Preserve the Dunes Inc v. Dept of Environmental Quality ( 2004 )


Menu:
  •                                                          Michigan Supreme Court
    Lansing, Michigan
    Chief Justice:	         Justices:
    Opinion                            Maura D. Corrigan 	     Michael F. Cavanagh
    Elizabeth A. Weaver
    Marilyn Kelly
    Clifford W. Taylor
    Robert P. Young, Jr.
    Stephen J. Markman
    FILED JULY 30, 2004
    PRESERVE THE DUNES, INC.,
    Plaintiff-Appellee,
    v                                                        No. 122611
    MICHIGAN DEPARTMENT OF
    ENVIRONMENTAL QUALITY,
    Defendant,
    and
    TECHNISAND, INC.,
    Defendant-Appellant.
    ______________________________
    PRESERVE THE DUNES, INC,
    Plaintiff-Appellee,
    v                                                        No. 122612
    MICHIGAN DEPARTMENT OF
    ENVIRONMENTAL QUALITY,
    Defendant-Appellant,
    and
    TECHNISAND, INC,
    Defendant.
    _______________________________
    1
    BEFORE THE ENTIRE BENCH
    CORRIGAN, C.J.
    Defendant Michigan Department of Environmental Quality
    (DEQ) and defendant TechniSand, Inc., appeal a Court of
    Appeals decision holding that the DEQ improperly granted a
    sand       dune    mining    permit     to    TechniSand,         contrary     to   the
    Michigan environmental protection act (MEPA), MCL 324.1701
    et seq.1          The only issue properly before us is whether MEPA
    authorizes a collateral challenge to the DEQ’s decision to
    issue a sand dune mining permit under the sand dune mining
    act    (SDMA),       MCL     324.63701       et    seq.,    in    an    action      that
    challenges         flaws     in   the   permitting         process     unrelated     to
    whether      the     conduct      involved        has   polluted,      impaired,     or
    destroyed,         or   will      likely     pollute,       impair,      or   destroy
    natural resources protected by MEPA.                       Because MEPA does not
    authorize such a collateral attack, we reverse the decision
    of    the    Court      of   Appeals     and      remand     to   that      Court   for
    expedited         review     of   the    remaining         issues      of   plaintiff
    Preserve the Dunes (PTD).2
    1
    
    253 Mich App 263
    ; 655 NW2d 263 (2002).
    2
    PTD is an ad hoc organization of local citizens
    formed for the purpose of instituting this lawsuit.
    2
    I.    Factual Background and Procedural Posture
    In 1991, defendant TechniSand purchased a sand mining
    operation with a mining permit that was set to expire in
    1993.         That     permit   did    not     allow    mining    in    adjacent
    property, the Nadeau Site Expansion Area (NSE), which had
    been classified in 1989 as a “critical dune” area under MCL
    324.35301 et seq.
    Mining    in     critical     dune    areas    was   prohibited    after
    July     5,      1989,     subject      to    certain        narrowly    defined
    exceptions to MCL 324.63702(1):
    Notwithstanding any other provision of this
    part, the department shall not issue a sand dune
    mining permit within a critical dune area as
    defined in part 353 [MCL 324.35301 et seq.] after
    July 5, 1989, except under either of the
    following circumstances:
    (a) The operator seeks to renew or amend a
    sand      dune mining permit that was issued
    prior to July 5,    1989, subject to the criteria
    and standards applicable      to  a   renewal  or
    amendatory application.
    (b) The operator holds a sand dune mining
    permit issued pursuant to section 63704 and is
    seeking to amend the mining permit to include
    land that is    adjacent to property the operator
    is permitted to      mine, and prior to July 5,
    1989, the operator owned      the land or owned
    rights to mine dune sand in the land   for which
    the operator seeks an amended permit.
    In late 1994, TechniSand applied for an amended permit
    under MCL 324.63702(1)(b). In April 1995, the Department of
    3
    Natural       Resources   (DNR)3    denied         the   application     on   the
    ground that TechniSand was ineligible for an amended permit
    under       subsection    1(b)     because         it    had   purchased       the
    operation after July 5, 1989.
    In May 1996, TechniSand amended and resubmitted its
    application and supporting documentation to the DEQ.                        After
    a public hearing, the DEQ approved TechniSand’s application
    on November 25, 1996.            TechniSand began mining the NSE area
    thereafter.
    Nineteen     months      later,       in    July     1998,    PTD     sued
    defendants, seeking injunctive and declaratory relief under
    MEPA.       MEPA provides a cause of action for declaratory and
    other equitable relief for conduct that is likely to result
    in the pollution, impairment, or destruction of Michigan’s
    natural resources.        MCL 324.1701 et seq.
    PTD    alleged    that    the     DEQ      violated    MEPA    when     it
    approved TechniSand’s amended mining permit.                         It further
    alleged       that   TechniSand’s       mining      conduct    violated     MEPA.
    Defendants sought summary disposition because PTD’s action
    was     time-barred.      The    circuit        court      denied    defendants’
    3
    During this time, the DNR was the administrative
    agency that regulated sand mining.          In 1995, this
    responsibility was transferred from the DNR to the DEQ by
    Executive Reorganization Order No. 1995-16 (codified at MCL
    324.99903).
    4
    motion.
    PTD    sought    summary    disposition   after   the   original
    circuit judge had retired.         His successor ruled that PTD’s
    claim under the SDMA was indeed time-barred. It also held
    that plaintiff had established a prima facie MEPA claim on
    the basis of TechniSand’s mining conduct.
    After a seven-day bench trial on the MEPA claim alone,
    the court ruled that defendants had successfully rebutted
    PTD’s prima facie case and         entered a judgment of no cause
    of action.     The court specifically found that “any adverse
    impact on the natural resources which will result from the
    sand mining will not rise to the level of impairment or
    destruction    of    natural    resources   within   the   meaning    of
    MEPA.”
    The Court of Appeals reversed and remanded for entry
    of an order granting summary disposition for PTD. The Court
    of Appeals concluded that (1) the DEQ’s decision to grant
    a permit could be challenged at any time under MEPA and (2)
    TechniSand did not qualify for a permit under § 63702.               The
    DEQ and TechniSand filed applications for leave to appeal
    in this Court, and we granted leave.4
    4
    
    468 Mich 869
     (2003).
    5
    II. Standard of Review
    The issue presented involves a question of statutory
    interpretation. We review de novo questions of statutory
    interpretation.       Oade v Jackson Nat’l Life Ins Co, 
    465 Mich 244
    , 250; 632 NW2d 126 (2001).
    III
    A.    Overview of MEPA
    MEPA is contained in part 17, MCL 324.1701 et seq., of
    the Natural Resources and Environmental Protection Act, MCL
    324.101 et seq.        To prevail on a MEPA claim, the plaintiff
    must make a “prima facie showing that the conduct of the
    defendant has polluted, impaired, or destroyed or is likely
    to pollute, impair, or destroy the air, water, or other
    natural resources, or the public trust in these resources.
