Odiorne Lane Solar, LLC, et al. v. Town of Eliot et al. , 2023 ME 67 ( 2023 )


Menu:
  • MAINE SUPREME JUDICIAL COURT                                               Reporter of Decisions
    Decision:  
    2023 ME 67
    Docket:    Yor-23-80
    Argued:    October 5, 2023
    Decided:   November 7, 2023
    Panel:         STANFILL, C.J., and MEAD, JABAR, HORTON, and CONNORS, JJ.
    ODIORNE LANE SOLAR, LLC, et al.
    v.
    TOWN OF ELIOT et al.
    CONNORS, J.
    [¶1] The question presented is whether a large solar array project
    constitutes a “public utility facility” within the meaning of the Town of Eliot’s
    Zoning Ordinance. Because we conclude that the project does not fit the
    Ordinance’s plain language definition, we vacate the judgment of the Superior
    Court (York County, Douglas, J.) with instructions to reinstate the decision of
    the Town’s Board of Appeals vacating the Planning Board’s approval of the
    application for a permit for the project.
    I. BACKGROUND
    [¶2] Odiorne Lane Solar, LLC1 applied to the Planning Board in the spring
    1   NHSOLARGARDEN.COM, LLC was Odiorne’s co-applicant for this project. We refer to the
    applicants collectively as Odiorne.
    2
    of 2021 for site-plan review and change-of-use approval to build a large solar
    array project on land located in the Town’s Rural District.2 Eliot, Me. Code
    § 45-402 (June 12, 2021). The lot on which the project was to be located
    comprises approximately seventy acres, with approximately eleven of those
    acres to be developed. The project consists of a large array of ground-mounted
    solar panels capable of generating two megawatts of power. Odiorne posited
    that the large solar array use was a permitted use within the district because
    “public utility facilities” are allowed within every district. Town of Eliot, Me.
    Code § 45-290 (Nov. 2, 2021).
    [¶3] The Planning Board approved the application. Abutters appealed
    that approval to the Board of Appeals, which sustained the appeal, vacating the
    approval of the Planning Board. Odiorne appealed that decision to the Superior
    Court pursuant to M.R. Civ. P. 80B, and the court vacated the decision of the
    Board of Appeals. One of the abutters, Jay Meyer, timely appealed to us from
    the decision of Superior Court. See M.R. App. P. 2B(c)(1); 14 M.R.S. § 1851
    (2023).
    2 The lot on which the array would be built is partially within a shoreland and resource-protection
    overlay zone, but the portions of property to be developed do not fall within the overlay zone.
    3
    II. DISCUSSION
    A.       We review the decision of the Planning Board de novo.
    [¶4] “In a Rule 80B appeal, the Superior Court acts in an appellate
    capacity, and, therefore, we review the agency’s decision directly.” 21 Seabran,
    LLC v. Town of Naples, 
    2017 ME 3
    , ¶ 9, 
    153 A.3d 113
     (quotation marks omitted).
    The administrative decision on review here is that of the Planning Board
    because the Eliot Board of Appeals acts only in an appellate capacity in this
    context. See Eliot, Me. Code § 45-49 (June 8, 2021); Mills v. Town of Eliot, 
    2008 ME 134
    , ¶¶ 13-16, 
    955 A.2d 258
    .
    [¶5] The determinative question in this appeal is whether the array
    constitutes a “public utility facility” within the meaning of the Ordinance.3 With
    respect to the characterization of a use, we have explained that
    [w]hen there is no ambiguity in the language of the ordinance, we
    ordinarily review a Board’s characterization of a structure as a
    finding of fact, giving deference to the Board’s ultimate
    conclusion. . . . Interpretations of municipal ordinances, however,
    are questions of law subject to de novo review. . . . Thus, we review
    the interpretation of the ordinance de novo, but we afford the
    Board’s ultimate characterization of the structure substantial
    deference.
    Meyer also argued that that the project does not meet the Ordinance’s back-lot requirements.
    3
    Given our ruling, we need not and do not address this issue.
    4
    Jordan v. City of Ellsworth, 
    2003 ME 82
    , ¶¶ 8-9, 
    828 A.2d 768
    . Here, the dispute
    focuses on the meaning of the text of the Ordinance, as opposed to whether the
