Friends of Maine's Mountains v. Board of Environmental Protection ( 2013 )


Menu:
  • MAINE SUPREME JUDICIAL COURT                                                           Reporter of Decisions
    Decision: 
    2013 ME 25
    Docket:   BEP-12-137
    Argued:   November 8, 2012
    Decided:  March 5, 2013
    Panel:          SAUFLEY, C.J., and LEVY, SILVER, MEAD, GORMAN, and JABAR, JJ.*
    FRIENDS OF MAINE’S MOUNTAINS et al.
    v.
    BOARD OF ENVIRONMENTAL PROTECTION et al.
    SILVER, J.
    [¶1] Friends of Maine’s Mountains, Friends of Saddleback Mountain, and
    several individuals1 (collectively, Friends) appeal from a final order of the Board
    of Environmental Protection.                     The Board affirmed the Department of
    Environmental Protection’s order approving the application of Saddleback Ridge
    Wind, LLC (Saddleback), for a permit to construct the Saddleback Ridge Wind
    Project.
    [¶2] Friends argues that the Board abused its discretion when determining
    which nighttime sound level limit to apply to the applications. Friends also makes
    three constitutional arguments: (1) that the Maine Wind Energy Act, 35-A M.R.S.
    *
    Alexander, J., sat at oral argument but did not participate in the development of the opinion.
    1
    The record is unclear about which specific individuals are appealing to this Court. The parties that
    appealed the Department’s decision to the Board, however, included several individuals who own
    properties that are located near the project site and were used in the Noise Impact Study.
    2
    §§ 3401-3458 (2012)2, denies Friends equal protection by denying protection for
    lakes not rated for scenic resources in the Maine’s Finest Lakes Study
    (MFL Study); (2) that the Wind Energy Act violates the Separation of Powers
    Clause of the Maine Constitution by having overly vague criteria for assessing
    visual impact pursuant to 35-A M.R.S. § 3452(3); and (3) that the Department and
    Board demonstrated bias, thus violating Friends’s due process rights. We vacate
    the Board’s order related to nighttime sound requirements and remand for further
    proceedings.
    I. BACKGROUND AND PROCEDURE
    [¶3]   On October 26, 2010, Saddleback filed with the Department
    applications pursuant to the Site Location of Development Law and the Natural
    Resource Protection Act, seeking a permit to build a wind energy development in
    the Towns of Carthage, Canton, and Dixfield. The applications described the
    development as a “12-turbine, 33 [megawatt] wind energy project and associated
    transmission line and substation.” The applications included a noise impact study
    and a visual impact assessment, which the Department hired consultants to review
    as part of its application review. The visual impact assessment evaluated the effect
    of the project on “scenic resource[s] of state or national significance,” 35-A M.R.S.
    2
    The Maine Wind Energy Act, 35-A M.R.S. §§ 3401-3458 (2012), was amended in 2011, but the
    amendments do not impact this opinion. P.L. 2011, ch. 655 (Apr. 24, 2012); P.L. 2011, ch. 682
    (Aug. 30, 2012).
    3
    § 3451(9), that are located near the project. It did not assess the visual impact on
    Webb Lake, which is located near the project, because the lake is not classified as a
    “scenic resource of state or national significance.”      The noise impact study
    assessed the effect of the noise from the project on the thirty-four residences
    located near the project.
    [¶4] Friends objected to the permit application, attaching exhibits including
    extensive scientific literature on the health effects of the noise emitted by wind
    turbines, and requested that the Department hold a public hearing.               The
    Department reviewed the material, and the acting commissioner for the
    Department issued a letter denying the hearing request.
    [¶5] In response to the public interest in the project, the Department held a
    public meeting, pursuant to 38 M.R.S. § 345-A(5) (2012), in the Town of Dixfield.
    During the meeting, many individuals shared their concerns about the project.
    Apart from the meeting, the Department also received comments, articles, and
    petitions from individuals and organizations both for and against the project. As
    part of its opposition to the project, Friends commissioned a report that found that
    Webb Lake fulfilled “the definitions for the label ‘significant’ or ‘outstanding’ as
    they relate to scenic quality and shoreline character” as assessed in the MFL Study.
