Construction Services, Inc. of Duluth v. Town of Alborn ( 2015 )


Menu:
  •                            This opinion will be unpublished and
    may not be cited except as provided by
    Minn. Stat. § 480A.08, subd. 3 (2014).
    STATE OF MINNESOTA
    IN COURT OF APPEALS
    A14-0977
    Construction Services, Inc. of Duluth,
    Appellant,
    vs.
    Town of Alborn,
    Respondent.
    Filed April 27, 2015
    Affirmed
    Reyes, Judge
    St. Louis County District Court
    File No. 69DUCV132351
    William D. Paul, William Paul Law Office, Duluth, Minnesota (for appellant)
    Daniel R. Gregerson, Margaret L. Evavold, Gregerson, Rosow, Johnson & Nilan, Ltd.,
    Minneapolis, Minnesota (for respondent)
    Considered and decided by Hudson, Presiding Judge; Bjorkman, Judge; and
    Reyes, Judge.
    UNPUBLISHED OPINION
    REYES, Judge
    Appellant Construction Services, Inc. of Duluth challenges a district court’s
    summary judgment in favor of respondent Town of Alborn. Appellant seeks to collect
    funds it claims it is entitled to under the parties’ construction contract arguing that (1) it
    did not materially breach the parties’ contract; (2) respondent breached the contract by
    failing to timely pay a draw request; and (3) respondent failed to follow the contract’s
    termination procedure. We affirm.
    FACTS
    On April 30, 2008, the parties entered into a contract for the construction of a
    wastewater-treatment facility. The contract price for the project was $509,610. Pursuant
    to Minnesota law and article 5 of the contract, appellant entered into an indemnity
    agreement (indemnity agreement) with performance and payment bonds from a surety
    (performance bond), North American Specialty Insurance Company (NAS). See Minn.
    Stat. § 574.26, subd. 2 (2014) (requiring contractors to obtain performance and payment
    bonds for public-works projects). Appellant agreed to indemnify NAS for any losses
    NAS might suffer as a result of issuing bonds for appellant.
    The contract originally called for work to be substantially completed by November
    30, 2008. However, unexpected weather conditions caused delays, and the parties
    mutually agreed to extend the substantial completion date to June 30, 2009.
    On June 9, 2009, the project’s engineer, Ayres Associates (Ayres), informed
    appellant that appellant was unlikely to achieve substantial progress by the June 30
    deadline. Ayres did not issue a certificate of substantial completion until July 15, 2009.
    Attached to the certificate was a punch list of 265 items that, by the terms of the contract,
    were required to be fixed or completed by appellant within 30 days. They were not
    completed on time. On August 15, 2009, respondent’s town board, along with Ayres,
    met with appellant to discuss outstanding punch-list items and a possible date for the
    2
    project’s final completion. Appellant could not provide a final completion date at that
    time.
    On August 26, 2009, appellant submitted an application for the project’s sixth
    progress payment in the amount of $151,001. The terms of the contract require appellant
    to submit an application for payment to Ayres to receive a progress payment. Ayres
    would then review the application and either make a written recommendation for
    payment to respondent, or return the application to appellant with reasons why it was
    refusing to recommend payment. If a payment application was returned, appellant was to
    correct and resubmit the application. Payment would then be due 20 days after
    respondent received a payment application with Ayres’s recommendation.
    On September 10, 2009, respondent sent a letter to NAS and appellant notifying
    them that it was considering declaring appellant to be in default after its failure to timely
    complete its work.
    On September 15, 2009, Ayres sent a memorandum to appellant informing them
    that the amount approved on their August 26 application for the sixth progress payment
    was reduced to $117,253. Ayres sent a follow-up memorandum on September 18, 2009,
    which further reduced the approved payment price to $105,121.49. Appellant did not
    resubmit a payment application and was unresponsive to Ayres’s letters.
    In accordance with the performance bond, the parties held a conference on
    September 18, 2009. At that time, appellant agreed to complete the remaining punch-list
    items within one week of September 21, 2009. On October 2, 2009, the punch-list items
    were still incomplete and respondent sent another letter to appellant proposing that they
    3
    would not declare appellant to be in default if appellant agreed to pay for the additional
    engineering and legal fees incurred as a result of the delay. In addition to the delay,
    appellant failed to pay its subcontractors, resulting in mechanic’s liens on the property,
    and appellant failed to complete closeout and warranty work as required by the contract.
    Finally, on July 13, 2010, after a number of subsequent communications, conferences,
    and failed mediation sessions, respondent terminated the contract pursuant to the terms of
    the indemnity agreement. Following the termination procedures of the performance
    bond, respondent notified appellant and NAS that it was declaring appellant to be in
    default.
