Warren Construction Group, LLC v. Leslie Reis , 2016 Me. LEXIS 6 ( 2016 )


Menu:
  • MAINE SUPREME JUDICIAL COURT                                      Reporter of Decisions
    Decision: 
    2016 ME 11
    Docket:   Cum-15-104
    Argued:   December 10, 2015
    Decided:  January 14, 2016
    Panel:       SAUFLEY, C.J., and ALEXANDER, MEAD, GORMAN, JABAR, and HJELM, JJ.
    WARREN CONSTRUCTION GROUP, LLC
    v.
    LESLIE REIS et al.
    GORMAN, J.
    [¶1] Leslie and Michael Reis appeal from a summary judgment entered in
    the Superior Court (Cumberland County, Cole, J.) in favor of Warren Construction
    Group, LLC, on Warren’s claims for breach of contract, violation of the Prompt
    Payment Act, 10 M.R.S. §§ 1111-1120 (2015), and enforcement of a mechanic’s
    lien. We conclude that the Reises did not preserve the argument they raise on
    appeal, and we affirm the judgment.
    I. BACKGROUND
    [¶2] The summary judgment record reveals the following undisputed facts,
    which we view in the light most favorable to the Reises, the nonprevailing parties.
    See Budge v. Town of Millinocket, 
    2012 ME 122
    , ¶ 12, 
    55 A.3d 484
    . The parties
    entered into an oral contract pursuant to which the Reises would pay Warren to
    renovate their house in Freeport. Warren began the project in late September of
    2
    2012, but stopped working in early February of 2013 when the Reises had yet to
    make any payments.
    [¶3] In May of 2013, Warren perfected a mechanic’s lien on the Reises’
    property and filed a five-count complaint in the Superior Court. Warren alleged
    breach of contract (Count I), quantum meruit (Count II), unjust enrichment
    (Count III), violation of the Prompt Payment Act, 10 M.R.S. §§ 1111-1120
    (Count IV), and enforcement of its mechanic’s lien (Count V). In the answer he
    filed, Michael Reis1 admitted the following assertion: “Warren and the Reises
    entered into a binding contract for construction of the Project.” Five months later,
    Warren moved for summary judgments on its breach of contract, Prompt Payment
    Act, and mechanic’s lien claims.
    [¶4] Michael Reis2 filed an unsigned opposition statement that did not
    comply, in any way, with M.R. Civ. P. 56, and that concluded with the following
    statement: “Based on the facts presented [here] there is no reason for Warren to
    receive a mechanics lien or other damages and legal fees until the work is
    completed properly and at that time he will be entitled to the balance due him of
    1
    Michael signed the answer to the complaint “for Leslie and Michael Reis.” Michael Reis is not
    authorized to practice law in Maine and therefore cannot represent Leslie in court. 4 M.R.S. § 807(1)
    (2015). Had Warren so requested, the court could have entered a default judgment against Leslie for
    failing to answer the complaint.
    2
    Throughout the litigation, Michael Reis filed unsigned documents with the court, ostensibly
    representing himself. Because Leslie Reis filed no opposition to the motion for summary judgment, she
    would not be entitled to any relief even if Michael had prevailed on appeal.
    3
    [$29,592.06].” After Warren filed a reply, Michael Reis filed a second unsigned
    “reply to oppose summary judgment.” In this second document, which also failed
    to comply with the requirements of M.R. Civ. P. 56, Michael Reis listed eleven
    items that he claimed Warren had failed to complete satisfactorily.
    [¶5]   After the court granted Warren’s motion and entered summary
    judgments on the requested claims, the Reises filed a “Verified Motion to Alter or
    Amend [Judgment] pursuant to Rule 59.” In this motion, signed by both Reises,
    they stated that they had opposed Warren’s motion for summary judgment and that
    they “did controvert a single issue.” They described that issue as “the time and
    manner of payment.”
    [¶6] In their Rule 59 motion, the Reises also mentioned, for the first time,
    the Home Construction Contracts Act (HCCA), 10 M.R.S. §§ 1486-1490 (2015),
    stating that the “entire oral contract claims are a violation of the [HCCA].”
    But, immediately following the mention of that statute, the Reises reverted to their
    assertion that their dispute was not about the HCCA, but rather about the terms of
    payment they had agreed to.      They stated: “The single issue of material fact
    controverted by the defendants in their opposition and in Michael Reis’s deposition
    should be allowed to establish a genuine issue of material fact permitting the case
    to proceed to [trial].” The court denied the motion without specific reference to the
    Reises’ arguments.
    4
    [¶7] We dismissed the Reises’ first appeal as interlocutory because the court
    had not adjudicated Warren’s claims for quantum meruit and unjust enrichment,
    Counts II and III of the complaint.                See Warren Constr. Grp., LLC v. Reis,
    
