in Re Application of Encana Oil & Gas Re Beaver Creek Pipeline ( 2017 )


Menu:
  •                            STATE OF MICHIGAN
    COURT OF APPEALS
    ___________________________________________
    In re Application of Encana Oil & Gas re Garfield 36
    Pipeline.
    JOHN BUGGS and DANIEL BONAMIE,                         UNPUBLISHED
    May 16, 2017
    Appellants,
    v                                                      No. 329781
    MPSC
    MICHIGAN PUBLIC SERVICE COMMISSION                     LC No. 00-017195
    and DTE MICHIGAN GATHERING HOLDING
    COMPANY,
    Appellees.
    In re Application of Encana Oil & Gas re Beaver
    Creek Pipeline.
    _________________________________________
    JOHN BUGGS and DANIEL BONAMIE,
    Appellants,
    v                                                      No. 329909
    MPSC
    MICHIGAN PUBLIC SERVICE COMMISSION                     LC No. 00-017196
    and DTE MICHIGAN GATHERING HOLDING
    COMPANY,
    Appellees.
    Before: MARKEY, P.J., and MURPHY and METER, JJ.
    PER CURIAM.
    -1-
    In these consolidated appeals, appellants John Buggs and Daniel Bonamie appeal an
    order of the Michigan Public Service Commission (PSC) granting applications filed by Encana
    Oil & Gas, Inc.,1 to construct and operate natural gas pipelines. We affirm.
    I. BACKGROUND
    The PSC’s order on appeal is the second order approving construction of natural gas
    pipelines known as Garfield 36 and Beaver Creek 11. The first order was challenged by
    appellants, and in Buggs v Pub Serv Comm, unpublished opinion per curiam of the Court of
    Appeals, issued January 13, 2015 (Docket Nos. 315058, 315064), this Court vacated the order
    and remanded the matter to the PSC for further proceedings, concluding:
    Although the Commission minimally complied with the requirements for
    approving the applications under Act 9, it failed to follow the independent
    statutory requirement imposed under MEPA.[2] Because its orders approving the
    pipelines were unlawfully issued, we vacate those orders and remand for a new
    necessity determination in both dockets. In making its new determinations of
    necessity, the Commission shall specifically address the environmental impact as
    required under the MEPA and the decision in [State Hwy Comm v Vanderkloot,
    
    392 Mich. 159
    , 184-190; 220 NW2d 416 (1974) (opinion by WILLIAMS, J.)].
    [Buggs, unpub op at 11.]
    Appellants attempted, for the second time, to intervene in the proceedings before the
    3
    PSC. The PSC denied the motion to intervene, noting that in an earlier order it concluded that
    Buggs and Bonamie did not meet the test for intervening and that the earlier order had not been
    appealed. The PSC also noted that in 
    Buggs, supra
    , this Court did not instruct it to grant
    intervention on remand.
    On remand from this Court, the PSC again approved the construction and operation of the
    natural gas pipelines. The PSC noted that it sought and received additional information
    regarding the environmental impact of the pipelines and the efforts made by Encana to determine
    that the pipelines’ routes did not displace protected species or associated habitats. The PSC
    provided a 30-day public comment period after it received the additional information.
    The PSC reexamined the evidence and made detailed findings. To provide context for
    our resolution of these appeals, we quote liberally from the PSC’s opinion:
    1
    Encana assigned its interest in the pipelines to appellee DTE Michigan Gathering Holding
    Company.
    2
    The Michigan Environmental Protection Act, MCL 324.1701 et seq.
    3
    Buggs and Bonamie first filed a petition to intervene after the PSC entered ex parte orders in
    January 2013 approving the pipelines. The PSC denied the petition in an order entered on April
    16, 2013, and denied reconsideration in an order entered on June 28, 2013. Buggs and Bonamie
    did not seek leave to appeal the order denying the petition to intervene.
