Spring Harbor Club Condominium Association v. Greg Wright ( 2015 )


Menu:
  •                            STATE OF MICHIGAN
    COURT OF APPEALS
    SPRING HARBOR CLUB CONDOMINIUM                                       UNPUBLISHED
    ASSOCIATION, DON L. KESKEY, the ESTATE                               June 23, 2015
    OF PETER DONLIN, and BRUCE TRAVERSE
    d/b/a KESTRADON ENTERPRISES,
    Plaintiffs-Appellants,
    v                                                                    No. 321507
    Charlevoix Circuit Court
    GREG WRIGHT d/b/a WRIGHT ENTERPRISE                                  LC No. 13-061924-CK
    INC a/k/a BUILT WRIGHT CONSTRUCTION
    a/k/a BUILT WRIGHT CONTRACTORS a/k/a
    BUILT WRIGHT CORP, H. JACK BEGROW PC,
    HAROLD JACK BEGROW, and UNKNOWN
    SUBCONTRACTORS,
    Defendants-Appellees.
    Before: RONAYNE KRAUSE, P.J., and MURPHY and SERVITTO, JJ.
    PER CURIAM.
    Plaintiffs appeal by right the trial court’s grant of summary disposition in favor of
    defendants on the grounds that plaintiffs’ claims are time-barred. Plaintiffs are, in broad strokes,
    the owners of certain condominiums designed or constructed by defendants between 1991 and
    1994. In 2013, plaintiffs discovered significant problems with the structure, and upon further
    inspection they determined that the problems were due to defective construction or construction
    management. Furthermore, plaintiffs contend that the defective workmanship was totally
    undiscoverable in the interim. Defendants successfully argued that plaintiffs’ claims are time-
    barred by applicable statutes of limitation, statutes of repose, or a limitations period specified in
    the parties’ contracts. The issue before this Court is not the substantive merits of plaintiffs’
    claims, but rather solely whether those claims are indeed time-barred. We affirm in part, reverse
    in part, and remand.
    I. INTRODUCTION
    A grant or denial of summary disposition is reviewed de novo on the basis of the entire
    record to determine if the moving party is entitled to judgment as a matter of law. Maiden v
    Rozwood, 
    461 Mich. 109
    , 118; 597 NW2d 817 (1999). A motion brought under MCR
    -1-
    2.116(C)(8) should be granted only where the complaint is so legally deficient that recovery
    would be impossible even if all well-pleaded facts were true and construed in the light most
    favorable to the non-moving party. 
    Id. at 119.
    Only the pleadings may be considered when
    deciding a motion under MCR 2.116(C)(8). 
    Id. at 119-120.
    Under MCR 2.116(C)(7), where the
    claim is allegedly barred, the trial court must accept as true the contents of the complaint, unless
    they are contradicted by documentary evidence submitted by the moving party. 
    Id. at 119.
    For
    the purposes of the instant appeal, we presume the truth of the assertions in plaintiffs’ complaint.
    Plaintiffs’ Second Amended Complaint alleges one count each of breach of contract
    against defendant Greg Wright and defendant Jack Begrow, and counts of malpractice, breach of
    implied warranties, gross negligence, and negligence against both. Plaintiffs allege that they
    retained Wright and his associated business entities (collectively “Wright”), a licensed residential
    contractor, as general contractor to build the condominium project, and they retained Begrow, a
    licensed architect, to design the project and supervise its construction. “Greg Wright and Jack
    Begrow ignored critical design specifications, industry standards and applicable building codes
    during the construction of Spring Harbor Club thereby creating defective and unsafe conditions.”
    This alleged malfeasance caused considerable damage that was not discovered until 2013
    because of the hidden nature of the defects. Plaintiffs have promptly performed remediation at
    their expense but believe more damage remains to be discovered. For convenience, we will
    address the individual counts asserted by plaintiffs in sequence.
    II.(A) BREACH OF CONTRACT
    Plaintiffs assert that their breach of contract claims are not subject to any limitations
    period because they articulate indemnity claims, or because they contend they should be granted
    leave to amend their complaint to articulate indemnity claims. Our Supreme Court has explained
    that the contractor’s statute of repose, MCL 600.5839, only applies to tort claims, so a
    contractual claim against a contractor would instead be subject to the general 6-year limitations
    period for contract claims set forth in MCL 600.5807(8). See Miller-Davis Co v Ahrens Constr
    Inc (Miller-Davis II), 
    495 Mich. 161
    , 169-170; 848 NW2d 95 (2014). Our Supreme Court further
    explained that in a claim for indemnification, a party breaches an indemnity clause in a contract
    when the party refuses a demand to indemnify, which is independent of the date when the party
    allegedly breached any other obligations it might have had under the contract. 
    Id. at 180-182.
    Importantly, Miller-Davis II relied on the fact that the parties in that case had a broad and
    unambiguous indemnity clause in their contract. Miller-Davis 
    II, 495 Mich. at 174-175
    .
    Plaintiffs are correct in stating that if they could arguably show that defendants breached an
    indemnity clause in their contract, they should indeed have an opportunity to prove it.
    However, the indemnification clauses in the parties’ contracts are not as inclusive as the
    one at issue in Miller-Davis II. The indemnification clause in the contract with Wright states:
    To the fullest extent permitted by law, the Contractor shall indemnify and