    . . .”       MCL 324.1703(1).           The defendant may rebut the
    plaintiff’s     showing   with     contrary       evidence       or    raise    an
    affirmative     defense   that     (1)       there   is   no     feasible      and
    prudent alternative to the conduct and (2) the “conduct is
    consistent with the promotion of the public health, safety,
    and   welfare    in    light     of”        the   state’s        concern       with
    protecting Michigan’s natural resources. 
    Id.
     The focus of
    MEPA is on defendant’s conduct.
    MEPA    provides    for      immediate         judicial         review     of
    allegedly    harmful    conduct.    The       statute     does    not    require
    6
    exhaustion of administrative remedies before a plaintiff
    files suit in circuit court. MCL 324.1701(2).                   A court may,
    however, “direct the parties to seek relief” in available
    administrative proceedings.         MCL 324.1704(2).
    B. Overview of SDMA Permit Process
    The DEQ may authorize mining in critical sand dune
    areas    under     two   specific   conditions           set   forth    in    MCL
    324.63702(1)(a) and (b):
    Notwithstanding any other provision of this
    part, the department shall not issue a sand dune
    mining permit within a critical dune area as
    defined in part 353 [MCL 324.35301 et seq.] after
    July 5, 1989, except under either of the
    following circumstances:
    (a) The operator seeks to renew or amend a
    sand dune mining permit that was issued prior to
    July 5, 1989, subject   to   the   criteria  and
    standards applicable to a renewal or amendatory
    application.
    (b) The operator holds a sand dune mining
    permit issued pursuant to section 63704 and is
    seeking to amend the mining permit to include
    land that is adjacent to property the operator is
    permitted to mine, and prior to July 5, 1989, the
    operator owned the land or owned rights to mine
    dune sand in the land for which the operator
    seeks an amended permit.
    If   an   operator   does   not      fall    within    one     of   these
    limited exceptions to the SDMA ban on mining in critical
    dunes areas, the inquiry ends.                 Nowhere in this initial
    inquiry is the DEQ required to evaluate the permit seeker’s
    proposed      conduct.       Indeed,        such    an   inquiry     would     be
    7
    pointless    unless          the     DEQ     first     determined        that     the
    applicant was          eligible for a permit on the basis of the
    applicant’s status as either a past owner or operator.
    Once the DEQ determines that an applicant is eligible
    to apply for a sand dune mining permit in a critical dune
    area under § 63702(1), the applicant must                           fulfill the
    requirements       of    §     63704.      Specifically,         applicants      are
    required to submit the following to the DEQ:
    (a) A permit application on a form provided by
    the department.
    (b)      An environmental impact statement                          of the
    proposed      mining activity as prescribed by                           section
    63705.
    (c)   A    progressive  cell-unit  mining   and
    reclamation plan for the proposed mining activity as
    prescribed in section 63706.
    (d) A 15-year mining plan as prescribed by
    section 63707.
    After       the    DEQ    determines          that    the    applicant      has
    satisfied §§ 63702(1) and 63704(2), it must next determine
    whether the applicant meets the requirement of § 63709.
    Section 63709 prohibits the DEQ from approving an amended
    permit if the applicant’s proposed conduct “is likely to
    pollute,    impair,       or       destroy      the   air,   water,      or     other
    natural resources or the public trust in those resources,
    as provided by part 17.”                   Thus, MEPA, in part 17, MCL
    324.1701    et    seq.,      expressly          controls   the   DEQ’s    §     63709
    8
    determinations.
    C. MCL 324.1701 and Nemeth v Abonmarche Development
    In    addition   to   conferring         power   upon   the   attorney
    general,   MCL    324.1701(1)    authorizes       a   private      cause   of
    action under MEPA:
    The attorney general or any person may
    maintain an action in the circuit court having
    jurisdiction where the alleged violation occurred
    or is likely to occur for declaratory and
    equitable relief against any person for the
    protection of the air, water, and other natural
    resources and the public trust in these resources
    from pollution, impairment, or destruction.
    MCL 324.1701(2) provides:
    In granting relief provided by subsection
    (1), if there is a standard for pollution or for
    an antipollution device or procedure, fixed by
    rule   or   otherwise,   by  the   state  or   an
    instrumentality, agency, or political subdivision
    of the state, the court may:
    ***
    (b) If a court finds a standard to be
    deficient, direct the adoption of a standard
    approved and specified by the court.
    Thus,   in   Nemeth   v    Abonmarche       Development,      Inc,    
    457 Mich 16
    ; 576 NW2d 641 (1998), we held that a violation of
    the soil erosion and sedimentation control act (SESCA), MCL
    324.9101 et seq., may establish a plaintiff’s prima facie
    showing under MEPA because the SESCA contains a pollution
    control standard.
    9
    MCL 324.1702 is not applicable in this case because,
    unlike the SESCA, the SDMA does not contain an antipollution
    standard.       Consequently, it is not within the exception
    created by MCL 324.1701(2).                 Nemeth, therefore, does not
    support the argument that a violation of the SDMA may serve
    as a prima facie violation of MEPA.
    The    Court    of    Appeals    decision     to   the   contrary     was
    based on a misinterpretation of our holding in Nemeth:
    [A]lthough subsection 1701(2) speaks in
    terms of whether a “standard for pollution or
    antipollution device or procedure” exists, but
    does not specifically include whether a standard
    for impairment or destruction of a natural
    resources exists, our Supreme Court in Nemeth did
    not seem to find that to be an important point in
    that case in which soil erosion, rather than what
    is commonly thought of as pollution, was at
    issue. [
    253 Mich App 263
    , 286 n 2; 655 NW2d 263
    (2002).]
    The    Court    of    Appeals    conclusion     is    incorrect.       In
    Nemeth,     we expressly justified our holding in part because
    erosion    is   a   form   of   pollution.         Nemeth,    
    supra at 27
    (“Sedimentation      and    erosion     is     a   [sic]   well-recognized
    source of water pollution.”).
    10
    Moreover, in Nemeth, as in all MEPA actions, the focus
    was on defendant’s actual conduct.5         Specifically, this
    5
    Although we held in Nemeth that the SESCA creates a
    pollution control standard applicable to MEPA claims, we
    also specifically stated:
    We emphasize that this is not the end of the
    inquiry. The trial court held that plaintiffs'
    showing    of   defendants'    SESCA    violations
    established a prima facie claim under the MEPA.
    Then, defendants had the opportunity to rebut
    that prima facie showing either by submitting
    evidence to the contrary, i.e., that plaintiffs
    have shown neither pollution, impairment, nor
    destruction, nor the likelihood thereof, in spite
    of proof of the SESCA violations, or by showing
    that there is no feasible and prudent alternative
    to defendants' conduct.       Subsection 1703(1).
    [Nemeth at 36 n 10 (emphasis added).]
