Attorney General v. Polyone Corp ( 2018 )


Menu:
  •                          STATE OF MICHIGAN
    COURT OF APPEALS
    ATTORNEY GENERAL and DEPARTMENT OF                               UNPUBLISHED
    ENVIRONMENTAL QUALITY,                                           May 31, 2018
    Plaintiffs-Appellants,
    v                                                                No. 339754
    Ingham Circuit Court
    POLYONE CORPORATION, successor to M. A.                          LC No. 94-077813-CE
    HANNA COMPANY,
    Defendant-Appellee.
    Before: MURRAY, C.J., and SERVITTO and BOONSTRA, JJ.
    PER CURIAM.
    Plaintiffs, Attorney General and the Department of Environmental Quality (MDEQ),
    appeal as of right an opinion and order granting defendant summary disposition under MCR
    2.116(C)(10) (no genuine issue of material fact). They also challenge an opinion and order
    granting defendant PolyOne Corporation’s request to be reimbursed for the costs of operating a
    disputed water treatment system. We affirm.
    I. FACTS
    This case concerns an upwelling of acidic water from the Dober Mine Complex in Iron
    County, which was the subject of a 1998 consent decree between plaintiffs and M. A. Hanna
    Company, to whom defendant is the successor in interest. Among other things, the consent
    decree required M. A. Hanna and its successors to renew an NPDES1 permit and operate an
    existing remedial water treatment system at the mine. The decree provided that, after defendant
    had completed the decree’s requirements and had been issued “a final NPDES Permit,”
    defendant would submit a notice of completion to the MDEQ, which would decide whether
    defendant had completed the decree’s requirements. If the MDEQ determined that defendant
    1
    NPDES stands for “National Pollutant Discharge Elimination System,” a type of permit issued
    through the MDEQ as part of a state-administered program under the Federal Water Pollution
    Control Act. Mich Farm Bureau v Dep’t of Environmental Quality, 
    292 Mich. App. 106
    , 108-
    109; 807 NW2d 866 (2011).
    -1-
    had done so, it would issue a Certificate of Completion. The Certificate of Completion would
    end defendant’s obligations under the consent decree.
    On July 16, 2012, defendant sent the MDEQ a Notification of Completion and a draft
    final report. Ultimately, on December 6, 2012, the MDEQ issued defendant a Certificate of
    Completion. In its letter, the MDEQ stated that defendant would still be required to operate and
    maintain the NPDES permit and maintain the water treatment system at the Dober Mine
    Complex. This created a dispute between the parties regarding whether defendant had an
    obligation independent of the consent decree to do so.
    On May 14, 2013, the MDEQ sent defendant a letter revoking the Certificate of
    Completion. Defendant responded by filing a petition for declaratory relief with the circuit
    court, asking the court to determine that defendant had no independent obligations to operate and
    maintain the water treatment system and that plaintiffs could not revoke the completion
    certificate. The circuit court ultimately agreed with defendant and ordered plaintiffs to pay
    defendant the costs of operating the system after December 2012, pursuant to stipulations
    between the parties.
    II. CONTINUING OBLIGATIONS
    Plaintiffs argue that the lower court erred by determining that the consent decree did not
    require defendant to continue operating the existing water remediation system after the MDEQ
    issued the Certificate of Completion. We conclude that plaintiffs’ position is without merit
    because the consent decree did not provide for ongoing maintenance obligations.
    This Court reviews de novo the trial court’s decision on a motion for summary
    disposition. Maiden v Rozwood, 
    461 Mich. 109
    , 118; 597 NW2d 817 (1999). A party is entitled
    to summary disposition under MCR 2.116(C)(10) if “there is no genuine issue as to any material
    fact, and the moving party is entitled to judgment . . . as a matter of law.” A genuine issue of
    material fact exists if, when viewing the record in the light most favorable to the nonmoving
    party, reasonable minds could differ on the issue. Gorman v American Honda Motor Co, Inc,
    
    302 Mich. App. 113
    , 116; 839 NW2d 223 (2013).
