in Re Application of Dte Electric Company for 2015 Reconciliation ( 2018 )


Menu:
  •                            STATE OF MICHIGAN
    COURT OF APPEALS
    In re APPLICATION OF DTE ELECTRIC
    COMPANY FOR 2015 RECONCILIATION.
    DTE ELECTRIC COMPANY,                                                UNPUBLISHED
    December 6, 2018
    Petitioner-Appellant,
    v                                                                    No. 339557
    MPSC
    MICHIGAN PUBLIC SERVICE COMMISSION,                                  LC No. 00-017680-R
    Appellee.
    Before: RIORDAN, P.J., and RONAYNE KRAUSE and SWARTZLE, JJ.
    PER CURIAM.
    Petitioner, DTE Electric Company (DTE), appeals as of right an order entered by the
    Michigan Public Service Commission (PSC) that, in relevant part, disallowed DTE’s request to
    include a refund in its 2015 power supply cost recovery (PSCR) reconciliation balance under
    MCL 460.6j.1 The refund was issued by DTE in 2015, as a consequence of overbilling a major
    customer for electrical power between 2008 and 2014. The PSC concluded that because the
    refund was for power consumed outside of the 12-month reconciliation period for 2015, it could
    not be included in the reconciliation. The PSC therefore denied DTE’s request. We reverse in
    part and remand.
    I. INTRODUCTION
    One of the ways in which an electric utility can recover its power supply costs from its
    customers is by including a “PSCR clause” in its rate schedule. See In re App of Consumers
    Energy Co for Reconciliation of 2009 Costs, 
    307 Mich. App. 32
    , 35 n 1; 859 NW2d 216 (2014),
    1
    While this matter was pending in the PSC, the Legislature amended MCL 460.6j pursuant to
    
    2016 PA 341
    . The PSC did not specify which version of the statute it used; however, neither we
    nor the parties have discovered any substantive alterations of relevance to the instant appeal.
    Therefore, all references to MCL 460.6j in this opinion will be to the prior version of the statute,
    which was in effect during the 2015 reconciliation period at issue.
    -1-
    aff’d on alternative grounds 
    499 Mich. 885
    (2016). “PSCR” stands for “power supply cost
    recovery.” See MCL 460.6j(1). This Court has explained the PSCR process as follows:
    A PSCR clause is “a clause in the electric rates or rate schedule of a utility which
    permits the monthly adjustment of rates for power supply to allow the utility to
    recover the booked costs, including transportation costs, reclamation costs, and
    disposal and reprocessing costs, of fuel burned by the utility for electric
    generation and the booked costs of purchased and net interchanged power
    transactions by the utility incurred under reasonable and prudent policies and
    practices.” MCL 460.6j(1)(a). Each year, a utility with a PSCR clause in its rate
    schedule must file a PSCR plan for the upcoming year and a five-year forecast of
    power supply requirements. MCL 460.6j(3) and (4). The PSC approves,
    disapproves, or modifies the proposed PSCR plan. MCL 460.6j(6). After the end
    of the year, the PSC conducts a reconciliation case in which it makes adjustments
    to take into account the utility's true cost of supplying power. MCL 460.6j(12)
    and (13). [In re App of Indiana Michigan Power Co, 
    275 Mich. App. 369
    , 370-
    371; 738 NW2d 289 (2007).]
    “Electric utilities can recover two types of power supply costs through a PSCR clause: (1)
    ‘booked costs, including transportation costs, reclamation costs, and disposal and reprocessing
    costs, of fuel burned by the utility for electric generation;’ or (2) ‘booked costs of purchased and
    net interchanged power transactions.’ ” Attorney General v Pub Service Comm, 
    483 Mich. 998
    ,
    998; 764 NW2d 278 (2009), quoting MCL 460.6j(1)(a).
