Spartan Specialties Ltd v. Senior Services Inc ( 2017 )


Menu:
  •                            STATE OF MICHIGAN
    COURT OF APPEALS
    SPARTAN SPECIALTIES, LTD.,                                               UNPUBLISHED
    July 20, 2017
    Plaintiff/Counter-Defendant-
    Appellant,
    v                                                                        No. 331528
    Kalamazoo Circuit Court
    SENIOR SERVICES, INC.,                                                   LC No. 2013-000499-CK
    Defendant/Counter-Plaintiff-
    Appellee.
    Before: SAWYER, P.J., and HOEKSTRA and BECKERING, JJ.
    PER CURIAM.
    Plaintiff, Spartan Specialties, Ltd, appeals as of right the November 23, 2015 judgment.
    Following a jury trial, in accordance with the jury’s verdicts, the trial court entered judgment in
    favor of plaintiff in the amount of $0 on plaintiff’s claim for breach of contract and judgment in
    favor of defendant, Senior Services, Inc., in the amount of $0 on defendant’s counterclaim for
    breach of contract. We affirm.
    Defendant built a commercial kitchen, the Pauline Allen Nutrition Center, in 1997.
    Within a year, the kitchen’s floor had started to settle. As part of “a major repair” for the
    commercial kitchen, defendant contracted with plaintiff for the installation of 305 mini-piles
    under the kitchen’s floor. Under the contract, plaintiff was to complete the work described in
    “the Contract Documents.”
    Two of the contract documents, the drawings and the project manual, included
    specifications for the mini-piles. The drawing that showed where the mini-piles were to be
    installed under the floor included the following specifications:
    FS-1    Mini-pile capacity to be 6000 pounds; unfactored load, plus 3.0 safety
    factor.
    FS-2    Pile capacity is to be verified by at least two pile load tests. . . .
    ***
    -1-
    FS-6    Length of mini-pile installation is to be adequate to get through the
    organic and fill soils below the slab and into undisturbed soil to a depth
    adequate for obtaining the required capacity. . . .[1]
    The specifications in the project manual provided, in pertinent part:
    3.11    The piles should have a minimum-working load of 4 tons and 3 tons per
    pile as noted on the drawings and a minimum factor of safety of 3.0.
    3.12    The piles should be driven to a minimum of 25 feet below the slab level.
    ***
    3.15    A grout bulb should be formed at the base of the mini-pile with a
    minimum diameter of 2.0 feet.
    The project manual provided that “[i]n the case of an inconsistency between Drawings and
    Specifications or within either Document not clarified by an addendum, the better quality or
    greater quality of Work shall be provided in accordance with the Architect’s interpretation.”
    Plaintiff finished installing the mini-piles in October 2007. Two mini-piles were tested,
    one in August 2007 and one in October 2007, and both mini-piles met the required capacity.
    However, plaintiff did not drive all the mini-piles to a minimum depth of 25 feet and it only used
    one grout bulb, which defendant believed were requirements of the contract. Plaintiff sued
    defendant for breach of contract in October 2013, after it submitted its second application for
    payment and defendant refused to pay. Defendant counterclaimed for breach of contract.
    On appeal, plaintiff argues that the trial court erred in not striking Nathan Whitaker from
    defendant’s witness list. The trial court held that Whitaker was not qualified to testify as an
    expert witness, but he could testify as a lay witness regarding matters within his personal
    knowledge, including quotations that he had prepared for defendant in 2014. We review a trial
    court’s evidentiary decisions for an abuse of discretion. Zaremba Equip v Harco Nat’l Ins Co,
    
    302 Mich. App. 7
    , 21; 837 NW2d 686 (2013). A trial court abuses its discretion when its decision
    falls outside the range of principled outcomes. 
