Van Buren Charter Township v. Visteon Corporation , 923 N.W.2d 266 ( 2019 )


Menu:
  • Order                                                                         Michigan Supreme Court
    Lansing, Michigan
    March 8, 2019                                                                    Bridget M. McCormack,
    Chief Justice
    156018                                                                                David F. Viviano,
    Chief Justice Pro Tem
    Stephen J. Markman
    VAN BUREN CHARTER TOWNSHIP,                                                              Brian K. Zahra
    Plaintiff-Appellant,                                                      Richard H. Bernstein
    Elizabeth T. Clement
    v                                                        SC: 156018                Megan K. Cavanagh,
    Justices
    COA: 331789
    Wayne CC: 15-008778-CK
    VISTEON CORPORATION,
    Defendant-Appellee.
    _________________________________________/
    On October 9, 2018, the Court heard oral argument on the application for leave to
    appeal the May 16, 2017 judgment of the Court of Appeals. On order of the Court, the
    application is again considered, and it is DENIED, there being no majority in favor of
    granting leave to appeal or taking other action.
    VIVIANO, J. (dissenting).
    I respectfully dissent from the Court’s order denying leave to appeal. I believe
    that the circuit court and the Court of Appeals erred in holding that plaintiff’s declaratory
    judgment claim was not ripe. The Court of Appeals then proceeded to determine whether
    the parties had any present rights or obligations under their settlement agreement, even
    though such a determination was not necessary to the Court’s ripeness analysis.
    Regardless, I believe the Court of Appeals further erred by concluding that the parties
    had no present rights or obligations under the settlement agreement. Accordingly, I
    would vacate Part (III)(A) of the Court of Appeals’ opinion and remand to the trial court
    for further proceedings.
    I. FACTS AND PROCEDURAL HISTORY
    In 2002, defendant Visteon Corporation entered into discussions with plaintiff Van
    Buren Charter Township about the possibility of locating its national headquarters in the
    Township. Specifically, defendant discussed building its headquarters in plaintiff’s Local
    Development Finance Authority District (LDFA District). In 2003, plaintiff issued over
    $28 million in bonds to assist in the construction of defendant’s headquarters, known as
    “Visteon Village.” Plaintiff projected that property-tax revenue from the LDFA District
    would cover the costs of bond issuance.
    By 2006, tax revenues from the LDFA District were lower than projected, so
    plaintiff issued new bonds in order to advance refund a portion of the original bonds.
    This allowed plaintiff more time to pay the principal on the original bonds. As a result,
    plaintiff was able to temporarily avoid a shortfall, i.e. not having sufficient funds to make
    the bond payments.
    2
    Then, in 2009, defendant filed for bankruptcy. Plaintiff filed an unsecured claim
    to recover unpaid amounts from earlier tax abatement agreements. In 2010, the parties
    entered into a settlement agreement, which provided that plaintiff would significantly
    lower Visteon Village’s assessed taxable value. In exchange, defendant agreed to pay
    $2.2 million toward plaintiff’s claimed amount and to not object to the remainder of
    plaintiff’s unsecured claim. 1 The settlement agreement also contained the following
    provision, the meaning of which is now in dispute:
    Section 3. Bond Payments
    Visteon acknowledges that the Township assisted Visteon in the
    construction of the Village through the issuance by the Township of certain
    bonds supported by the full faith and credit of the Township, the proceeds
    of which were used to help construct the Village. To the extent that the
    property tax payments made by Visteon to the Township, including
    payments made by Visteon to the Township pursuant to Section 2.2, are
    inadequate to permit the Township to meet its payment obligations with
    respect to that portion of the bonds that were used to help fund the Village,
    Visteon hereby agrees to negotiate with the Township in good faith to
    determine the amount of the shortfall with respect to those bonds and make
    a non-tax payment, payment in-lieu-of tax, (PILOT) to the Township to
    assist the Township in making timely payments on the bonds.
    Visteon emerged from bankruptcy later that year.
    In 2013, plaintiff retained Public Financial Management (PFM) to conduct a cash-
    flow analysis to determine plaintiff’s ability to pay on the bonds. In its report, PFM
    predicted that a shortfall ranging from $23.7 million to $36.4 million would occur
    sometime between 2017 and 2018. 2 Based on the report, plaintiff demanded that
    defendant enter into negotiations to determine defendant’s payment obligations under the
    agreement with respect to the projected shortfall. Defendant met with plaintiff but argued
    that it had no obligation to negotiate until plaintiff experienced an actual shortfall and,
    even in the event of a shortfall, defendant argued that it may not owe plaintiff any amount
    under the contract.
    Plaintiff filed suit, seeking both a declaratory judgment and damages for breach of
    contract. As to the declaratory judgment claim, plaintiff asked that the court “adjudicate
    the Parties’ rights and obligations under the Settlement Agreement” and “enter a