    In very general terms, the PSC compares an electric utility’s revenues to its costs,
    “reconciles” the two, and permits the electric utility to adjust its rates accordingly. See Attorney
    General v Pub Service Comm, 
    237 Mich. App. 27
    , 30; 602 NW2d 207 (1999). If the utility
    collected more revenue than its costs, it must refund or credit the excess to its customers. MCL
    460.6j(14) and (16). If it collected less revenue than its costs, it may recover the difference from
    its customers. MCL 460.6j(15) and (16).2
    II. FACTUAL BACKGROUND
    2
    In part, MCL 460.6j(16) states, “Costs incurred by the utility for refunds and interest on refunds
    shall not be charged to customers.” In context, this appears to refer to refunds issued as a
    consequence of the reconciliation process and therefore does not pertain to the refund at issue
    here. Furthermore, DTE argued at oral argument, and the PSC did not dispute, that the term
    “costs . . . for refunds” is understood to mean ancillary costs such as postage, processing, or
    programming, rather than the refund itself. Either understanding is supported by the lack of
    discussion of this sentence below. Consequently, we conclude that this sentence is irrelevant to
    the instant appeal. The Severstal refund is an entirely different kind of refund than a
    reconciliation refund, which “enjoys a broader meaning” because it can also encompass an
    adjustment of future rates in addition to a direct repayment of money. In re Detroit Edison Co
    Application, 
    297 Mich. App. 377
    , 385-387; 823 NW2d 433, 437 (2012), result aff’d but criticized
    on other grounds 
    495 Mich. 884
    (2013).
    -2-
    Between 2008 and 2014, DTE overbilled one of its large customers for electricity, due to
    an undiscovered technical error. The customer, Severstal Dearborn, LLC (Severstal), which is
    not a party to the instant matter, discovered the error in 2014, whereupon it filed a complaint
    against DTE with the PSC. In 2015, the PSC ordered DTE to repay approximately $19.65
    million to Severstal, plus 7% interest. Notably, it is undisputed, and in fact expressly admitted
    by both parties at oral argument, that because of Severstal’s overpayment, DTE’s other
    customers enjoyed artificially lowered energy rates in 2008 through 2014. Consequently, DTE
    did not profit from the overbilling.
    The instant proceeding is a separate reconciliation proceeding. In relevant part, DTE
    sought to have approximately $13.45 million of the Severstal refund considered a “negative
    revenue” in 2015 for the purpose of reconciliation. DTE contends that this amount reflects only
    “the PSCR portion” of the Severstal refund, and it therefore excludes the substantial interest
    DTE was required to pay.3 If that amount is “reconciled,” DTE would be permitted to raise its
    energy rates to counteract that loss. In effect, DTE would theoretically recoup the windfall from
    the same customers who previously enjoyed it. The PSC rejected DTE’s request. The PSC held
    that the Severstal refund could not be reconciled in 2015 because it represented “lost PSCR
    revenue from the cost of power supply consumed between the years 2008 and 2014,” and
    therefore outside “[t]he 12-month period covered by DTE Electric’s PSCR plan [which] began
    on January 1, 2015 and ended December 31, 2015.”
    III. STANDARD OF REVIEW
    As this Court recently explained in In re Reliability Plans of Electric Utilities for 2017-
    2021, ___ Mich App ___, ___; ___ NW2d ___ (2018) (Docket No. 340600), slip op at 8, lv
    pending:
    To be valid, a final order of the MPSC must be authorized by law, and
    also must be supported by competent, material, and substantial evidence on the
    whole record. Const 1963, art 6, § 28; Attorney General v Pub Serv Comm, 
    165 Mich. App. 230
    , 235; 418 NW2d 260 (1988). Agencies have authority to interpret
    the statutes that they administer and enforce, Clonlara, Inc v State Board of Ed,
    
    442 Mich. 230
    , 240; 501 NW2d 88 (1993), and we respectfully consider an
    agency’s interpretation of a statute that it is empowered to execute, and will not
    overrule that construction absent cogent reasons. In re Complaint of Rovas
    Against SBC Mich, 
    482 Mich. 90
    , 103; 754 NW2d 259 (2008). But the
    construction the [PSC] gives to a statute is not binding on the courts. 
    Id. Ultimately, the
    statutory language itself is controlling, 
    id. at 108,
    and this Court
    will neither abandon nor delegate its responsibility to determine legislative intent.
    3
    At oral argument, DTE was asked what incentive it had “to get it right” if it was allowed to
    reconcile the PSCR portion of the Severstal refund. DTE observed that at most it would be
    “getting our principle back,” without the benefit of “interest going back to 2008.” It appears
    that, in contrast, the 7% interest imposed upon the refund requires DTE to compensate Severstal
    for Severstal’s lost benefit of that interest.