    hold harmless the Owner and the Architect and their agents and employees from
    and against all claims, damages, losses and expenses, including but not limited to
    attorneys’ fees, arising out of or resulting from the performance of the Work,
    provided that any such claim, damage, loss or expense (1) is attributable to bodily
    injury, sickness, disease or death, or to injury to or destruction of tangible
    -2-
    property (other than the Work itself) including the loss of use resulting therefrom,
    and (2) is caused in whole or in part by any negligent act or omission of the
    Contractor, any Subcontractor, anyone directly or indirectly employed by any of
    them or anyone for whose acts any of them may be liable, regardless of whether
    or not it is caused in part by a party indemnified hereunder.
    Parsing the above provision, the first requirement for an indemnification claim explicitly
    excludes claims arising from Wright’s performance to the extent any such claim arises out of
    harm to the work performed itself. Reading plaintiffs’ complaint as a whole, the entirety of
    plaintiffs’ action is based on damage to the condominium structure and other construction work
    allegedly performed by Wright. The indemnity clause in Miller-Davis II contained no such
    exclusion. Furthermore, plaintiffs have not articulated any document purporting to be a
    contractual indemnity provision between themselves and defendant Begrow. We are not
    persuaded that it is possible for plaintiffs to articulate an indemnity claim.
    II.(B) MALPRACTICE
    Plaintiffs correctly state that, unlike many of the other claims at issue, a claim for
    malpractice enjoys a “discovery rule” that tolls the applicable limitations period to a certain
    extent. Other than medical or legal malpractice claims, the general rule is that a claim for
    malpractice “accrues” when a licensed professional discontinues professionally serving a
    plaintiff, MCL 600.5838(1), but, with exceptions not relevant here, an action may be commenced
    “within 6 months after the plaintiff discovers or should have discovered the existence of the
    claim.” MCL 600.5838(2). Actions against architects or contractors for damages to property
    “arising out of the defective or unsafe condition of an improvement to real property” are,
    however, subject to a statute of repose, establishing a maximum limit of ten years after the
    improvement is occupied or accepted. MCL 600.5839(1)(b). A superficial reading of the latter
    statute leads to the conclusion that plaintiffs’ claims expired in 2004 at the latest.
    Plaintiffs argue that our Supreme Court has held that MCL 600.5839 “does not apply to
    claims against contractors and design professionals for damage to the improvement itself.” This
    is technically accurate, but it is incomplete. Our Supreme Court in fact held that MCL 600.5839
    applies to tort actions and not to breach of contract actions. Miller-Davis Co v Ahrens Constr Inc
    (Miller-Davis I), 
    489 Mich. 355
    , 370; 802 NW2d 33 (2011). Malpractice does not neatly fit the
    definition of either a tort or a contract. However, although our Supreme Court did not explicitly
    articulate whether MCL 600.5839 applies to malpractice actions, our Supreme Court did cite to
    and quote from, with approval, this Court’s decision in City of Marysville v Pate, Hirn & Bogue
    Inc, 
    154 Mich. App. 655
    , 660; 397 NW2d 859 (1986), superseded by statute on other grounds as
    stated in Ostroth v Warren Regency GP, LLC, 
    263 Mich. App. 1
    ; 687 NW2d 309 (2004). In
    pertinent part, the quoted provision opined that MCL 600.5839 did not apply to “claims for
    deficiencies in the improvement itself,” which, critically, included professional malpractice
    claims. Miller-Davis 
    I, 489 Mich. at 369-370
    .
    Consequently, by necessary implication, the trial court erred to the extent it held that
    MCL 600.5839 applied to plaintiffs’ malpractice claims, and to the extent it granted summary
    disposition in favor of defendants on those claims pursuant to an assertion that they are time-
    barred pursuant to any statute of limitations or repose.
    -3-
    II.(C) BREACH OF WARRANTY
    Plaintiffs captioned Count IV as “breach of implied warranties,” but looking beyond the
    applied label, they actually articulated both express and implied warranty claims. “In actions for
    damages based on breach of a warranty of quality or fitness the claim accrues at the time the
    breach of the warranty is discovered or reasonably should be discovered.” MCL 600.5833. To
    the extent any such claim is based on the express provisions of a contract, MCL 600.5839 is
    inapplicable as we have described. However, defendants correctly point out that if a contract
    provides for a shortened limitations period, that shortened period must be enforced, no matter
    how unreasonable it might be, unless it is actually illegal, contrary to public policy, or subject to
    some other contractual defense. Rory v Continental Ins Co, 
    473 Mich. 457
    , 465-490; 703 NW2d
    23 (2005).
    In relevant part, the contract with Wright provides as follows:
    The making of final payment shall constitute a waiver of all claims by the
    Owner except those arising from:
    1. Unsettled liens;
    2. Faulty or defective Work appearing after Substantial Completion;
    3. Failure of the Work to comply with the requirements of the Contract
    Documents, or;
    4. Terms of any special warranties required by the Contract Documents.
    * * *
    The Contractor warrants to the Owner and the Architect that all materials
    and equipment furnished under this Contract will be new unless otherwise