    1
    Plaintiff subsequently sold the unsecured claim for approximately $5.7 million.
    2
    Because plaintiff used the payments made by defendant pursuant to the settlement
    agreement, as well as the funds obtained by the sale of the unsecured claim, to pay a
    portion of the interest on the bonds, the shortfall is now projected to occur in 2019.
    3
    declaration that Visteon is responsible for payment of any shortfall . . . .” As to the
    breach of contract claim, plaintiff asserted that defendant breached the agreement by “(i)
    refusing to negotiate the amount of the Bond debt service shortfall in good faith and (ii)
    failing to provide – or commit to provide – the Township with funds to pay for any
    shortfall with the Bond debt service payments.” Plaintiff also claimed anticipatory
    repudiation, pointing to certain statements made by defendant indicating that defendant
    did not believe it owed plaintiff anything under the agreement.
    Defendant filed a motion for summary disposition under MCR 2.116(C)(4) and
    (C)(8), arguing that plaintiff’s claims were not ripe. Defendant argued that plaintiff’s
    claims rested upon a hypothetical future shortfall; thus, no actual controversy presently
    existed. The trial court agreed, granting summary disposition in defendant’s favor. On
    the record, the trial court explained its reasoning as follows:
    The Court agrees with the defendant that this case epitomizes why
    the ripeness doctrine exists, mainly to prevent courts from becoming
    prematurely embroiled in complex disputes involving hypothetical and
    contingent facts when, especially when the projected [shortfall] is estimated
    three years from now.
    The Court of Appeals affirmed in a published opinion. In finding plaintiff’s
    declaratory judgment claim unripe, the court explained:
    According to the plain language of the contract, defendant is
    obligated to “negotiate with [plaintiff] in good faith to determine the
    amount of the shortfall,” but only “[t]o the extent that the property tax
    payments made by [defendant]” are “inadequate to permit [plaintiff] to
    meet its payment obligations” and only “with respect to that portion of the
    bonds that were used to help fund the Village.” Thereafter, defendant is
    obligated to “make a non-tax payment” in order to “assist” plaintiff in
    making “timely” payments on those bonds. In each case, the tense of the
    verb is present, not future. No reasonable person reading this provision
    could find it ambiguous or conclude that defendant is obligated to engage in
    negotiations before the shortfall. Indeed, the contract admits of but one
    interpretation, in which the occurrence of the shortfall is a condition
    precedent to defendant’s obligation to perform, and defendant is not
    obligated to do anything until after plaintiff has experienced a shortfall. In
    fact, defendant is not obligated to perform until after two conditions have
    been met: (1) a shortfall has occurred, and (2) property taxes paid by
    defendant are inadequate for plaintiff to pay that portion of the bonds that
    was used to fund the Village. This second condition cannot be met until
    after the shortfall has occurred and the parties have determined the amount
    due.
    4
    Contrary to plaintiff’s assertion on appeal, the requirement that
    defendant negotiate in good faith to “determine the amount of the shortfall”
    does not force the implication that defendant must be required to negotiate
    before the occurrence of a shortfall. Plaintiff forgets that the provision
    contains qualifying language, requiring defendant to negotiate in good faith
    to determine the amount of the shortfall only “with respect to those bonds”
    that were “supported by the full faith and credit of [plaintiff], the proceeds
    of which were used to help construct the Village.” Defendant is therefore
    clearly obligated to engage in negotiations once a shortfall occurs, to
    determine which part of the shortfall can be attributed to bonds it is
    obligated to assist plaintiff to pay.[3]
    Similarly, regarding plaintiff’s breach of contract claim, the Court of Appeals found the
    claim unripe because “defendant could not have breached its contract by failing to
    perform before the time of performance has even arrived.” 4 Further, the Court of
    Appeals explained that, “at least at this time, plaintiff’s alleged damages are conjectural,
    speculative, and clearly ‘dependent upon the chances of business or other
    contingencies.’ ” 5
    Following plaintiff’s appeal to our Court, we ordered oral argument on the
    application, directing the parties to address
    whether the Court of Appeals: (1) properly determined that a declaratory
    judgment was not ripe under MCR 2.605; and (2) properly interpreted the
    contract to determine that “defendant is not obligated to perform [under the
    contract] until . . . a shortfall has occurred, and . . . property taxes paid by
    defendant are inadequate for plaintiff to pay that portion of the bonds that
    was used to fund the Village.”[6]
    II. ANALYSIS
    A. RIPENESS OF PLAINTIFF’S DECLARATORY JUDGMENT CLAIM
    Declaratory judgment in Michigan is governed by MCR 2.605, which provides in
    relevant part, “In a case of actual controversy within its jurisdiction, a Michigan court of
    record may declare the rights and other legal relations of an interested party seeking a
    3
    Van Buren Charter Twp v Visteon Corp, 
    319 Mich. App. 538
    , 548-549 (2016).
    4
    