    -3-
    Consumers Energy Co[ v Pub Service Comm], 268 Mich App [171,] 174-175[;
    707 NW2d 633 (2005)]. Moreover, we review de novo issues of statutory
    interpretation, Uniloy Milacron USA Inc v Dep’t of Treasury, 
    296 Mich. App. 93
    ,
    96; 815 NW2d 811 (2012), including the MPSC’s determinations regarding the
    scope of its own authority. Consumers Power Co v Pub Serv Commission, 
    460 Mich. 148
    , 157; 596 NW2d 126 (1999); In re Application of Consumers Energy
    Co to Increase Rates, 
    316 Mich. App. 231
    , 237; 891 NW2d 871 (2016). In sum,
    when considering the construction given to a statute by an agency, our ultimate
    concern is the proper construction of the plain language of the statute regardless
    of the agency’s interpretation, 
    Rovas, 482 Mich. at 108
    , and our primary
    obligation is to discern and give effect to the Legislature’s intent. City of
    Coldwater v Consumers Energy Co, 
    500 Mich. 158
    , 167; 895 NW2d 154 (2017).
    Additionally, we review de novo questions of constitutional law and questions concerning
    subject-matter jurisdiction. In re Consumers Energy Co, 
    322 Mich. App. 480
    , 491; 913 NW2d
    406 (2017); In re Petition of Wayne Co Treasurer for Foreclosure, 
    286 Mich. App. 108
    , 110; 777
    NW2d 507 (2009). The relevant facts are not meaningfully disputed, and the PSC’s final
    decision set forth no factual findings that DTE challenges on appeal.
    In particular, we note that several relevant facts are undisputed or presumed. First, the
    Severstal refund was money with which DTE parted in 2015. Second, the Severstal refund
    reflects a return of money collected outside of 2015, for power that was consumed outside of
    2015. Furthermore, DTE did not truly profit from the overcollection; rather, the overcollection
    benefitted DTE’s customers, and those customers would also bear the burden if the refund were
    to be “reconciled.” Finally, the PSC did not actually render a final decision about whether the
    overcollection was due to DTE acting unreasonably and imprudently. Although the PSC
    “rejected” the ALJ’s finding that DTE incurred the overbilling by acting imprudently and
    unreasonably, the PSC did so because it deemed “that line of inquiry” unnecessary. Therefore,
    we presume, but explicitly do not decide, that DTE acted reasonably and prudently at all relevant
    times.
    IV. THE RECONCILIATION PERIOD
    We first conclude that reconciliations cover a 12-month period. Subsection (12) indicates
    that the reconciliation process must occur “[n]ot less than once a year” and that the PSC must
    “commence” it “not later than 3 months after the end of the 12-month period covered by a
    utility’s power supply cost recovery plan[.]” (Emphasis added.) When discussing what is to be
    reconciled, subsection (12) further provides:
    At the power supply cost reconciliation the commission shall reconcile the
    revenues recorded pursuant to the power supply cost recovery factors and the
    allowance for cost of power supply included in the base rates established in the
    latest commission order for the utility with the amounts actually expensed and
    included in the cost of power supply by the utility. The commission shall
    consider any issue regarding the reasonableness and prudence of expenses for
    which customers were charged if the issue was not considered adequately at a
    previously conducted power supply and cost review. [MCL 460.6j(12).]
    -4-
    This language must be read in context. Madugula v Taub, 
    496 Mich. 685
    , 696; 853 NW2d 75
    (2014). In particular, subsections (3), (6), and (10) clearly indicate that PSCR plans always
    cover a discrete, specific “12-month period.” Referring to “the 12-month period” would make
    no sense unless it means the particular 12-month period covered by a particular PSCR plan. This
    is consistent with commencing a reconciliation yearly, and at a time specifically tied to “the 12-
    month period.” It is also consistent with the express provision of a mechanism for considering
    certain prior expenses “not considered adequately at a previously conducted power supply and
    cost review.”
    It follows that the subsections under which the PSC may order a recovery from (or a
    refund to) a utility’s customers must pertain to the same period. The specific authorization for
    any recovery from DTE’s customers is found in subsection (15), which states in relevant part:
    In its order in a power supply cost reconciliation, the commission shall authorize a
    utility to recover from customers any net amount by which the amount determined
    to have been recovered over the period covered was less than the amount
    determined to have been actually expensed by the utility for power supply, and to
    have been incurred through reasonable and prudent actions not precluded by the
    commission order in the power supply and cost review. [MCL 460.6j(15).]
    Because these subsections address orders “in a power supply cost reconciliation,” it would again
    make no sense unless “the period covered” is the same period considered at the reconciliation.
    Therefore, “the period covered” must be the specific 12-month period covered by the PSCR plan
    at issue. In this case, that period would be January 1, 2015 through December 31, 2015.