    Thus, it is clear that a defendant’s opportunity to
    rebut a prima facie MEPA violation remains the same whether
    that violation has been established independently or by
    reference to another statute’s pollution control standard,
    and that the determinative consideration is whether
    defendant’s conduct will, in fact, pollute, impair, or
    destroy a natural resource. In the instant case, the Court
    of Appeals erroneously concluded that § 63702 of the SDMA
    creates a pollution control standard and that defendant
    violated it.          Having so concluded, the Court of Appeals
    effectively concluded that defendant’s violation of § 63702
    amounted to a MEPA violation per se. It failed to consider
    at all whether TechniSand had submitted evidence sufficient
    to rebut the alleged prima facie MEPA violations.            The
    trial court, however, did consider this evidence after
    finding that PTD presented a prima facie MEPA violation
    independent of the SDMA.               The trial court held that
    TechniSand had rebutted the prima facie MEPA violation.
    The Court of Appeals failure to consider whether TechniSand
    could rebut the (erroneously found) prima facie MEPA
    violation evidences the extent to which it improperly
    Footnotes continued on following page.
    11
    Court reiterated in Nemeth the findings of fact required of
    a trial court as announced in Ray v Mason Co Drain Comm’r,
    
    393 Mich 294
    ; 224 NW2d 883 (1975).                In Ray, we stated:
    The trial judge must find the facts on which
    the plaintiff claims to have made a prima facie
    case   under   [§   1703(1)],  namely   that  the
    defendant's conduct     "has, or is likely     to
    pollute, impair or destroy the air, water or
    other natural resources.” . . .     Obviously the
    evidence necessary to constitute a prima facie
    showing will vary with the nature of the alleged
    environmental degradation involved.   [Ray at 309
    (some emphasis supplied).]
    That the Court of Appeals failed to recognize that
    MEPA    is   concerned      only   with     harmful      conduct     is   readily
    apparent from its characterization of the circuit court’s
    focus on TechniSand’s mining conduct as error:
    Judge    Schofield   simply   addressed   whether
    TechniSand’s proposed mining was likely to “pollute,
    impair, or destroy” the natural resource in this case—
    the critical dune area. [
    253 Mich App 286
    .]
    Plaintiff     and    the   dissent        urge    us    to   hold     that
    although TechniSand’s mining operation may or may not be
    likely to pollute, impair, or destroy the air, water, or
    other     natural      resources,     its         predecessor’s       allegedly
    deficient      past     relationship         to     the     mining        property
    negatively     affects      the    environment.            We   decline     their
    invitation to accept such fuzzy logic.                    Where a defendant’s
    failed to consider whether TechniSand’s conduct would
    actually “pollute, impair, or destroy” a natural resource.
    12
    conduct      itself       does    not    offend    MEPA,       no    MEPA   violation
    exists.
    D. Review of the DEQ’s MCL 624.63702(1) Decisions6
    We reject the dissent’s gloomy prediction that this
    orderly          understanding      of    MEPA    “insulates         [SDMA]    permit
    eligibility determinations from judicial review.”                             Post at
    22.
    As previously discussed, DEQ determinations of permit
    eligibility under §§ 63702(1) and 63704(2) are unrelated to
    whether the applicant’s proposed activities on the property
    violate MEPA.            Therefore, MEPA provides no private cause of
    action in circuit court for plaintiffs to challenge the
    DEQ’s determinations of permit eligibility made under §§
    63702(1) and 63704(2).
    An improper administrative decision, standing alone,
    does       not    harm    the    environment.           Only    wrongful      conduct
    offends MEPA.
    In        general,      judicial     review      of     an    administrative
    decision          is     available       under    the      following        statutory
    schemes: (1) the review process prescribed in the statute
    applicable         to    the     particular      agency,       (2)   an     appeal   to
    6
    PTD does not challenge TechniSand’s satisfaction of
    the requirements under § 63704(2).
    13
    circuit court pursuant to the Revised Judicature Act (RJA),
    MCL 600.631, and Michigan Court Rules 7.104(A), 7.101, and
    7.103, or (3) the review provided in the Administrative
    Procedures Act (APA), MCL 24.201 et seq.                     Palo Group Foster
    Care, Inc v Dep't of Social Services, 
    228 Mich App 140
    ,
    145; 577 NW2d 200 (1998).
    The SDMA does not expressly establish procedures for
    disputing a DEQ determination in a contested case unrelated
    to MEPA.      We need not decide here whether PTD’s challenge
    to the DEQ’s permit decision is governed by the RJA or the
    APA     because    the     challenge       is     time-barred     under     either
    statute.     PTD brought this action nineteen months after the
    DEQ’s    decision     to    grant    TechniSand’s        application        for    an
    amended     permit,      which    far     exceeds     the    sixty-day      period
    allowed by the APA, MCL 24.304(1), and the twenty-one-day
    period provided by MCR 7.101(B)(1), which governs appeals
    under MCL 600.631 of the RJA pursuant to MCR 7.104(A).                            The
    DEQ   and   TechniSand       properly           interposed   this    defense       in
    their    initial    pleadings.            Thus,     PTD’s    claim    was    time-
    barred.
    E. Participation and Intervention
    During The Permit Process Under the SDMA or MEPA
    Parties    who     wish     to    intervene      during      the    permit
    process have two options.                They may intervene either under
    14
    the procedures governed by the SDMA or those governed by
    MEPA.
    MCL 324.63708(5) of the SDMA establishes a procedure
    for notifying interested parties of permit applications:
    The department shall provide a list of all
    pending sand dune mining applications upon a
    request from a person.   The list shall give the
    name and address of each applicant, the legal
    description of the lands included in the project,
    and a summary statement of the purpose of the
    application.
    Thus, the SDMA provides a mechanism whereby interested
    parties may learn of and participate in agency decisions
    regarding approval of critical dune area mining permits.
    MEPA provides another procedure for intervention in
    permit proceedings.      MCL 324.1705(1). This statute requires
    a potential intervenor to file a pleading asserting that
    the   proceeding   or   action   for     judicial    review    involves
    conduct that has violated, or is likely to violate, MEPA.
    Thus,    while   PTD   could   have     intervened   in   TechniSand’s
    permit process under MEPA, its only basis for intervention
    would have been TechniSand’s proposed conduct.                MEPA does
    not allow such intervention on the basis of anything other
    than alleged wrongful conduct.
    F. Review of DEQ’s MCL 324.63709 Determinations
    As already discussed, a challenge under MEPA may be
    filed in circuit court before or during the time that the
    15
    alleged MEPA violation occurs, without any requirement that
    a litigant exhaust administrative remedies.                      Thus, whether
    TechniSand was ineligible for the permit under § 63709 on
    the basis of alleged harmful conduct was a question that
    was properly before the circuit court.                    The circuit court
    ruled against PTD.
    The   Court    of    Appeals     has    not   reviewed    the    circuit
    court’s decision that TechniSand’s conduct did not violate
    the MEPA standard incorporated into the SDMA under § 63709.