    specified, and that all Work will be of good quality, free from faults and defects
    and in conformance with the Contract Documents. All Work not conforming to
    these requirements, including substitutions not properly approved and authorized,
    may be considered defective. If required by the Architect, the Contractor shall
    furnish satisfactory evidence as to the kind and quality of materials and
    equipment.
    * * *
    The Contractor shall correct any Work that fails to conform to the
    requirements of the Contract Documents where such failure to conform appears
    during the progress of the Work, and shall remedy any defects due to faulty
    materials, equipment or workmanship which appear within a period of eighteen
    (18) months from the date of the Final Certificate of Occupancy or within such
    longer period of time as may be prescribed by law or by the terms of any
    applicable special guarantee required by the Contract Documents.
    -4-
    This is not, contrary to defendants’ assertions, an unambiguous limitation on the warranty itself,
    but rather a limitation on the period within which the Contractor is required to make corrections,
    and even that limitation is subject to “any applicable special guarantee required” elsewhere in the
    contract. In contrast, the case upon which defendants rely involved no “warranty” at all, but
    rather only a provision requiring the contractor to correct defective work that may appear within
    a particular time period. See Cree Coaches Inc v Panel Suppliers Inc, 
    384 Mich. 646
    , 648; 186
    NW2d 335 (1971).
    The contract is not as clear as might be hoped, but it sufficiently clearly draws a
    distinction between a warranty that contains no limitations, and an obligation to correct defective
    work, which does have limitations. The latter 18-month limitation, however, is itself subject to
    extension pursuant to any other guarantees made in the contract. Furthermore, the “waiver”
    contemplated by the making of final payment explicitly does not cover anything covered by a
    contractual warranty or later-appearing defective work. In short, the contract appears not to
    impose an expiration date on the warranty contained therein. Furthermore, the plain language of
    the warranty provision shows that it is a warranty of quality or fitness, and consequently it is
    subject to MCL 600.5833. The trial court should not have granted summary disposition as to
    plaintiffs’ express warranty claims against Wright.
    The contract with Begrow, in contrast, explicitly states: “[t]he Architect will not have
    control or charge of and will not be responsible for construction means, methods, techniques,
    sequences or procedures, or for safety precautions and programs in connection with the Work,
    and he will not be responsible for the Contractor’s failure to carry out the Work in accordance
    with the Contract Documents.” The only provision seemingly constituting a warranty applies to
    the Contractor only, and is similar to the warranty provision described above, subject to
    essentially the same partial waiver upon final payment as described above. Plaintiffs have not
    pointed to any other contractual provision appearing to constitute an express warranty made by
    defendant Begrow.
    As to plaintiffs’ implied warranty claims, an “implied warranty of habitability” attaches
    to the sale of new homes sold by a builder-vendor, but not to the construction of a home by a
    contractor engaged to build a new home on land already owned by the purchaser, as is the
    situation in the instant matter. Smith v Foerster-Bolser Constr Inc, 
    269 Mich. App. 424
    , 430-431;
    711 NW2d 421 (2006). Plaintiffs argue that an implied warranty of habitability is not the same
    as an implied warranty of quality or fitness. However, Smith, and the case upon which Smith
    relied in significant part, Weeks v Slavick Builders Inc, 
    24 Mich. App. 621
    ; 180 NW2d 503
    (1970), treated the concepts as synonymous in the context of the sale of a home. This is logical
    and reasonable, because the “fitness” and “quality” of a home would naturally depend on its
    “habitability.” We therefore find no support in the case law for the distinction plaintiffs attempt
    to draw, so we are unable to find an implied warranty here.
    II.(D) GROSS NEGLIGENCE AND NEGLIGENCE
    Plaintiffs do not mount any argument in opposition to the trial court’s grant of summary
    disposition in favor of defendants as to Counts V and VI, asserting gross negligence and
    negligence, respectively. Issues not briefed are considered abandoned. Etefia v Credit
    Technologies Inc, 
    245 Mich. App. 466
    , 471; 628 NW2d 577 (2001). In any event, as discussed
    -5-
    above, MCL 600.5839 unambiguously does apply to tort actions. The period of repose having
    long since expired, summary disposition was proper as to these counts.
    III. CONCLUSION
    The trial court improperly granted summary disposition in favor of defendants as to
    plaintiffs’ malpractice claims and as to plaintiffs’ breach of express warranty claim against
    Wright. The trial court’s grant of summary disposition is reversed as to those claims. The
    remaining claims were properly dismissed, rendering plaintiffs’ other arguments on appeal moot.
    In all other respects we affirm, and we remand for further proceedings. No costs, no party
    having prevailed in full. We do not retain jurisdiction.
    /s/ Amy Ronayne Krause
    /s/ William B. Murphy
    /s/ Deborah A. Servitto
    -6-
    

Document Info

Docket Number: 321507

Filed Date: 6/23/2015

Precedential Status: Non-Precedential

Modified Date: 4/18/2021