	 article	 II(Z)(4)
    reasonably,	 by	 considering	 the	 purposes	 and	 structure	 of	 the	 Ordinance	 to
    avoid	absurd	or	illogical	results.		See	Fryeburg	Tr.,	
    2016 ME 174
    ,	¶	5,	
    151 A.3d 933
    .		After	examining	the	entirety	of	the	Ordinance,	we	conclude	that	the	plain
    and	 unambiguous	 language	of	the	Ordinance	 makes	 clear	 that	 article	 II(Z)(4)
    applies	only	to	new-tower-construction	applicants.
    [¶17]		At	the	outset,	article	II(Z)	announces	that	one	of	the	purposes	of
    the	Ordinance	is	to	encourage	co-location	and	“[p]ermit	the	construction	of	new
    towers	 only	 where	 all	 other	 reasonable	 opportunities	 have	 been	 exhausted.”
    See	Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(1).		Accordingly,	article	II(Z)(4)
    describes	 the	 process	 that	 new-tower-construction	 applicants	 must	 use	 to
    exhaust	 their	 opportunities	 for	 co-location	 before	 they	 can	 obtain	 Planning
    Board	approval	of	their	new-tower-construction	application.
    [¶18]		No	language	in	article	II(Z)(4)	states	that	the	provisions	apply	to
    co-location	 applicants.	 	 Instead,	 article	 II(Z)(4)(a)(1)	 expressly	 requires
    new-tower-construction	 applicants	 to	 undertake	 a	 search	 for	 existing	 and
    previously	 approved	 co-location	 sites	 that	 can	 accommodate	 the	 applicant’s
    12
    proposed	communications	equipment;	article	II(Z)(4)(a)(2)	requires	payment
    of	 fees	 if	 a	 co-location	 site	 is	 found	 in	 that	 search;	 and	 article	 II(Z)(4)(a)(3)
    creates	 a	 presumption	 of	 unsuitability	 if	 the	 Planning	 Board	 agrees	 with	 the
    new-tower-construction	applicant	that	a	co-location	site	is	unsuitable,	and	the
    effect	of	the	presumption	is	that,	unless	additional	information	is	provided	to
    the	Planning	Board,	and	the	Board	determines	“that	new	technology	or	other
    considerations	 enables	 the	 existing	 or	 approved	 tower	 or	 Alternative	 Tower
    Structure	 to	 accommodate	 the	 equipment,”	 later	 new-tower-construction
    applicants	 proposing	to	install	“similar	[communications]	equipment”	do	 not
    have	to	submit	any	evidence	to	the	Planning	Board	about	the	unsuitability	of
    that	 particular	 co-location	 site	 when	 attempting	 to	 comply	 with	 article
    II(Z)(4)(a)(1).	 	 Finally,	 article	II(Z)(4)(a)(4)	 requires	 the	 Town	 to	 maintain	 a
    list	 of	 existing	 and	 approved	 co-location	 sites.	 	 We	 reject	 Olson	 and	 Rabin’s
    interpretation	of	the	Ordinance	because	it	would	increase	the	burden	for	co-
    location	 applicants,	 produce	 the	 illogical	 result	 of	 decreasing	 the	 number	 of
    sites	 available	 to	 co-location	 applicants,	 and	 ultimately	 result	 in	 the
    construction	of	more	new	towers.5		See	Desfosses	v.	City	of	Saco,	
    2015 ME 151
    ,
    5	 	 The	 Superior	 Court	 affirmed	 the	 Planning	 Board’s	 decision	 by	 concluding	 that
    article	II(Z)(4)(a)(3)	 applies	 only	 “when	 there	 has	 been	 a	 Planning	 Board	 determination	 that
    ‘telecommunications	equipment	.	.	.	cannot	be	accommodated	on	an	existing	or	approved	tower	or
    Alternative	Tower	Structure’”	and	because	the	2001	denial	of	Sprint’s	application	expressly	found
    13
    ¶	16,	 
    128 A.3d 648
     (“[W]e	 must	 interpret	 [the	 Ordinance]	 to	 avoid	 absurd,
    illogical,	 unreasonable,	 inconsistent,	 or	 anomalous	 results	 if	 an	 alternative
    interpretation	avoids	such	results.”	(quotation	marks	omitted)).
    [¶19]		The	Planning	Board	did	not	err	in	declining	to	require	Verizon	to
    rebut	a	presumption	of	unsuitability.
    B.	     Investigation	of	Other	Technically	Feasible	Sites
    [¶20]		Olson	 and	Rabin	next	assert	that	we	should	 vacate	the	Planning
    Board’s	decision	or	remand	for	further	fact-finding	because	the	Board	did	not
    receive	 substantial	 evidence	 that	 Verizon	 investigated	 other	 “technically
    feasible	sites,”	as	required	by	article	II(Z)(9)(c)	of	the	zoning	ordinance.