    Because the Court of Appeals never reached PTD’s claim that
    TechniSand’s mining operation violates MEPA, that issue is
    not ripe for this Court’s review.                     We remand the case to
    the Court of Appeals to review the circuit court’s findings
    regarding TechniSand’s sand mining activity.                     The Court of
    Appeals is directed to expedite its consideration of this
    case.
    F. Response to the Dissent
    The dissent initially contends that it is undisputed
    that TechniSand is “ineligible for a permit.” Post at 2.
    We    disagree.        The     time     for      challenging      TechniSand’s
    eligibility      for    a    permit     is     long   past.    TechniSand       is
    lawfully entitled to mine sand dunes in Michigan according
    to the DEQ permit.             Whether the DEQ’s permitting decision
    was   “unprincipled”          or   an   “illegal      about-face”   is    not    a
    16
    determination for this Court to make. Post at 2.                               That
    decision is time-barred.
    The      dissent       further   asserts       that    the   DEQ’s    permit
    decision         “will       directly   enable    destruction       of     critical
    dunes.”         Post    at    3-4   (emphasis    supplied).         The     dissent
    asserts that critical dunes will be destroyed because the
    Court of Appeals stated that TechniSand had acknowledged as
    much       in   an     environmental    impact     statement.         The    entire
    environmental            impact     statement    is    not     in   the     record.7
    Moreover, the trial court expressly found to the contrary
    when it ruled on the MEPA claim.                  It specifically held that
    TechniSand’s mining would not destroy a critical dune. The
    Court of Appeals never addressed this finding.
    The dissent’s conclusion that the permitting process
    is subject to collateral attack is not defensible on the
    basis of MEPA’s language, structure, or purpose.                          Countless
    entities apply for and receive permits for conduct that
    affects Michigan’s natural resources.                        Under the dissent’s
    7
    The excerpt in the record indicates that TechniSand
    acknowledged that the project would “greatly alter”
    approximately 61% of the NSE. In any case, the trial court
    expressly found more credible TechniSand’s expert witnesses
    and ultimately held “the adverse impact on the environment
    caused by the mining as permitted will not rise to the
    level of impairment or destruction within the meaning of
    MEPA.”
    17
    regime, the permitting decision can never be final.                                 Were
    we to adopt the dissent’s extreme understanding of MEPA,
    every permit that has ever been issued would be subject to
    challenge;        any    undotted       “i”     or     uncrossed         “t”    could
    potentially       invalidate       an    existing      permit.           We    do    not
    believe the Legislature intended MEPA to destabilize the
    state’s permitting system in this manner.
    Imagine the world that the dissent’s reasoning would
    create.     The present energy crisis offers a good example.
    For many years, our country has sought to decrease our
    reliance on foreign sources of oil.                   Suppose an oil company
    decided     to     invest   in     oil     exploration        in      Michigan        in
    reliance on a DEQ-issued permit. Under the dissent’s view,
    MEPA would authorize a challenge at any time to flaws in
    the   permitting        process.        Moreover,       under      the    dissent’s
    reasoning, a court must accept as true the bare assertion
    that a company’s conduct will destroy natural resources.
    It can never rely on a permit to do business.                             What sane
    investor would take such a risk?                     As gas prices soar, few
    people in Michigan would thank this Court for “protecting”
    the environment in this radical fashion.
    The       dissent’s   regime       would       render     the      permitting
    process     a    useless    exercise.          It    would    cripple         economic
    expansion in Michigan and probably lead to disinvestment.
    18
    No   one    would       invest       money     to    obtain       a    permit       that   is
    subject to endless collateral attacks.
    MEPA    nowhere          strips        the       permitting             process     of
    finality.          It    is     the       dissent    that    makes          a    mockery    of
    legislative        intent       by    failing       to    anchor       its      exaggerated
    claims in the statute’s actual language. See post at 3.
    MEPA does not impose the radical requirement that courts
    indefinitely            police        administrative              agencies’             permit
    procedures and decisions.                    As noted in Oscoda Chapter of
    PBB Action Comm, Inc v Dep’t of Natural Resources, 
    403 Mich 215
    , 232-233; 248 NW2d 240 (opinion by Levin, J.) (1978):
    A court is not empowered to prevent any
    conduct . . . which does not rise to the level of
    environmental risk proscribed by [MEPA].      The
    standard, ‘has or is likely to pollute, impair or
    destroy,’ is a limitation as well as a grant of
    power.
    Moreover, the Court of Appeals never reached the issue
    of whether TechniSand’s actual conduct is likely to harm
    natural     resources.               As    already       noted,       the       trial    court
    specifically held that TechniSand’s conduct did not violate
    MEPA.      Given this procedural posture, we are puzzled by the
    dissent’s statement that defendant’s mining “will” destroy
    critical dunes.
    After   taking        extensive        testimony      on       the       issue,    the
    trial      court        ruled    that        any     “adverse          impact       on     the
    19
    environment caused by the mining as permitted will not rise
    to   the   level   of    impairment     or    destruction    within   the
    meaning of MEPA.”       The Court of Appeals did not explicitly
    reject the trial court’s findings.            Instead, it erroneously
    concluded that a permit that affects the environment in any
    way may be challenged at any time under MEPA.                   For the
    reasons articulated above, the Court of Appeals erred in
    interpreting MEPA in this manner.
    CONCLUSION
    MEPA affords no basis for judicial review of agency
    decisions under MCL 324.63702(1) because that inquiry is
    outside the purview of MEPA.             The focus of MEPA is to
    protect our state’s natural resources from harmful conduct.
    It offers no basis for invalidating an issued permit for
    reasons unrelated to the permit holder’s conduct.               To hold
    otherwise would broaden by judicial fiat the scope of MEPA
    and create a cause of action that has no basis in MEPA’s
    language or structure.
    The Court of Appeals erred by treating PTD’s challenge
    to   TechniSand’s       eligibility     for    a   permit    under    MCL
    324.63702(1) as a MEPA claim.                Because PTD brought its
    claim more than nineteen months after the DEQ issued the
    permit,    PTD’s   claim    is   time-barred.        We     reverse   the
    decision of the Court of Appeals on that issue.
    20
    We remand the case to the Court of Appeals to review
    the   circuit   court’s   findings   that   TechniSand’s   mining
    conduct does not violate MEPA, and direct the Court of
    Appeals to expedite its review.
    Maura D. Corrigan
    Clifford W. Taylor
    Robert P. Young, Jr.
    Stephen J. Markman
    21
    S T A T E     O F   M I C H I G A N
    SUPREME COURT
    PRESERVE THE DUNES, INC,
    Plaintiff-Appellee,
    v                                                      No. 122611
    MICHIGAN DEPARTMENT OF
    ENVIRONMENTAL QUALITY,
    Defendant,
    and
    TECHNISAND, INC,
    Defendant-Appellant.