    NAS filed suit against appellant to recoup losses that it incurred as a result of
    acting as a surety for appellant and, in July 2011, was awarded default judgment against
    appellant for $69,241.17. In September 2011, NAS sought to recover from respondent
    any remaining contract funds due to appellant as a secured creditor pursuant to the
    indemnity agreement. In March 2012, respondent paid NAS $4,928.37 in net contract
    funds in accordance with NAS’s assertion of its right under the indemnity agreement. In
    September 2013, appellant filed this lawsuit against respondent seeking to recover funds
    it believes it was owed under the contract.1 Both parties filed motions for summary
    judgment, and a motion hearing took place on March 11, 2014. The district court denied
    appellant’s summary judgment motion, granted respondent’s motion, and summary
    1
    Appellant asserted four causes of action: (1) breach of contract; (2) unjust enrichment;
    (3) quantum merit; and (4) failure to promptly pay. On appeal, appellant only argues that
    it was entitled to summary judgment on its breach-of-contract theory and has accordingly
    waived its other claims. See Melina v. Chaplin, 
    327 N.W.2d 19
    , 20 (Minn. 1982) (stating
    that issues not briefed on appeal are waived).
    4
    judgment was entered. The district court concluded that appellant’s assignment of its
    rights to NAS barred the relief it sought from respondent. This appeal follows.
    DECISION
    “Summary judgment is appropriate when the evidence, viewed in the light most
    favorable to the nonmoving party, establishes that no genuine issue of material fact exists
    and that the moving party is entitled to judgment as a matter of law.” Citizens State Bank
    Norwood Young Am. v. Brown, 
    849 N.W.2d 55
    , 61 (Minn. 2014); see also Minn. R. Civ.
    P. 56.03. “No genuine issue of material fact exists when the record taken as a whole
    could not lead a rational trier of fact to find for the nonmoving party.” Frieler v. Carlson
    Mktg. Grp., Inc., 
    751 N.W.2d 558
    , 564 (Minn. 2008) (quotations omitted). A district
    court’s grant of summary judgment is reviewed de novo. Dukowitz v. Hannon Sec.
    Servs., 
    841 N.W.2d 147
    , 150 (Minn. 2014).
    The district court concluded that summary judgment in favor of respondent was
    appropriate because appellant had assigned any right to recovery to NAS in the event of
    default. To determine whether the award of summary judgment was made in error, we
    must decide if there is a genuine issue of material fact as to whether appellant defaulted
    on the contract such that appellant’s indemnity agreement with NAS was triggered. “The
    plain and ordinary meaning of the contract language controls, unless the language is
    ambiguous.” Bus. Bank v. Hanson, 
    769 N.W.2d 285
    , 288 (Minn. 2009). The indemnity
    agreement between appellant and NAS provides that appellant agrees to
    assign, transfer, pledge and convey to [NAS] (effective as of
    the date of each such bond, but only in the event of default,
    breach or failure as referred to in preceding Section 4(c))
    5
    . . . all of their rights under the contracts referred to in such
    bonds, including their right, title and interest in and to
    . . . (c) any and all sums due or which may thereafter become
    due under such contracts, and all sums due or to become due
    on all other contracts, bonded or unbonded, in which any or
    all of the Indemnitors have an interest.
    (Emphasis added). Section 4(c), as referenced above, states in relevant part:
    If any such bond be given in connection with a
    contract, [NAS] in its sole discretion is hereby authorized, but
    not required . . . in the event of any breach or default in the
    performance of the contract, or the breach of this Agreement
    or of any bond connected therewith, or the failure to
    diligently prosecute the work under any contract, or to pay
    for labor and materials used in the prosecution of the
    contract . . . to take possession of the work under the contract,
    and, at the expense of the Indemnitors, to complete the
    contract or cause the same to be completed or to consent to
    the completion thereof.
    (Emphasis added). Neither party claims the language of the indemnity agreement is
    ambiguous. Accordingly, by the “plain and ordinary meaning of the contract language,”
    
    Hanson, 769 N.W.2d at 288
    , appellant’s rights will be assigned “only in the event of
    default, breach or failure” in the performance of the contract.
    The district court stated that the terms of the indemnity agreement make clear that
    “if [appellant] defaults on any of its bonded contracts then NAS assumes all [appellant’s]
    rights and interest under that contract, even money due and owing to [appellant].”
    (Emphasis added). The district court further stated that “[e]ven though [respondent]
    gratuitously provided [appellant] with numerous extensions to complete the contracted
    work . . . , [appellant] still managed to default and as a result [respondent] terminated the
    contract.” Thus, it appears the district court concluded that there was no genuine issue of
    6
    material fact with regard to appellant’s default. Appellant argues that this determination
    was made in error.