    [¶6]     In its final order, issued by the acting commissioner on
    October 6, 2011, the Department approved the application subject to certain
    4
    conditions. Although only the Department has jurisdiction to grant wind energy
    applications, 38 M.R.S. § 341-D(2) (2012) (removing jurisdiction from the Board
    for expedited wind energy developments); 35-A M.R.S. § 3451(8)(A) (defining the
    Department as the primary siting authority for expedited wind energy
    developments), the Board3 conducts appellate review of the Department’s
    expedited wind energy development decisions, 38 M.R.S. § 341-D(4)(D) (2012).
    On appeal, the Board has the authority to “affirm, amend, reverse or remand to the
    commissioner for further proceedings . . . permit decisions regarding an expedited
    wind energy development.” 
    Id. The Board
    is also tasked with responsibility for
    “major substantive rulemaking, decisions on selected permit applications . . . and
    recommending changes in the law to the Legislature.” 38 M.R.S. § 341-B (2012)
    (stating the purpose of the Board).
    [¶7] Friends appealed the Department’s order to the Board. On appeal,
    Friends requested “a public hearing before an impartial hearing officer” to assist
    the Board in understanding the conflicting technical evidence. See 38 M.R.S.
    § 345-A(1-A) (2012) (permitting public hearings at the discretion of the Board).
    Friends also challenged the Department’s order regarding its findings on noise,
    visual impact, and tangible benefit payments. The Board issued its final order on
    3
    The Board consists of seven members appointed by the Governor, 38 M.R.S. § 341-C(1) (2012), and
    is a subset of the Department, 38 M.R.S. § 341-A(2) (2012) (stating that the Department consists of the
    Board and the commissioner).
    5
    February 18, 2012, denying the request for a public hearing and affirming the
    Department’s approval of the permit application.
    [¶8] Specifically, the Board affirmed the Department’s decision to apply the
    nighttime sound level limit in effect at the time of the order, which was 45 dBA.
    The Board also found that the visual impact criteria of the Wind Energy Act
    provided adequate guidance for its consideration of the project, and that neither the
    Department nor the Board had the authority to treat Webb Lake as a “scenic
    resource of state or national significance.” Friends appealed the Board’s order
    directly to this Court, pursuant to 38 M.R.S. § 346(4) (2012) (providing the Law
    Court with exclusive jurisdiction to review the Board’s final action on expedited
    wind energy developments).
    [¶9] While Saddleback’s applications were pending before the Department,
    the Board, in its role as the body responsible for making rules and providing
    guidance to the Legislature, was studying the noise emitted by wind energy
    developments. A petition to amend the noise regulation at 2 C.M.R. 06 096 375-6
    to -15 § 10 (2001) was filed with the Board on December 17, 2010, sixty days after
    Saddleback submitted its permit applications. The Board received comments and
    evidence regarding the amendment and held a hearing on July 7, 2011.             On
    September 15,    2011—twenty-one      days    before   the   Department    approved
    Saddleback’s permit limiting the nighttime noise emission to 45 dBA—the Board
    6
    provisionally adopted the amendment that, among other changes, lowered the
    nighttime sound limit for wind energy projects from 45 dBA to 42 dBA.
    Compare 2 C.M.R. 06 096 375-7 § 10(C)(1)(a)(v) (2001) with 2 C.M.R. 06 096
    375-15 § 10(I)(2)(b) (2012). The Board submitted the rule to the Legislature for
    final adoption, pursuant to 5 M.R.S. § 8072 (2012). After legislative approval, the
    amendment went into effect on June 10, 2012.
    [¶10] As noted above, the Board’s affirmance of the Department’s decision
    to apply the 45 dBA limit to this project occurred on February 15, 2012, five
    months after the Board adopted the 42 dBA nighttime sound level limits, subject
    only to final legislative approval.
    II. DISCUSSION
    [¶11] Friends asserts that the Board applied the incorrect nighttime sound
    level limit to Saddleback’s permit applications.     Additionally, it makes three
    constitutional arguments, two of which challenge the constitutionality of the Wind
    Energy Act, with the third argument asserting that the Board and Department
    violated Friends’s due process rights. We review for an abuse of discretion the
    Board’s decision regarding which sound level limit to apply.            5 M.R.S.
