328-barry-avenue-llc-v-nolan-properties-group-llc-and-third-party-v ( 2015 )


Menu:
  •                          This opinion will be unpublished and
    may not be cited except as provided by
    Minn. Stat. § 480A.08, subd. 3 (2014).
    STATE OF MINNESOTA
    IN COURT OF APPEALS
    A14-0724
    328 Barry Avenue, LLC,
    Appellant,
    vs.
    Nolan Properties Group, LLC, defendant and third party plaintiff,
    Respondent,
    vs.
    Carciofini Company, third party defendant,
    Respondent,
    Marvin Windows, Inc., third party defendant,
    Respondent,
    Minuti-Ogle Co., Inc., third party defendant,
    Respondent,
    R. T. L. Construction, Inc., third party defendant,
    Respondent,
    Stellar Contractors, Inc. d/b/a Stellar Concrete & Masonry, third party defendant,
    Respondent.
    Filed February 2, 2015
    Affirmed
    Reyes, Judge
    Hennepin County District Court
    File No. 27-CV-12-20125
    J. Robert Keena, Hellmuth & Johnson, P.L.L.C., Edina, Minnesota (for appellant)
    Michael A. Breen, Amy M. Sieben, Fisher, Bren & Sheridan, L.L.P., Minneapolis,
    Minnesota (for respondent Nolan Properties Group, LLC)
    Cara C. Passaro, Murphy & Passaro, P.A., Mendota Heights, Minnesota (for respondent
    Carciofini Company)
    Michael E. Obermueller, Winthrop & Weinstine, P.A., Minneapolis, Minnesota (for
    respondent Marvin Windows, Inc.)
    Justin P. Short, Timothy A. Sullivan, Kyle R. Hardwick, Best & Flanagan, L.L.P.,
    Minneapolis, Minnesota (for respondent Minuti-Ogle Co., Inc.)
    Neal J. Robinson, The Cincinnati Insurance Co., Coon Rapids, Minnesota (for respondent
    R.T.L. Construction, Inc.)
    Considered and decided by Reyes, Presiding Judge; Worke, Judge; and
    Johnson, Judge.
    UNPUBLISHED OPINION
    REYES, Judge
    On appeal from the district court’s grant of summary judgment to respondents,
    appellant argues that (1) genuine issues of material fact exist as to when appellant
    discovered its injury for statute-of-limitation purposes; (2) the district court
    misinterpreted Minnesota’s statute of limitations; and (3) genuine issues of material fact
    exist regarding whether equitable estoppel should have precluded summary judgment.
    We affirm.
    FACTS
    Appellant 328 Barry Avenue, LLC (328 Barry) and respondent Nolan Properties
    Group, LLC (NPG) are limited-liability companies located at 328 Barry Avenue in
    Wayzata. Both companies have the same sole owner, John Nolan. 328 Barry owns the
    property and used NPG as general contractor for the construction of a building on the
    property. Construction began in 2008. As general contractor, NPG entered into contracts
    with several subcontractors, including respondents Carciofini Company, Marvin
    2
    Windows, Inc., Minuti-Ogle Co., Inc. (MOC), R.T.L. Construction, Inc., and Stellar
    Contractors, Inc. d/b/a Stellar Concrete & Masonry. But, according to Nolan, there was
    no construction contract between 328 Barry and NPG.
    In October 2009 while construction was ongoing, NPG discovered water intrusion
    on the property. It asked MOC to correct the water leakage on the east side of the
    building. MOC applied clear silicone to two window joints and suggested that NPG get
    the window tested. Two weeks later, NPG asked MOC to perform additional work
    because water was still leaking. When MOC returned to inspect the property on
    November 3, NPG and MOC used a garden hose to spray the building and saw water
    “slowly seep[ing] in” through a window. MOC again told NPG to get the window tested.
    The record contains no evidence that MOC corrected the problem or that NPG tested the
    windows at this time. When 328 Barry received a certificate of occupancy for the
    property in January 2010, not every floor of the building had been completed.
    NPG next contacted MOC in August 2010 regarding water infiltration. In
    response, MOC again recommended that NPG test the windows and window caulking.
    MOC referred NPG to a forensic building scientist who could test the windows.