    I.     Appellant’s breach
    “The moving party has the burden of showing an absence of factual issues before
    summary judgment can be granted.” Anderson v. State, Dep’t of Natural Res., 
    693 N.W.2d 181
    , 191 (Minn. 2005). Respondent alleges that there is no factual issue with
    regard to appellant’s breach because appellant continuously failed to timely complete its
    work and failed to timely pay for certain labor and material provided by subcontractors.
    The record substantiates these claims. Despite agreeing to reach substantial completion
    by June 30, 2009, appellant did not receive a certificate of substantial completion until 15
    days later. Appellant then failed to complete the 265 items on the punch list within 30
    days, as required by the contract. Moreover, in a letter dated March 19, 2009, respondent
    notified appellant that it learned that appellant failed to make payments to the project’s
    subcontractors. Because “failure to diligently prosecute the work” and “failure . . . to pay
    for labor” are both specifically listed under section 4(c) of the indemnity agreement,
    respondent satisfied its burden as the moving party to show an absence of factual issues.
    “[W]hen the moving party makes out a prima facie case, the burden of establishing
    that the facts raise a genuine issue falls to the opposing party.” 
    Brown, 849 N.W.2d at 62
    . “To defeat a summary judgment motion, the nonmoving party must do more than
    rest on averments or denials of the adverse party’s pleadings.” 
    Id. at 61-62
    (citing Minn.
    R. Civ. P. 56.05). “[T]he nonmoving party must present more than evidence which
    merely creates a metaphysical doubt as to a factual issue and which is not sufficiently
    7
    probative with respect to an essential element of the nonmoving party’s case to permit
    reasonable persons to draw different conclusions.” Valspar Refinish, Inc. v. Gaylord’s,
    Inc., 
    764 N.W.2d 359
    , 364 (Minn. 2009) (quotation omitted). Here, appellant asserts that
    even if it technically breached the terms of the contract, it did not materially breach the
    contract because it received a certificate of substantial completion and finished 262 of the
    265 required punch-list items. Appellant argues that the materiality of its breach is a fact
    issue precluding summary judgment.
    We disagree. “A material breach is ‘[a] breach of contract that is significant
    enough to permit the aggrieved party to elect to treat the breach as total (rather than
    partial), thus excusing that party from further performance and affording it the right to
    sue for damages.’” BOB Acres, LLC v. Schumacher Farms, LLC, 
    797 N.W.2d 723
    , 728-
    29 (Minn. App. 2011) (citing Black’s Law Dictionary 214 (9th ed. 2009)). A material
    breach “goes to the root or essence of the contract.” 15 Samuel Williston & Richard A.
    Lord, A Treatise on the Law of Contracts § 44:55 (4th ed. 2000). Even when viewed in
    the light most favorable to appellant, a review of the record reveals that appellant’s
    breach was material. Appellant failed to substantially complete the project by the agreed-
    upon June 30 deadline. Although a certificate of substantial completion was eventually
    issued, it was issued after the June 30 deadline and appellant failed to complete all of the
    punch-list items within the required 30 days. Even after the parties extended the punch-
    list deadline, appellant again failed to finish the remaining items. Moreover, appellant
    did not pay its subcontractors, which resulted in mechanic’s liens on the property, and
    appellant failed to complete closeout and warranty work which was required by the
    8
    contract. These uncontested facts show that appellant’s breach was material and thus the
    provisions of the indemnity agreement were triggered. As such, the district court
    appropriately awarded summary judgment to respondent.
    II.    Respondent’s breach
    In granting respondent’s motion for summary judgment, the district court
    simultaneously denied appellant’s motion for summary judgment. Appellant argues that
    the district court erred in denying its motion because respondent breached the contract
    with respect to the proper payment and claims procedure. “The elements of a breach of
    contract claim are (1) formation of a contract, (2) performance by plaintiff of any
    conditions precedent to his right to demand performance by the defendant, and (3) breach
    of the contract by defendant.” Lyon Fin. Servs., Inc. v. Ill. Paper & Copier Co., 
    848 N.W.2d 539
    , 543 (Minn. 2014) (quotation omitted). Because the parties do not dispute
    that a contract was formed, our inquiry is limited to the second and third elements.
    A.     Breach via payment
    Appellant first argues that respondent breached the contract by failing to timely
    pay the sixth progress payment. Appellant argues that it satisfied its conditions precedent
    sufficient to require payment. We are not persuaded. “A condition precedent is an event
    that must occur before a party is required to perform a certain contractual duty.”
    Minnwest Bank Cent. v. Flagship Prop. LLC, 
    689 N.W.2d 295
    , 299 (Minn. App. 2004).