    2014 ME 144
    , 
    107 A.3d 1120
    .               On remand, the court dismissed those remaining
    counts. This appeal followed.
    II. DISCUSSION
    [¶8]    The Reises’ single argument on appeal is that Warren could not
    succeed on any of its claims because the parties’ oral contract is unenforceable
    pursuant to the HCCA.3 Warren contends that the Reises did not present this
    argument to the trial court in a manner sufficient to preserve it for appellate review.
    We agree.
    [¶9] Although the Reises were unrepresented throughout the litigation in the
    trial court, “[w]e have long recognized the principle that pro se litigants are held to
    the same standards as represented litigants.” Richards v. Bruce, 
    1997 ME 61
    , ¶ 8,
    
    691 A.2d 1223
    .            Those standards include the general rule that, unless a
    fundamental liberty interest is at stake, we will not reach an issue that is raised for
    the first time on appeal. Alexander, Maine Appellate Practice § 402(a) at 243
    (4th ed. 2013); see also Teel v. Colson, 
    396 A.2d 529
    , 534 (Me. 1979) (“It is a well
    3
    The HCCA provides, in relevant part: “Any home construction contract for more than $3,000 in
    materials or labor must be in writing and must be signed by both the home construction contractor and the
    homeowner or lessee.” 10 M.R.S. § 1487 (2015).
    5
    settled universal rule of appellate procedure that a case will not be reviewed by an
    appellate court on a theory different from that on which it was tried in the court
    below.”). “An issue is raised and preserved if there was a sufficient basis in the
    record to alert the court and any opposing party to the existence of that issue.”
    Verizon New England, Inc. v. Pub. Utils. Comm’n, 
    2005 ME 16
    , ¶ 15,
    
    866 A.2d 844
    (quotation marks omitted); see also Dillon v. Select Portfolio
    Servicing, 
    630 F.3d 75
    , 80 (1st Cir. 2011) (holding that an argument made for the
    first time in a motion for reconsideration is not preserved for appeal).
    [¶10]   Here, throughout the litigation in the trial court, Michael Reis’s
    defense was predicated on his theory that the contract did not require him to pay
    Warren anything until Warren had satisfactorily completed all of the renovation
    work. Michael Reis did not raise the enforceability of the contract pursuant to the
    HCCA as a defense in his answer and did not allege the HCCA as the basis for a
    counterclaim. He also failed to raise any concerns relating to the HCCA in either
    of his summary judgment filings. The Reises’ Rule 59 motion itself focused on the
    payment terms, and included only a glancing reference to the HCCA, simply
    quoting the statute and referring to Warren’s claims as a “violation.” At no time
    did either Michael Reis or the Reises argue to the trial court, as the Reises do on
    appeal, that a contract that violates the HCCA cannot give rise to liability for
    breach of contract.
    6
    [¶11] The Reises’ glancing reference to the HCCA in their Rule 59 motion
    was insufficient to alert the trial court that they claimed that the contract was
    invalid. As a result, they have not preserved the issue for our review, and we
    therefore affirm the court’s judgment.
    The entry is:
    Judgment affirmed.
    On the briefs:
    David C. Pierson, Esq., Eaton Peabody, Portland, for appellants
    Leslie and Michael Reis
    A. Robert Ruesch, Esq., and Taylor R. Neff, Esq., Verrill Dana,
    LLP, Portland, for appellee Warren Construction Group, LLC
    At oral argument:
    David C. Pierson, Esq., for appellants Leslie and Michael Reis
    Taylor R. Neff, Esq., for appellee Warren Construction Group,
    LLC
    Cumberland County Superior Court docket number RE-2013-183
    FOR CLERK REFERENCE ONLY