    -2-
    Garfield 36 Pipeline Project
    In Case No. U-17195, Encana indicates in its application that the Garfield
    36 Pipeline was to be constructed “adjacent to the well pad access road on
    Michigan Department of Natural Resource[s] (MDNR) land and within county
    road right of way.” January 11, 2013 Application, p. 2. Encana’s “Exhibit A” is
    a map showing the proposed route of the Garfield 36 Pipeline. It depicts a route
    that closely follows two roads, W. Township Line Road and Naples Road. The
    proposed route veers off of W. Township Line Road to cut a corner in meeting
    Naples Road. It then veers off Naples Road in a direct line to the closest gas well
    pad, State Garfield C4-36. Encana’s Exhibit D is an environmental impact
    assessment regarding the project. It indicates that as the pipeline route leaves the
    well pad, it follows a well access road for 2,600 feet. Thus, the application and
    exhibits show that approximately 90% of the proposed route for the Garfield 36
    Pipeline runs along already-existing roads, avoiding the need for the creation of
    new corridors.
    The environmental impact assessment discusses the land use and ecology
    and describes the pipeline route area as primarily mixed deciduous forest and
    describes the area along the well access road as semi-open forest. Regarding
    impairment to protected wildlife, the assessment indicates that there are no
    threatened or endangered species within the proposed easement or along the
    proposed route to the best of the author’s knowledge. Supplemental information
    filed in this docket on August 6, 2015, indicates that Encana submitted a request
    to the Michigan State University Michigan Natural Features Inventory (MNFI)
    requesting a review of the MNFI records regarding the potential presence of a
    protected species in the vicinity of the well sites and access roads used for the
    wells to which the proposed pipelines would ultimately be connected. Encana
    received a Rare Species Review response letter for the well site served by the
    Garfield 36 Pipeline. The letter stated that, “there are no legally protected or
    special concern species or other natural features within 1.5 miles of the project
    site” based on the MNFI database. Dean Farrier, whom Encana hired to prepare
    the environmental impact assessments, indicated in his August 4, 2015 letter to
    the Commission that, even though this Rare Species Review response letter was
    requested regarding the well sites to which the pipelines would ultimately
    connect, the 1.5 mile radius used in the database search includes the entire
    Garfield 36 Pipeline route.
    In addition to the onsite survey of the well sites and access roads for the
    potential presence of threatened and endangered species that Mr. Farrier
    conducted in order to prepare the environmental impact assessments that he
    submitted to the MDEQ’s Office of Oil, Gas and Minerals, Mr. Farrier also
    conducted both an initial review of the pipeline route for “obvious environmental
    concerns” as well as a “more thorough onsite survey” of the pipeline route “for
    the presence of protected species and habitat that might be impacted by pipeline
    construction.” Dean Farrier’s August 4, 2015 letter to the Commission, p. 2.
    He explained that he traveled the entire pipeline route and observed the cover
    -3-
    type and habitat that were present, specifically searching for dense young jack
    pine stands for the Kirtland’s warbler habitat, large high crowning trees, ideal for
    raptor nests, and “frost pocket” areas where special species might be found. 
    Id. Mr. Farrier
    indicated that his focus was on the potential presence of protected
    upland species and habitat, including Bald Eagle nests, other raptor nests,
    Kirtland’s warbler habitat, frost pockets and dead trees with cracks or loose bark
    for bat roosts. 
    Id. Mr. Farrier
    explained that the reason he focused on these
    protected species and habitats was because of his knowledge of the potential
    range and location of such species, their habitat, as well as MNFI Rare Species
    Review letters for other sites having a similar habitat to that along the pipeline
    route. He explained that he summarized his observations and conclusions
    regarding the habitat that was present and the absence of protected species within
    the easement and pipeline route in the environmental impact assessment report he
    prepared and submitted to the Commission in this matter.
    Regarding wetlands and other surface waters, the environmental impact
    assessment submitted for the Garfield 36 Pipeline project indicates that the
    proposed route involves one wetland crossing, and further indicates that
    directional drilling will be used to avoid disturbance to this area. The proposed
    route includes directional drilling around wetlands for a distance of 1,027 feet.
    The assessment also provides that the directional drilling and construction activity
    involved will not result in ground disturbance to the wetland or surface
    waterbody banks and that a minimum buffer of 50 feet from wetland boundaries
    will be maintained. It further indicates that the proposed construction activity
    will not disturb the stream contained in the larger wetland and that a minimum
    depth of 10 feet will be maintained under the streambed.