    This Court interprets judgments entered by agreement of the parties in the same manner
    as contracts. Gramer v Gramer, 
    207 Mich. App. 123
    , 125; 523 NW2d 861 (1994). This Court
    reviews de novo the proper interpretation of an unambiguous contract. Klapp v United Ins
    Group Agency, Inc, 
    468 Mich. 459
    , 463; 663 NW2d 447 (2003). This Court also reviews de
    novo the legal effects of contractual clauses. Quality Prods & Concepts Co v Nagel Precision,
    Inc, 
    469 Mich. 362
    , 369; 666 NW2d 251 (2003).
    The goal of contractual interpretation is to honor the parties’ intent and to enforce the
    contract’s plain terms. Davis v LaFontaine Motors, Inc, 
    271 Mich. App. 68
    , 73; 719 NW2d 890
    (2006). This Court discerns the parties’ intent from the contract’s language. 
    Id. If no
    reasonable
    person could dispute the meaning of the contract’s plain language, this Court must enforce that
    language as written. Rory v Continental Ins Co, 
    473 Mich. 457
    , 468; 703 NW2d 23 (2005). We
    construe contractual terms in context, according to their commonly used meanings. Henderson v
    State Farm Fire & Cas Co, 
    460 Mich. 348
    , 354; 596 NW2d 190 (1999). We must interpret a
    -2-
    contract in a way that gives every word, phrase, and clause meaning, and must avoid
    interpretations that render parts of the contract surplusage. 
    Klapp, 468 Mich. at 468
    .
    In this case, § XXVI of the consent decree states: “Upon issuance of the Certificate of
    Completion of Response Activities Performed Pursuant to this Decree, the Defendant’s
    obligations as set forth in this Decree shall terminate, except as otherwise provided herein.”
    Accordingly, unless an ongoing obligation is provided in the decree, defendant’s obligations end
    when a Certificate of Completion is issued.
    Plaintiffs rely on ¶ 4.4 (defining “Existing Remedial System”) and ¶ 4.8 (defining
    “Operation and Maintenance Activities” or “O & M Activities”) of the decree to argue that the
    consent decree provided an ongoing obligation to operate and maintain the existing remedial
    system. Plaintiffs’ argument is not persuasive because these paragraphs are in the “definitions”
    section of the consent decree. Because these paragraphs are only definitions, not terms and
    conditions of the consent decree, they cannot constitute other obligations. Similarly, while § 3 of
    the consent decree states that a general goal of the consent decree is “to operate and maintain the
    Existing Remedial System,” this general statement of goals is not in the area of the decree that
    defines the parties’ obligations.
    Regarding operation and maintenance, the decree provided that defendant had an
    obligation to “implement[] . . . the O&M Activities and sampling required by the current NPDES
    Permit.” (Emphasis added.) However, the then-current permit ended at some point before
    PolyOne renewed the permit on October 1, 2005.2 Because this provision was specifically
    limited to the “current” permit, it would not require defendant to engage in operation and
    maintenance activities past the expiration of that permit. Nowhere else does the decree mention
    any obligations for ongoing operation and maintenance.
    Also contrary to plaintiffs’ position, the consent decree contemplates that plaintiffs may
    bring future actions against defendant regarding “response activities related to the facility” after
    issuing a Certificate of Completion. The decree provides:
    Plaintiffs’ Post-Certification of Completion Reservations: Notwithstanding any
    other provision of this Decree except as provided in Paragraph 21.1(e), the
    Plaintiffs reserve, and this Decree is without prejudice to, the right to institute
    proceedings in this action or in a new action, or to issue an administrative order
    seeking to compel Defendant (1) to perform further response activities relating to
    2
    Plaintiffs argue that defendant’s actions in consistently renewing the NPDES permit and
    engaging in continued maintenance and operation of the facility provided evidence that the
    parties intended defendant’s obligation to extend beyond the current NPDES permit. Extrinsic
    evidence may help the finder of fact determine the meaning of a contract. 
    Klapp, 468 Mich. at 471
    n 13. However, extrinsic evidence of the parties’ intent is only relevant when attempting to
    determine the meaning of an ambiguous contract. 