    _______________________________
    PRESERVE THE DUNES, INC,
    Plaintiff-Appellee,
    v                                                      No. 122612
    MICHIGAN DEPARTMENT OF
    ENVIRONMENTAL QUALITY,
    Defendant-Appellant,
    and
    TECHNISAND, INC,
    Defendant.
    _______________________________
    KELLY, J. (dissenting).
    In 1995, the Michigan Department of Natural Resources
    (DNR)       denied    defendant     TechniSand         permission      to      mine
    critical dunes because it was ineligible for a permit under
    the sand dune mining act1 (SDMA), MCL 324.63701 et seq.                         One
    year later, following Governor Engler’s reorganization of
    the   DNR,     the    newly    created        Department    of    Environmental
    Quality      (DEQ)    invited    TechniSand       to   apply     again,     citing
    “changes in state government.”                   TechniSand reapplied and
    the DEQ granted a permit despite the fact, now undisputed,
    that TechniSand remained ineligible to mine critical dunes.
    As a result, critical dunes that would otherwise remain
    untouched will be impaired and perhaps destroyed.
    Through the decision in this case, a court majority of
    four sanctions the DEQ’s unexplained and illegal about-face
    on    TechniSand’s      critical     dune       mining     permit.        In    the
    process,      it     strikes    a   devastating        blow      to   Michigan’s
    environmental law.2             This majority perpetuates the DEQ’s
    1
    The Sand Dune Mining Act is codified as part 637 of
    the Natural Resources and Environmental Protection Act, MCL
    324.101 et seq.
    2
    The majority’s decision to significantly narrow the
    scope of the applicability of the Michigan environmental
    protection act (MEPA), MCL 324.1701 et seq., in this case
    is compounded by its recent decision in Nat'l Wildlife
    Federation & Upper Peninsula Environmental Council v
    Cleveland        Cliffs       Iron     Co and Michigan Dep't of
    Footnotes continued on following page.
    2
    unprincipled decision to permit illegal mining of critical
    dunes by insulating it from the scrutiny of the Michigan
    environmental protection act (MEPA).              MCL 324.1701 et seq.
    Its holding that the DEQ’s decision to grant the permit to
    mine critical dunes is “unrelated to” the destruction of
    those       critical     dunes    defies   reality.         It   mocks    our
    Legislature’s       intent   to    prevent    environmental      harm.    In
    addition,      it   is    contrary   to    this   Court’s    earlier     MEPA
    decisions.3
    Critical sand dunes, like those at issue in this case,
    are specially protected natural resources.                  The mining act
    protects these irreplaceable resources by strictly limiting
    who is eligible to mine them.                MEPA works in tandem with
    the mining act to, in its own words, supplement “existing
    administrative and regulatory procedures provided by law.”
    MCL 324.1706.          Issuance of the permit will directly enable
    Environmental Quality, 471 Mich ___ ; ___ NW2d ___ (2004).
    There, the same majority ignores thirty years of precedent
    and   applies   judge-created   standing  tests   to   MEPA
    plaintiffs. It makes this ruling despite the fact that the
    statute explicitly grants standing to “any person” to
    maintain an action to prevent pollution, impairment, or
    destruction of our natural resources. MCL 324.1701(1).
    3
    See e.g., Eyde v Michigan, 
    393 Mich 453
    , 454; 225
    NW2d 1 (1975), Ray v Mason Co Drain Comm’r 
    393 Mich 294
    ,
    304-305; 224 NW2d 883 (1975), West Michigan Environmental
    Action Council v Natural Resources Comm, 
    405 Mich 741
    , 751;
    275 NW2d 538 (1979) (WMEAC), and Nemeth v Abonmarche Dev,
    Inc, 
    457 Mich 16
    ; 576 NW2d 641 (1998).
    3
    destruction of critical dunes that would otherwise remain
    untouched.      Hence,   it    is    inescapable     that   the    DEQ’s
    decision to issue the permit may be challenged under the
    environmental protection act.
    Moreover, the environmental protection act does not
    impose a statutory period of limitations on legal actions
    that assert that a party’s conduct will cause environmental
    pollution, impairment, or destruction.           Therefore, I would
    hold   that   plaintiff’s     challenge   is   not   limited      by   the
    statutory period of either the Administrative Procedures
    Act (APA) or the Revised Judicature Act (RJA).              MCL 24.201
    et seq., MCL 600.101 et seq.
    I dissent because the majority’s decision subverts the
    purposes of the sand dunes mining act and the environmental
    protection act by incorrectly insulating the DEQ’s permit
    decision from scrutiny under the environmental protection
    act.    Defendant TechniSand is not eligible for a permit to
    mine critical dunes sand under the sand dunes mining act.
    Accordingly, I would affirm the decision of the Court of
    Appeals.
    4
    The Majority's Response to the Dissent
    The majority’s “Response to the Dissent”4 is an abrupt
    departure         from    its     precedent         of    declining    to        amend
    legislative policy decisions with which it disagrees.5 Its
    discussion of the wisdom of the Legislature's decision to
    bar sand dune mining by anyone who does not meet limited
    eligibility criteria is unsuited for a judicial opinion.
    Moreover,        the     majority’s    comparison         of   the    eligibility
    problem      in     the    permit     to        a   clerical   error    and       its
    suggestion that my position would allow endless challenges
    for such trifles are gross exaggerations.                       Ante at 17-18.
    Granting a permit to mine critical dunes to an ineligible
    operator is a substantive fault.                    It is a violation of the
    law   that       allows    conduct    likely         to   pollute,    impair,      or
    destroy      a    natural       resource        specially   protected       by    the
    Legislature.           Economic development in this state has not
    ceased in the past thirty years.                    It will not now grind to
    a halt under the oppressive weight of permit challenges if
    4
    Ante at 16-20.
    5
    This Court has scrupulously declined to consider the
    wisdom of the Legislature’s policy decision.      See e.g.
    Oakland Co Rd Commr’s v Michigan Prop & Cas Guaranty Ass'n,
    
    456 Mich 590
    , 612-613; 575 NW2d 751 (1998).
    5
    this Court reaffirms its prior holdings that MEPA allows
    challenges to environmentally destructive permit decisions.
    Facts and Proceedings Below
    Defendant TechniSand purchased real property in 1991
    that   included      both    critical      and      noncritical     dune    areas.
    Along with its purchase, it obtained a permit to mine sand
    in noncritical dune areas on one portion of the property.
    In 1994, TechniSand applied for an amendment of this permit
    to expand sand dune mining to critical dune areas on an
    adjacent portion of the property.
    The   Michigan       Department        of    Natural    Resources,      the
    agency charged with reviewing SDMA permit applications at
    the    time,   denied       the    application         on   the    ground     that
    TechniSand     was    ineligible        for    an    amended      permit.      The
    original permit was to mine in noncritical dune areas and
    did not include the property’s critical dune areas.                          Also,
    TechniSand     had    purchased      the      land    and     mining   operation
    after the deadline to apply for an unassociated permit to
    mine the critical dune areas.                MCL 324.63702(1)(b).