    In early 2011, NPG hired Indigo Environmental “to assess the stucco cladding at
    the East elevation to determine the source for the water intrusion into the 2008
    constructed building.” According to Indigo, water infiltration had previously been
    observed “on the East elevation first and second floor[s]” but was now observed “from
    the North first and second floor windows” and occasionally “from the middle windows
    on each floor.” Indigo completed its report in June 2011 and determined that “building
    3
    materials were installed contrary to the written specifications.” NPG later hired other
    companies to analyze the property and discovered several areas of water damage.
    On October 3, 2012, 328 Barry filed suit against NPG, alleging that its actions as
    general contractor were negligent. NPG denied responsibility and sued Carciofini,
    Marvin, MOC, and R.T.L. for contribution and indemnification. NPG later amended its
    third-party complaint to include Stellar.
    Nolan was deposed as both the representative of appellant 328 Barry and the
    representative of respondent NPG. On behalf of NPG, he stated that all of the issues
    raised during construction in 2009 with the windows, doors, and caulking were
    “addressed and corrected” by the subcontractors. As a result, according to NPG,
    everything was fixed and there were no water-intrusion issues until August 2010. Nolan
    agreed that the location of the current water intrusion was the same as the intrusion in
    2009 but disagreed that the cause of the intrusion was the same.
    The parties brought five motions for summary judgment, and the district court
    conducted a hearing on the competing motions.1 In February 2014, the district court
    granted Carciofini and MOC’s joint motion for summary judgment based on 328 Barry’s
    failure to bring suit within the statute of limitations and dismissed the other motions. The
    district court explained that, because 328 Barry served NPG with its summons and
    complaint on June 14, 2012, it must have discovered its injury after June 14, 2010 to have
    1
    After the hearing, 328 Barry reached a settlement with Stellar Contractors “on a
    [Pierringer] basis.” In a Pierringer release, a plaintiff settles a claim with one or more
    defendants, the settling defendants are dismissed, and any cross-claims involving those
    defendants are also dismissed. Frey v. Snelgrove, 
    269 N.W.2d 918
    , 922 (Minn. 1978).
    4
    met the statute of limitations. See Minn. R. Civ. P. 3.01(a). The district court concluded
    that 328 Barry first discovered the water infiltration in October 2009 and that this water
    infiltration “is the same injury [328 Barry] is complaining of now.” The district court
    therefore dismissed 328 Barry’s complaint because it failed to file suit within the statute
    of limitations.
    328 Barry requested reconsideration of the district court’s order, arguing that the
    district court erred in its analysis of the statute of limitations. One day before the filing of
    this request, the district court judge who had heard the case retired. After another district
    court judge was assigned to the case, 328 Barry again moved for reconsideration. The
    new district court judge denied 328 Barry’s motion for reconsideration. 328 Barry
    appeals.2
    DECISION
    I.
    A district court shall grant summary judgment “if the pleadings, depositions,
    answers to interrogatories, and admissions on file, together with the affidavits, if any,
    show that there is no genuine issue as to any material fact and that either party is entitled
    to a judgment as a matter of law.” Minn. R. Civ. P. 56.03. On appeal from an award of
    summary judgment, this court reviews de novo whether there is a genuine issue of
    material fact and whether the district court erred when it applied the law. STAR Ctrs.,
    Inc. v. Faegre & Benson, L.L.P., 
    644 N.W.2d 72
    , 76-77 (Minn. 2002). “We view the
    2
    After the filing of this appeal, the parties stipulated to the dismissal of all claims against
    Stellar, and the district court ordered the dismissal.
    5
    evidence in the light most favorable to the party against whom summary judgment was
    granted.” 
    Id.
    The statute of limitations at issue states:
    Except where fraud is involved, no action by any
    person in contract, tort, or otherwise to recover damages for
    any injury to property, real or personal, or for bodily injury or
    wrongful death, arising out of the defective and unsafe
    condition of an improvement to real property, shall be
    brought against any person performing or furnishing the
    design, planning, supervision, materials, or observation of
    construction or construction of the improvement to real
    property or against the owner of the real property more than
    two years after discovery of the injury, nor in any event shall
    such a cause of action accrue more than ten years after
    substantial completion of the construction.             Date of
    substantial completion shall be determined by the date when
    construction is sufficiently completed so that the owner or the
    owner’s representative can occupy or use the improvement
    for the intended purpose.
    
    Minn. Stat. § 541.051
    , subd. 1(a) (2014). Under this subdivision, “a cause of action
    accrues upon discovery of the injury.” 
    Id.,
     subd. 1(c) (2014).