    V. DEFINING THE SEVERSTAL REFUND
    The central issue in this appeal is how to define the Severstal refund. Again, the
    Severstal refund consists of money that left DTE’s coffers in 2015. The money satisfies a return
    of monies that were overcollected between 2008 and 2014. DTE did not benefit from that
    overcollection, and because the refund includes interest that DTE cannot ever recover, DTE
    would remain “in the negative” even with the reconciliation of the $13.45 million it seeks.
    Between 2008 and 2014, DTE’s customers benefitted from the overpayment, and reconciliation
    would mean those customers must return their windfall. The one characterization upon which
    both parties expressly agree is that the Severstal refund is not an “expense.”
    DTE argues that the Severstal refund is a “negative revenue” because it is a “revenue
    recorded,” albeit a negative one. The PSC argues that the refund is “not a cost of power supply
    but lost revenue from the cost of power consumed” (emphasis in original). Therefore, both
    parties seemingly also agree that the Severstal refund was some kind of revenue. However, DTE
    has not provided us with a definition of “negative revenue,” and the PSC protests that it does not
    know how a “negative revenue” would be defined. Finding no helpful definitions4 in either
    4
    DTE stated that “expenses” are defined under the Michigan Public Service Commission Act,
    but we have not found any such express statutory definition, nor has either party cited to one.
    -5-
    party’s briefs or in the Act, we turn to a dictionary. See In re Certified Question from the United
    States Court of Appeals for the Ninth Circuit (Deacon v Pandora Media, Inc), 
    499 Mich. 477
    ,
    484-485; 885 NW2d 628 (2016).
    An “expense” may be defined as synonymous with expenditure or cost, or “something
    expended to secure a benefit or bring about a result.” Merriam-Webster’s Collegiate Dictionary
    (11th ed), p 440. However, accounting terminology suggests that “expense” and “expenditure”
    have distinct meanings. Although both may entail an exchange of value for value, an
    expenditure particularly refers to the outlay of money itself, whereas an expense particularly
    refers to using up an asset or exchanging that asset for revenue. See Siegel & Shim, Dictionary
    of Accounting Terms, 3d ed (Hauppage, New York: Barron’s, 2000), pp 169-170.5 A “cost” may
    be defined as a penalty incurred, as “the amount or equivalent paid or charged for something,” or
    as an “outlay or expenditure.” Merriam-Webster’s, p 282. In accounting terminology, “[t]he
    concepts of cost and expense are often used interchangeably,” but a cost would generally be a
    “sacrifice, measured by the price paid, to acquire, produce, or maintain goods or services.”
    Dictionary of Accounting Terms, p 104. Finally, “revenue” may be treated as gross income or
    total income from a particular source. Merriam-Webster’s, p 1066. In accounting terminology,
    it means an “increase in the assets of an organization or the decrease in liabilities during an
    accounting period, primarily from the organization’s operating activities.” Dictionary of
    Accounting Terms, p 380.
    We conclude that at least for accounting purposes, the concepts of “expense,”
    “expenditure,” and “cost” all nominally imply a degree of exchange for value. Clearly, the
    Severstal refund was not exchanged for any value. We are therefore inclined to agree with the
    parties that it was neither an “expense” nor a “cost.” In contrast, “revenue” appears to pertain
    more simply to money or assets transferred to an entity. Rather than leave the Severstal refund
    in an undefined limbo, we conclude that “lost revenue,” as the PSC puts it, most sensibly6 fits the
    definition of “revenue,” with the modifier “negative” merely indicating the direction of that
    revenue. See, e.g., “negative income tax,” Merriam-Webster’s, p 829. In other words,
    “revenue” pertains to an inflow of money, and “negative revenue” therefore pertains to an
    outflow of money. We therefore accept and adopt DTE’s contention that the Severstal refund is
    a “negative revenue” that indisputably occurred during 2015.
    VI. CONSIDERATION OF THE SEVERSTAL REFUND
    5
    See also, discussions online at https://www.accountingtools.com/articles/2017/5/6/expense and
    https://www.accountingcoach.com/blog/difference-expense-expenditure.
    6
    Our Supreme Court has rejected “the so-called ‘absurd result’ rule of statutory construction.”
    Piccalo v Nix, 
    466 Mich. 861
    ; 643 NW2d 233 (2002), citing People v McIntire, 
    461 Mich. 147
    ,
    155-156, n 2; 599 NW2d 102 (1999). However, the discussion in McIntire concerned a
    departure from the literal language of a statute on the grounds that the literal result would be
    unwise. 
