Rodney Woods v. City of Saginaw ( 2019 )


Menu:
  •             If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
    revision until final publication in the Michigan Appeals Reports.
    STATE OF MICHIGAN
    COURT OF APPEALS
    RODNEY WOODS, doing business as RODNEY                             UNPUBLISHED
    WOODS BUILDER,                                                     October 15, 2019
    Plaintiff-Appellant,
    v                                                                  No. 344025
    Saginaw Circuit Court
    CITY OF SAGINAW,                                                   LC No. 16-029129-CB
    Defendant-Appellee.
    Before: REDFORD, P.J., and JANSEN and LETICA, JJ.
    PER CURIAM.
    In this contract dispute, plaintiff, Rodney Woods, a demolition contractor doing business
    as Rodney Woods Builder, appeals by right the trial court’s order granting defendant, the City of
    Saginaw, summary disposition. We affirm.
    I. PERTINENT FACTS AND PROCEDURAL HISTORY
    This case involved blight demolition efforts in the Saginaw area under the Troubled
    Asset Relief Program (“TARP”). Defendant and the Saginaw County Land Bank Authority
    (“SCLBA”) secured over $11,000,000 in TARP funds from the Michigan State Housing
    Development Authority for blight elimination. Defendant and the SCLBA entered into a
    partnership to demolish up to 950 blighted properties. The SCLBA would be responsible for
    acquiring, owning, and maintaining properties slated for demolition, and defendant would be
    responsible for hiring demolition contractors and overseeing their work. In 2013, defendant
    began soliciting bids from numerous demolition contractors to take on the role of demolishing
    the blighted properties. One of these contractors was plaintiff, a sole proprietor.
    Defendant created a procedure in which each contractor submitted a “per unit costs” for
    various services related to demolition. Such services included foundation removal, tree removal,
    and asbestos removal. Each of these services was assigned a particular number of points.
    Defendant would award demolition work to the “highest qualified contractor with the lowest
    accepted and approved bids” for a period of two years, and defendant had the option to extend
    this period for a third year. The remaining contractors would be ranked according to the number
    -1-
    of points they scored. The lowest best bid would receive the first chance for work, the second
    lowest best bid would receive the second chance for work, and so on down the list. The
    demolition properties would be awarded to a contractor “until such time that the contractor
    cannot meet the volume demands as determined by the City at which time the City will award
    work to the second lowest best bid and so on until such time as the volume demands are met.”
    Plaintiff submitted his bid proposal and “won” the bidding process. As the highest
    ranked contractor, plaintiff had first pick of the demolition properties and received 240 out of a
    total 480 initial properties. In total, plaintiff demolished approximately 600 houses over the life
    of the contract. At certain points during the life of the contract, defendant determined that
    plaintiff could not handle more demolitions than those he already had, and defendant
    subsequently gave demolition work to other contractors on the list.
    Plaintiff filed a three-count complaint. In Count I, a breach of contract claim, plaintiff
    claimed that defendant increased the scope of the contract, and then was not adequately
    compensated for the extra work performed. In Count II, plaintiff sought relief under a quantum
    meruit theory for the extra work performed. The extra work relevant to Count I and Count II
    was primarily related to grading and seeding of the properties after demolition, which plaintiff
    claimed was not included in the parties’ original contract. In support of his claim for additional
    compensation, plaintiff attached a letter from John C. Stemple, Chief Inspector for defendant, in
    which Stemple issued a change order acknowledging that plaintiff, and other contractors, had
    been performing work beyond the original contract and would receive additional compensation
    for prospective demolitions. Finally, in Count III, plaintiff made a second claim for breach of
    contract, this time claiming that defendant allocated demolitions to other contractors, thereby
    breaching an implied covenant of good faith.
    Defendant filed its first motion for summary disposition in October 2017, which the trial
    court granted in part as to Count I, and denied in part as to Count II and Count III.1 In granting
    summary disposition to defendant on Count I, the trial court concluded that the change order
    dealt with prospective demolitions, not demolitions already performed, and plaintiff had agreed
    to receiving payment for work performed after the change order was issued. However, because
    plaintiff only sought compensation for extra work performed before the change order was issued,
    plaintiff was unable to maintain a breach of contract claim based solely on the change order
    letter.
    In March 2018, defendant filed a renewed motion for summary disposition of Count II
    and Count III. The trial court granted summary disposition in favor of defendant of Count II,
    plaintiff’s quantum meruit claim, under MCR 2.116(C)(8) and (C)(10), and of Count III under