    bundle of factual characteristics of the project fit an unambiguous ordinance
    definition. Therefore, the question is subject to our de novo review.
    [¶6] Finally, “[w]e examine an ordinance for its plain meaning and
    construe its terms reasonably in light of the purposes and objectives of the
    ordinance and its general structure. If an ordinance is clear on its face we will
    look no further than its plain meaning.” Town of Minot v. Starbird, 
    2012 ME 25
    ,
    ¶ 14, 
    39 A.3d 897
     (citations and quotation marks omitted).
    B.    The solar array project is not a “public utility facility” within the
    meaning of the Ordinance.
    [¶7] The Ordinance does not define “public utility facility.” It defines
    “public utility” as “any person, firm, corporation, municipal department, board
    or commission authorized to furnish gas, steam, electricity, waste disposal,
    transportation or water to the public.” Eliot, Me. Code § 1-2 (Nov. 2, 2021)
    (emphasis added).
    [¶8] To furnish electricity to the public in Maine, an entity must be
    authorized to do so by the Public Utilities Commission pursuant to Title 35-A.
    As the electricity market is structured in Maine, solar arrays are not public
    utilities authorized to furnish electricity to the public.     See 35-A M.R.S.
    5
    §§ 2101-2102 (2020)4 (providing that only public utilities allowed within a
    service territory may “furnish” services, and listing as electric public utilities
    only transmission and delivery, not generation).
    [¶9] Odiorne admits that it is not a public utility within the meaning of
    Title 35-A. See 35-A M.R.S. § 102(13) (2020). In 1999 and 2000, the Legislature
    restructured the electricity market so that the owners and operators of the
    transmission and distribution (T&D) network are public utilities, while
    generators are not. 35-A M.R.S. § 3202 (2020). Indeed, there is a strict
    separation between T&D utilities and non-utility generation; T&D utilities are
    prohibited from owning a generating plant. See Competitive Energy Servs. LLC
    v. Pub. Utilities Comm’n, 
    2003 ME 12
    , ¶ 1, 
    818 A.2d 1039
    ; Cent. Me. Power Co. v.
    Pub. Utilities Comm’n, 
    2014 ME 56
    , ¶ 2, 
    90 A.3d 451
    .5
    4 All citations to Title 35-A refer to the 2020 version because that was the version that applied
    when Odiorne applied to the Planning Board, and some sections of Title 35-A have been amended
    since the 2020 statute took effect, though not in any way relevant to the present case.
    5 The reasoning behind this separation is that the entities that transmit and distribute electricity
    should be regulated as public utilities because they are monopolies that serve the public, requiring
    comprehensive regulatory oversight. In contrast, generators compete to provide a commodity.
    See Competitive Energy Servs. LLC v. Pub. Utilities Comm’n, 
    2003 ME 12
    , 
    818 A.2d 1039
    ; GRIDSOLAR,
    LLC, Petition for Finding of Public Convenience and Necessity and Related Approvals for the GridSolar
    Transmission Reliability Project, No. 2009-00152, Order (Me. P.U.C., Dec. 31, 2009) (stating that the
    delivery of electricity or transmission and distribution service is a utility service, but generation is
    not), citing, inter alia, Cent. Me. Power Co., Request for Approval of Location of Easements by Eminent
    Domain over Six Parcels of Land in Oxford County, No. 1999-00467, Order (Me. P.U.C., Sept. 29, 1999)
    (distinguishing generation plant from T&D facilities).
    6
    [¶10] Instead of being a component of a public utility transmission and
    distribution network, this solar array would be classified by statute as a
    non-utility “distributed generation resource,” defined as “an electric generating
    facility with a nameplate capacity of less than 5 megawatts that uses a
    renewable fuel or technology under section 3210, subsection 2, paragraph B-3
    and is located in the service territory of a transmission and distribution utility
    in the State.” 35-A M.R.S. § 3481(5) (2020). This definition gives this type of
    generation certain favorable treatment regarding “net billing” and certain other
