in Re Application of Indiana Michigan Power Co to Reconcile Costs ( 2016 )


Menu:
  •                            STATE OF MICHIGAN
    COURT OF APPEALS
    ___________________________________________
    In re Application of INDIANA MICHIGAN POWER
    COMPANY to Reconcile Costs.
    INDIANA MICHIGAN POWER COMPANY,                                  UNPUBLISHED
    November 29, 2016
    Appellant,
    v                                                                No. 326405
    MPSC
    MICHIGAN PUBLIC SERVICE COMMISSION,                              LC No. 00-017283
    Appellee.
    In re Application of INDIANA MICHIGAN
    POWER COMPANY to Reconcile Costs.
    _________________________________________
    INDIANA MICHIGAN POWER COMPANY,
    Petitioner-Appellant,
    v                                                                No. 327716
    MPSC
    MICHIGAN PUBLIC SERVICE COMMISSION,                              LC No. 00-017603
    Appellee.
    Before: RONAYNE KRAUSE, P.J., and O’CONNELL and GLEICHER, JJ.
    PER CURIAM.
    In these consolidated appeals, appellant Indiana Michigan Power Company (I&M)
    appeals from orders entered on September 26, 2014, and May 14, 2015, by the Michigan Public
    Service Commission (PSC) denying I&M’s request to reconcile net lost revenues for the 12-
    month period ending December 31, 2012, and approving I&M’s request to reconcile its energy
    optimization revenues and expenses for 2013, respectively. For the reasons discussed below, we
    -1-
    remand these cases for reconsideration in light of Enbridge Energy Ltd P’ship v Upper Peninsula
    Power Co, 
    313 Mich. App. 669
    ; 884 NW2d 581 (2015).
    I. BACKGROUND
    On January 27, 2010, I&M filed a general rate case application. The application, which
    was docketed as Case No. U-16180, relied on a 2010 test year, sought a revenue increase of
    $62.5 million, and included proposals for several rate adjustment mechanisms to track and align
    costs and rates, including a Net Lost Revenue Recovery Tracker (NLRT). On October 14, 2010,
    the PSC entered an order approving the parties’ settlement agreement and a rate increase of $35
    million. Paragraph 15k of the settlement agreement provided:
    The Company requested a pilot Energy Optimization (EO) decoupler that limits
    recovery to lost sales resulting from I&M’s EO plan approved in U-15808.
    I&M’s Net Lost Revenues will be recovered through a surcharge mechanism as
    discussed in the direct testimony of Staff witness Morgan and as modified in the
    rebuttal testimony of Company witness Roush. When calculating I&M’s Net Lost
    Revenues for 2011, I&M will use one-half the certified EO savings reflected in
    I&M’s 2010 sales forecast and one-half of its certified EO savings for 2011. The
    Company will be authorized to create a regulatory asset for the Net Lost
    Revenues effective January 1, 2011 to be recovered through the Net Lost Revenue
    Recovery Surcharge. The Company shall file an annual reconciliation of any over
    or under recovery of the Net Lost Revenue Recovery Surcharge coincident with
    Energy Optimization Annual Report/Reconciliation—no later than April 30th of
    each year. Since EO savings are cumulative, future EO reconciliations should
    reflect one-half of the certified EO savings for 2010 and 2011.
    I&M filed an application in its EO plan reconciliation on April 29, 2011. The application
    was docketed as Case No. U-16311. I&M requested authority to reconcile its EO plan costs, and
    also requested that in accordance with the approved Settlement Agreement in Case No. U-16180,
    it be authorized to recover Net Lost Revenues as reflected in the updated EO billing factors.
    While the application in Case No. U-16311 was pending I&M filed a general rate case on
    July 1, 2011. The rate case was docketed as Case No. U-16801. I&M relied on a 2012 test year
    and requested a rate increase of $24.5 million, noting that its existing rates were established in
    the approved Settlement Agreement in Case No. U-16180. I&M sought approval of “proposed
    changes to its terms and conditions for services as well as its proposed rate adjustment
    mechanisms.” The application made no specific reference to the NLRT approved in Case No. U-
    16180.