    § 11007(C)(6) (2012). “An abuse of discretion may be found where an appellant
    demonstrates that the decisionmaker exceeded the bounds of the reasonable
    choices available to it, considering the facts and circumstances of the particular
    7
    case and the governing law.” Sager v. Town of Bowdoinham, 
    2004 ME 40
    , ¶ 11,
    
    845 A.2d 567
    .             Whether the Wind Energy Act is constitutional and whether
    Friends’s due process rights were violated are questions of law we review de novo.
    Town of Frye Island v. State, 
    2008 ME 27
    , ¶ 13, 
    940 A.2d 1065
    (regarding
    constitutionality of statutes); State v. Bilynsky, 
    2008 ME 33
    , ¶ 5, 
    942 A.2d 1234
    (regarding due process).
    A.         Nighttime Sound Level Limits
    [¶12] The Board regulates the sound levels of wind projects to protect “the
    health and welfare of nearby neighbors.” 2 C.M.R. 06 096 375-6 § 10(A) (2012).
    In order to fulfill this goal, the Board’s rules provide it with the flexibility
    necessary to impose limits on proposed wind projects so that sound levels are
    adequately controlled. 2 C.M.R. 06 096 375-10 § 10(E) (2012).4 See also Martha
    A. Powers Trust v. Bd. of Envtl. Prot., 
    2011 ME 40
    , ¶ 12, 
    15 A.3d 1273
    (noting
    that the Board may alter sound level limits). The Department and then the Board
    are solely responsible for ensuring that wind energy developments do not present
    4
    The Board has discretion pursuant to 2 C.M.R. 06 096 375-10 § 10(E) (2012):
    The Board may, as a term or condition of approval, establish any reasonable requirement
    to ensure that the developer has made adequate provision for the control of noise from the
    development and to reduce the impact of noise on protected locations. Such conditions
    may include, but are not limited to, enclosing equipment or operations, imposing limits
    on hours of operation, or requiring the employment of specific design technologies, site
    design, modes of operation, or traffic patterns.
    8
    undue hazards to the health of Maine’s people.5 While acting in its legislative
    capacity, the Board recognized that the 45 dBA limit did not adequately protect the
    health and welfare of a project’s neighbors. Here, by applying the 45 dBA limit,
    the Board failed to meet its statutory obligation to protect the health and welfare of
    the project’s neighbors. In so doing, it abused its discretion.
    [¶13] Saddleback’s permit application shows that the project does meet the
    45 dBA nighttime sound level limit, as required by the pre-amendment rules. See
    2 C.M.R. 06 096 375-7 § 10(C)(1)(a)(v) (2001). The application does not show,
    however, that the project meets the amended nighttime sound level limit of
    42 dBA. See 2 C.M.R. 06 096 375-15 § 10(I)(2)(b) (2012). On appeal, the Board
    “is not bound by the [acting] commissioner’s findings of fact or conclusions of law
    but may adopt, modify or reverse findings of fact or conclusions of law established
    by the commissioner.” 38 M.R.S. § 341-D(4)(A) (2012). However, the Board
    generally must limit its factual consideration to the Department’s record.
    38 M.R.S. § 341-D(4)(D). Here, Friends provided the Department with essentially
    the same evidence it provided the Board regarding the rule amendment. As a
    result, the evidence the Board reviewed for the appeal of Saddleback’s permit
    included the evidence that it reviewed for the rule amendment, i.e., the evidence
    5
    In addition to issues concerning noise, the Department and Board are also responsible for ensuring
    that wind power projects do not cause groundwater contamination. 2 C.M.R. 06 096 375-5 § 7 (2012).
    9
    that convinced the Board that wind project nighttime noise of 45 dBA or louder
    has a negative effect on the health of residents who live near wind project sites.
    Saddleback provided substantial evidence showing that the modeled sound level
    limit would meet the then-existing level of 45 dBA. It did not attempt to show that
    the project would meet the 42 dBA limit.
