in-the-matter-of-minnesota-powers-petitions-for-approval-of-its-boswell ( 2014 )


Menu:
  •                           This opinion will be unpublished and
    may not be cited except as provided by
    Minn. Stat. § 480A.08, subd. 3 (2012).
    STATE OF MINNESOTA
    IN COURT OF APPEALS
    A14-0253
    In the Matter of Minnesota Power's Petitions for
    Approval of its Boswell Energy Center Unit 4
    Environmental Retrofit Project and
    Boswell 4 Environmental Improvement Rider.
    Filed November 3, 2014
    Affirmed
    Bjorkman, Judge
    Minnesota Public Utilities Commission
    File No. E015/M-12-0920
    Leigh K. Currie, Minnesota Center for Environmental Advocacy, St. Paul, Minnesota (for
    relators Minnesota Center for Environmental Advocacy, Izaak Walton League of
    America – Midwest Office, Fresh Energy, and Sierra Club)
    Lori Swanson, Attorney General, Lisa A. Crum, Kathryn Fodness, Assistant Attorneys
    General, St. Paul, Minnesota (for respondent Minnesota Public Utilities Commission)
    Michael C. Krikava, Elizabeth M. Brama, Briggs and Morgan, P.A., Minneapolis,
    Minnesota; and
    David R. Moeller, Minnesota Power, Duluth, Minnesota (for respondent Minnesota
    Power)
    Andrew Moratzka, Sarah Elizabeth Johnson Phillips, Stoel Rives LLP, Minneapolis,
    Minnesota (for respondent Large Power Intervenors)
    Considered and decided by Smith, Presiding Judge; Larkin, Judge; and Bjorkman,
    Judge.
    UNPUBLISHED OPINION
    BJORKMAN, Judge
    Relators challenge respondent commission’s approval of respondent power
    company’s mercury-emissions-reduction plan, arguing that the commission erred by
    approving the plan without the required environmental analysis. We affirm.
    FACTS
    Under the Mercury Emissions Reduction Act (MERA), Minn. Stat. §§ 216B.68-
    .688 (2012), a public utility that owns a large coal-fired power plant in Minnesota must
    prepare a plan for reducing the plant’s mercury emissions and submit the plan to
    respondent Minnesota Public Utilities Commission (MPUC) for approval. There are six
    such existing plants, including respondent Minnesota Power’s Boswell 4 facility.
    On August 31, 2012, Minnesota Power filed a petition under Minn. Stat.
    § 216B.6851, seeking approval of its mercury-emissions-reduction plan for Boswell 4.
    Minnesota Power proposed a four-year project to retrofit Boswell 4 with a semi-dry flue-
    gas desulfurization system, fabric filter, and powder-activated carbon-injection system,
    asserting that these measures would reduce the plant’s mercury emissions by 90%, reduce
    the output of multiple other pollutants, and reduce plant wastewater. Minnesota Power
    also detailed its process of identifying and evaluating various approaches to reducing
    emissions of mercury and other pollutants, from a range of carbon-injection retrofit
    options to retiring Boswell 4 in favor of a natural-gas replacement.
    The Minnesota Pollution Control Agency (MPCA) reviewed Minnesota Power’s
    retrofit plan. The MPCA determined that the plan presents a technically feasible, cost-
    2
    effective means of providing multiple environmental and public-health benefits,
    including 90% reduction in mercury emissions.           The MPCA also observed that
    Minnesota Power described “alternatives to mercury controls that included replacing the
    entire unit with natural gas-fired generation,” but it did not evaluate the environmental
    effects of a natural-gas replacement. The MPCA recommended that the MPUC approve
    the retrofit plan.
    After two rounds of comments on the plan—including joint comments from
    relators Minnesota Center for Environmental Advocacy, Izaak Walton League of
    America–Midwest Office, Fresh Energy, and Sierra Club—and a public hearing, the
    MPUC approved Minnesota Power’s retrofit plan.                  Relators petitioned for
    reconsideration, which the MPUC denied. Relators appeal.
    DECISION
    The MPUC’s approval of a mercury-emissions-reduction plan is subject to appeal
    under the Minnesota Administrative Procedure Act. See Minn. Stat. § 216B.52, subd. 1
    (2012); In re N. States Power Co., 
    775 N.W.2d 652
    , 655-56 (Minn. App. 2009). Under
    the act, we may affirm the MPUC’s decision, remand the case for further proceedings, or
    reverse or modify the decision if the petitioner’s substantial rights have been prejudiced
    because the findings, inferences, conclusions, or decision are affected by an error of law,
    unsupported by substantial evidence, or are arbitrary and capricious. 
    Minn. Stat. § 14.69
    (2012).
    Relators argue that the MPUC committed legal error by approving Minnesota
    Power’s retrofit plan in the absence of the full environmental assessment MERA requires.
    3
    This argument presents a question of statutory interpretation. While we defer to an
    administrative agency on matters within its field of expertise, we do not defer to an
    agency’s statutory interpretation when statutory language “is clear and capable of
    understanding.” In re Annandale NPDES/SDS Permit Issuance, 
    731 N.W.2d 502
    , 511,
    513 (Minn. 2007). Instead, we effectuate the intent of the legislature by interpreting the
    text of the statute according to its plain language. Minn. Transitions Charter Sch. v.
    Comm’r of Minn. Dep’t of Educ., 
    844 N.W.2d 223
    , 227 (Minn. App. 2014), review
    denied (Minn. May 28, 2014). This includes consideration of the statute “as a whole,”
    accounting for the context of the surrounding words and sentences. In re Minn. Power,
    