    Regarding the construction methods employed, Mr. Farrier writes in his
    environmental impact assessment that the clearing, removal of topsoil, and
    grading will be limited to a minimum area required for safe and efficient
    construction. The assessment discusses the procedure for the clearing of large
    vegetation, such as shrubs and trees, within the pipeline route. The assessment’s
    summary concludes that the route proposed minimally impacts the local
    ecosystems and land use as it runs along existing corridors and is directionally
    drilled around the wetland. Therefore, the assessment concludes that the
    construction of the Garfield 36 Pipeline will not cause any new corridors.
    The Commission also considered the public comments filed in this matter
    regarding the Garfield 36 Pipeline. Specifically, the Commission reviewed the
    comments the petitioners filed. The petitioners point out in their comments that
    they had, in their previous filings with the Commission, criticized the
    environmental impact assessments prepared for the pipeline construction projects
    on the grounds that Mr. Farrier lacked the credentials to support his claim to be a
    biologist, claimed no knowledge and checked no inventories regarding protected
    species, and because the assessments only purported to analyze conditions within
    the 35-foot easements as opposed to the surrounding vicinity. The comments
    -4-
    also note that the supplement does not discuss forest fragmentation resulting from
    future development of gas wells for gas production.
    Regarding these statements, the Commission notes that Mr. Farrier’s
    supplemental information provides an overview of his education and years of
    experience conducting surveys for the potential presence of protected species
    and their habitat, and also explains the lengths he went to in this matter to rule
    out the potential presence of protected species within the pipeline routes. With
    regard to the petitioners’ criticism that the assessments improperly focus on the
    impact to the 35-foot easement as opposed to the “surrounding vicinity,” the
    Commission observes that the pipeline installation project considered here does
    not, in and of itself, have much of an impact on the surrounding vicinity because
    all of the construction and installation work would legally have been limited to
    the easement area as opposed to the surrounding vicinity. Finally, a consideration
    of possible future gas well development for gas production and forest
    fragmentation resulting from gas production is neither ripe for review nor within
    the scope of the Commission’s jurisdiction in this matter.2
    The petitioners’ comments discuss their affidavits as well as the affidavit
    of Gary Cooley, which were attached as “exhibits” to a previous petition for
    intervention and that apparently document past observations of Kirtland’s
    warblers in the petitioners’ [backyards] as well as Cooley’s observations of two
    dead Kirtland’s warblers in the path of an Encana/DTE power shovel. The
    pipelines in this matter were initially approved ex parte, the Commission has yet
    to grant the petitioners intervention, and the exhibits the petitioners attached to
    their various filings were not a part of the initial company application and filing
    the Commission considered when it originally approved of the pipelines. Thus,
    the Commission has not considered these affidavits, nor are they a part of the ex
    parte record in this matter. Nevertheless, the Commission notes that the
    petitioners have never alleged that their [backyards] are located within the 35-foot
    easement within which the pipelines were constructed. Moreover, the public
    comments filed do not include Mr. Cooley’s basis for concluding that the birds
    he observed are in fact protected species or that they were presumably harmed
    because of pipeline construction activity within the proposed pipeline routes.
    Moreover, Encana’s failure to inform DNR or adequately respond to Mr. Cooley’s
    observations is of little consequence here both because the company’s subsequent
    activities presumably occurred after the Commission initially approved
    construction of the pipelines and because they are outside the scope of this order.