    Id. at 554.
    5
    
    Id. at 552,
    quoting Doe v Henry Ford Health Sys, 
    308 Mich. App. 592
    , 601 (2014).
    6
    Van Buren Charter Twp v Visteon Corp, 
    501 Mich. 1069
    (2018).
    5
    declaratory judgment, whether or not other relief is or could be sought or granted.” 7
    Regarding the purpose of the declaratory judgment rule, our Court has stated, “The
    declaratory judgment rule was intended and has been liberally construed to provide a
    broad, flexible remedy with a view to making the courts more accessible to the people.” 8
    “One great purpose is to enable parties to have their differences authoritatively settled in
    advance of any claimed invasion of rights, that they may guide their actions accordingly
    and often may be able to keep them within lawful bounds . . . .” 9 As noted by one
    scholar, “[p]robably one of the most useful functions of the declaratory judgment in
    preventing litigation lies in the fact that it enables parties to obtain in case of doubt and in
    advance of the necessity of acting upon their own interpretation of their obligations, with
    the resulting invitation of a lawsuit, an authoritative judicial interpretation of their mutual
    rights, powers, duties, etc., under written instruments.” 10
    That a declaratory judgment must address an “actual controversy” is central to the
    legitimacy of the device. In Washington-Detroit Theatre Co v Moore, our Court
    considered the Legislature’s second attempt to enact a declaratory judgment act that
    satisfied constitutional standards. 11 We had found the prior declaratory judgment act
    unconstitutional, explaining that “it requires that the time of the court shall be taken, not
    in the determination of actual controversies where rights have been invaded and wrongs
    have been done, but in the giving of advice to all who may seek it.” 12 The new act,
    however, conditioned that a declaratory judgment was only available in “ ‘cases of actual
    7
    MCR 2.605(A)(1).
    8
    Shavers v Attorney General, 
    402 Mich. 554
    , 588 (1978).
    9
    Merkel v Long, 
    368 Mich. 1
    , 13 (1962), quoting Sigal v Wise, 114 Conn 297, 301-302
    (1932).
    10
    Borchard, The Declaratory Judgment—A Needed Procedural Reform (Washington,
    DC: United States Government Printing Office, 1919), p 45. See also 11 Williston on
    Contracts § 30:2 (4th ed), p 36 (“A frequently employed means of demonstrating in an
    authoritative manner the intent of the parties to a contract, either for the purpose of
    establishing rights or the nonexistence of liabilities, is the petition for declaratory
    judgment.”).
    11
    Washington-Detroit Theatre Co v Moore, 
    249 Mich. 673
    (1930). This act, 
    1929 PA 36
    ,
    was codified into the Judicature Act and governed declaratory judgment actions in
    Michigan until it was repealed by the Revised Judicature Act, 
    1961 PA 236
    . In the same
    period, our Court adopted a rule governing declaratory judgment actions, GCR 1963,
    521, now MCR 2.605. Thus, declaratory judgment actions in Michigan are no longer
    governed by statute, but instead are governed by court rule.
    12
    Anway v Grand Rapid R Co, 
    211 Mich. 592
    , 606 (1920).
    6
    controversies’ ” and was therefore constitutional. 13
    In order to satisfy the “actual controversy” requirement, a plaintiff’s claim must be
    justiciable. 14 Thus, the “actual controversy” requirement contained in the court rule
    incorporates the concepts of standing, mootness, and ripeness. 15 Like in an ordinary
    action, ripeness in the declaratory judgment context requires a present legal controversy,
    not one that is merely hypothetical or anticipated in the future. 16 Unlike an ordinary
    action, however, in a declaratory action “a court is not precluded from reaching issues
    before actual injuries or losses have occurred.” 17 Indeed, “the basic purpose of a
    declaratory judgment act is to provide for declaratory judgments without awaiting a
    breach of existing rights.” 18
    13
    Washington-Detroit Theatre 
    Co, 249 Mich. at 676
    , quoting 
    1929 PA 36
    . Anway and
    Washington-Detroit Theatre Co have been widely cited by federal courts and our sister
    state courts in deciding the constitutionality of declaratory judgment acts within their
    jurisdictions.
    14
    See 
    Shavers, 402 Mich. at 589
    (“[A] plaintiff must allege and prove an actual
    justiciable controversy.”).
    15
    See Associated Builders and Contractors v Dep’t of Consumer & Industry Servs Dir,
    