    [¶14] The Board does not commit an abuse of discretion simply by making
    discretionary judgments that we, as a reviewing court, disagree with.                         Sager,
    
    2004 ME 40
    , ¶ 11, 
    845 A.2d 567
    . Here, however, the Board, in its legislative role,
    explicitly determined that 45 dBA does not protect nearby residents as a nighttime
    sound level limit for wind projects, but it does nonetheless continue to apply that
    sound level limit in its adjudicatory role.6
    [¶15] As discussed above, in its legislative capacity, the Board adopted the
    reduced sound level limit in order to minimize the impact from wind projects on
    the health of nearby residents, noting “[t]he available data demonstrates that
    persons living near existing wind energy development with actual sound level
    measurements near the 45 dBA limit . . . are experiencing adverse effects.” The
    Board made this finding and took this action before Friends appealed the
    Department’s decision to it.
    6
    Pursuant to 38 M.R.S. § 341-H(1) (2012) the Board is tasked with amending substantive rules, such
    as the rule at issue here. The Department’s staff reviews and comments on the change, but the Board
    makes the final decision regarding the amendment. See 38 M.R.S. § 341-H(3) (2012) (describing the
    Department’s role in rulemaking).
    10
    [¶16] Saddleback’s noise impact study shows that the modeled nighttime
    sound level at the most significantly affected residence7 is 44 dBA, and it asserts
    that due to the use of conservative models, the monitored level is likely to be even
    lower. The Board appeared to rely on this model calibration in its decision to
    uphold the Department’s approval of the permit application, stating:
    If the Board was convinced under specific facts that requiring lower
    sound levels in the modeling results was necessary in order to achieve
    adequate control of noise from a development the Board could do so
    under Chapter 375(10)(E). However, the Board finds that the
    Chapter 375 standards currently in effect should adequately control
    noise due to the reliability of the model and the facts and assumptions
    used by the applicant in its modeling.
    In essence, the Board found that the residents would not be exposed to the effects
    of 45 dBA nighttime sound levels, but instead the noise would be somewhere
    below that limit. There is no indication, however, that the nighttime sound levels
    would be as low as 42 dBA.8
    7
    This residence is 1133 meters, or 3716 feet, from the closest turbine. The buffer area around this
    residence has a modeled nighttime sound level of 45 dBA.
    8
    It is unclear from the record how the Department and Board intend to enforce sound level limits for
    wind projects. In its response to public comment, the Board noted, “[T]he 42 dBA sound limit is an
    enforceable standard which must be met regardless of pre-development modeling predictions.” The
    Board’s rules provide guidance on obtaining measurements for enforcement, but not on the enforcement
    procedure. 2 C.M.R. 06 096 375-14 § 10(H)(4.1)(a) (2012). If the Board enforces the 42 dBA limit after
    approving the permits pursuant to the 45 dBA limit, then Saddleback is subjected to an unfair double
    standard. If the Board enforces the project pursuant to the 45 dBA standard, then any potential benefit is
    not guaranteed after construction, leaving the residents without protection. By requiring Saddleback’s
    model to comply with the amended limits, the project is treated with consistency and the residents’ health
    is protected.
    11
    [¶17] Because the Board is responsible for regulating sound levels in order
    to minimize health impacts—and because when doing so it determined that the
    appropriate nighttime sound level limit to minimize health impacts is 42 dBA—the
    Board abused its discretion by approving Saddleback’s permit applications.9
    Although the project’s models predict nighttime sound levels slightly below
    45 dBA, the Board failed to give the nearby residents the acknowledged protection
    of the amended rules. We vacate the Board’s order and remand for further review
    using the 42 dBA nighttime sound level limit as introduced in 2 C.M.R. 06 096
    375-15 § 10(I)(2)(b) (2012).
    B.       Equal Protection Clause and the Wind Energy Act
    [¶18] Friends argues that the Wind Energy Act violates the Equal Protection
    Clause by refusing to treat Webb Lake as a “scenic resource of state or national
    significance.” Because the users of Webb Lake are not members of a suspect
    class, Friends must show “(1) that similarly situated persons are not treated equally
    under the law, and (2) that the statute is not rationally related to a legitimate state
    interest.” MacImage of Me., LLC v. Androscoggin Cnty., 
    2012 ME 44
    , ¶ 33,
    
    40 A.3d 975
    (quotation marks omitted).
    9
    To be clear, we do not determine that the provisional rules became applicable to the previously
    pending application as a matter of law. Rather, in this case, where the Board is directly responsible for
    protecting the public health, we conclude that the Board cannot ignore its own findings related to public
    health in deciding whether the project is harmful to the public.