    MCR 2.116(C)(10) for the implied warranty of good faith claim. This appeal followed.
    1
    Plaintiff does not challenge the grant of summary disposition in favor of defendant as to Count
    I on appeal.
    -2-
    II. STANDARDS OF REVIEW
    “This Court reviews de novo a trial court’s decision on a motion for summary
    disposition, as well as questions of statutory interpretation and the construction and application
    of court rules.” Dextrom v Wexford Co, 
    287 Mich. App. 406
    , 416; 789 NW2d 211 (2010). A
    motion is properly granted pursuant to MCR 2.116(C)(8) when the opposing party fails to state a
    claim upon which relief can be granted. Such a motion “tests the legal sufficiency of the claim
    on the basis of the pleadings alone . . . .” Bailey v Schaaf, 
    494 Mich. 595
    , 603; 835 NW2d 413
    (2013). When reviewing the motion, the trial “court must accept as true all factual allegations
    contained in the complaint.” 
    Id. The trial
    court must grant the motion “if no factual
    development could justify the plaintiff’s claim for relief.” 
    Id. (quotation marks
    and citation
    omitted).
    Additionally, a motion is properly granted pursuant to MCR 2.116(C)(10) when “there is
    no genuine issue with respect to any material fact and the moving party is entitled to judgment as
    a matter of law.” 
    Dextrom, 287 Mich. App. at 415
    . This Court “must examine the documentary
    evidence presented and, drawing all reasonable inferences in favor of the nonmoving party,
    determine whether a genuine issue of material fact exists. A question of fact exists when
    reasonable minds could differ as to the conclusions to be drawn from the evidence.” 
    Id. at 415-
    416. “This Court is liberal in finding genuine issues of material fact.” Jimkoski v Shupe, 
    282 Mich. App. 1
    , 5; 763 NW2d 1 (2008).
    Finally, this Court reviews de novo the trial court’s decision on whether a claim for
    unjust enrichment can be maintained as well as the trial court’s decision on an equitable matter.
    Morris Pumps v Centerline Piping, Inc, 
    273 Mich. App. 187
    , 193; 729 NW2d 898 (2006).
    III. ANALYSIS
    A. QUANTUM MERUIT
    Plaintiff first argues that the trial court erroneously awarded summary disposition on his
    quantum meruit claim.
    Michigan law “has long recognized the equitable right of restitution when a person has
    been unjustly enriched at the expense of another” despite there being no contract between the
    parties. Morris 
    Pumps, 273 Mich. App. at 193
    (quotation marks and citation omitted). The
    “person who has been unjustly enriched at the expense of another is required to make restitution
    to the other.” 
    Id. (quotation marks
    and citation omitted). “The theory underlying quantum
    meruit recovery is that the law will imply a contract in order to prevent unjust enrichment when
    one party inequitably receives and retains a benefit from another.” 
    Id. at 194.
    However, a party
    may not recover in quantum meruit if an express contract between the parties covers the same
    subject matter. 
    Id. In this
    case, plaintiff seeks additional compensation for extra work performed. Plaintiff
    relies heavily on the change order from Stemple to support his claim that he should receive
    additional compensation for extra work performed on demolition jobs before the change order
    was issued. However, based on the record before us, the change order only applied to
    -3-
    prospective demolitions; it was not to have retroactive effect. Whether Stemple had the authority
    to issue the change order, or had the authority to bind defendant to the terms of the change order,
    is irrelevant, as plaintiff conceded in the trial court that he did receive additional compensation
    for extra work performed after Stemple issued the change order. Accordingly, we conclude that
    not only was plaintiff fairly compensated for demolitions performed in accordance with the
    original contract, but also, by his own admission, plaintiff was also fairly compensated for
    demolitions performed after the change order was issued. In fact, plaintiff received several
    million dollars for the approximately 600 demolitions he performed. Thus, plaintiff cannot
    recover in quantum meruit on an unjust enrichment claim, and the trial court did not err in
    granting summary disposition in favor of defendant on that basis. Having discerned no error in
    the trial court’s ruling on MCR 2.116(C)(8), we need not address its alternative theory premised
    on MCR 2.116(C)(10), and we decline to do so here.
    B. IMPLIED COVENANT OF GOOD FAITH
    Plaintiff next argues that the trial court erroneously granted summary disposition
    regarding his breach-of-contract claim premised on an implied covenant of good faith.
    A “covenant of good faith and fair dealing is an implied promise contained in every
    contract ‘that neither party shall do anything which will have the effect of destroying or injuring
    the right of the other party to receive the fruits of the contract.’ ” Hammond v United of
    Oakland, Inc, 
    193 Mich. App. 146
    , 151-152; 483 NW2d 652 (1992) (citations omitted). This
    implied promise applies to a contract that “makes the manner of [a party’s] performance a matter
    of its own discretion . . . .” Ferrell v Vic Tanny Int’l, Inc, 
    137 Mich. App. 238
    , 243; 357 NW2d
    669 (1984) (quotation marks and citation omitted). The implied promise requires such a party to