    Petitioners also take issue with the timing Mr. Farrier chose to conduct his
    on-site surveys of the proposed pipeline routes, suggesting that these surveys
    occurred in either mid-May or January, a time when Kirtland’s warblers would
    not yet have arrived in northern Michigan. As petitioners acknowledge in their
    comments, the exact day or month during which Mr. Farrier conducted his on-
    site surveys is unclear.      Nevertheless, Mr. Farrier writes that he conducted
    surveys at each location on two different occasions, both an initial review before
    Encana’s engineers agreed on a proposed route, and a second more thorough
    -5-
    survey afterwards. Further, the fact that Mr. Farrier did not just limit his survey
    to actual sightings of protected species but also looked for the presence of dense
    young jack pines and other natural features that would serve as habitat for certain
    the Kirtland’s warbler provides the Commission with some assurance that, even in
    the event that Mr. Farrier conducted both the initial review and the more
    thorough on-site survey during the winter months when the Kirtland’s warbler
    was outside of Michigan, he would still have discovered its habitat in undertaking
    a thorough on-site survey during the winter months when the protected species
    was elsewhere. Thus, the fact that the Commission lacks information regarding
    the exact dates that the on-site surveys were conducted is not dispositive on the
    issue of whether the proposed project impairs the environment.
    Finally, petitioners also criticize the environmental impact assessments
    submitted because they suggest that Mr. Farrier ignored wetland and stream
    areas along the Garfield 36 pipeline route, which amounted to 1,027 feet that was
    in the vicinity of the pipeline to be constructed. As both DTE Gathering and the
    petitioners acknowledge, those areas were left undisturbed due to the use of
    directional drilling. Because there was no disturbance to the surface, and no
    impact to threatened or endangered species, the Commission finds it reasonable
    that Mr. Farrier would focus on the potential presence of protected upland
    species and habitat. The Commission is satisfied based on the information
    provided in the assessment and supplemental information provided that the
    proposed project will not destroy, impair, or pollute wetlands or other surface
    waters.
    Given the fact that 90% of the proposed route follows already existing
    rural roads, based on the assessment’s determination that there will be no
    disturbance to wetlands, streams, or other surface waters, in light of the
    assessment’s conclusion that construction of the pipeline will not cause any new
    corridors, and based on the assessment and the supplemental information
    provided that adequately describes the efforts made and resources used to
    determine no protected wildlife exists in the proposed easement or along the
    proposed route, the Commission finds that the Garfield 36 Pipeline project as
    proposed will not impair the environment.
    Beaver Creek 11 Pipeline Project
    Regarding the Beaver Creek 11 Pipeline project in Case No. U-17196, the
    application and exhibits presented show a 3.1 mile route that runs entirely along
    existing county roads or well access roads, again avoiding the need to create new
    corridors. Encana’s application provides that the Beaver Creek 11 Pipeline “will
    be constructed adjacent to the well pad access road on Michigan Department of
    Natural Resource[s] (MDNR) land and within county road right of way on MDNR
    land.” January 11, 2013 Application, p. 2. Encana submitted an environmental
    impact assessment as its Exhibit D that indicates the impact on the environment is
    “minimal.”3 The assessment indicates the pipeline route runs primarily through
    mixed deciduous forest, and that, to the best of the author’s knowledge there are
    -6-
    no threatened or endangered species within the proposed easement or route. The
    assessment further indicates that there are no wetlands or stream crossings within
    the proposed route.
    Having reviewed the application and supporting exhibits, the Commission
    further determines that there is no impairment to the environment resulting from
    the construction or installation of the Beaver Creek 11 Pipeline. The proposed
    3.08-mile route runs along county and well access roads and crosses no wetlands
    or surface waters. The environmental impact assessment indicates that the entire
    proposed route is adjacent to existing corridors and does not require the creation
    of new corridors. It also indicates that the route traverses lands owned by the
    State of Michigan, with the exception of one area that is privately owned, where
    the route is in county right-of-way for King Road. The assessment further
    describes the land through which the proposed route runs as primarily mixed
    deciduous forest with Sugar Maple, Red Oak, Aspen and Birch being the dominant
    species.