    12
    [¶19] When reviewing a permit application pursuant to the Wind Energy
    Act, the Board determines whether the project “significantly compromises views
    from a scenic resource of state or national significance.” 35-A M.R.S. § 3452(1).
    The phrase “scenic resource of state or national significance” is defined in relation
    to “great ponds” in organized areas as: “One of the 66 great ponds located in the
    State’s organized area identified as having outstanding or significant scenic quality
    in the ‘Maine’s Finest Lakes’ study . . . .” 35-A M.R.S. § 3451(9)(D)(1). In 1989,
    the Department of Conservation’s Land Use Regulation Commission conducted an
    assessment that inventoried a variety of natural values associated with Maine lakes
    that are ten acres or larger in size.                The findings from this assessment were
    published in the MFL Study, which noted that “these lake ratings should be
    regarded as minimal findings.” Although Friends presented evidence that Webb
    Lake meets all of the necessary criteria to have an “outstanding” or “significant”
    rating in the MFL Study, the lake did not receive such a rating.
    [¶20] The Legislature enacted the Wind Energy Act as a means to promote
    wind as a renewable energy source and streamline the permitting process for wind
    energy. See 35-A M.R.S. § 3402(1)-(2).10 We have previously held that the “state
    10
    The general purpose of the Wind Energy Act is stated in 35-A M.R.S. § 3402:
    The Legislature finds that it is in the public interest to explore opportunities for and
    encourage the development, where appropriate, of wind energy production in the State in
    a manner that is consistent with all state and federal environmental standards and that
    13
    interest in facilitating the rapid development of alternative, renewable energy
    resources” is a legitimate interest that rationally relates to provisions in the Wind
    Energy Act. Friends of Lincoln Lakes v. Bd. of Envtl. Prot., 
    2010 ME 18
    , ¶¶ 1, 30,
    
    989 A.2d 1128
    (rejecting an equal protection argument regarding the Board’s
    jurisdiction for wind permit applications and the direct appeals to this Court
    allowed by the Wind Energy Act). Here, the State streamlined the permitting
    process by concisely defining a “scenic resource of state or national significance.”
    Because this statutory definition rationally relates to the State’s legitimate interest
    in promoting wind energy and using an efficient permitting process, it does not
    violate the Equal Protection Clause.
    C.       Separation of Powers Clause and the Wind Energy Act
    [¶21] Friends argues that the Wind Energy Act’s criteria for assessing visual
    impact, 35-A M.R.S. § 3452(3), is overly vague and, therefore, it results in an
    unlawful delegation that violates the Separation of Powers Clause. A statute is not
    achieves reliable, cost-effective, sustainable energy production on those sites in the State
    that will attract investment and permit the development of viable wind energy
    projects. . . . The Legislature finds it is in the public interest to encourage the
    construction and operation of community wind power generation facilities in the State.
    The Wind Energy Act also states findings related to the regulatory process in 35-A M.R.S. § 3402(2):
    The Legislature finds that it is in the public interest to reduce the potential for
    controversy regarding siting of grid-scale wind energy development by expediting
    development in places where it is most compatible with existing patterns of development
    and resource values when considered broadly at the landscape level. Accordingly, the
    Legislature finds that certain aspects of the State’s regulatory process for determining the
    environmental acceptability of wind energy developments should be modified to
    encourage the siting of wind energy developments in these areas.
    14
    an unlawful delegation of power if it offers “an intelligible principle to which the
    person or body authorized to act is directed to conform.” Uliano v. Bd. of Envtl.
    Prot., 
    2009 ME 89
    , ¶ 30, 
    977 A.2d 400
    (quotation marks omitted). In evaluating
    the statute, we will, if possible, “construe the statute to preserve its
    constitutionality.” Town of Baldwin v. Carter, 
    2002 ME 52
    , ¶ 9, 
    794 A.2d 62
    .
    Although it is preferable for statutes to have clarity, “[o]bjective quantification,
    mathematical certainty, and absolute precision are not required by either the United
    States Constitution or Maine Constitution.” 
    Id. ¶ 7
    n.2.