    In 1995, Governor John Engler created a new agency,
    the    Michigan   Department       of     Environmental         Quality     (DEQ).
    Executive Reorganization Order No. 1995-16 (codified at MCL
    324.99903).           The    DEQ    was       given     responsibility         for
    administering the SDMA and other environmental permitting
    6
    programs, and the Governor appointed its director.                     The DEQ
    then wrote to TechniSand indicating that “changes in state
    government”        and   “additional    information”        from   TechniSand
    would allow the DEQ to review the permit application.6
    TechniSand        resubmitted        the     environmental       impact
    statement and reclamation plan that it had submitted with
    its    previous      application,      without       providing     additional
    information        demonstrating     how     it     was    eligible    for   an
    amended permit.          The DEQ issued the permit later that year.
    It    did    not   explain    how    TechniSand      met    the    eligibility
    criteria in the SDMA.          Also, it does not now dispute that
    TechniSand is ineligible for a permit.
    Plaintiff Preserve the Dunes was formed in 1996.                      In
    1998, it sued TechniSand and the DEQ for injunctive relief
    to    stop    TechniSand’s    mine     expansion.          Plaintiff   alleged
    that TechniSand was ineligible for an SDMA permit and that
    its mine expansion violated MEPA.
    The trial court ruled that plaintiff’s challenge to
    the        permitting     decision     was        time-barred      under     the
    6
    Letter dated April 1, 1996 from Douglas Daniels and
    Kimberly Rice of the DEQ. The letter makes reference to an
    April 20, 1995, letter by which Roger Whitener of the DNR
    informed TechniSand that, pursuant to an opinion of the
    state attorney general, TechniSand was ineligible to mine
    critical dunes. The April 1, 1996, letter did not address
    TechniSand’s ineligibility to mine critical dunes.
    7
    Administrative Procedures Act and that the environmental
    impact of the mining was insufficient to implicate MEPA.
    The Court of Appeals reversed the ruling.              
    253 Mich App 263
    ; 655 NW2d 263 (2002).         It held that the DEQ’s decision
    to grant TechniSand’s amended permit could be challenged
    under MEPA and that TechniSand did not qualify for a permit
    under § 63702 of the SDMA.             The DEQ’s decision to amend
    TechniSand’s permit, it concluded, violated MEPA.
    The Court of Appeals remanded the case to the trial
    court    for    entry   of   summary    disposition   for   plaintiff.
    Because it had found TechniSand ineligible for a permit to
    mine the critical dune area, it did not review the trial
    court’s finding that the mining itself violated MEPA.            This
    Court granted the applications for leave to appeal filed by
    the DEQ and TechniSand.       
    468 Mich 869
     (2003).
    The Sand Dune Mining Act Protects Michigan’s
    Critical Dunes from Destruction
    It is without contest that the Legislature enacted the
    sand dune mining act to stringently protect Michigan's sand
    dune areas from further destruction.           They are one of the
    state's prized natural resources.          The Legislature included
    in the act special provisions to preserve dune areas it
    labeled "critical."
    8
    It expressly indicated:
    The critical dune areas of this state are a
    unique, irreplaceable, and fragile resource that
    provide   significant    recreational,  economic,
    scientific,   geological,     scenic,  botanical,
    educational,    agricultural,     and  ecological
    benefits to the people of this state and the
    people from other states and countries who visit
    this resource. [MCL 324.35302(a).]
    The Legislature enacted the SDMA out of concern that
    mining the dunes consumes them and harms the environment.
    The    act        is    an     expression     of    the     state’s    “paramount”
    interest in protecting the dunes.                         See MCL 324.1701.    It
    defines “Sand dune mining” as the “removal of sand from
    sand       dune    areas      for     commercial    or    industrial    purposes.”
    MCL 324.63701(l).7              It requires all persons seeking to mine
    sand       dunes       to    obtain    a   sand    dune    mining   permit.   MCL
    324.63704.             Regarding critical dunes, the act states that
    “the removal of any volume of sand that is not sand dune
    mining within a critical dune area as defined in part 353
    is subject to the critical dune protection provisions of
    part 353.”         MCL 324.63701(l).
    7
    The statute exempts from this definition the removal
    of “volumes of less than 3,000 tons” of sand if the removal
    is a “1-time occurrence and the reason the sand is removed
    is not for the direct use for an industrial or commercial
    purpose.”
    9
    The SDMA’s flat prohibition against mining any sand in
    designated critical sand dune areas is subject only to a
    narrow exception.    That is, authorized mining entities that
    existed when the SDMA was enacted may continue operation
    (1) on land in which they had a mining interest before July
    5, 1989 or (2) on land adjacent to property in which they
    had a mining interest before that date.       MCL 324.63702(1).8
    These      “grandfathering”       exceptions    reflect     the
    Legislature’s    attempt   to   balance   mining    interests   that
    predated the critical dune designation of July 5, 1989,
    with the preservation of the remaining and newly designated
    8
    MCL 324.62702(1) provides in full:
    Notwithstanding any other provision of this
    part, the department shall not issue a sand dune
    mining permit within a critical dune area as
    defined in part 353 after July 5, 1989, except
    under either of the following circumstances:
    (a) The operator seeks to renew or amend a
    sand dune mining permit that was issued prior to
    July 5, 1989, subject to the criteria and
    standards applicable to a renewal or amendatory
    application.
    (b) The operator holds a sand dune mining
    permit issued pursuant to section 63704 and is
    seeking to amend the mining permit to include
    land that is adjacent to property the operator is
    permitted to mine, and prior to July 5, 1989 the
    operator owned the land or owned the rights to
    mine dune sand in the land for which the operator
    seeks the amended permit.
    10
    critical dunes.             New entities would be unable to begin
    operation.           Existing          entities           would     have         limited
    opportunities        to     mine     additional          areas.          By     limiting
    critical dune mining to those entities with a preexisting
    interest, existing entities would be allowed to continue
    operating      while        ensuring    that        mining        would       not      last
    indefinitely.
    The Legislature mandated that these narrow exceptions
    for   sand      dune        mining     would        be     implemented           through
    regulatory permits.             MCL 324.63704.              The act created a
    permitting procedure to ensure that future mining would be
    only by parties with a pre-existing legal interest, and in
    a manner protective of critical dune areas.                                   It cannot
    reasonably be suggested that the eligibility criteria that
    completely      prohibit       all     but     an     expressly          defined       few
    operators from mining critical dunes are not a measure of
    environmental protection.
    Only     if      eligibility        is        verified        do        additional
    environmental        protections         come        into         play.             Permit
    applications by eligible entities are reviewed on a case-
    by-case      basis     to    ensure     that        the    proposed           mining    is
    environmentally acceptable.               The applicant must submit an
    environmental impact statement describing the anticipated
    environmental        damage     that     will       occur      from       the       mining
    11
    operation. MCL 324.63704(2)(b).             The applicant must explain
    why    alternative    mining      locations       were     not     chosen.    MCL
    324.63705(h).      It must include a reclamation plan for the
    area to be mined.         MCL 324.63704(2)(c), 324.63706.