    In the environmental impact assessment, Mr. Farrier explains that there are
    no threatened or endangered species within the proposed easement to the best of
    his knowledge. Again, Mr. Farrier’s August 4, 2015 letter states that the
    environmental impact assessment process began with Encana submitting a
    request to the MNFI staff requesting a review of the MNFI records regarding the
    potential presence of protected species in the vicinity of the well sites and access
    roads used for the wells to which the proposed pipelines would ultimately be
    connected. The Rare Species Review response letter for the Beaver Creek 11
    Pipeline stated that it was “highly unlikely that listed species will be impacted by
    this activity.” The response letter indicates that the listed species is a butterfly
    called Henry’s elfin. Further, Mr. Farrier’s August 4, 2015 letter explains that
    the determinations made in the Rare Species Review response letter related to the
    protected or special concern species or other natural features within 1.5 miles of
    the proposed well site, which would include 56% of the Beaver Creek 11
    pipeline route. As with the Garfield 36 Pipeline, Mr. Farrier again indicates in his
    August 4, 2015 letter that he conducted two reviews of the pipeline route, an
    initial review of the route for “obvious environmental concerns” and a more
    thorough onsite-survey of the pipeline route for the presence of protected species
    and habitat that might be impacted by pipeline construction.            As with the
    Garfield 36 Pipeline, Mr. Farrier conducted his on-site survey by traveling the
    entire pipeline route and observing the cover type and habitat present. Again, the
    focus was on the potential presence of protected upland species and habitat. Mr.
    Farrier’s observations led him to conclude in the environmental impact
    assessment that no protected wildlife is known to exist within the proposed route.
    Mr. Farrier discusses in the environmental impact assessment the
    construction methods to be used, explaining that the clearing, removal of topsoil,
    and grading will be limited to the minimum area required for safe and efficient
    construction and further setting forth the procedure for the removal of large
    vegetation such as trees and shrubs. It also discusses the method for excavating
    -7-
    and sloping the trench-line or ditch, and explains that gaps will be made in subsoil
    stockpiles so as to avoid ponding or excessive diversion of natural runoff during
    storm events in addition to implementation of erosion and sedimentation permit
    conditions, where applicable, and best management practices. The assessment’s
    description of the construction methods further provides that, after construction,
    the workspace will be graded as near as possible to the pre-construction contours
    and/or restored in accordance with Crawford County Road Commission permit
    requirements and natural runoff and drainage patterns will be restored. In
    addition, permanent erosion control measures will be installed and all disturbed
    workspace will be reseeded. Again, as with the assessment for the Garfield 36
    Pipeline, Mr. Farrier’s environmental impact assessment for the Beaver Creek 11
    Pipeline concludes by indicating that the proposed route minimally impacts the
    local ecosystems and land use, and that the construction of this pipeline will not
    cause any new corridors.
    The Commission, having considered the applications and accompanying
    environmental impact assessment submitted as well as the supplemental
    information provided by Mr. Farrier, concludes that the construction and
    installation of the Beaver Creek 11 Pipeline as proposed does not impair the
    environment. The Commission’s findings and conclusions that it articulates in
    this order with respect to petitioners’ filed comments apply equally to both the
    Garfield 36 and the Beaver Creek 11 pipeline applications. Having considered
    the record in this matter, the Commission is satisfied that competent, material,
    and substantial evidence on the whole record supports the Commission’s
    conclusion that environmental impairment has not been established.
    The Commission further notes that the remaining criteria that the Court
    instructed the Commission to consider on remand, i.e. “whether there was a
    feasible and prudent alternative to the impairment; and, whether the impairment
    was consistent with the promotion of the public health, safety, and welfare in
    light of the state’s paramount concern for the protection of its natural resources
    from pollution, impairment or destruction” pertain to an agency finding that
    impairment to the environment has occurred. Here, however, the Commission
    concludes, based on the record before it, that the proposed pipeline projects did
    not impair the environment. Accordingly, the Commission need not consider
    feasible and prudent alternatives to the impairment, or whether the impairment
    was consistent with the promotion of the public health, safety, and welfare in light
    of the state’s paramount concern for the protection of its natural resources. For
    the reasons articulated in this order, the Commission finds that the proposed
    Garfield 36 and Beaver Creek 11 Pipelines will serve the public convenience and
    necessity, and that ex parte approval is appropriate.
    __________________________________________________________________
    2
    The Commission notes that, although petitioners alleged in their various filings
    with the Commission that the pipelines would serve as “bait” inviting the
    construction and addition of new gas wells in the area, the regulation of gas wells,
    or any potential impairment to the environment caused by hydraulic fracturing in
    -8-
    Michigan is beyond the purview of the Commission. The Commission lacks the
    statutory authority to regulate hydraulic fracturing, or the drilling of gas wells in
    Michigan. That authority, and the concomitant environmental obligations that it
    engenders, rests with the State Supervisor of Wells and the Department of
    Environmental Quality. Here, the Commission’s sole concern on remand is the
    effect of the pipelines’ construction and operation on the environment and the
    state’s natural resources.