    McIntire, 461 Mich. at 155-159
    . If construction of a statute is necessary, any such
    construction should nevertheless avoid an absurd result to the extent consistent with its plain
    language. See Rafferty v Markovitz, 
    461 Mich. 265
    , 270; 602 NW2d 367 (1999).
    -6-
    Having concluded that the Severstal refund is a “negative revenue,” DTE next argues that
    the PSC is required to include it in the 2015 reconciliation. However, the reconciliation process
    does not include any revenue, but rather “revenues recorded pursuant to the power supply cost
    recovery factors.” MCL 460.6j(12) (emphasis added). Therefore, whether the Severstal refund
    is a “revenue” does not end the inquiry.
    The Act defines “power supply cost recovery factor” as:
    that element of the rates to be charged for electric service to reflect power supply
    costs incurred by an electric utility and made pursuant to a power supply cost
    recovery clause incorporated in the rates or rate schedule of an electric utility.
    [(MCL 460.6j(1)(b)).]
    A PSCR clause permits the recovery of “(1) ‘booked costs, including transportation costs,
    reclamation costs, and disposal and reprocessing costs, of fuel burned by the utility for electric
    generation;’ or (2) ‘booked costs of purchased and net interchanged power transactions.’ ”
    Attorney 
    General, 483 Mich. at 998
    , quoting MCL 460.6j(1)(a). Notably, a PSCR clause is
    distinct from a PSCR plan. A PSCR clause appears to be a durable part of a utility’s rates, rather
    than specific to a particular year. “Pursuant to” means “in carrying out” or “in conformity with.”
    Merriam-Webster’s, p 1011. Alternately, it means “in compliance with; in accordance with;
    under.” Black’s Law Dictionary (8th ed), p 1272. We conclude that “revenues recorded pursuant
    to the power supply cost recovery factors” means revenues that pertain to the costs recoverable
    under a PSCR clause.
    As noted, DTE contends that the $13.45 million it seeks to reconcile is the “PSCR
    portion” of its payment to Severstal. According to the proposal for decision by the ALJ, the
    PSC’s staff did not dispute that characterization. In its final decision, the PSC reiterated that its
    staff had not disputed that the $13.45 million is a “PSCR expense,” and nowhere in the final
    decision do we find any indication that the PSC or its staff took any subsequent exception to that
    characterization. We adopt what appears to be an undisputed fact: that the $13.45 million
    portion of the Severstal refund is a “revenue recorded pursuant to the power supply cost recovery
    factors,” notwithstanding the fact that it is negative. Because the revenue itself occurred in 2015,
    it must be reconciled as part of the 2015 reconciliation.
    We briefly observe that our conclusion appears to be consistent with past PSC practices,
    as reflected by the two PSC cases discussed below. In In re the application of DTE Electric
    Company for reconciliation of its power supply cost recovery plan for the 12-month period
    ending December 31, 2013, MPSC Case No. U-17097-U, DTE received a payment of
    $28,607,330 from Consumers Energy in 2013 compensating for a 2008 billing error by a third
    party, and the PSC included that payment in DTE’s 2013 reconciliation. In In re the application
    of Consumers Energy Company for the reconciliation of power supply cost recovery costs and
    revenues for the Calendar Year 2012, MPSC Case No. U-16890-R, the same payment was
    -7-
    included in Consumers Energy’s 2012 reconciliation, even though it made the payment in 20137
    and the billing errors occurred between 2008 and 2011. We do not mean to suggest that the PSC
    is bound by stare decisis and we recognize the PSC’s explanation that those cases are factually
    distinguishable from the instant matter. Nevertheless, even considering the factual differences,
    those cases clearly reflect an understanding that a refund addressing costs that occurred in other
    plan-years may be reconciled in the year the refund itself occurs.8
    Therefore, we conclude that the PSC erred by refusing to reconcile the PSCR portion of
    the Severstal refund, which is not disputed to be the $13.45 million at issue here.