    Id. at 470.
    The consent decree in this case is
    not ambiguous. We will not look beyond the plain language of the consent decree to determine
    its meaning.
    -3-
    the Facility or (2) to reimburse the State of Michigan for additional costs of
    response if, subsequent to Certificate of Completion of the response activity:
    (a) Conditions at the Facility, previously unknown to the MDEQ, are
    discovered; or
    (b) Information is received, in whole or in part, and these previously
    unknown conditions or this information together with other relevant information
    indicate that the remedial action is not protective of the public health, safety and
    welfare, or the environment. [Emphasis added.]
    The consent decree expressly contemplates that further response activities may be required after
    the decree ends. This phrase would be surplusage if we accepted plaintiffs’ assertion that the
    consent decree obligated defendant to perform ongoing maintenance operations until they were
    no longer required. We decline to interpret the decree in such a fashion.
    Further, the circuit court’s interpretation is consistent with the use of the indefinite article
    “a” in ¶ 25.1 when referring to when plaintiffs could issue a Certificate of Completion. The
    consent decree provides: “Within sixty (60) days after Defendant is issued a final NPDES
    Permit, Defendant shall submit to the MDEQ a Notification of Completion . . . .” (Emphasis
    added.) Because the consent decree refers to “a” final NPDES permit, it does not refer to a
    singular and specific permit. The circuit court’s interpretation was consistent with this paragraph
    because the use of the indefinite article indicates that any of several NPDES permits may be final
    for the purposes of the decree.
    We conclude that the circuit court properly determined that defendant did not have an
    obligation of ongoing maintenance and operation after the termination of the consent decree.
    Reading the decree as a whole, defendant’s obligations to perform ongoing maintenance
    activities — beyond those required by the NPDES permit that was current in 1999 — terminated
    when plaintiffs issued a Certificate of Completion.
    III. REVOCATION
    Plaintiffs argue that the circuit court erred when it determined that they could not revoke
    the Certificate of Completion because an agency has inherent authority to correct a decision that
    was based on mistaken information. Plaintiffs assert that they validly revoked the certificate
    because the decision was based on a mistake about who owned the Dober Mine Complex.
    Because the mistake was not material to whether defendant was entitled to a completion
    certificate, we disagree.
    This Court reviews de novo the scope of an administrative agency’s statutory authority.
    Mich Farm Bureau v Dep’t of Environmental Quality, 
    292 Mich. App. 106
    , 127; 807 NW2d 866
    (2011). An agency acting in the public interest has both the duty and the right to correct its own
    errors. Walter Toebe & Co v Dep’t of State Highways, 
    144 Mich. App. 21
    , 34; 373 NW2d 233
    (1985).
    Presuming that plaintiffs operated under a mistaken belief that defendant owned the
    Dober Mine Complex, this mistake would not entitle plaintiffs to relief in this case because
    -4-
    plaintiffs cannot show that the initial decision to issue the Certificate of Completion was
    erroneous. The consent decree provides as follows regarding issuance of a Certificate of
    Completion:
    Within sixty (60) days after receipt of the Notification of Completion, the
    MDEQ will review the Notification of Completion and will determine whether
    Defendant has completed satisfactorily all requirements of this Decree. Within
    the sixty (60) day period after receipt of the Notification of Completion, MDEQ
    will notify Defendant of its determination as to whether or not Defendant has
    satisfied all requirements of the Decree. If MDEQ has determined that Defendant
    has satisfied all requirements of the Decree, it shall issue a Certification of
    Completion of Response Activities Performed Pursuant to this Decree within the
    sixty (60) day period. If MDEQ has determined that Defendant has not satisfied
    all requirements of the Decree, the letter so advising Defendant shall specify those
    requirements which Defendant has not satisfied. [Emphasis added.]