    In reviewing the application, the DEQ must ensure that
    the    proposed   mining     is   unlikely       to     pollute,    impair,    or
    destroy   natural    resources      or     the    public    trust     in   those
    resources.    MCL 324.63709.         Any permit issued must require
    that the provisions of the applicant’s progressive cell-
    unit     mining    and      reclamation          plan     are      met.       MCL
    324.63706(3).        If    threatened      or     endangered       species    are
    present, the plan must include provisions either to protect
    them or to mitigate the effect of mining on them.                             MCL
    324.63706(3)(g).
    Plaintiffs May Challenge the Permit Eligibility
    Determination Under the Michigan
    Environmental Protection Act
    The environmental protection act provides that
    . . . any person may maintain an action in the
    circuit court . . . where the alleged violation
    occurred or is likely to occur for declaratory
    and equitable relief against any person for the
    protection of the air, water, and other natural
    resources and the public trust in these resources
    from pollution, impairment, or destruction. [MCL
    324.1701(1).]
    Under this act, a plaintiff makes a prima facie case
    by showing “that the conduct of defendant is likely to
    12
    . . . destroy the . . . natural resources or the public
    trust       in    these    resources.”         MCL     324.1703(1).9        The
    Legislature         expressly      provided     that     MEPA     supplements
    existing regulatory procedures that were provided by law.
    MCL 324.1706.
    The SDMA’s eligibility restrictions protect critical
    dunes from mining by ineligible operators whose conduct is
    likely      to    impair    or   destroy     critical    dunes    that    would
    otherwise         remain   untouched.         Hence,     the    environmental
    protection act is applicable to decisions regarding an SDMA
    permit      applicant’s      eligibility.         The    SDMA    specifically
    incorporates        the    Legislature’s      recognition       that   critical
    dunes       are     “irreplaceable”          natural     resources.         MCL
    324.35302(a).         It provides that “the removal of any volume
    of sand . . . within a critical dune area . . . is subject
    to the critical dune protection provisions of part 353.”
    MCL     324.63701(l).            Its   provisions       strictly       limiting
    eligibility to mine critical dunes are intended to help
    protect      critical      dunes    from     pollution,     impairment,      or
    destruction.
    9
    The majority's reference to MCL 324.1702(2) is
    misplaced. Ante at 10. Plaintiffs are not challenging the
    DEQ’s imposition on Technisand of the SDMA’s pollution
    control standards.    They do not challenge the manner in
    which permissible activity is undertaken.     They challenge
    whether Technisand's conduct is permissible at all.
    13
    Thus,     the        majority’s       suggestion         that      permit
    eligibility is unrelated to whether the conduct permitted
    will harm the environment is untenable.                          Issuance of a
    permit to an ineligible operator to engage in any mining of
    critical    dunes       will   allow         “conduct    .   .    .     likely   to
    pollute, impair, or destroy . . . natural resources or the
    public trust in these resources.”                   MCL 324.1703(1); see
    also West Michigan Environmental Action Council v Natural
    Resources Comm,         
    405 Mich 741
    , 751; 275 NW2d 538 (1979)
    (WMEAC).
    MEPA is intended to prevent conduct that is likely to
    harm the environment as well as to stop conduct that is
    presently harming it.            In WMEAC, this Court ordered that a
    permanent injunction be entered prohibiting the drilling of
    oil and gas wells pursuant to a DNR permit.                       The “issuance
    of permits was properly before the circuit court as conduct
    alleged    to     be    likely    to   pollute,     impair,        or    destroy”
    natural resources under MEPA.                WMEAC at 751.        The drilling
    would     cause     “apparently        serious     and       lasting,      though
    unquantifiable, damage” to elk herd population.                          WMEAC at
    760.      This Court concluded that the previous MEPA, MCL
    691.1203(1),        is violated whenever the effects of permit
    issuance    harm       the   environment      to   the   requisite        degree.
    WMEAC at 751, 760.
    14
    Unlike permit eligibility for fossil fuel drilling and
    other activities that may pollute the environment if done
    improperly,10           SDMA     permit         eligibility     is      severely
    restricted.         The applicant must demonstrate a preexisting
    mining       interest,     and       no   mining    may    occur     until   this
    requirement         has    been       satisfied.           It   reflects      the
    Legislature’s premise that the removal of even one bucket
    of sand from a critical dune by an ineligible operator will
    inordinately impair the state's critical dune areas.                          An
    action       that   enables      such     conduct    may   be   challenged    as
    destruction or impairment under MEPA.
    This Court observed in Nemeth11 that a violation of a
    permitting procedure can support a prima facie claim under
    MEPA.        A “plaintiff’s prima facie case is ‘not restricted
    to actual environmental degradation but also encompasses
    probable       damage     to   the    environment     as   well.’”       Nemeth,
    supra at 25, quoting Ray v Mason Co Drain Comm’r, 
    393 Mich 294
    , 309; 224 NW2d 883 (1975).                     In the soil erosion and
    10
    See also MCL 324.5505 and 324.3106, requiring
    permits for activities that may pollute the air and water
    without imposing stringent eligibility criteria.
    11
    See n 3.
    15
    sedimentation            control    act,12        the   Legislature      created     a
    pollution control standard that this Court held could be
    enforced through MEPA.              Nemeth, 
    supra at 35
    .
    The Legislature chose to make the SDMA more protective
    of the environment than the soil erosion and sedimentation
    control       act.         As     already      explained,13      the    Legislature
    determined that any mining of critical dunes by ineligible
    entities       is    an    unacceptable        destruction       of    this   natural
    resource.                Hence,     the        majority’s        conclusion      that
    eligibility         is     unrelated      to      conduct   is    premised     on   an
    artificial and hypertechnical bifurcation of the permitting
    process.            When    concluding         that     permit    eligibility       is
    unrelated to conduct, the majority buries its head in the
    sand.
    Its characterization of the eligibility review as an
    “initial inquiry”14 is not based on the language of the
    statute.        The eligibility criteria in MCL 324.63702 are as
    much a condition to engage in critical sand dune mining as
    the requirements in §§ 63704 through 63706.                           The SDMA does
    not enact a hierarchy or order to be followed by those
    12
    MCL 324.9101 et seq.
    13
    Supra beginning at 7.
    14
    Ante at 7.
    16
    reviewing a permit application.                         Unlike this Court’s recent
    decision in Nemeth, here the majority reads “likely to” out
    of the statute.
    The majority argues that an inquiry into the effect on
    the environment of the proposed mining “would be pointless
    unless        the   DEQ     first    determined           that    the       applicant       was
    eligible        for    a    permit      on    the       basis    of    the       applicant’s
    status”.        Ante at 7-8.            We could not agree more.                   It would
    be   pointless         for    the    DEQ      to    review       the    effect         of   the
    proposed        mining      if    the    applicant         were       ineligible        for    a
    permit.        If the applicant is not eligible, no mining will
    occur.        Critical dunes will not be destroyed.