    328 Barry argues that, under section 541.051, subdivision 1(a), “[a]n ‘actionable’
    injury requires knowledge of NPG’s and its [s]ubcontractor[s’] negligence and resulting
    damage that required repair.” (Emphasis omitted). But 328 Barry misstates the statutory
    standard. Before the amendment of this statute of limitations in 1988, “one had to be
    aware of the defect causing the injury.” Dakota Cnty. v. BWBR Architects, 
    645 N.W.2d 487
    , 492 n.3 (Minn. App. 2002), review denied (Minn. Aug. 20, 2002). Now, “the statute
    of limitations begins to run when an actionable injury is discovered or, with due
    diligence, should have been discovered, regardless of whether the precise nature of the
    6
    defect causing the injury is known.” 
    Id. at 492
    . “[A] party need not be aware of the
    extent of its injury for the statute of limitations to begin to run so long as the party is
    aware of the injury and the need for repairs.” Day Masonry v. Indep. Sch. Dist. 347, 
    781 N.W.2d 321
    , 334 (Minn. 2010).
    The district court determined that 328 Barry learned of the water intrusion in
    October 2009, that the 2009 problem was not fixed, and that 328 Barry sued for the
    “same injury” in 2012. 328 Barry argues that a genuine issue of material fact exists about
    when it discovered its injury because the 2009 water intrusion was corrected, and it
    discovered a new injury in August 2010.3 As evidence, 328 Barry cites Nolan’s
    deposition, in which he stated that all issues discovered during construction in 2009 were
    “addressed and corrected” by the subcontractors and that there were no water-intrusion
    problems until August 2010. Even viewing Nolan’s testimony in the light most favorable
    to 328 Barry, Nolan’s testimony merely averred that the 2009 water-intrusion problem
    was corrected. This averment is not enough to resist a motion for summary judgment.
    See DLH, Inc. v. Russ, 
    566 N.W.2d 60
    , 71 (Minn. 1997) (“[T]he party resisting summary
    judgment must do more than rest on mere averments.”).
    Contrary to 328 Barry’s assertion, the record contains no evidence supporting
    Nolan’s averment that the 2009 water-intrusion problem was corrected. MOC applied
    3
    The parties do not dispute that 328 Barry discovered water infiltration in October 2009.
    Because Nolan acted as the sole owner and decision-maker for both 328 Barry and NPG,
    NPG’s knowledge can be imputed to 328 Barry. See Travelers Indem. Co. v.
    Bloomington Steel & Supply Co., 
    718 N.W.2d 888
    , 896 (Minn. 2006) (explaining that
    knowledge is attributed from agent to principal when agent acquires the knowledge in the
    course of his employment); see also Day Masonry, 781 N.W.2d at 334 (stating that
    custodians’ knowledge of leaks is imputed to their employer).
    7
    clear silicone to two window joints in October 2009. But this action did not fix the water
    leakage, and NPG asked MOC to perform additional repairs. MOC returned to inspect
    the property in November 2009 and, with NPG, performed an unscientific garden-hose
    test, which uncovered continued water leakage. The record contains no evidence that
    MOC performed any additional repairs in November 2009. Similarly, MOC told NPG to
    get the windows tested, but there is no evidence that NPG tested the windows or any
    other part of the building until early 2011, after noticing water infiltration in August
    2010.
    Section 541.051, subdivision 1(a) requires a plaintiff to file suit no more than two
    years after discovering an actionable injury. 
    Minn. Stat. § 541.051
    , subd. 1(a). But the
    statute of limitations begins to run when the plaintiff discovers or should have discovered
    an actionable injury. BWBR Architects, 
    645 N.W.2d at 492
    . Even viewing the record in
    the light most favorable to 328 Barry, we agree with the district court that 328 Barry
    discovered its injury in October 2009. At the latest, 328 Barry should have discovered its
    injury in November 2009 because the garden-hose test uncovered continued leakage and
    there is no evidence that this leakage was corrected. Given the leakage during the
    garden-hose test, it was not reasonable for 328 Barry to conclude that the problem was
    corrected in 2009. Because 328 Barry discovered its injury in October 2009, was aware
    of the need for repairs, and did not correct the problem, the statute of limitations began to
    run at that time. See Day Masonry, 781 N.W.2d at 334 (explaining that the statute of
    limitations begins to run when “the party is aware of the injury and the need for repairs”);
    8
    BWBR Architects, 
    645 N.W.2d at 492
     (suggesting that, when an injury is discovered and
    not corrected, the statute of limitations begins to run at the date of discovery).