    Id. Most of
    plaintiff’s argument concerns why Whitaker was not qualified to give testimony
    about “foundation failures” and remediation of those failures. However, Whitaker did not testify
    that the floor of the mechanical room in the commercial kitchen had settled and how the
    settlement should be remediated. Rather, Whitaker testified to a plan that would render the floor
    of the mechanical room irrelevant so that, if the soils underneath the room settled, the settlement
    1
    The drawing for the mini-piles that would be used to support the interior bearing walls
    indicated that the capacity of those mini-piles was “to be 8000 pounds; unfactored load, plus 3.0
    safety factor.”
    -2-
    would not affect the items in the room or the underground utilities. The proposed work was a
    precautionary measure in case the soils should settle.
    We cannot conclude that the trial court abused its discretion in allowing Whitaker to
    testify as a lay witness about matters within his personal knowledge. 
    Id. Plaintiff makes
    no
    argument that Whitaker’s testimony about the plan to render the floor of the mechanical room
    irrelevant should the soils underneath the room settle was improper lay testimony.
    Plaintiff also argues that the trial court erred in not prohibiting Robert Littke, defendant’s
    president and CEO, from giving testimony that described settlement. The trial court held that
    Littke could testify about what he personally observed and what he personally believed to be
    settlement. We review a trial court’s evidentiary decisions for an abuse of discretion. 
    Id. Plaintiff does
    not identify the specific testimony of Littke that it believes the trial court
    should have precluded. We assume that plaintiff is challenging Littke’s testimony about the
    condition of the mechanical room. Littke testified that he was familiar with the condition of the
    mechanical room in 2007 after plaintiff and Miller Davis Company, the company that did the
    repair finishes, completed their work. According to Littke, pictures of the mechanical room
    shown to him did not represent the condition of the mechanical room in 2007 after Miller Davis
    Company finished its work. The pictures showed gaps underneath the baseboards and stretched
    wallpaper near a doorframe. Neither of these conditions, Littke testified, existed after Miller
    Davis Company finished its work. Littke explained that he had prepared a punch list for Miller
    Davis Company and that he would have identified both of these conditions in 2007, listed them
    on the punch list, and had Miller Davis Company correct them. Additionally, Littke testified that
    the door to the mechanical room sticks in its frame, which it did not do in 2007. He explained
    that the door, had it been sticking in the frame, would have been placed on the punch list.
    Littke’s testimony about the condition of the mechanical room was not complicated, and
    there is no claim that Littke testified about a matter for which he did not have personal
    knowledge. See MRE 601. Littke testified that, based on his conduct and observations in 2007,
    the pictures of the mechanical room did not represent the condition of the room after Miller
    Davis Company finished its work in 2007. Spartan Services does not cite any authority that
    prohibits a lay witness from testifying that a picture of a room does not accurately portray the
    condition of the room at a previous time. Accordingly, we reject plaintiff’s argument that the
    trial court erred in denying its motion to limit the testimony of Littke.
    Next, plaintiff argues that the trial court erred in denying its motion for summary
    disposition. According to plaintiff, if there was no genuine issue of material fact that the mini-
    piles were installed in accordance with the specifications, then it was entitled to judgment that it
    did not breach the contract. It was undisputed that plaintiff did not use grout bulbs and did not
    drive all the mini-piles to a minimum depth of 25 feet. Thus, plaintiff only complied with the
    contract if the contract did not require it to use grout bulbs and to drive the mini-piles to a
    minimum depth of 25 feet. Plaintiff makes no argument that the language of the contract, when
    the contract is read as a whole, Detroit Pub Sch v Conn, 
    308 Mich. App. 234
    , 373; 863 NW2d 373
    (2014), is unambiguous and that the only mandatory requirement regarding the installation of the
    mini-piles was that the mini-piles met capacity. Accordingly, plaintiff has abandoned its claim
    -3-
    that the trial court erred in denying its motion for summary disposition, see Peterson Novelties,
    Inc v Berkley, 
    259 Mich. App. 1
    , 14; 672 NW2d 351 (2003), and we decline to address it.