    472 Mich. 117
    , 125 (2005) (“Moreover, the rule requires that there be ‘a case of actual
    controversy’ and that a party seeking a declaratory judgment be an ‘interested party,’
    thereby incorporating traditional restrictions on justiciability such as standing, ripeness,
    and mootness.”), overruled on other grounds by Lansing Sch Ed Ass’n v Lansing Bd of
    Ed, 
    487 Mich. 349
    (2010).
    16
    Borchard, Declaratory Judgments (1934), p 40 (“When the complaint on these tests is
    considered premature, the dismissal may be explained by any one of a series of labels,
    e.g., that there is as yet no ‘controversy,’ that the issue is hypothetical, that the result
    would be only an advisory opinion, etc.”); 26 CJS, Declaratory Judgment, § 28, p 66
    (“[A] controversy is justiciable, such that a declaratory judgment action may be
    maintained, when present legal rights are affected, not when a controversy is merely
    anticipated.”).
    17
    
    Shavers, 402 Mich. at 589
    . See also 26 CJS, Declaratory Judgment, § 28, p 67 (“A
    party should not be forced to wait until the event giving rise to the claim occurs before a
    court may determine the party’s rights and obligations in a declaratory judgment
    action.”).
    18
    
    Id. See also
    9A Michigan Pleading & Practice (2d ed), § 69:8, p 390-391 (“[A]n actual
    present controversy, justifying a declaratory judgment, is present where uncertainties and
    controversies arise between interested parties about what their respective rights will be
    when those rights accrue or become vested, and it is necessary to have those rights
    determined at the present time to avoid needless hazards or possible losses in the future.
    In these situations, courts are not precluded from reaching issues before actual injuries or
    7
    In this case, plaintiff’s request for a declaratory judgment involves a
    present legal controversy—it is a dispute over the parties’ present rights
    and obligations under Section 3 of the 2010 settlement agreement. In
    particular, plaintiff argues that defendant has a present duty under the
    settlement agreement to negotiate with plaintiff to determine the amount of
    the projected shortfall and to make a payment to the township to assist it in
    making timely payments on the bonds; and defendant claims that it has no
    present duty under the agreement. Thus, even if plaintiff has not yet shown
    an injury, plaintiff has presented an “actual controversy” within the
    meaning of MCR 2.605. 19
    It may be true, as defendant argues, that determining the exact
    amount of defendant’s liability is not possible at this time. 20 This is not
    relevant, however, to plaintiff’s declaratory judgment claim. Plaintiff’s
    declaratory judgment claim does not seek a specific amount of damages,
    but instead seeks a declaration of the parties’ present obligations under the
    losses have occurred.”).
    19
    Even if the Court of Appeals was correct that defendant has no obligations under the
    settlement agreement until after a shortfall occurs, and that therefore plaintiff’s claim
    only involved future rights and obligations, its conclusion that plaintiff’s claim was
    unripe would still be on shaky ground. It is true that, generally, a declaratory judgment
    must address “the existing law on an existing state of facts.” Borchard, Declaratory
    Judgments, p 40. But this is not an inflexible rule—a declaratory judgment may address
    parties’ rights under future, or even contingent, events or circumstances. 
    Id. at 44
    (“[C]ourts have been less inclined to refuse declarations where they were convinced that
    the future event was certain or practically certain to occur, and that a useful purpose
    could be served, whereas theretofore they were disposed to ask for more accrued facts as
    a condition of adjudication.”). Indeed, as we have previously recognized, “ ‘to carry out
    the purposes intended to be served by [declaratory] judgments, it is sometimes necessary
    to determine rights which will arise or become complete only in the contingency of some
    future happening.’ ” 
    Merkel, 368 Mich. at 13
    , quoting Sigal, 114 Conn at 301-302.
    “Courts continually declare rights which have not become fixed under an existing state of
    facts, but are prospective only; they may not, however, be so remote and speculative as to
    be hypothetical and abstract.” 
    Merkel, 368 Mich. at 13
    , quoting Borchard, Declaratory
    Judgments (2d ed), pp 422-424. Thus, the Court of Appeals erred by assuming that, if
    plaintiff’s claim involved future rights and obligations, it could not be ripe.
    20
    See Appellee’s Answer Brief at 27 (“But even if the Township is right that a shortfall
    in some amount is “certain” to occur at some point in the future, when that might happen
    is simply unknown. More importantly, there is no way to know what the amount of any