    The PSC issued an order on January 12, 2012, approving a Settlement Agreement in Case
    No. U-16311. The Settlement Agreement provided in pertinent part:
    The parties agree to defer to I&M’s filing in 2012 all issues concerning I&M’s
    proposed mechanism to recover lost power supply and distribution revenues, as
    authorized in paragraph 15.k. of the Settlement Agreement in Case No. U-16180.
    -2-
    On February 15, 2012, the PSC approved a Settlement Agreement in Case No. 16801.
    The order approved a rate increase for I&M in the amount of $14.6 million. Neither the PSC
    order nor the parties’ Settlement Agreement made reference to the NLRT approved in Case No.
    U-16180.
    On April 10, 2012, this Court released its decision in In re Application of Detroit Edison
    Co, 
    296 Mich. App. 101
    ; 817 NW2d 630 (2012). In that case, Detroit Edison requested authority
    to realign electric rates for certain institutional customers and, among other things, to use a
    revenue decoupling mechanism (RDM).1 The PSC issued an order allowing Detroit Edison to
    adopt an RDM. This Court reversed this portion of the PSC’s order, holding that pursuant to
    MCL 460.1089(6), the PSC had authority to approve the use of an RDM for gas utilities, but not
    electric utilities. 
    Id. at 108-110.
    On April 27, 2012, I&M filed an application, docketed as Case No. U-16739, seeking
    authority to reconcile EO revenues and expenses for 2011, and to recover net lost revenues of
    $1,137,616. I&M sought to recover the NLT through the implementation of an NLRT, which
    I&M asserted was both consistent with other NLRTs approved by the PSC and distinguishable
    from the RDM that the PSC disallowed in In re Application of Detroit Edison Co.
    II. FACTS AND PROCEEDINGS IN UNDERLYING CASES
    A. Docket No. 326405
    On April 30, 2013, I&M filed an application, docketed as Case No. U-17283, requesting
    that the PSC “commence an Energy Optimization (EO) Plan Cost Reconciliation proceeding for
    the period ended December 31, 2012 and approve [I&M’s] reconciliation of Certified Net Lost
    Revenues (CNLR) resulting from the EO plan.” On December 19, 2013, the PSC issued an
    order approving a partial Settlement Agreement. The Settlement Agreement provided in
    pertinent part:
    4. Subsequent to the prehearing conference, the parties have engaged in
    audit procedures and settlement discussions and, as a result, have reached
    agreement on the following issues in this case. The parties to this Partial
    Settlement Agreement agree as follows:
    a. The 2012 payments for electric and gas totaled $4,420,319 to the
    Independent Energy Optimization Program Administrator satisfy the payment
    requirements set forth in MCL 460.1091(1).
    1
    A revenue decoupling mechanism is a “mechanism that adjusts for sales volumes that are above
    or below the projected levels that were used to determine the revenue requirement authorized in
    the natural gas provider’s most recent rate case. In determining the symmetrical revenue
    decoupling true-up mechanism utilized for each provider, the commission shall give deference to
    the proposed mechanism submitted by the provider.” MCL 460.1089(6).
    -3-
    b. The proposed reconciliation of 2012 Energy Optimization revenues and
    payments should be approved and results in a net under-recovery of $710,067
    (including interest) through December 31, 2012. The total net under-recovery of
    $903,516 includes $193,449 of the 2011 under-recovery and should be reflected
    as the beginning balance of I&M’s 2013 Energy Optimization costs and
    reconciliation.
    c. The proposed revised Energy Optimization surcharges incorporated
    into the tariff sheets attached hereto as Attachment 1 should be approved for bills
    beginning with the first billing cycle of January 2014 or the first billing cycle in
    the month following a Commission order.
    5. The parties reserve the right to address in briefs all other issues raised
    by I&M’s testimony and exhibits but not resolved by this Partial Settlement
    Agreement. Specifically, the parties intend to address in brief issues arising from
    I&M’s proposals related to the Net Lost Revenue Tracker in this case.