    Plaintiff argues that the trial court erred in denying its motion for JNOV. We review a
    trial court’s decision on a motion for JNOV de novo. Alfieri v Bertorelli, 
    295 Mich. App. 189
    ,
    193; 813 NW2d 772 (2012). We view the testimony and all legitimate inferences in a light most
    favorable to the nonmoving party. Morinelli v Provident Life & Accident Ins Co, 
    242 Mich. App. 255
    , 260; 617 NW2d 777 (2002). If reasonable jurors could have honestly reached different
    conclusions, the jury verdict must stand. 
    Id. at 260-261.
    Plaintiff asserts that it was entitled to JNOV because it did not breach the contract and
    defendant failed to pay for its performance. The basis for plaintiff’s argument is that the mini-
    piles met capacity and that it was not required to use grout bulbs and to drive the mini-piles to a
    minimum depth of 25 feet. “A party asserting a breach of contract must establish by a
    preponderance of the evidence that (1) there was a contract (2) which the other party breached
    (3) thereby resulting in damages to the party claiming breach.” Miller-Davis Co v Ahrens Const,
    Inc, 
    495 Mich. 161
    , 178; 848 NW2d 95 (2014).
    The specifications in the drawings for the mini-piles stated that the capacity for the mini-
    piles was “to be” 6,000 or 8,000 pounds and that the length of the mini-piles was “to be”
    adequate to get into undisturbed soil to a depth adequate for obtaining the required capacity. The
    specifications in the project manual stated that the mini-piles “should” have a capacity of 4 tons
    and 3 tons, that the mini-piles “should” be driven to minimum depth of 25 feet, and that a grout
    bulb “should” be formed at the base of a mini-pile. Kenneth Winters, an expert in structural
    engineering, and Richard Anderson, an expert in geotechnical engineering, agreed with Steve
    Maranowski, plaintiff’s president, that the specifications in the project manual, because those
    specifications used the word “should,” were permissive and suggestions of what plaintiff could
    do to achieve the required capacity. However, the trial court, when it instructed the jury on how
    to interpret the contract, instructed the jury that it was to interpret the words of the contract by
    giving them their ordinary and common meaning. An ordinary and common meaning of the
    word “should” is that it denotes a mandatory obligation. See People v Fosnaugh, 
    248 Mich. App. 444
    , 455; 639 NW2d 587 (2001) (stating that “the word ‘should’ can, in certain contexts,
    connote an obligatory effect”); Merriam-Webster’s College Dictionary (11th ed) (defining
    “should,” in pertinent part, as “used in auxiliary function to express obligation, propriety, or
    expediency”).2 Accordingly, viewing the evidence in a light most favorable to defendant,
    reasonable jurors could have honestly reached different conclusions on whether the
    specifications in the project manual were mandatory and, because Maranowski admitted that
    plaintiff did not use grout bulbs and did not drive all the mini-piles at least 25 feet into the
    ground, whether plaintiff breached the contract. 
    Morinelli, 242 Mich. App. at 260-261
    .
    Additionally, Winters and Anderson admitted that the two sets of specifications could be
    viewed as inconsistent. Under the project manual, when there was an inconsistency, “the better
    2
    We note that defendant, in its closing argument, argued that the word “should” can be seen as
    “prohibitive or as mandatory in many contexts.”