    advantages. See 35-A M.R.S. §§ 3209-A, 3482 (2020).6 But being registered as
    a distributed generation resource does not make a generator a public utility.
    [¶11] As a factual matter, this solar array would not sell its generated
    electricity to the public. Rather, it would connect its generation plant to the
    network of Central Maine Power Company, the T&D utility authorized to serve
    the public in Eliot. CMP would then deploy the electricity generated from the
    6 When Odiorne applied to the Town Board, the superseded versions of sections 3209-A and 3482
    cited above applied. Section 3209-A has since been amended to add subsections pertaining to
    consumer protection, enforcement, applicability, and unused kilowatt-hour credits. See, e.g., P.L.
    2021, ch. 705, § 13 (effective Aug. 8, 2022) (codified at 35-A M.R.S. § 3209-A (2023)); 35-A M.R.S.
    § 3209-A (2023) (codifying multiple amendments). Section 3482 has since been amended to prohibit
    the Commission from “procur[ing] distributed generation resources in the shared distributed
    generation and commercial or institutional distributed generation market segments using the targets
    and procurement methods described in this chapter.” See P.L. 2021, ch. 390, § 3 (effective
    Oct. 18, 2021) (codified at 35-A M.R.S. § 3482(1) (2023)).
    7
    solar array, as well as a host of other generators, throughout the region to serve
    its retail customers.
    [¶12] Odiorne is correct that some approvals from the Commission are
    required for large solar arrays and that some solar generators have subscribers,
    but these arguments are not helpful to either its cause or its position. Nothing
    in the record indicates that this solar array has subscribers, and generators—
    solar or otherwise—are not authorized to be a public utility.7
    [¶13] Odiorne argues that Title 35-A is irrelevant because the issue here
    is how the Town defines a public utility facility, not how the Legislature has
    done so. Municipalities are free to define a public utility or public utility facility
    differently than the Legislature does, but here, the Ordinance specifically
    defines a public utility as an entity “authorized” to furnish electricity to the
    7 In its first presentation before the Planning Board, Odiorne mentioned that there was a program
    created by the Legislature to incentivize individuals to purchase power from projects like this solar
    array, but there is no further mention of this program in the record, so it appears that Odiorne did
    not participate in this program. In any event, this reference appears to relate to a state program
    through which the State encourages development of distributed generation. See 35-A M.R.S.
    §§ 3484-3487 (2020); 65-407 C.M.R. ch. 312 (effective Dec. 29, 2019). Under this program, the State
    procures power from participating generators through competitive solicitation. There are two types
    of generators that can participate in this program, a “shared distributed generation resource on
    behalf of subscribers” or a “commercial or institutional distributed generation resource.” 35-A M.R.S.
    § 3481(14) (2020). The solar array here appears to fall into the latter category. But it would make
    no difference if the solar array were the first type of resource. As to either type, the State, through
    the Commission, still buys the power; the generator is not a public utility; and a subscriber remains
    a customer of the T&D utility. See 35-A M.R.S. §§ 3484, 3485(3), 3486(4). A subscriber can either
    own or be allocated generation from the resource, and when the T&D utility bills its retail customers
    who are subscribers to that resource, the power generated by that resource is, as an accounting
    measure, attributed to the resource for pricing purposes. See 35-A M.R.S. §§ 3481(18), 3487(2)
    (2020).
    8
    public. Whether an applicant may furnish service to the public is a function of
    state law, and Title 35-A reflects that Odiorne, like other generators, would not
    furnish electricity to the public because it is not authorized to do so.
    [¶14] To interpret the Ordinance to include generation within the
    definition of a public utility would also produce absurd results. See Jordan,
    