    838 N.W.2d 747
    , 754 (Minn. 2013).
    When a public utility submits a mercury-emissions-reduction plan for approval
    under MERA, the MPCA is required to “evaluate” the plan and submit its evaluation to
    the MPUC. Minn. Stat. § 216B.684. In doing so, the MPCA must
    (1) assess whether the utility’s plan meets the requirements of
    [Minn. Stat. § 216B.6851], (2) evaluate the environmental
    and public health benefits of each option proposed or
    considered by the utility, including benefits associated with
    reductions in pollutants other than mercury, (3) assess the
    technical feasibility and cost-effectiveness of technologies
    proposed or considered by the utility for achieving mercury
    emissions reduction, and (4) advise the commission of the
    appropriateness of the utility’s plan.
    Id. The MPCA may “request additional information from the utility, especially with
    regard to alternative technologies or configurations applicable to the specific unit, and the
    estimated costs of those alternatives.” Id.
    4
    Relators argue that the natural-gas-replacement alternative that Minnesota Power
    mentioned in its petition is an “option” that the MPCA was required to evaluate, and that
    the MPUC could not approve the retrofit plan without that evaluation. We disagree.
    An “option” is something that is “available as a choice.” American Heritage
    Dictionary 1238 (5th ed. 2011). The broader context of MERA defines whether a
    particular mercury-emissions-reduction measure is “available as a choice” and therefore
    requires MPCA assessment. MERA requires public utilities to reduce mercury emissions
    at existing coal-fired power plants. See Minn. Stat. § 216B.68, subd. 8 (defining a
    “targeted unit” as a “coal-fired electric generation unit”); see also Minn. Stat.
    §§ 216B.682, subd. 1(a) (requiring utility to file a plan “for mercury emissions reduction
    at each such unit”), .6851, subd. 3 (requiring plan “to achieve total mercury reduction at
    targeted and supplemental units”). It does not mention retiring or repowering those
    plants as a means of reducing their emissions of mercury or any other pollutant. 1 Instead,
    MERA expressly anticipates that these reductions will be accomplished by installing
    pollution-control equipment at those plants.      See Minn. Stat. §§ 216B.68, subd. 7
    (referring to “mercury-control equipment” being “installed at a targeted unit”), .686,
    subd. 1 (referring to “pollution control equipment” being “installed at facilities in
    1
    The only mention in MERA of retiring or repowering coal-fired power plants is in the
    narrow provision (undisputedly applicable only to Minnesota Power) that permits a utility
    with two wet-scrubbed coal-fired power plants to stagger submission of mercury-
    emissions-reduction plans but requires multi-faceted annual reports on the second plant,
    including an assessment of whether state or federal pollution controls might warrant
    “retiring or repowering” that plant, rather than installing mercury-emissions-reduction
    technology. See Minn. Stat. § 216B.6851, subd. 5(b)(2)(iii).
    5
    Minnesota”).    In short, the plain language of MERA indicates that the legislature
    intended to regulate, not replace, coal-fired power plants.2
    Replacing a coal-fired plant with a facility that uses a cleaner fuel source might be
    a viable pollution-control measure. But it is an alternative to regulation under MERA,
    not an “option” in a mercury-emissions-reduction plan that the MPCA is required to
    evaluate. Accordingly, we conclude that the MPCA did not violate its statutory duty
    under section 216B.684 by declining to substantively assess the prospect of retiring and
    replacing Boswell 4 with a natural-gas facility.
    Moreover, any deficiency occasioned by the MPCA’s failure to evaluate the
    environmental effects of a natural-gas replacement is harmless.           Under MERA, the
    MPUC’s authority to do anything other than approve a utility’s preferred plan is limited.
    The MPUC “shall approve a utility’s mercury emissions-reduction plan that [the MPUC]
    reasonably expects will come closest to achieving” the 90 percent goal “in a manner that
    provides for increased environmental and public health benefits without imposing
    excessive costs on the utility’s customers.” Minn. Stat. § 216B.6851, subd. 6(b). Only if
    the MPUC is “unable” to approve the utility’s preferred plan (the “90 percent reduction
    plan filed under subdivision 3”) may it order the utility to implement some other plan. Id.
    The MPCA thoroughly evaluated Minnesota Power’s retrofit plan, including its
    environmental and public-health benefits, technical feasibility, and cost-effectiveness.
    The MPUC considered that evaluation and the substantial evidentiary record and
    2
    Indeed, if a utility were to retire its coal-fired power plant, it would no longer be subject
    to MERA.
    6
    determined that the retrofit plan achieves MERA’s 90% goal, provides for increased
    environmental and public-health benefits, and does not impose excessive costs on
    Minnesota Power’s customers. Relators do not challenge the sufficiency of the MPCA’s
    review of the retrofit plan or any of the MPUC’s findings as to its effectiveness, benefits,
    or costs. Under these circumstances, the MPUC was not only permitted but required to
    approve the retrofit plan. Accordingly, we conclude that the MPUC did not commit legal
    error by approving Minnesota Power’s retrofit plan.
    Affirmed.
    7
    

Document Info

Docket Number: A14-253

Filed Date: 11/3/2014

Precedential Status: Non-Precedential

Modified Date: 4/17/2021