    3
    It is important to note that Mr. Farrier’s observations that the proposed pipeline
    projects have a minimal impact on the environment are not the same as a
    Commission finding that there is no impairment to the environment. The
    Commission applies the plain meaning to these terms and further notes that Mr.
    Farrier’s determination that the proposed routes minimally impact local
    ecosystems and land use supports its conclusion that the projects as proposed do
    not impair the environment.
    __________________________________________________________________
    Appellants claimed an appeal from each PSC order and this Court consolidated the
    appeals for hearing and decision.
    II. STANDARD OF REVIEW
    Pursuant to MCL 462.25, all rates, fares, charges, classification and joint rates,
    regulations, practices, and services prescribed by the PSC are presumed, prima facie, to be lawful
    and reasonable. See Mich Consol Gas Co v Pub Serv Comm, 
    389 Mich. 624
    , 635-636; 209
    NW2d 210 (1973). A party aggrieved by an order of the PSC has the burden of proving by clear
    and satisfactory evidence that the order is unlawful or unreasonable. MCL 462.26(8). A final
    order of the PSC must be authorized by law and be supported by competent, material, and
    substantial evidence. Const 1963, art 6, § 28; Attorney Gen v Pub Serv Comm, 
    165 Mich. App. 230
    , 235; 418 NW2d 660 (1987).
    We give due deference to the PSC’s administrative expertise, and we will not substitute
    our judgment for that of the PSC. Attorney Gen v Pub Serv Comm No 2, 
    237 Mich. App. 82
    , 88;
    602 NW2d 225 (1999). We give respectful consideration to the PSC’s construction of a statute
    that the PSC is empowered to execute, and we will not overrule that construction absent cogent
    reasons. In re Complaint of Rovas Against SBC Mich, 
    482 Mich. 90
    , 103; 754 NW2d 259 (2008).
    If the language of a statute is vague or obscure, the PSC’s construction serves as an aid to
    determining the legislative intent, and will be given weight if it does not conflict with the
    language of the statute or the purpose of the Legislature. 
    Id. at 103,
    108. However, the
    construction given to a statute by the PSC is not binding on us. 
    Id. at 103.
    “Whether the PSC
    exceeded the scope of its authority is a question of law that we review de novo.” In re
    Complaint of Pelland Against Ameritech Mich, 
    254 Mich. App. 675
    , 682; 658 NW2d 849 (2003).
    III. ANALYSIS
    Appellants argue that the PSC erred by denying their second attempt to intervene.
    Appellants assert that this Court’s decision vacating the PSC’s previous orders approving the
    -9-
    applications for the pipelines vacated the PSC’s previous order denying the first motion to
    intervene. Appellants also assert that their interests were affected by the pipelines and they were
    entitled to intervene on that basis.
    A lower court or tribunal must strictly comply with an appellate court’s instructions on
    remand. K & K Constr, Inc v Dep’t of Environmental Quality, 
    267 Mich. App. 523
    , 544-545; 705
    NW2d 365 (2005).
    Appellants did not appeal the PSC’s order denying their first motion to intervene. In
    
    Buggs, supra
    , this Court vacated the PSC’s orders granting the applications to construct the
    pipelines and remanded the matter to the PSC for further consideration pursuant to applicable
    requirements, but did not disturb the PSC’s order denying appellants’ motion to intervene.
    Appellants’ assertion that by vacating the PSC’s orders granting the applications this Court also
    vacated the PSC’s order denying their motion to intervene is without factual or legal support. An
    appellate argument must be supported by citation to appropriate authority or policy. MCR
    7.212(C)(7); Woods v SLB Prop Mgt, LLC, 
    277 Mich. App. 622
    , 626-627; 750 NW2d 228 (2008)
    (no citation of authority for assertion that party entitled to evidentiary hearing). In addition, in
    the order denying appellants’ second motion to intervene, the PSC reviewed appellants’ position
    but found that no subsequent developments required it to change its previous conclusion
    regarding the timeliness of appellants’ motion. We find no basis for appellate relief.