    shortfall might be.”).
    8
    settlement agreement. 21 To the extent that the Court of Appeals found
    plaintiff’s declaratory judgment claim unripe because the Court could not
    determine the exact amount of defendant’s liability at this time, the Court
    of Appeals erred in this regard as well. 22
    For these reasons, plaintiff’s claim as to the parties’ rights and obligations under
    the agreement is ripe for adjudication.
    B. THE COURT OF APPEALS’ INTERPRETATION OF THE SETTLEMENT
    AGREEMENT
    Had the Court of Appeals merely held that plaintiff’s claim was not ripe, my
    analysis would end here. However, the Court of Appeals proceeded to partially
    determine the parties’ rights and obligations under the settlement agreement, stating as
    follows:
    [T]he contract admits of but one interpretation, in which the occurrence of
    the shortfall is a condition precedent to defendant’s obligation to perform,
    and defendant is not obligated to do anything until after plaintiff has
    experienced a shortfall. In fact, defendant is not obligated to perform until
    after two conditions have been met: (1) a shortfall has occurred, and (2)
    property taxes paid by defendant are inadequate for plaintiff to pay that
    portion of the bonds that was used to fund the Village. This second
    condition cannot be met until after the shortfall has occurred and the parties
    have determined the amount due.[23]
    21
    It is true that plaintiff’s complaint sought a declaration that defendant was obligated to
    pay the full amount of any shortfall.               See Plaintiff’s Complaint at 14-15
    (“WHEREFORE, the Township seeks a declaratory judgment pursuant to MCR 2.605 to
    adjudicate the Parties’ rights and obligations under the Settlement Agreement, and the
    Township respectfully requests the Court enter a declaration that Visteon is responsible
    for payment of any shortfall in the Bond debt service payments identified in this
    Complaint, as well as any other relief as justice and fairness require.”). Even this,
    however, is not a request for the court to determine the exact amount of a shortfall.
    Instead, plaintiff is seeking an interpretation of the settlement agreement that would
    require defendant to pay the full amount of the shortfall, whatever that amount might be.
    22
    While the impossibility of determining plaintiff’s actual damages at this time does not
    render plaintiff’s declaratory judgment claim unripe, it does affect plaintiff’s breach of
    contract claim, which requires plaintiff to make a showing as to damages. Accordingly, I
    would not disturb the Court of Appeals’ holding as to plaintiff’s breach of contract claim.
    23
    Van 
    Buren, 319 Mich. App. at 548
    .
    9
    In so holding, the Court of Appeals essentially entered a partial declaratory judgment
    determining when defendant’s obligations under the contract are triggered. Having
    concluded that plaintiff’s declaratory judgment claim is ripe for adjudication, I now
    believe it necessary to address the Court of Appeals’ determination that defendant’s
    contractual duties are not triggered until a shortfall has occurred.
    In concluding that defendant has no obligation under the contract until after a
    shortfall has occurred, the Court of Appeals relied primarily on the verb tense used in the
    settlement agreement, explaining:
    [T]he tense of the verb[s] is present, not future. No reasonable person
    reading this provision could find it ambiguous or conclude that defendant is
    obligated to engage in negotiations before the shortfall. Indeed, the
    contract admits of but one interpretation, in which the occurrence of the
    shortfall is a condition precedent to defendant’s obligation to perform, and
    defendant is not obligated to do anything until after plaintiff has
    experienced a shortfall.[24]
    We have relied on verb tense in the past when interpreting legal texts. 25 We have
    also recognized, however, that verb tense is not always determinative and must be
    considered in the context of the surrounding text. 26 Accordingly, a close inspection of
    the verbs contained within the agreement is necessary to determine whether the Court of
    Appeals is correct that the verb tense is indicative of the timing of defendant’s
    obligations. The agreement uses the following verbs: “To the extent that the property tax
    payments . . . are inadequate to permit the Township to meet its payment obligations . . . ,
    Visteon hereby agrees to negotiate with the Township in good faith to determine the
    amount of the shortfall with respect to those bonds and make a non-tax payment . . . to
    the Township to assist the Township in making timely payments on the bonds.”
    (Emphasis added.) 27 With two exceptions—“are” and “agrees”—each of the verbs
    identified above is in the infinitive form. 28 Unlike finite verbs, infinitives primarily
    24
    