    VII. CONSIDERATION OF “EXPENSES” FROM PRIOR YEARS
    The final sentence of MCL 460.6j(12) provides that “[t]he commission shall consider any
    issue regarding the reasonableness and prudence of expenses for which customers were charged
    if the issue was not considered adequately at a previously conducted power supply and cost
    review.” “Shall” is mandatory, and “any” is all-inclusive. See McGrath v Clark, 
    89 Mich. App. 194
    , 197; 280 NW2d 480 (1979), superseded by rule on other grounds as stated in Young v
    Robin, 
    146 Mich. App. 552
    , 556 n 2; 382 NW2d 182 (1985). This sentence does not itself
    explicitly reference reconciliation. However, the parties agree that it serves as a limited
    exception to the general prohibition against reconciling expenses for power supplied outside of
    the PSCR period under consideration. Despite the extensive briefing dedicated to this sentence,
    the parties at oral argument otherwise concluded that it was not, in fact, the proper basis for
    resolving this appeal. We therefore decline to address it.
    Nevertheless, the proceedings before the ALJ involved considerable dispute about
    whether the overbilling occurred due to DTE acting in an unreasonable and imprudent manner.
    The PSC ultimately “rejected” the ALJ’s finding regarding that issue, because it concluded that
    the basis for its final decision rendered it “unnecessary for the Commission to consider or discuss
    that line of inquiry.” We expressly reject both parties’ arguments pertaining to whether DTE did
    act in an unreasonable and imprudent manner. Because the PSC did not decide that factual issue,
    we will not review or consider it.
    The PSC has requested that, in light of our conclusion that it erred by failing to reconcile
    the PSCR portion of the Severstal refund, we remand for an express decision as to whether DTE
    acted unreasonably and imprudently. Because we decline to consider the last sentence of MCL
    460.6j(12), we decline to impose such a specific requirement upon the PSC. However, we direct
    that on remand, the PSC shall permit the parties to submit further briefing on the issue, including
    7
    Consumers Energy used a bookkeeping methodology that required the payment to be booked in
    2012.
    8
    The PSC argues that it has the discretion to allow such a reconciliation if the equities are
    proper, but has been unable to articulate any source for that discretion, any guidelines for how to
    exercise that discretion, or how to identify when the equities are proper.
    -8-
    whether it would be proper for the PSC to make such a decision at this time. We express no
    opinion on the matter.
    VIII. UNCONSTITUTIONAL TAKING
    DTE finally argues that the PSC’s disallowance of the Severstal refund from the 2015
    reconciliation effectuates an unconstitutional taking of its property. In light of our resolution of
    the other issues in this appeal, we need not address this argument. However, for the benefit of
    the bench and bar, we briefly clarify that in Champion’s Auto Ferry, Inc v Pub Service Comm,
    
    231 Mich. App. 699
    , 717; 588 NW2d 153 (1998), we did not hold that the Court of Claims was
    the only avenue for relief available to a party that believes it has suffered an unconstitutional
    taking from the actions of an administrative agency. Rather, we held that it was unnecessary for
    us to address the appellant’s takings argument at that time because commencing suit in the Court
    of Claims would remain an option for the appellant in the future. Indeed, “when a constitutional
    issue is intermingled with issues properly before an administrative agency,” the proper procedure
    is generally not a separate action, but to pursue the constitutional claim on direct appeal from the
    administrative agency. See Womack-Scott v Dep’t of Corrections, 
    246 Mich. App. 70
    , 79-81; 630
    NW2d 650 (2001). We hold only that DTE’s takings claim, if any, is not yet ripe for our review,
    and pursuant to Champion’s Auto Ferry, DTE will not be precluded from pursuing it in the
    future should it have the need.
    IX. CONCLUSION
    The PSC’s order is reversed to the extent it found that the $13.45 million PSCR portion
    of the Severstal refund cannot be included in DTE’s 2015 reconciliation under MCL 460.6j. We
    do not disturb any other portion of the PSC’s order. We decline to address DTE’s constitutional
    takings issue. We express no opinion whether DTE incurred the expenses underlying the
    Severstal refund by acting in an unreasonable and imprudent manner, nor do we express any
    opinion whether that issue is a proper consideration at this time. However, on remand the PSC
    shall permit the parties to submit further briefs regarding whether it is required to make that
    determination pursuant to the final sentence of MCL 460.6j(12), what its factual findings should
    be, and how any such findings may be relevant to the ultimate reconciliation.
    Reversed in part and remanded as set forth above. We do not retain jurisdiction. We
    direct that the parties shall bear their own costs. MCR 7.219(A).
    /s/ Michael J. Riordan
    /s/ Amy Ronayne Krause
    /s/ Brock A. Swartzle
    -9-
    

Document Info

Docket Number: 339557

Filed Date: 12/6/2018

Precedential Status: Non-Precedential

Modified Date: 12/7/2018