    Next, appellants argue that the PSC, when conducting its environmental impact review,
    should have considered the environmental and forest-fragmenting effects in the vicinity of the
    lines and not simply within the routes and the corridors surrounding the routes.
    In its initial decision, this Court held that the PSC failed to address the environmental
    impact of the pipelines when making its initial review of the applications. Buggs, unpub op at 9-
    11. The Buggs Court vacated the PSC’s orders approving the applications and remanded this
    matter with instructions that the PSC “specifically address the environmental impact as required
    under the MEPA and the decision in State Hwy 
    Comm, 392 Mich. at 184-190
    (opinion by
    WILLIAMS, J.).” Buggs, unpub op at 11.
    On remand, the PSC reexamined the Environmental Impact Assessments (EIAs)
    submitted by Encana with the original applications, and requested and received supplemental
    information regarding the environmental impact of the pipelines. Thereafter, the PSC discussed
    the evidence as it applied to each pipeline and concluded that neither pipeline would have a
    negative impact on the environment. The PSC specifically noted the parameters of the remand
    as constructed by this Court. The PSC noted appellants’ comments regarding the environmental
    impact on the vicinity surrounding each pipeline, as well as the risk of forest fragmentation
    resulting from future construction. The PSC concluded that the impact on the vicinity around
    each pipeline would be minimal because construction was limited to the easement area, and that
    the topic of future forest fragmentation was neither ripe for review nor within the PSC’s
    jurisdiction.
    Appellants assert that the PSC erred by failing to consider the environmental impact in
    the vicinity of the pipelines, and cite what they characterize as the “federal vicinity rule” as
    stated in 18 CFR 380.12(e)(5). This argument is without merit. The PSC conducted proceedings
    -10-
    as directed by this Court on remand. Neither MEPA nor the State Hwy Comm decision required
    the PSC to consider the federal vicinity rule when conducting its analysis. The PSC was
    required to strictly comply with this Court’s instructions on remand, K & K Constr, 267 Mich
    App at 544-545, and did so. Nothing more was required.
    Next, appellants argue that Encana’s EIAs were inadequate because they failed to detect
    the presence of Kirtland Warblers, a bird in the area. The contend that Dean Farrier, the
    biologist who conducted the EIAs, was not put forward as an expert and did not conduct a
    complete and competent search on which the PSC could properly rely.
    The law-of-the-case doctrine provides that an appellate ruling on a particular issue binds
    the appellate court and all lower tribunals with regard to that issue. Reeves v Cincinnati, Inc
    (After Remand), 
    208 Mich. App. 556
    , 559; 528 NW2d 787 (1995). A question of law decided by
    an appellate court will not be decided differently on remand or in a subsequent appeal in the
    same case when the material facts remain the same. 
    Id. “The doctrine
    applies to questions
    specifically decided in an earlier decision and to questions necessarily determined to arrive at
    that decision.” Webb v Smith (After Second Remand), 
    224 Mich. App. 203
    , 209; 568 NW2d 378
    (1997). Whether the law-of-the-case doctrine applies is a question of law that we review de
    novo. Ashker v Ford Motor Co, 
    245 Mich. App. 9
    , 13; 627 NW2d 1 (2001).