    The district court did not err in determining that there were no genuine issues of
    material fact regarding 328 Barry’s knowledge of its injury in October 2009 and that the
    statute of limitations began to run at that time. Because 328 Barry served its summons
    and complaint in June 2012—over two years after discovering its injury—the district
    court properly granted summary judgment to respondents. See 
    Minn. Stat. § 541.051
    ,
    subd. 1(a).
    II.
    328 Barry next argues that the statute of limitations cannot begin to run until the
    completion of construction. The district court rejected this argument as a confusion of
    the statute of limitations and statute of repose.4
    Section 541.051 contains both a statute of limitations and a statute of repose.
    Weston v. McWilliams & Assocs., Inc., 
    716 N.W.2d 634
    , 643 (Minn. 2006). “[A] statute
    of limitations limits the time within which a party can pursue a remedy (that is, it is a
    procedural limit), whereas a statute of repose limits the time within which a party can
    acquire a cause of action (thus it is a substantive limit).” Id. at 641. Based on the clear
    4
    328 Barry also argues that the district court used an “improper trigger” for the statute of
    limitations because it referred to the “defect” and the “discovery of the defect” several
    times in its written order. But the district court also made multiple references to the
    “injury” and cited the proper legal standard that “a cause of action accrues upon
    discovery of the injury.” See 
    Minn. Stat. § 541.051
    , subd. 1(c). Given the district court’s
    conclusion that the 2009 and 2010 water infiltrations were the “same injury” and that 328
    Barry was aware of its “injury” in 2009, we disagree that the district court applied an
    improper legal standard under section 541.051, subdivision 1(a).
    9
    language of section 541.051, subdivision 1(a), a plaintiff has “two years after discovery
    of the injury” to bring suit and meet the statute of limitations, and “ten years after
    substantial completion of the construction” to accrue a cause of action and meet the
    statute of repose. See 
    Minn. Stat. § 541.051
    , subd. 1(a); see also Fiveland v. Bollig &
    Sons, Inc., 
    436 N.W.2d 478
    , 481 (Minn. App. 1989) (“[T]he legislature has expressly
    provided two separate limitation periods: one running for two years commencing upon
    discovery of the injury; and the other running for 10 years from the substantial
    completion of construction.”), review denied (Minn. Apr. 24, 1989). At oral argument
    before this court, 328 Barry conceded that the language “substantial completion of the
    construction” does not apply to the two-year statute of limitations under section 541.051,
    subdivision 1(a).
    But 328 Barry argues that the concept of “substantial completion” should still
    apply to the two-year statute of limitations. This argument has been previously rejected
    by this court. In Fiveland, we concluded that “[t]he legislature has . . . considered the
    importance of the time of substantial completion of construction as a measure for
    commencing a time period, and has chosen not to use this point as commencement for the
    two-year limitation period.”5 
    436 N.W.2d at 481
    .
    5
    328 Barry suggests that section 541.051, subdivision 4 and Vlahos v. R&I Constr. of
    Bloomington, Inc., 
    676 N.W.2d 672
     (Minn. 2004) support its argument that the statute of
    limitations “cannot begin to run until the improvement is completed.” We disagree.
    Section 541.051, subdivision 4 applies to suits based on a breached warranty, and is
    inapplicable to 328 Barry’s lawsuit. See 
    Minn. Stat. § 541.051
    , subd. 4 (2014).
    Moreover, in Vlahos, the supreme court rejected a respondent’s argument that a phrase in
    subdivision 1 was synonymous with a different phrase in subdivision 4. 676 N.W.2d at
    677 n.4.
    10
    328 Barry also argues that no Minnesota case has “dismissed a lawsuit because a
    defect was discovered during ongoing construction and before substantial completion of
    construction.” But respondents cite two cases dismissing lawsuits when injuries were
    discovered before the completion of construction. In O’Connor v. M.A. Mortenson Co.,
    an employee was injured while working on a construction site and sued over five years
    later. 
    424 N.W.2d 92
    , 93 (Minn. App. 1988), review denied (Minn. July 28, 1988). This
    court applied a previous version of 
    Minn. Stat. § 541.051
    , subd. 1, and determined that
    the employee’s suit was “barred by the statute’s two-year statute of limitations.” Id. at
    94-95. In Fiveland, a homeowner sued the contractor and subcontractors working on his
    home over two years after he was injured during construction. 
    436 N.W.2d at 479
    . This
    court again determined that the suit was barred by the two-year statute of limitations. 