    2003 ME 82
    , ¶ 10, 
    828 A.2d 768
     (“A court’s interpretation of an ordinance must
    not create absurd, inconsistent, unreasonable or illogical results.”) (quotation
    marks omitted). Such inclusion could result in large industrial biomass, natural
    gas, or nuclear plants being located anywhere in the Town, including the Rural
    District. It would also ignore the logical reason why the Ordinance allows
    public utility facilities in every district—to ensure that the heavily regulated
    monopoly T&D electricity network can be deployed throughout the
    municipality.
    [¶15]     Finally, the Ordinance provides that any use not listed is
    prohibited. Eliot, Me. Code § 45-290 (Nov. 2, 2021). Although the Ordinance
    specifically addresses “solar energy systems,” this solar array does not fit that
    definition, Eliot, Me. Code § 1-2 (Nov. 2, 2021), supporting the conclusion that
    the larger system was not intended to be a permitted use. See In re Scates,
    9
    
    94 Me. 579
    , 580, 
    48 A. 113
    , 113 (1901) (applying the maxims “noscitur a sociis”
    and “ejusdem generis”).8
    [¶16] In sum, under the plain language of the Ordinance, “public utility
    facility” means a facility of a public utility authorized to furnish service to the
    public. The solar array does not meet this definition.9
    III. CONCLUSION
    [¶17] Whether the location of solar arrays in rural districts is a good idea
    as a matter of policy is not the question before us. It is up to the voters in the
    Town of Eliot to decide what uses may be allowed, reflected in the language
    they adopt in their ordinances. Given the language they chose to define the
    permitted use of public utility facilities, we agree with the Board of Appeals
    8 The Ordinance also allows, with the approval of the code enforcement officer, “[u]ses similar to
    uses requiring a planning board permit.” Eliot, Me. Code § 45-290 (Nov. 2, 2021). But we can base
    our review only on the ground upon which the Planning Board made its decision, and it did not base
    its decision on confirmation of the conclusion of the code enforcement officer that a large solar array
    was similar to a use permitted in the Rural District. Any similarity to a “solar energy system” would
    not help Odiorne here either because such systems “are allowed only as accessory uses,” suggesting
    that a large-scale, stand-alone array would not be deemed similar and therefore would not be
    allowed. Eliot, Me. Code § 1-2 (Nov. 2, 2021).
    9 In their briefs and at oral argument, the parties alluded to an amendment to the Ordinance that
    may expressly allow large solar arrays in the Rural District. But no one has submitted the amended
    language to us, and as we have stated repeatedly, we cannot take judicial notice of ordinance
    language. Mills v. Town of Eliot, 
    2008 ME 134
    , ¶ 23, 
    955 A.2d 258
    ; Summit Realty, Inc. v. Gipe, 
    315 A.2d 428
    , 429-30 (Me. 1974) (“We have consistently held that the existence of municipal ordinances
    must be proved and that they are not subject to judicial notice.”). Hence, we cannot consider whether
    any such amendment was intended to clarify or change the existing Ordinance language, and we do
    not know what conditions, if any, attach to this purported permission.
    10
    that, at the relevant times for this application, the Ordinance did not permit the
    location of the project within the Rural District.
    The entry is:
    Judgment vacated. Remanded to the Superior
    Court with instructions to enter a judgment
    affirming the decision of the Board of Appeals.
    Patrick S. Bedard, Esq. (orally), Bedard & Bobrow, P.C., Eliot, for appellant Jay
    Meyer
    Leah B. Rachin, Esq. (orally), and Amy K. Olfene, Esq., Drummond Woodsum,
    Portland, for appellee Odiorne Lane Solar, LLC, and NHSOLARGARDEN.COM,
    LLC
    Sandra L. Guay, Esq. (orally), Archipelago Law, LLP, Portland, for appellee Town
    of Eliot
    York County Superior Court docket number AP-2022-9
    FOR CLERK REFERENCE ONLY
    

Document Info

Docket Number: Yor-23-80

Citation Numbers: 2023 ME 67

Judges: Valerie Stanfill, Andrew M. Mead, Jospeh M. Jabar, Andrew M. Horton, Catherine R. Connors

Filed Date: 11/7/2023

Precedential Status: Precedential

Modified Date: 1/28/2024