    [¶22] The criteria in dispute consist of six factors the Board considers when
    making its determination regarding a wind energy project’s impact on scenic
    resources.           35-A M.R.S. § 3452(3)(A)-(F).11                    These criteria are not easily
    quantified. See Uliano, 
    2009 ME 89
    , ¶ 30, 
    977 A.2d 400
    (noting that “scenic and
    aesthetic uses are not readily susceptible to quantitative analysis”).                                Even the
    11
    The statute, 35-A M.R.S. § 3452(3)(A)-(F), lists the factors as follows:
    A. The significance of the potentially affected scenic resource of state or national
    significance;
    B. The existing character of the surrounding area;
    C. The expectations of the typical viewer;
    D. The expedited wind energy development’s purpose and the context of the proposed
    activity;
    E. The extent, nature and duration of potentially affected public uses of the scenic
    resource of state or national significance and the potential effect of the generating
    facilities’ presence on the public’s continued use and enjoyment of the scenic resource of
    state or national significance; and
    F. The scope and scale of the potential effect of views of the generating facilities on the
    scenic resource of state or national significance, including but not limited to issues related
    to the number and extent of turbines visible from the scenic resource of state or national
    significance, the distance from the scenic resource of state or national significance and
    the effect of prominent features of the development on the landscape.
    15
    Department’s expert from Scenic Quality Consultants, who reviewed the visual
    impact assessment, initially found the criteria difficult to interpret and apply.
    Regardless, we do not find statutes unconstitutional merely due to difficult
    application. See Town of Baldwin, 
    2002 ME 52
    , ¶ 7 n.2, 
    794 A.2d 62
    (discussing
    the difficulty in defining an “annoying” dog bark). In Uliano, we upheld the
    “existing scenic and aesthetic use standard” of the National Resource Protection
    Act, 38 M.R.S. § 480-D(1) (2012), despite its non-quantifiable and difficult to
    apply characteristics. 
    2009 ME 89
    , ¶¶ 25-28, 
    977 A.2d 400
    . We upheld that
    statute because it provided sufficient guidance to the agency regarding its
    application, and any risk that the agency would commit an abuse of discretion was
    tempered by the Maine Administrative Procedure Act and agency regulations. 
    Id. See also
    In re Spring Valley Dev., 
    300 A.2d 736
    , 749-52 (Me. 1973) (declining to
    find the Site Location Law unconstitutionally vague). Here, the statute has similar
    guidance and protections and, therefore, it is not so vague as to constitute a
    violation of the Separation of Powers Clause.
    D.    Due Process Rights and the Bias
    [¶23]   Finally, Friends argues that its due process rights were violated
    because the Department and Board were not impartial fact-finders. Due process
    requires a fair and unbiased hearing. Lane Constr. Corp. v. Town of Washington,
    
    2008 ME 45
    , ¶ 29, 
    942 A.2d 1202
    . In order to show bias, however, Friends must
    16
    present evidence sufficient to overcome a presumption that the fact-finders, as state
    administrators, acted in good faith. Mallinckrodt LLC v. Littell, 
    616 F. Supp. 2d 128
    , 142 (D. Me. 2009); see Mutton Hill Estates, Inc. v. Town of Oakland,
    
    468 A.2d 989
    , 991 (Me. 1983) (finding bias due to ex parte meetings). Although
    the Department and Board ruled against Friends, the rulings do not demonstrate
    bias. As a result, Friends’s due process rights were not violated.
    The entry is:
    Judgment vacated and remanded for further
    proceedings consistent with this opinion.
    On the briefs:
    Rufus E. Brown, Esq., Brown & Burke, Portland, for appellants Friends of
    Maine’s Mountains, Friends of Saddleback Mountain, and several
    individuals
    William J. Schneider, Attorney General, and Gerald D. Reid, Asst. Atty.
    Gen., Augusta, for appellee Board of Environmental Protection
    Gordon R. Smith, Esq., and Juliet T. Browne, Esq., Verrill Dana, LLP,
    Portland, for appellee Saddleback Ridge Wind, LLC
    At oral argument:
    Rufus E. Brown, Esq., for appellants Friends of Maine’s Mountains, Friends
    of Saddleback Mountain, and several individuals
    Gerald D. Reid, Asst. Atty. Gen., for appellee Board of Environmental
    Protection
    17
    Gordon R. Smith, Esq., for appellee Saddleback Ridge Wind, LLC
    Board of Environmental Protection case number L-25137
    FOR CLERK REFERENCE ONLY