    The term “shall” is mandatory. Walters v Nadell, 
    481 Mich. 377
    , 383; 751 NW2d 431
    (2008). Thus, this paragraph required the MDEQ to issue a Certificate of Completion if
    defendant had completed the requirements of the consent decree. Nothing in this paragraph, or
    the remainder of the consent decree, requires defendant to continue to own the Dober Mine
    Complex. Because the term “shall” in ¶ 25.2 is mandatory, plaintiffs did not have discretion to
    deny defendant a Certificate of Completion if defendant met the requirements of the consent
    decree, and those requirements do not include ownership. As previously discussed, ongoing
    operation and maintenance is also not a requirement of the parties’ consent decree. Accordingly,
    we conclude that plaintiffs have not shown that their mistake regarding the owner of the mine led
    to an erroneous initial decision. While the circuit court did not explicitly address an agency’s
    inherent authority to correct an error, the court did not err by determining that plaintiffs could not
    revoke the Certificate of Completion.
    IV. COSTS AS DAMAGES
    Plaintiffs argue that the circuit court erred by failing to grant them summary disposition
    on defendant’s claim for damages on the basis of governmental immunity. Plaintiffs’ argument
    is without merit because this case concerns an action arising from a contract and governmental
    immunity applies only to tort-based claims.
    This Court reviews de novo questions concerning the applicability of governmental
    immunity. Moraccini v Sterling Hts, 
    296 Mich. App. 387
    , 391; 822 NW2d 799 (2012).
    Generally, governmental entities are immune from tort liability. Koenig v South Haven, 
    460 Mich. 667
    , 675; 597 NW2d 99 (1999). “However, governmental immunity does not extend to
    contract actions, even when the contract action arises out of the same facts that would support a
    tort action.” 
    Id. A tort
    action arises from an action concerning a contractual obligation only if
    the obligation violates “a legal duty separate and distinct from the contractual obligation.” Fultz
    v Union-Commerce Assoc, 
    470 Mich. 460
    , 467; 683 NW2d 587 (2004) (quotation marks and
    citation omitted).
    -5-
    Plaintiffs argue that defendant’s claim used language similar to language used for a tort
    action. However, the question is not what language defendant used, but whether this case arose
    from a separate and distinct legal duty outside the consent decree. In this case, defendant alleged
    that plaintiffs breached the parties’ consent agreement by purporting to revoke its Certificate of
    Completion. Defendant’s costs were incurred from its operation and maintenance of the water
    remediation at the Dober Mine Complex under the NPDES permit after plaintiffs issued the
    certificate. The claims did not arise from separate, distinct legal duties between the parties.
    Accordingly, we conclude that the lower court properly determined that governmental immunity
    did not apply to bar defendant’s claim for damages because the damages arose from a contract,
    not a tort.
    V. DISCOVERY ON COSTS
    Plaintiffs argue that the lower court erred by denying them the opportunity to engage in
    discovery regarding costs. We conclude that plaintiffs have waived this issue.
    A waiver is an intentional relinquishment or abandonment of a known right. Quality
    
    Prod, 469 Mich. at 374
    . A party may not take a position before this Court that is contrary to a
    position the party took before the lower court. Grant v AAA Mich/Wisconsin, Inc (On Remand),
    
    272 Mich. App. 142
    , 148; 724 NW2d 498 (2006).
    In this case, the following exchange took place:
    [Counsel for defendant]. . . . I am pleased I have worked with [counsel
    for plaintiffs], and we have agreed and stipulated that the costs that were
    submitted . . . were, in fact, incurred by PolyOne and were incurred in connection
    with the Dober Mine, although he retains all his other arguments regarding the
    collectability of those costs. But we need not have a witness he has agreed.
    THE COURT. So the amounts, [counsel for plaintiffs], are not in dispute?
    [Counsel for plaintiffs]. Correct.
    Plaintiffs thus expressly agreed that the costs that defendant submitted were in fact incurred by
    defendant in connection with the Dober Mine Complex. To allow plaintiffs to challenge this
    issue on appeal would be to allow them to take a position contrary to the position they took
    before the lower court. We decline to allow plaintiffs to do so.
    Affirmed.
    /s/ Christopher M. Murray
    /s/ Deborah A. Servitto
    /s/ Mark T. Boonstra
    -6-