    Id. 25 See,
    e.g., City of Coldwater v Consumers Energy Co, 
    500 Mich. 158
    , 176 (2017)
    (noting that the phrase “already receiving” within MCL 124.3(2) is a present participle
    and that “[t]he verb tense is meaningful here because it indicates a present-tense lens”).
    26
    See Rock v Crocker, 
    499 Mich. 247
    , 263 (2016) (recognizing that “the Legislature
    deviated from the general rules of grammar in MCL 600.2169(1)(a) by using the present
    tense when referring to an event that had already occurred”).
    27
    “Making” is a gerund in this context, which functions as a noun. See The Chicago
    Manual of Style (16th ed), p 233.
    28
    
    Id. at 232
    (“An infinitive verb, also called the verb’s root or stem, is a verb that in its
    10
    function as nouns, adjectives, or adverbs, 29 and are widely considered to have no tense. 30
    Additionally, when an infinitive is paired with a present tense finite verb, such as “agrees
    to negotiate,” the result can indicate either present or future action. 31 Thus, while
    “agrees” is in present tense, because it is paired with the infinitive it may refer to either
    present or future obligations.
    We are left, then, to determine whether the agreement’s single remaining use of
    present tense in the noninfinitive form—“are inadequate”—is sufficient to conclude that
    defendant’s obligations under the agreement come into effect at the time of the shortfall.
    The Court of Appeals’ interpretation of the agreement assumed that the property tax
    payments will become “inadequate” at the time that the shortfall occurs. This is not the
    only possible reading, however. The agreement may, alternatively, consider the
    payments “inadequate” when a shortfall is projected to occur. Under this reading, the tax
    payments are presently inadequate because they will not allow plaintiff to continue
    making timely payments. Because both of these readings are grammatically acceptable, I
    do not think the use of present tense for “are inadequate” necessarily leads to the Court of
    Appeals’ conclusion.
    Accordingly, we must look to the remainder of the provision to determine the
    appropriate interpretation. As plaintiff points out, the agreement requires that defendant
    “make a non-tax payment . . . to assist [plaintiff] in making timely payments.” “Timely”
    is defined as “coming early or at the right time.” 32 Suffice it to say that, if defendant is
    principal uninflected form may be preceded by to {to dance} {to dive}.”).
    29
    See Vitto, Grammar by Diagram: Understanding English Grammar Through
    Traditional Sentence Diagramming (2d ed), p 219.
    30
    See Garner, Garner’s Modern English Usage (4th ed), p 853 (“An infinitive is the
    tenseless form of a verb preceded by to, such as to dismiss or to modify.”). But see
    Stowell, The Tense of Infinitives, 13 Linguistic Inquiry 561 (1982) (discussing infinitive
    tenses). Moreover, the infinitives here clearly serve functions unrelated to the timing of
    defendant’s obligations. “[T]o permit,” “to determine,” and “to assist” all function as
    adverbs, denoting the purpose of defendant’s agreed-to actions. See Vitto, pp 222-224.
    Similarly, “to meet,” “to negotiate,” and “[to] make” are each nouns, functioning as the
    direct objects of “permit” and “agrees.” 
    Id. at 221.
    Thus, each of the infinitives in the
    agreement is functioning not as a verb, whose tense could indicate the timing of
    defendant’s obligations, but instead as either an adverb or a noun.
    31
    See Curme, College English Grammar (Richmond: Johnson Publishing Company,
    1925), p 301 (“Here the present tense indicates time contemporaneous or future with
