Warren Constrution Group, LLC v. Leslie Reis ( 2014 )


Menu:
  • MAINE SUPREME JUDICIAL COURT                                      Reporter of Decisions
    Decision:    
    2014 ME 144
    Docket:      Cum-14-211
    Submitted
    On Briefs: December 1, 2014
    Decided:     December 18, 2014
    Panel:       SAUFLEY, C.J., and ALEXANDER, MEAD, GORMAN, JABAR, and HJELM, JJ.
    WARREN CONSTRUCTION GROUP, LLC
    v.
    LESLIE REIS et al.
    HJELM, J.
    [¶1] Leslie and Michael Reis appeal from a summary judgment entered by
    the Superior Court (Cumberland County, Cole, J.) in favor of Warren Construction
    Group, LLC, on its claims for breach of contract, violation of the Prompt Payment
    Act, 10 M.R.S. §§ 1111-20 (2013), and enforcement of a mechanic’s lien. Because
    the court did not address the claims for quantum meruit and unjust enrichment that
    Warren also asserted in its complaint, there is no final judgment, and we dismiss
    the appeal as interlocutory without reaching the merits.
    I. BACKGROUND
    [¶2] Warren entered into an agreement with Leslie and Michael Reis to
    make improvements to the Reises’ house in Freeport. Warren began the project in
    late September 2012, but by February 2013 had not received payment for any of
    2
    the work. Warren then stopped working on the project and recorded a mechanic’s
    lien against the Reises’ property. In May 2013, after still not receiving payment,
    Warren filed a five-count complaint in Superior Court (Cumberland County)
    alleging: (1) breach of contract; (2) quantum meruit; (3) unjust enrichment; and
    (4) violation of section 1113 of the Prompt Payment Act. See 10 M.R.S. § 1113.
    In the fifth count of the complaint, Warren sought enforcement of the mechanic’s
    lien pursuant to 10 M.R.S. § 3251 (2013).
    [¶3]   In November 2013, Warren moved for summary judgment on its
    claims for breach of contract, violation of the Prompt Payment Act, and
    enforcement of the mechanic’s lien. The motion did not encompass Warren’s
    claims for quantum meruit and unjust enrichment. On April 4, 2014, the court
    entered summary judgment for Warren specifically on those three counts, awarding
    damages for breach of contract, as well as attorney fees and interest as provided in
    the Prompt Payment Act.       See 10 M.R.S. § 1118(4) (2013).        The summary
    judgment order made no mention of Warren’s quantum meruit or unjust
    enrichment claims, and no further orders were entered regarding those claims.
    Following the denial of their motion to alter or amend the judgment pursuant to
    M.R. Civ. P. 59, the Reises appealed.
    3
    II. DISCUSSION
    [¶4] It is a “long-standing” rule that “a party may not appeal a decision until
    a final judgment has been rendered in the case.” Irving Oil Ltd. v. ACE INA Ins.,
    
    2014 ME 62
    , ¶ 8, 
    91 A.3d 594
    (quotation marks omitted). In particular, “[a] court
    order that adjudicates less than all the claims . . . does not terminate the action as to
    any of the claims . . . ,” Sanborn v. Sanborn, 
    2005 ME 95
    , ¶ 4, 
    877 A.2d 1075
    , and
    “an appeal taken from entry of a partial summary judgment is generally
    interlocutory and nonappealable.” O’Connor v. Counseling Servs., Inc., 
    2008 ME 114
    , ¶ 3, 
    951 A.2d 78
    ; see also Me. Health Alliance v. Med. Mut. Ins. Co. of Me.,
    
    2003 ME 144
    , ¶ 8, 
    837 A.2d 135
    (dismissing an appeal from summary judgment
    that did not address all of the counts in a complaint). Although neither party has
    challenged the finality of the judgment, “we are obliged to raise the issue on our
    motion.” Durgin v. Robertson, 
    428 A.2d 65
    , 67 (Me. 1981).
    [¶5] In this case, the summary judgment order specifically concluded that
    Warren was entitled to judgment on its claims for breach of contract, violation of
    the Prompt Payment Act, and enforcement of the mechanic’s lien, which were the
    counts on which Warren sought summary judgment, but the order did not address
    or refer to the remaining two counts in the complaint. Further, no action was taken
    on those two outstanding counts after the entry of summary judgment. Thus, two
    of Warren’s claims are still pending, and there is no final judgment on any of
    4
    Warren’s causes of action from which the Reises may take an appeal.1 See Kinney
    v. Me. Mut. Grp. Ins. Co., 
    2005 ME 70
    , ¶ 13, 
    874 A.2d 880
    (“If any count of a
    complaint . . . remains to be decided after the entry of a judgment from which an
    appeal is taken, the appeal is not taken from a final judgment.”). Because there is
    no final judgment, the Reises’ appeal is interlocutory and must be dismissed. See
    Me. Health Alliance, 
    2003 ME 144
    , ¶ 8, 
    837 A.2d 135
    .
    The entry is:
    Appeal dismissed.
    On the briefs:
    David C. Pierson, Esq., Eaton Peabody, Portland, for appellant
    Leslie Reis and Michael Reis
    A. Robert Ruesch, Esq., and Taylor R. Neff, Esq., Verrill Dana,
    LLP, Portland, for appellee Warren Construction Group, LLC
    Cumberland County Superior Court docket number RE-2013-183
    FOR CLERK REFERENCE ONLY
    1
    We have recognized several exceptions to the final judgment rule that allow for appeal of
    interlocutory orders under special circumstances. See Sanborn v. Sanborn, 
    2005 ME 95
    , ¶ 6, 
    877 A.2d 1075
    . “A party urging that we reach the merits of an otherwise interlocutory appeal has the burden of
    demonstrating to us that one of those exceptions to the final judgment rule justifies our reaching the
    merits of the appeal.” 
    Id. Because none
    of the parties in this case raised the issue of finality, that burden
    has not been met, and we do not consider the application of any of the exceptions to the final judgment
    rule. See O’Connor v. Counseling Servs., Inc., 
    2008 ME 114
    , ¶ 3, 
    951 A.2d 78
    .
    

Document Info

Docket Number: Docket Cum-14-211

Judges: Saufley, Alexander, Mead, Gorman, Jabar, Hjelm

Filed Date: 12/18/2014

Precedential Status: Precedential

Modified Date: 10/26/2024