    Id. at 481
    .
    328 Barry argues that O’Connor and Fiveland are inapplicable because they
    involve personal injuries. But neither case contains language limiting its analysis of the
    two-year statute of limitations to personal-injury actions. Indeed, the statute is clear that
    it applies to both personal and property injuries. See 
    Minn. Stat. § 541.051
    , subd. 1(a).
    In Fiveland, this court explained that the two-year statute of limitations commences upon
    discovery of an injury and that the legislature did not toll this limitation period during the
    course of construction. 
    436 N.W.2d at 481
    .
    The district court properly concluded that construction need not be completed
    before the start of the two-year limitation period, and it did not err in its analysis of
    section 541.051, subdivision 1.
    11
    III.
    Finally, 328 Barry argues that genuine issues of material fact regarding its
    equitable-estoppel argument precluded summary judgment. Equitable estoppel is
    “intended to prevent a party from taking unconscionable advantage of his own wrong by
    asserting his strict legal rights.” Brown v. Minn. Dep’t of Pub. Welfare, 
    368 N.W.2d 906
    ,
    910 (Minn. 1985) (quotation omitted). “Specifically with regard to 
    Minn. Stat. § 541.051
    , estoppel is pled where, after discovery of a cause of action, the injured party
    has been induced to forego suit in reliance on the other party’s assurances that corrective
    action would be taken.” BWBR Architects, 
    645 N.W.2d at 493
    .
    In Rhee v. Golden Home Builders, Inc., the homeowners notified their builder of
    water infiltration in their new home. 
    617 N.W.2d 618
    , 620 (Minn. App. 2000). The
    builder then assured the homeowners that it would fix the problem, “made numerous
    unsuccessful repair attempts and repeatedly told the [homeowners] that eventually the
    problem would be solved.” 
    Id.
     When the homeowners finally sued, the builder
    attempted to assert a statute-of-limitations defense. 
    Id.
     This court held that there was a
    genuine issue of material fact regarding whether the builder “is equitably estopped from
    asserting a statute-of-limitations defense.” 
    Id. at 622
    .
    328 Barry argues that “[t]his case is on point with Rhee” because NPG assured it
    that the building would be repaired. But the record contains no evidence of an assurance
    from NPG to 328 Barry. Contrary to 328 Barry’s allegation, NPG’s decision to ask MOC
    to perform additional work in 2009 does not provide evidence of an assurance to 328
    Barry that it would correct the problem. In addition, there is no evidence that MOC or
    12
    any other subcontractor provided assurance to NPG. To the contrary, MOC
    recommended that NPG test the windows and denied responsibility for the water
    intrusion; it did not assure NPG that it would take corrective action.
    Rather than being “on point with Rhee,” this case is similar to Oreck v. Harvey
    Homes, Inc., 
    602 N.W.2d 424
     (Minn. App. 1999), review denied (Minn. Jan. 25, 2000).
    In Oreck, the homeowners notified their contractor of several continuing problems
    involving water leakage. 
    602 N.W.2d at 426
    . The contractor examined the house, asked
    a subcontractor to perform repair work, and made other suggestions regarding the
    problems. 
    Id.
     The homeowners sued the contractor over two years after discovering
    their injuries. 
    Id.
     Because there was no evidence that the contractor made assurances to
    the homeowners that it would correct the problems, this court concluded that the
    contractor was not equitably estopped from asserting a statute-of-limitations defense. 
    Id. at 429, 431
    . As in Oreck, there is no evidence that NPG promised to correct 328 Barry’s
    water-infiltration problem and there is no evidence that NPG induced 328 Barry to delay
    filing suit. See 
    id. at 429
    .
    Because there is no evidence that 328 Barry relied on any assurances that
    corrective action would be taken, it cannot raise an equitable-estoppel argument to the
    running of the statute of limitations. See BWBR Architects, 
    645 N.W.2d at 493
    . And
    there is no genuine issue of material fact regarding whether equitable estoppel precluded
    the district court’s grant of summary judgment to respondents. See Oreck, 
    602 N.W.2d at
    13
    428 (“[W]hen only one inference can be drawn from the facts, the question is one of
    law,” rather than one for the jury. (quotation omitted)).6 We therefore affirm.
    Affirmed.
    6
    Because we affirm the district court’s grant of summary judgment to respondents, we do
    not consider respondents’ argument that the summary-judgment order could be affirmed
    on alternative grounds.
    14