    The     majority      attempts        to    restrict          the    inquiry        into
    Technisand's conduct to consideration of the nature of its
    relationship           to     the       property          at     issue.            This       is
    misleading.15               The   conduct          in     question          is   more       than
    TechniSand’s          “relationship          to     the    mining       property.”            It
    necessarily           encompasses        TechniSand’s            proposal         to    remove
    large        quantities      of   sand       from       designated      critical         dunes
    that would otherwise remain untouched.                           This is the “actual
    15
    See, e.g., ante at 11 n 5. The majority’s implicit
    recognition that [c]ountless entities apply for and receive
    permits for conduct that affects Michigan's natural
    resources,"   ante   at   17,  demonstrates  the   internal
    inconsistency of its argument.
    17
    conduct” that the permit at issue allows and that plaintiff
    alleges is “likely to pollute, impair, or destroy” critical
    dunes under MEPA.       MCL 324.1703(1).            Because the critical
    dunes    could   not   have   been    mined    by    TechniSand   at   all
    without the erroneous eligibility determination, plaintiff
    should be allowed to pursue its MEPA cause of action.
    Statutory provisions must be read in the context of
    the entire act so as to produce a harmonious whole. Macomb
    Co Prosecutor v Murphy, 
    464 Mich 149
    , 159; 627 NW2d 247
    (2001).     Subsections a and b of § 63702(1) must be read
    together    because    of   their    juxtaposition.        Subsection    b
    applies when the permit holder seeks to expand the permit
    to include adjacent land that contains a critical dune area
    that it owned before July 5, 1989.             In contrast, subsection
    a applies to the amendment or renewal of a permit that
    already authorizes mining in a particular area.
    The permit issued to TechniSand authorized mining only
    in the noncritical dune areas.             TechniSand had to apply for
    a permit amendment to add the adjacent critical dune areas
    to its permit.         Therefore, subsection b applies to this
    case.      However, TechniSand did not own the land or the
    rights to mine the sand before 1989 as required by the
    statute.     Therefore, it could not have obtained the permit
    18
    amendment and could not have engaged in any critical sand
    dune mining.
    TechniSand’s         environmental                impact     statement16
    acknowledged that mining the critical dunes at issue would
    “significantly impair the environment and would permanently
    destroy       critical     dune.”      
    253 Mich App 269
    .    Witnesses
    testified from the statement that the mining will change
    “the nature of the result in the environment . . . for
    hundreds of years”17 and a “large percent of the critical
    dune will be removed.”18             Plaintiff’s expert testified that
    “The critical dune will be gone.”19
    Nonetheless,       the      majority    holds        that    the     DEQ’s
    determination that TechniSand is eligible to mine critical
    dunes        is   unrelated      to     whether           TechniSand’s      mining
    activities        will   pollute,     impair,        or    destroy   a     natural
    16
    The majority criticizes me for citing a document
    “not in the record.” Ante at 17. However, it was Exhibit
    21 at trial, and witnesses read from it. See Trial Tr at
    122, 582, 785, and 932. Plaintiff’s brief on appeal in the
    Court of Appeals quoted it at p 6.    The record on appeal
    includes all original papers filed in the courts below.
    MCR 7.311(A).     Plaintiff included an excerpt in the
    appendix (p 14b) to its brief on oral argument before this
    Court. See MCR 7.308.
    17
    Trial Tr at 935.
    18
    Id. at 785.
    19
    Id. at 122.
    19
    resource.       Thus, it concludes that plaintiff cannot rely on
    MEPA to challenge the permit that has been issued.                                    The
    majority’s        reasoning       undermines            the        critical         dunes
    protections       in   the    SDMA,     the    intent        of    MEPA,      and    this
    Court’s earlier MEPA decisions.
    Plaintiff is not required to challenge issuance of the
    permit     as    an    administrative          decision       under       either      the
    Administrative         Procedures        Act      (APA)           or    the     Revised
    Judicature       Act   (RJA).         The      MEPA     is    “supplementary           to
    existing administrative and regulatory procedures provided
    by law.”        MCL 324.1706.     It was intended to create a common
    law of environmental protection.                  Ray at 306.             It does not
    require that a plaintiff exhaust administrative remedies.
    MCL   324.1701(1).           Accordingly,         the    statutory           period    of
    limitations       of   neither     the      APA    nor       the       RJA    apply    to
    plaintiff’s        MEPA      claim.20          Plaintiff’s             challenge       to
    Technisand’s permit under the MEPA is not time-barred.
    The DEQ does not dispute that TechniSand is ineligible
    for   a    permit.        Recognizing       plaintiff’s           claim      under    the
    20
    The MEPA itself imposes no statutory period of
    limitations, but equitable claims under the Natural
    Resources and Environmental Protection Act, which houses
    MEPA, have been held subject to the six-year statutory
    period of MCL 600.5813.    Attorney General v Harkins, 
    257 Mich App 564
    , 571; 669 NW2d 296 (2003).
    20
    environmental protection act expresses no disrespect for an
    administrative agency’s decision.                  The majority abdicates
    its    responsibility        by    refusing    to    review     this    permit
    eligibility determination under MEPA.21
    Conclusion
    The majority's decision today wrongly insulates Sand
    Dune    Mining   Act    permit       eligibility     determinations        from
    judicial review.       The decision to issue a sand dune mining
    permit      pursuant    to     the     SDMA    inherently       includes     an
    environmental component.             I would hold that issuance of the
    permit in this case can be challenged under the Michigan
    environmental protection act.
    The Legislature intended the act to apply to permit
    determinations.             Application       of    the   act    to     permit
    determinations         is         entirely     consistent        with       the
    Legislature’s intent to stringently preserve Great Lakes
    sand dunes against degradation and to protect the integrity
    21
    The majority cites Oscoda Chapter of PBB Action
    Comm, Inc v Dep’t of Natural Resources, 
    403 Mich 215
    , 233;
    268 NW2d 240 (1978) to support its finality argument. But
    its quotation from the case is taken out of context and is
    from an opinion that did not garner a majority of votes.
    The statement addressed the court’s authority to consider
    feasible and prudent alternatives to proposed conduct, an
    issue entirely unrelated to the majority’s decision that
    this permit challenge under MEPA is time-barred.
    21
    of that environment.       The majority’s reasoning frustrates
    that intent.
    Plaintiff's   cause    is   not   barred   by   the   statutory
    limitations periods of the APA and the RJA.           The Court of
    Appeals correctly remanded the case for entry of an order
    granting summary disposition for plaintiff.           Its decision
    should be affirmed.
    Because the majority ignores both the reality of the
    permitting process and the Legislature’s intent to protect
    critical dune areas from destruction, I must dissent.
    Marilyn Kelly
    Michael F. Cavanagh
    Elizabeth A. Weaver
    22