    The Proposal for Decision (PFD) concluded that I&M’s NLRT terminated when new
    rates were approved in Case No. U-16801, and stated:
    Contrary to I&M’s arguments, the cumulative nature of the reconciliation
    calculations in which sales reductions (savings) in one year are carried forward
    into future years, does not mean that the mechanism was intended to apply to
    rates set in future rate cases. Instead, the provision that Energy Optimization
    savings are cumulative and thus future period reconciliations should reflect prior
    period savings also shows that the mechanism is intrinsically linked to the rate
    case in which it was authorized, because the savings are calculated with reference
    to the sales level established in that case.
    Although the settlement agreement refers to future reconciliations, i.e.
    indicating that reconciliations were expected for more than just one year, this also
    does not mean that the mechanism was intended to apply once base rates were
    revised.
    The PFD rejected I&M’s argument that the Staff’s contention that the NLRT did not
    survive beyond Case No. U-16180 constituted a collateral attack on the Settlement Agreements
    entered in Case Nos. U-16180, U-16311, U-16379, and U-16801, and concluded that the NLRT
    established in Case No. U-16180 did not exist independently from the rates established in that
    case.
    The PFD also contained the following relevant statement:
    As discussed in section II above, the parties also disagree whether the
    Commission could have approved the pilot decoupling mechanism of Net Lost
    Revenue Tracker in Case No. U-16801, based on the Court of Appeals rulings
    that the Commission does not have authority to approve a revenue decoupling
    mechanism. This PFD finds that it is not necessary to resolve the dispute whether
    the Net Lost Revenue Tracker is truly a revenue decoupling mechanism covered
    -4-
    by the Court’s rulings. As I&M argues, the decision in the first of these cases, In
    re Application of Detroit Edison Co, 
    296 Mich. App. 101
    (2012), was not issued
    until April 10, 2012. By that point, Case No. U-16801 had been resolved by
    settlement agreement, with a final Commission order issued February 15, 2012.
    Had the parties agreed to include a Net Lost Revenue Tracker in that settlement
    agreement, it would have been presumptively lawful, consistent with the
    Commission’s August 14, 2013 decision in Case No. U-16990.
    The PSC entered an order on September 26, 2014, adopting the findings and conclusions
    set out in the PFD. The order concluded as follows:
    The Commission finds the PFD well-reasoned and adopts its findings and
    conclusions as discussed below. First, the Commission agrees that the NLRT is
    indeed linked to the sales approved in the rate case. I&M admitted as much when
    Mr. Yontz testified that while the method from Case No. U-16180 was used in
    calculating the lost revenues for 2012 and 2013, the revised sales from Case No.
    U-16801 were used in the calculation. More importantly, because these lost sales
    are cumulative, and past losses are apparently used to adjust the sales projection
    in the next rate proceeding, it is essential that the company provide some
    explanation of how these accumulated losses were accounted for, so that other
    parties might have an opportunity to evaluate and audit the changes in sales due to
    past EO efforts. In I&M’s case, this accounting did not occur because the
    company did not include any discussion of the NLRT in its filing in Case No. U-
    16801.
    I&M argues that pursuant to MCL 462.25 and MCL 460.57, any rate, fare,
    charge, tariff, or rate schedule remains effective until the Commission
    affirmatively terminates it. In addition, I&M cites the November 9, 2009 order in
    Case No. U-15645 as a recent example where the Commission explicitly ended
    the CIM for Consumers Energy Company. I&M points out that, in contrast, the
    Commission did not affirmatively end the NLRT when it approved the settlement
    agreement in Case No. U-16801. Therefore, according to I&M, the NLRT
    continued after new rates were approved in that case.
    There are several problems with this argument. First, MCL 462.25 and
    MCL 460.57 refer to rates, fares, charges, tariffs, and the like, but the NLRT is
    merely a mechanism for calculating a particular charge. The actual charge
    associated with the NLRT is the surcharge that was approved in Case No. U-
    16739, related solely to the settlement agreement in Case No. U-16180, which has
    in fact continued because the Commission has not affirmatively ended the charge.