    exercise its discretion “honestly and in good faith.” 
    Id. (quotation marks
    and citation omitted).
    Michigan law does not recognize a separate action for breach of an implied covenant of good
    faith apart from a claim for breach of the contract on which the implied promise is premised.
    Belle Isle Grill Corp v Detroit, 
    256 Mich. App. 463
    , 476; 666 NW2d 271 (2003). “A lack of good
    faith cannot override an express provision in a contract.” Eastway & Blevins Agency v Citizens
    Ins Co of America, 
    206 Mich. App. 299
    , 303; 520 NW2d 640 (1994).
    In the present case, the contract provided that the demolitions would be awarded “until
    such time that the contractor cannot meet the volume demands as determined by the City at
    which time the City will award work to the second lowest best bid and so on until such time as
    the volume demands are met” (emphasis added). There was no further instruction for how
    defendant was to determine if a contractor could not meet volume demands. Accordingly, an
    implied covenant of good faith applied in this instance to safeguard plaintiff against seemingly
    unbridled discretion by defendant. See 
    Ferrell, 137 Mich. App. at 243
    .
    However, plaintiff failed to demonstrate any evidence of bad faith. Defendant, as the
    moving party, submitted the Stemple affidavit in which Stemple averred that defendant had a
    process to determine whether a contractor was at capacity and could not handle any further
    properties for the time being. Various factors were considered in this process, including “the
    contractor’s level of experience with demolitions, the contractor’s quality of work, and whether
    the contractor was fully completing demolitions that had been assigned in a timely and efficient
    manner.” Stemple averred that he had been concerned about plaintiff’s lack of experience with
    -4-
    demolition work and the fact that he at one point had over 100 incomplete demolition properties.
    Moreover, plaintiff had received continuous work throughout the contract’s life so long as he
    was able to meet volume demands and was the first contractor considered when allocating
    additional properties.
    Accordingly, defendant provided documentary evidence to support its position that it had
    not acted in bad faith in its allocution of demolition properties. The affidavit demonstrated that
    there was a process by which defendant determined if a contractor was able to receive more
    demolition properties, and, through this process, defendant determined that plaintiff was at
    volume capacity at certain periods of time, which required defendant to allocate properties to
    other contractors.
    In response, plaintiff submitted an e-mail from one of his employees in which the
    employee stated that plaintiff was capable of taking on more work. However, this did not rebut
    the Stemple affidavit; rather the e-mail demonstrated plaintiff’s employee held the subjective
    belief that plaintiff was capable of taking on more properties at that period in time. It did not
    address the other periods of time, and it did nothing to demonstrate that the process defendant
    utilized was undertaken in bad faith or that defendant had applied the process in bad faith.
    Plaintiff may have disagreed with defendant’s determination that he was unable to meet volume
    demands, but plaintiff failed to show any evidence of bad faith in making that determination.
    See 
    Ferrell, 137 Mich. App. at 243
    . Accordingly, defendant was entitled to summary disposition
    under MCR 2.116(C)(10). 
    Dextrom, 287 Mich. App. at 415
    -416.
    Briefly, we note that plaintiff also argues that the trial court applied the incorrect standard
    in granting summary disposition in favor of defendant. However, even assuming that the trial
    court should have used the standard put forth by plaintiff, the result would not be different.
    Plaintiff contends that the standard for the implied covenant of good faith is for the party to
    utilize its discretion “honestly and in good faith.” 
    Ferrell, 137 Mich. App. at 243
    (quotation
    marks and citation omitted). As discussed previously, the Stemple affidavit provided the process
    that defendant used in allocating the properties, which included a number of factors and
    considerations. The e-mail did nothing to show that the process provided by Stemple was
    dishonest or undertaken in bad faith. Under plaintiff’s proposed standard, summary disposition
    was still proper. See Outdoor Sys, Inc v Clawson, 
    262 Mich. App. 716
    , 720 n 4; 686 NW2d 815
    (2004) (stating that this Court will not reverse the trial court for reaching the correct result for the
    wrong reasons).2
    2
    Finally, plaintiff again takes issue with the trial court’s failure to consider his affidavit.
    However, as discussed previously, the affidavit was untimely, and, even if considered, it
    espoused essentially the same contentions as those in the e-mail, i.e., that plaintiff was not near
    capacity. Accordingly, the affidavit would not have affected the outcome because it had the
    same deficiency as the e-mail: it failed to demonstrate bad faith.
    -5-
    Affirmed.
    /s/ James Robert Redford
    /s/ Kathleen Jansen
    /s/ Anica Letica
    -6-
    

Document Info

Docket Number: 344025

Filed Date: 10/15/2019

Precedential Status: Non-Precedential

Modified Date: 10/16/2019