    -4-
    quality or greater quality of Work shall be provided in accordance with the Architect’s
    interpretation.” Similarly, under another contract document, TMP Architecture, the architect for
    the “major repair,” was to “interpret and decide matters concerning performance under and
    requirements of the Contract Documents.” The dispute between plaintiff and defendant
    regarding the use of grout bulbs was submitted to TMP Architecture. TMP Architecture viewed
    the specification regarding the use of grout bulbs as a mandatory requirement. In the project
    memo it issued, TMP Architecture wrote that the “deviation” of plaintiff from specification 3.15
    was done with no documentation of change from it or Robert Darvas Associates, a structural
    engineering firm that was used by TMP Architecture. It also wrote that if the “deviation” was
    acceptable to Robert Darvas Associates, “the documents should be amended from the
    specification requirement to that of a performance type of spec and the piles should be
    individually tested to prove that performance is met.” It further wrote, “Once the documents
    were drafted and Spartan was contracted for the work as specified, the Owner, architect and
    engineer have the expectation of the work being done in strict accord with those documents. It is
    not in the purview of Spartan to any longer deviate from those set specs.” TMP Architecture
    gave two choices: (1) plaintiff could continue with work “as specified with bulb being installed”
    or (2) Robert Darvas Associates could suggest to TMP Architecture and defendant that the
    requirement be changed to a performance specification, with plaintiff making the final decision.
    Under the contract documents, changes in the work could only be accomplished through
    change orders. Littke testified that no change orders were ever requested. Because TMP
    Architecture interpreted the specification regarding the use of grout bulbs as a mandatory
    requirement, and because plaintiff did not submit a change order regarding the specification,
    reasonable jurors could have honestly reached different conclusions whether plaintiff, by not
    using grout bulbs, breached the contract. 
    Morinelli, 242 Mich. App. at 260-261
    .
    Additionally, even if plaintiff did not breach the contract by not using grout bulbs and by
    not driving the mini-piles to a minimum depth of 25 feet, reasonable jurors could have honestly
    reached different conclusions on whether plaintiff was entitled to payment from defendant. The
    trial court provided the following instruction to the jury:
    Senior Services claims that Spartan Specialties and it agreed that Senior
    Services did not have to perform its part of the contract unless Spartan Specialties
    posted a performance bond, had the architect certify all pay application requests
    and submitted waivers of lien so in order to qualify for final payment. These
    requirements are called conditions precedent. A condition precedent is a fact or
    event that the parties intended must take place before the other has to perform.
    Spartan Specialties denies that these conditions were part of the contract.
    Whether a provision in a contract is a condition precedent which excuses
    performance depends on the intent of the parties. The parties’ intent is to be
    ascertained from a fair and reasonable construction of the language used in light
    of the surrounding circumstances when they executed the contract. If you find
    that the conditions precedent were part of the contract you must decide whether
    the required event occurred. If you decide that the condition or event did not
    -5-
    occur then Senior Services is not required to perform its part of the contract.
    Senior Services has the burden of proof that the required condition did not
    occur.[3]
    Pertinent provisions in the contract documents regarding the alleged conditions precedent
    included the following: (1) “Based on Contractor’s Applications for Payment certified by the
    Architect, the Owner shall pay the Contractor . . . monthly with ten percent (10%) retainage;” (2)
    “Contractor shall deliver to Owner with request for payment sworn statements and waivers of
    lien satisfactory to Owner;” (3) “Based on the Architect’s observations and evaluations of the
    Contractor’s Applications for Payment, the Architect will review and certify the amounts due the
    Contractor;” (4) “The Architect will, within seven days after receipt of the Contractor’s
    Application for Payment, either issue to the Owner a Certificate for Payment, with a copy to the
    Contractor, for such amount as the Architect determines is properly due, or notify the Contractor
    and Owner in writing of the Architect’s reasons for withholding certification in whole or in
    part;” and (5) “Accepted bidders may be required to furnish satisfactory performance bond.”
    Littke testified that plaintiff was required to post a performance bond.
    Littke testified, as did Maranowski, that plaintiff did not post a performance bond. Littke
    also testified, as did Maranowski, that plaintiff did not provide any lien waivers in connection
    with its second application for payment. Additionally, it was undisputed that TMP Architecture
    did not certify plaintiff’s second application for payment. Viewing the evidence in a light most
    favorable to defendant, reasonable jurors could have honestly reached different conclusions
    whether the performance bond, certification of payment application requests, and submission of
    lien waivers were part of the contract between plaintiff and defendant and whether these
    preconditions were met. 