    Second, past trackers including forestry, uncollectibles, the CIM and various
    RDMs have consistently been raised by the applicants in subsequent rate
    proceedings, especially when the applicant seeks to continue the tracker. While
    I&M points to cases where trackers were contested and expressly terminated, it
    can point to no cases, and indeed the Commission is unaware of any, where a
    tracker (many of which began as pilots that were adjusted or refined in later cases)
    was automatically continued when it was not at least raised by the applicant in a
    -5-
    subsequent rate proceeding. If, as I&M asserts, the NLRT is indeed a vital
    ratemaking mechanism, it was incumbent on the company (not the Staff or
    intervenors) to ensure that the mechanism was addressed in any subsequent
    general proceeding.
    The PSC denied I&M’s request to reconcile certified net lost revenues for the 12-month
    period ending December 31, 2012, ended the surcharge for net lost revenues approved in the
    order entered on December 20, 2012, Case No. U-16739, and ordered I&M to file a
    reconciliation of revenues collected under the surcharge established in Case No. U-16739.
    B. Docket No. 327716
    On April 30, 2014, I&M filed an application, docketed as Case No. U-17603, seeking
    approval of its EO reconciliation of costs for the 12-month period ending December 31, 2013,
    and requesting approval of an NLRT surcharge.
    The PFD noted that the parties agreed that I&M’s EO reconciliation, which showed an
    EO underrecovery of $261,083, plus interest, for 2013 should be approved. In response to
    I&M’s argument that the PSC’s September 26, 2014, order was wrongly decided, the PFD
    stated:
    Further, based on a review of the record and the briefs of the parties, this
    PFD concludes that the proper disposition of I&M’s CNLPR surcharge request is
    controlled by the Commission’s September 26, 2014 and February 12, 2015
    orders in Case No. U-17283. In that case, the Commission found that I&M’s Net
    Lost Revenue tracking mechanism was not continued when rates were revised in
    Case No. U-16801. I&M sought rehearing of the Commission’s decision in Case
    No. U-17283. In its February 12, 2015 order in that docket, the Commission
    rejected I&M’s request for rehearing. I&M has not presented new arguments in
    this case that were not presented to the Commission in its rehearing request,
    including its argument that the Commission’s September 26, 2014 order was
    wrongly decided, that I&M acted in good faith, that public policy favors revenue
    decoupling mechanisms to encourage energy efficiency, and that the
    Commission’s order works a hardship on I&M. Thus, although I&M claims this
    case raises new issues not raised in Case No. U-17283, this PFD does not find
    support for I&M’s position. On this basis, this PFD recommends that the
    Commission reject I&M’s proposed CNLR surcharge.
    The PSC entered an order on May 14, 2015, adopting the findings and conclusions set out
    in the PFD. The PSC noted that the NLRT was approved in Case No. U-16180, and concluded:
    Subsequently, in April 2011, in Case No. U-16311, an EO reconciliation
    case, I&M filed a request to implement a NLRT surcharge in accordance with
    approvals in the October 14 order. In the settlement in that case, the parties
    apparently agreed to defer the surcharge until a later reconciliation. While Case
    No. U-16311 was pending, I&M filed another rate case, Case No. U-16801. I&M
    did not request any trackers in that case and, significantly did not mention or
    -6-
    discuss the NLRT in its application or prefiled testimony. As such no party was
    given an opportunity to assess the efficacy of the NLRT or make any
    modifications to the tracker, as is very often done with pilot mechanisms. Case
    No. U-16801 was also settled, this time with no mention of the NLRT. The
    settlement agreement was approved in an order issued on February 15, 2012.
    That order did not authorize I&M to implement, or continue, the NLRT. As the
    Commission has repeatedly explained, I&M’s failure to request authority to
    continue the NLRT in the rate case subsequent to the case where the mechanism
    was initially approved was fatal to its claims in Case No. U-17283 and to those in
    the instant proceeding.
    I&M appealed the PSC’s September 26, 2014, and May 14, 2015, orders. This Court
    consolidated the appeals for purposes of hearing and decision.