    reference to that of the principal verb: I wish to go at once. I intend to write a line or two
    to her soon. Yesterday I intended to write a line to her, but forgot it.”).
    32
    Merriam-Webster’s Collegiate Dictionary (11th ed).
    11
    not obligated to even begin negotiations until after a shortfall occurs, then plaintiff’s
    payments to the bond holders will not be “coming early or at the right time.” The Court
    of Appeals sweeps this concern aside, concluding that the agreement is “perhaps
    inartfully worded.” 33 However, I believe the meaning is clear: defendant is required to
    “make a non-tax payment . . . to [plaintiff] to assist [plaintiff] in making timely
    payments”—i.e., to make whatever payment is owed, if any, before the shortfall occurs.
    The agreement also requires that defendant “negotiate with the Township in good
    faith to determine the amount of the shortfall with respect to those bonds [that were used
    to help fund the Village].” Plaintiff argues that this clause requires defendant to negotiate
    with plaintiff before a projected shortfall to estimate the amount of the shortfall.
    Defendant, on the other hand, argues that this clause only requires defendant to negotiate
    with plaintiff at the time of the shortfall to determine the proportion of the shortfall that
    correlates with the bonds that were issued to assist with the construction of Visteon
    Village. The word “amount,” however, refers not to a proportion, but to a “quantity.” 34
    Thus, under the agreement, the parties must negotiate the “quantity” of the shortfall, not
    merely the percentage of the shortfall correlating to the relevant bonds. Because the
    agreement requires the parties to negotiate a quantity, I believe the agreement
    contemplates negotiations before a shortfall has occurred. Otherwise, as plaintiff argues,
    the parties would have nothing to negotiate—the amount would already be determined.
    For the reasons stated above, I believe the parties’ agreement clearly contemplates
    that defendant has an obligation prior to the occurrence of a shortfall: (1) to negotiate
    with plaintiff to determine the amount of the projected shortfall, and (2) to make
    whatever payment it may owe to plaintiff to assist it in making timely payments on the
    bonds. Determining the nature and extent of defendant’s obligations in the first instance
    is a task properly left to the trial court.
    III. CONCLUSION
    I believe the Court of Appeals erred in its published opinion by finding plaintiff’s
    33
    Van Buren Charter 
    Twp, 319 Mich. App. at 547
    .
    34
    See Merriam-Webster’s Collegiate Dictionary (defining “amount” as “the total number
    or quantity” and “the quantity at hand or under consideration”).
    12
    declaratory judgment action unripe and in its determination that the parties had no present
    rights or obligations under the settlement agreement. Accordingly, I would vacate Part
    (III)(A) of the Court of Appeals’ opinion and remand to the trial court for further
    proceedings.
    MCCORMACK, C.J., joins the statement of VIVIANO, J.
    BERNSTEIN, J., would reverse the judgment of the Court of Appeals.
    CAVANAGH, J., did not participate in the disposition of this case because the Court
    considered it before she assumed office.
    I, Larry S. Royster, Clerk of the Michigan Supreme Court, certify that the
    foregoing is a true and complete copy of the order entered at the direction of the Court.
    March 8, 2019
    p0305
    Clerk
    

Document Info

Docket Number: SC: 156018; COA: 331789

Citation Numbers: 923 N.W.2d 266

Judges: Viviano

Filed Date: 3/8/2019

Precedential Status: Precedential

Modified Date: 10/19/2024