    Morinelli, 242 Mich. App. at 260-261
    . Consequently, reasonable jurors
    could have reached honestly different conclusions whether defendant’s obligation to pay plaintiff
    was triggered. 
    Id. We affirm
    the trial court’s denial of plaintiff’s motion for JNOV.
    Plaintiff also argues that the trial court erred in denying its motion for a new trial. We
    review a trial court’s decision on a motion for a new trial for an abuse of discretion. Rental
    Props Owners Ass’n of Kent Co v Kent Co Treasurer, 
    308 Mich. App. 498
    , 531; 866 NW2d 817
    (2014). A trial court abuses its discretion when its decision falls outside the range of reasonable
    and principled outcomes. 
    Id. Plaintiff claims
    that it is entitled to a new trial because the verdict was clearly or grossly
    inadequate. See MCR 2.611(A)(1)(d). “A verdict should not be set aside simply because the
    method of computation used by the jury in assessing damages cannot be determined, unless it is
    not within the range of evidence presented at trial.” Diamond v Witherspoon, 
    265 Mich. App. 673
    , 694; 696 NW2d 770 (2005). Plaintiff also claims that it is entitled to a new trial because the
    3
    See Reed v Citizens Ins Co of America, 
    198 Mich. App. 443
    , 447; 499 NW2d 22 (1993),
    overruled in part on other grounds by Griffith v State Farm Mut Auto Ins Co, 
    472 Mich. 521
    (2005) (“A ‘condition precedent’ is a fact or event that the parties intend must take place before
    there is a right to performance.”). On appeal, plaintiff makes no argument concerning the
    propriety of this instruction.
    -6-
    verdict was against the great weight of the evidence. See MCR 2.611(A)(1)(e). A verdict should
    not be set aside if there is competent evidence to support it. Dawe v Dr Reuven Bar-Levav &
    Assoc, PC (On Remand), 
    289 Mich. App. 380
    , 401; 808 NW2d 240 (2010).
    The ultimate basis for plaintiff’s claim for relief under MCR 2.611 is that the evidence
    established that plaintiff, by not using grout bulbs and by not driving the mini-piles to a
    minimum depth of 25 feet, did not breach the contract and that defendant, by not paying plaintiff,
    breached the contract. However, as previously explained, there was evidence from which the
    jury could have found that plaintiff breached the contract when it did not use grout bulbs and did
    not drive all the mini-piles 25 feet into the ground. There was also evidence from which the jury
    could have found that, even if plaintiff did not breach the contract, defendant’s obligation to pay
    plaintiff was not triggered and, therefore, defendant did not breach the contract when it failed to
    pay plaintiff. 4 Accordingly, the trial court did not abuse its discretion in denying plaintiff’s
    motion for a new trial. Rental Props Owners Ass’n of Kent 
    Co, 308 Mich. App. at 531
    .
    Affirmed.
    /s/ David H. Sawyer
    /s/ Joel P. Hoekstra
    /s/ Jane M. Beckering
    4
    Additionally, there was evidence from which the jury could have found that, if plaintiff
    breached the contract, defendant was damaged by the breach. Anderson testified that when he
    visited the mechanical room in July 2014 he saw evidence of settlement, including cracked tiles,
    although he believed that the evidence of settlement existed before plaintiff did any work in
    2007. But Littke and Nick Sawyer, an employee of Miller Davis Company, when shown
    pictures of the mechanical room, testified that the pictures did not represent the condition of the
    room in 2007 after Miller Davis Company finished its work. Specifically, Littke indicated that
    in 2007 there were no gaps between the baseboards and the floor, while Sawyer indicated that
    there had been no cracked tiles or gaps under the baseboards.
    -7-
    

Document Info

Docket Number: 331528

Filed Date: 7/20/2017

Precedential Status: Non-Precedential

Modified Date: 7/24/2017