    III. Standard of Review
    The standard of review for PSC orders is narrow and well defined. Pursuant to MCL
    462.25, all rates, fares, charges, classification and joint rates, regulations, practices, and services
    prescribed by the PSC are presumed, prima facie, to be lawful and reasonable. Mich Consol Gas
    Co v Pub Serv Comm, 
    389 Mich. 624
    , 635-636; 209 NW2d 210 (1973). A party aggrieved by an
    order of the PSC has the burden of proving by clear and convincing evidence that the order is
    unlawful or unreasonable. MCL 462.26(8). To establish that a PSC order is unlawful, the
    appellant must show that the PSC failed to follow a mandatory statute or abused its discretion in
    the exercise of its judgment. In re MCI Telecom Complaint, 
    460 Mich. 396
    , 427; 596 NW2d 164
    (1999). An order is unreasonable if it is not supported by the evidence. Associated Truck Lines,
    Inc v Pub Serv Comm, 
    377 Mich. 259
    , 279; 140 NW2d 515 (1966).
    A final order of the PSC must be authorized by law and be supported by competent,
    material, and substantial evidence on the whole record. Const 1963, art 6, § 28; Attorney
    General v Pub Serv Comm, 
    165 Mich. App. 230
    , 235; 418 NW2d 660 (1987).
    A reviewing court gives due deference to the PSC’s administrative expertise, and is not to
    substitute its judgment for that of the PSC. Attorney General v Pub Serv Comm No 2, 237 Mich
    App 82, 88; 602 NW2d 225 (1999). We give respectful consideration to the PSC’s construction
    of a statute that the PSC is empowered to execute, and we will not overrule that construction
    absent cogent reasons. If the language of a statute is vague or obscure, the PSC’s construction
    serves as an aid to determining the legislative intent, and will be given weight if it does not
    conflict with the language of the statute or the purpose of the Legislature. However, the
    construction given to a statute by the PSC is not binding on us. In re Complaint of Rovas
    Against SBC Mich, 
    482 Mich. 90
    , 103-109; 754 NW2d 259 (2008). Whether the PSC exceeded
    the scope of its authority is a question of law that we review de novo. In re Complaint of
    Pelland Against Ameritech Mich, 
    254 Mich. App. 675
    , 682; 658 NW2d 849 (2003).
    IV. Analysis
    On appeal, I&M argues that the PSC erred by finding that the NLRT approved in Case
    No. U-16180, i.e., the first general rate case, was terminated because I&M did not raise its
    -7-
    applicability in Case No. U-16801, i.e., the second general rate case. The PSC’s past practice
    showed that a tracker such as the NLRT continued absent an agreement by the parties or a
    directive from the PSC to terminate it. I&M relied on this past practice and so omitted reference
    to the NLRT in its application in the second general rate case. Under the circumstances, the PSC
    is equitably estopped from taking the position that the NLRT terminated upon the
    implementation of new rates in the second general rate case. I&M also argues that the PSC’s
    decision to terminate the NLRT deprived it of approximately $4.475 million in revenue it would
    have collected if the PSC had left the NLRT in place, and it of the right to fair and just treatment
    guaranteed by the Michigan Constitution. Const 1963, art 1, § 17.
    We hold that these cases must be remanded for reconsideration in light of Enbridge
    Energy Ltd P’ship v Upper Peninsula Power Co, 
    313 Mich. App. 669
    ; 884 NW2d 581 (2015).
    As noted above, in In re Application of Detroit Edison, this Court held that the PSC
    lacked the statutory authority to approve the use of an RDM by an electric utility because MCL
    460.1089(6) authorized the use of an RDM by a gas utility only. In re Application of Detroit
    
    Edison, 296 Mich. App. at 108-110
    .
    In Enbridge Energy, this Court considered the question whether the PSC had the statutory
    authority to approve a settlement agreement that provided for the use of an RDM by an electric
    utility. In that case, the Upper Peninsula Power Company (UPPC) filed an application in June
    2009 seeking a rate increase. The UPPC and other parties, including the PSC Staff, entered into
    a settlement agreement that granted UPPC a rate increase and implemented an RDM for the test
    year 2010. Enbridge 
    Energy, 313 Mich. App. at 671
    . In May 2011, UPPC filed an application for
    reconciliation of costs associated with the RDM and to recover a shortfall in revenues. While
    that application was pending, this Court decided In re Application of Detroit Edison.