    [¶21]		The	Board	did	not	make	specific	findings	on	Verizon’s	compliance
    with	particular	aspects	of	the	zoning	and	site	plan	ordinances	and	made	only
    the	following	finding:	“On	the	basis	of	the	application,	plans,	reports	and	other
    information	submitted	by	the	applicant,	information	from	the	public	hearing,
    information	and	the	findings	and	recommendations	contained	in	[the]	Planning
    that	the	water	tower	itself	was	an	appropriate	structure	and	the	denial	was	because	of	the	equipment
    on	the	ground,	the	rebuttable	presumption	did	not	apply.		We	agree	with	Olson	and	Rabin	that	this
    interpretation	was	incorrect	because	the	term	“telecommunications	equipment”	encompasses	not
    only	 the	 antennae	 on	 the	 water	tower,	 but	 also	 the	 equipment	 on	 the	 ground.	 	 However,	 it	 is	 the
    decision	of	the	Planning	Board	that	we	review,	not	the	decision	of	the	Superior	Court.		See	Osprey
    Family	Tr.,	
    2016 ME 89
    ,	¶	9,	
    141 A.3d 1114
    .
    14
    Board	Report	dated	September	23,	2016	.	.	.	the	Planning	Board	finds	that	the
    plan	is	in	conformance	with	Chapter	702,	Site	Plan	Review	Ordinance	.	.	.	.”
    [¶22]	 	 Planning	 Board	 findings	 must	 be	 supported	 by	 substantial
    evidence	in	the	record.		See	Osprey	Family	Tr.,	
    2016 ME 89
    ,	¶	9,	
    141 A.3d 1114
    .
    The	 Planning	 Board	 had	 substantial	 evidence	 that	 Verizon	 had	 investigated
    other	 technically	 feasible	 sites	 and	 concluded	 that	 none	 was	 available.
    Although	Verizon’s	written	submissions	to	the	Planning	Board	did	not	contain
    information	about	alternative	sites	that	it	had	considered,	Verizon’s	application
    included	detailed	information	about	its	site	selection	process,	and,	during	the
    May	 and	 September	 meetings,	 the	 Planning	 Board	 asked	 the	 Verizon
    representative	 about	 alternative	 sites	 that	 Verizon	 had	 considered.	 	 At	 the
    September	28	Planning	Board	meeting,	a	Verizon	representative	explained	that
    its	 site	 selection	 process	 consisted	 of	 looking	 for	 gaps	 in	 coverage	 and
    identifying	 sites	 that	 would	 fill	 those	 gaps	 and	 have	 a	 minimal	 effect	 on	 the
    Town.	 	 Verizon’s	 representative	 reported	 that	 the	 only	 feasible	 site	 for
    co-location	was	the	Yarmouth	Water	District	site	because	other	sites	were	not
    tall	 enough	 or	 would	 not	 fill	 the	 coverage	 gap.	 	 The	 Director’s	 report	 to	 the
    Planning	Board	referred	to	the	requirement	of	article	II(Z)(9)(c)	and	Verizon’s
    description	of	its	site	selection	process,	and	noted	that	“[t]his	site	allow[s]	the
    15
    antenna	to	be	located	on	an	existing	water	tower[,]	which	avoids	the	need	to
    construct	a	new	tower.”
    [¶23]		Because	the	Planning	Board’s	finding	was	supported	by	substantial
    evidence,	we	will	not	disturb	the	Board’s	conclusion	that	the	application	met
    ordinance	standards.		See	Bizier,	
    2011 ME 116
    ,	¶¶	8,	12,	
    32 A.3d 1048
    (“[W]e
    accord	 substantial	 deference	 to	 the	 Planning	 Board’s	 characterizations	 and
    fact-findings	 as	 to	 what	 meets	 ordinance	 standards.”)	 (quotation	 marks
    omitted)).
    The	entry	is:
    Judgment	affirmed.
    Nathaniel	A.	Bessey,	Esq.	(orally),	Brann	&	Isaacson,	Lewiston,	for	appellants
    Frederick	Olson	and	Leora	Rabin
    Philip	R.	Saucier,	Esq.	(orally),	Bernstein	Shur,	Portland,	for	appellee	Town	of
    Yarmouth
    Scott	 D.	 Anderson,	 Esq.	 (orally),	 Verrill	 Dana,	 LLP,	 Portland,	 for	 appellee
    Verizon	Wireless
    Cumberland	County	Superior	Court	docket	number	AP-2016-48
    FOR	CLERK	REFERENCE	ONLY