    As previously mentioned, the terms of the contract required appellant to submit payment
    applications to Ayres, who would then either (1) issue a recommendation for payment to
    respondent or (2) return the application to appellant with an explanation for its refusal.
    9
    Upon refusal, appellant could reapply. The terms of the contract dictate that payment
    was not due until respondent received a payment application with Ayres’s
    recommendation that payment be delivered. Ayres twice reduced the amount approved
    on appellant’s sixth progress payment application. Appellant failed to resubmit an
    application. Thus, appellant failed to perform a condition precedent and its summary
    judgment claim was properly denied.
    B.     Breach via claims procedure
    Appellant next argues that respondent breached when it adjusted the contract price
    without following the proper claims procedures. Under the contract, a party was required
    to submit a claim to Ayres if it sought to adjust the contract price. Submitting a claim
    required prompt written notice to the other party, who was then afforded the chance to
    respond. At that time, Ayres would issue a decision on the proposed claim.
    Respondent admits that it did not follow this procedure when it did not pay the
    sixth progress payment in its entirety. Instead, respondent contends that it did not adjust
    the contract price at all, but rather set-off its additional expenses incurred as a result of
    appellant’s deficient performance. We agree.
    The contract differentiates between contract price and set-offs. Contract price is
    defined in terms of “work,” which “includes and is the result of performing or providing
    all labor, services, and documentation necessary to produce such construction, and
    furnishing, installing, and incorporating all materials and equipment into such
    construction.” Accordingly, contract price relates to the price for appellant’s physical
    labor. This price, however, can be offset by costs respondent incurs as a result of
    10
    appellant’s insufficient performance. For example, in outlining the procedure for
    progress payments upon substantial completion, the contract states that respondent will
    pay a percentage of the contract price “less such amounts as [Ayres] shall determine or
    [respondent] may withhold, for incomplete work.” Because the contract makes this
    distinction, we agree that respondent did not make an adjustment to the contract price;
    rather, respondent offset the contract price against the additional expenses it accrued as a
    result of appellant’s delay. Thus, the district court did not err in denying summary
    judgment on appellant’s breach-of-contract claim.
    III.   Wrongful termination
    Finally, appellant contends that the district court improperly denied its summary
    judgment motion because respondent did not follow the proper process for terminating
    the contract. The district court did not address the merits of appellant’s wrongful-
    termination claim because it determined that it was not properly pleaded. We agree with
    the district court’s determination.
    “A pleading which sets forth a claim for relief . . . shall contain a short and plain
    statement of the claim showing that the pleader is entitled to relief.” Minn. R. Civ. P.
    8.01. Minnesota is a notice-pleading state and “does not require absolute specificity in
    pleading, but rather requires only information sufficient to fairly notify the opposing
    party of the claim against it.” Donnelly Bros. Constr. Co. v. State Auto Prop. & Cas. Ins.
    Co., 
    759 N.W.2d 651
    , 660 (Minn. App. 2009).
    Appellant served its original complaint on September 18, 2013, and its amended
    complaint on January 3, 2014. Neither explicitly asserted that respondent’s termination
    11
    of the contract was wrongful. Instead, the complaints focused solely on the breach-of-
    contract claims previously discussed. And while appellant argues that a breach-of-
    contract claim incorporates and includes a wrongful-termination-of-contract claim, it
    provides no citation for this proposition. See Schoepke v. Alexander Smith & Sons
    Carpet Co., 
    290 Minn. 518
    , 519-20, 
    187 N.W.2d 133
    , 135 (1971) (declaring that
    argument based on “mere assertion and not supported by any argument or
    authorities . . . is waived and will not be considered on appeal unless prejudicial error is
    obvious on mere inspection”). Thus, we agree with the district court’s determination that
    appellant is precluded from bringing a wrongful-termination claim when it was not
    properly pleaded.2
    Affirmed.
    2
    Even if such a claim was properly pleaded, we disagree with appellant’s assertion that
    the termination of the contract was wrongful. Appellant contends that under paragraph
    15.02.C of the contract, certain payment and review procedures must occur prior to
    termination. But paragraph 15.02.F reads: “If and to the extent that [appellant] has
    provided a performance bond . . . the termination procedures of that bond shall supersede
    the provisions of Paragraphs 15.02.B and 15.02.C.” Thus, respondent was required to
    comply with the termination procedures of the performance bond issued by NAS under
    the indemnity agreement and not the procedures outlined in paragraph 15.02.C of the
    contract. A review of the record indicates that the termination procedures of the
    performance bond were properly followed. Therefore, even if appellant properly pleaded
    its wrongful-termination claim, the district court did not err in denying appellant’s motion
    for summary judgment.
    12