    In their appeal of the PSC’s initial orders approving Encana’s pipeline applications,
    appellants argued that Farrier’s qualifications, and therefore his EIAs, were insufficient to allow
    the PSC to make adequate findings for an analysis of the environmental impact of the pipeline
    projects. The Buggs Court rejected this argument, holding:
    Buggs and Bonamie argue that Farrier’s environmental impact
    assessments were insufficient to allow the Commission to make the requisite
    findings required by the MEPA. They claim that the assessments themselves
    should have caused the Commission to realize that they were inadequate on their
    face: Farrier analyzed the impact within the proposed easement, but did not
    include the impact on the environment in the vicinity; Farrier professed not to
    know of protected or endangered species, but did not certify that there were none;
    and Farrier claimed to be a biologist, but listed no supporting credentials. They
    also assert that the assessments were not signed or dated. However, the cover
    pages bore a date of January 2013 and indicated that they were prepared by
    Farrier. Buggs and Bonamie cite no authority that speaks to the requisite
    sufficiency of proofs on which the Commission must base its decision. The
    assessments described the routes along existing corridors, indicated that to the
    best of Farrier’s knowledge “there were no threatened or endangered species
    within the proposed easements” or “along the proposed routes,” described the
    clearing that would take place, and represented that the “workspace will be graded
    as near as possible to pre-construction contours and/or restored in accordance
    with Kalkaska County Road Commission permit requirements, and natural runoff
    and drainage patterns will be restored. All existing improvements, such as fences,
    gates, bar ditches, and beaver deceivers, will be maintained and repaired to as
    good as or better than pre-construction conditions. Permanent erosion control
    measures will be installed, and all disturbed workspace will be reseeded.”
    -11-
    Although Buggs and Bonamie’s claims that the Kirtland Warbler is
    protected or endangered and that its habitat would be affected are troubling,
    allegations to this effect were not before the Commission at the time it reviewed
    the applications. Moreover, allegations that Encana Oil intended to add more
    pipelines that would create new corridors would seem to be pertinent to future
    applications for pipeline approval, but not to the lines at issue. While the
    Commission might have been inclined to seek more information if cognizant of
    the requirement that it assess whether there were feasible and prudent alternatives
    and whether the conduct is consistent with the promotion of the public health,
    safety, and welfare in light of the state’s paramount concern for the protection of
    its natural resources from pollution, impairment, or destruction, the
    representations made by Farrier in the Assessments were not inherently suspect
    such that they could not be deemed substantial evidence on the whole record to
    support the Commission’s findings. [Buggs, unpub op at 10-11.]
    In its opinion on remand, the PSC noted that appellants had claimed that Farrier lacked
    the credentials to allow his EIAs, which were supplemented with further information and
    analysis, to be considered credible, and again found Farrier to be credible and his EIAs reliable.
    The holding of the Buggs Court controlled on remand. At issue in the original appeal
    was whether the PSC conducted the required environmental impact analysis before granting
    Encana’s applications to build the pipelines. As noted, this Court held that the PSC did not do
    so, and consequently vacated the PSC’s orders and remanded for further proceedings. Buggs,
    unpub op at 11. However, the Buggs Court held that Farrier’s EIAs were substantial evidence on
    which the PSC was entitled to rely. 
    Id. at 10-11.
    Thus, the issue raised by appellants in these
    appeals was raised and decided in the previous appeal. The holding of the Buggs Court was
    binding on remand under the law-of-the-case doctrine and we find no error requiring reversal.
    Finally, appellants argue that the PSC should have considered and found credible
    information contained in the second affidavit from Gary Cooley, who averred that he saw dead
    Kirtland’s Warblers at or near a pipeline construction site.
    In Buggs, this Court noted, in ruling that Farrier’s EIAs were to be viewed as competent
    evidence, that appellants’ claim that two Kirtland’s Warblers were found dead at Encana’s
    excavation site was not before the PSC at the time the PSC considered Encana’s applications to
    build the pipelines. Buggs, unpub op at 10. Subsequently, on remand, the PSC found that
    because appellants had not been granted intervenor status, the affidavit was not part of the record
    before it. We find no error requiring reversal with regard to this finding.4
    4
    Appellants insist that the affidavit should have been considered as part of the public
    commenting process. However, it is unreasonable to hold that the PSC must rule upon or take
    into explicit consideration every single comment raised by members of the public. At any rate,
    the fact remains that the PSC’s order was supported by competent, material, and substantial
    evidence on the whole record.
    -12-
    Affirmed.
    /s/ Jane E. Markey
    /s/ William B. Murphy
    /s/ Patrick M. Meter
    -13-
    

Document Info

Docket Number: 329909

Filed Date: 5/16/2017

Precedential Status: Non-Precedential

Modified Date: 4/17/2021