    Notwithstanding this Court’s decision in In re Application of Detroit Edison, the PSC concluded
    that the RDM agreed to by UPPC and other parties could stand because it merely had to comply
    with the settlement agreement, and that it had the authority to approve the settlement agreement.
    Enbridge filed a formal complaint arguing that the PSC lacked the authority to approve the use of
    an RDM by an electric utility. The PSC rejected that argument and dismissed the complaint. 
    Id. at 671-673.
    In Enbridge Energy, this Court reversed the PSC’s decision, holding that the PSC
    exceeded its statutory authority by approving the underlying settlement agreement and
    dismissing Enbridge’s complaint. The Enbridge Energy Court emphasized that while MCL
    460.1089(6) authorized the PSC to approve the use of an RDM by gas utilities, no corresponding
    statute authorized the PSC to approve the use of an RDM by an electric utility. The PSC held
    that the fact that the RDM at issue was approved in the context of a settlement agreement was
    not dispositive. Enbridge 
    Energy, 313 Mich. App. at 675-677
    . The Enbridge Energy Court
    concluded:
    In sum, the PSC exceeded its clear statutory authority when it approved
    the RDM in Case No. U-16568. The fact that the approval was accomplished in
    the context of a settlement agreement does not transform the PSC’s ultra vires act
    into a legal one. See, e.g., Timney v Lin, 106 Cal App 4th 1121, 1127-1129; 131
    Cal Rptr 2d 387 (Cal App, 2003) (“[E]ven though there is a strong public policy
    -8-
    favoring the settlement of litigation, this policy does not excuse a contractual
    clause that s otherwise illegal or unjust.”). We stress that our holding is based on
    the fact that reasonable minds could not have disputed the extent of the PSC’s
    authority at the time it approved the settlement agreement. [Enbridge 
    Energy, 313 Mich. App. at 678
    .]
    I&M argues that Enbridge Energy is inapplicable because the NLRT is distinguishable
    from the RDM found void in Enbridge Energy. I&M notes that a PSC Staff witness stated that
    the NLRT was more limited in scope than other mechanisms approved by the PSC and focused
    on lost revenues.
    We remand these cases to the PSC for reconsideration in light of Enbridge Energy. The
    PSC has “only that authority granted to it by the Legislature.” Mich Elec Coop Ass’n v Pub Serv
    Comm, 
    267 Mich. App. 608
    , 616; 705 NW2d 709 (2005). No statutory authority allows the PSC
    to approve an RDM for an electric utility. In re Application of Detroit 
    Edison, 296 Mich. App. at 108-110
    . The relevant question, then, is whether the definition of an RDM is sufficiently
    expansive to include the NLRT approved in Case No. U-16180.
    The issue whether the NLRT is factually distinct from RDMs approved by the PSC in
    other cases requires analysis of the specific structure of the NLRT and comparison of that
    structure to RDMs approved by the PSC. The performance of such an analysis is more suited to
    the PSC in the first instance. We defer to the administrative expertise of the PSC. Attorney
    
    General, 237 Mich. App. at 88
    . Moreover, it is apparent that the PSC approves a number of
    RDMs and similar mechanisms. To have the PSC rule on the validity of the NLRT in light of
    Enbridge Energy would provide guidance for future cases.
    Whether these cases continue is entirely dependent on the applicability of Enbridge
    Energy. Therefore, an analysis of the issues raised by I&M is premature.
    V. CONCLUSION
    We conclude that analysis of the issues raised by I&M is premature in light of Enbridge
    Energy and remand these matters to the PSC for reconsideration in light of that case. We do not
    retain jurisdiction.
    /s/ Amy Ronayne Krause
    /s/ Peter D. O'Connell
    /s/ Elizabeth L. Gleicher
    -9-
    

Document Info

Docket Number: 327716

Filed Date: 11/29/2016

Precedential Status: Non-Precedential

Modified Date: 4/18/2021