Tony?s Construction v. Kraus-Anderson Construction Company, St. Louis County Schools - ISD 2142 ( 2016 )


Menu:
  •                            This opinion will be unpublished and
    may not be cited except as provided by
    Minn. Stat. § 480A.08, subd. 3 (2014).
    STATE OF MINNESOTA
    IN COURT OF APPEALS
    A16-0075
    Tony’s Construction,
    Appellant,
    vs.
    Kraus-Anderson Construction Company,
    Defendant,
    St. Louis County Schools - ISD #2142,
    Respondent.
    Filed July 5, 2016
    Affirmed
    Kirk, Judge
    St. Louis County District Court
    File No. 69VI-CV-14-740
    Gordon C. Pineo, Deal & Pineo, P.A., Virginia, Minnesota (for appellant)
    John M. Colosimo, Bonnie A. Thayer, Colosimo, Patchin & Kearney, Ltd., Virginia,
    Minnesota (for respondent)
    Considered and decided by Kirk, Presiding Judge; Stauber, Judge; and Bjorkman,
    Judge.
    UNPUBLISHED OPINION
    KIRK, Judge
    Appellant-subcontractor challenges the district court’s grant of summary judgment
    to respondent-owner, a school district, on appellant’s claims of quantum meruit, unjust
    enrichment, quasi or implied contract, and promissory estoppel. Appellant argues that
    genuine issues of material fact preclude summary judgment and that the district court erred
    by failing to address whether the general contractor served as respondent’s agent. We
    affirm because appellant’s release of the general contractor from liability released
    respondent from liability as well.
    FACTS
    This appeal centers on the alleged nonpayment of a subcontractor who worked on
    the Cherry School renovation project. The relationship between the parties is as follows:
    in August 2010, respondent St. Louis County Schools - ISD #2142 (ISD) hired Johnson
    Controls, Inc. (JCI) to act as the program manager for the renovation project. JCI hired
    defendant Kraus-Anderson Construction Company to serve as the construction manager of
    the project.   Other contracts described Kraus-Anderson as a “subconsultant” to the
    renovation project. Hammerlund Construction, a general contractor, accepted appellant
    Tony’s Construction’s bid to perform subcontracting work including excavation, backfill
    footings, and installation of erosion control and storm ponds.
    In December 2014, Tony’s filed a complaint against Kraus-Anderson and ISD under
    the theory of quantum meruit, alleging that it had not been paid for change-order work
    performed under the direction of Kraus-Anderson and with Hammerlund’s knowledge.
    Tony’s later amended its complaint to include claims of unjust enrichment, quasi or implied
    contract, and promissory estoppel.
    In a deposition, Anthony Lastovich, owner of Tony’s, testified that he and three of
    his employees worked at the Cherry School renovation site. During the renovation, Tony’s
    2
    executed several change orders. A change order was a new or different task that Tony’s
    was asked to perform.    Before Tony’s would begin work on a change order, Lastovich
    would determine the cost of labor and materials to complete the task and provide
    Hammerlund with this information. Hammerlund would then authorize Tony’s to perform
    the task, and Tony’s would complete the change order. The contractual agreement between
    Hammerlund and Tony’s stated that Tony’s agreed to secure Hammerlund’s consent and
    written authorization before performing any change-order work.
    During the early stages of the renovation, Hammerlund and Tony’s followed the
    change-order process as outlined in their contractual agreement. But as the workers faced
    a looming project deadline, Lastovich and his employees began taking directions on change
    orders from Kraus-Anderson’s onsite project manager despite the fact that Tony’s did not
    have a direct contractual relationship with Kraus-Anderson.              Zachary Preble,
    Hammerlund’s project manager for the renovation, testified in a deposition that the project
    was plagued with problems and did not run smoothly. Lastovich testified that Kraus-
    Anderson’s project manager ordered that any problems “be dealt with almost
    immediately.” He also told Lastovich to keep track of his work and hours and that Kraus-
    Anderson would pay for the change-order work at the end of the project. Lastovich
    expected that payment for the completed change-order work would be funneled from
    Kraus-Anderson to Hammerlund, who would then pay Tony’s.
    At the end of the project, Lastovich submitted 19 invoices for unpaid change orders
    totaling $76,579.62. Prior to initiating this action, Lastovich settled his dispute with
    3
    Hammerlund through a Pierringer release for $15,366.29. In 2015, Tony’s dismissed its
    claim against Kraus-Anderson with prejudice.
    Tony’s sued ISD under the theory of quantum meruit, quasi or implied contract, and
    unjust enrichment, arguing that ISD was unjustly enriched by its work on the renovation
    project, citing unusual circumstances including a poorly run renovation project, the large
    number of change orders, and the fact that the parties did not always follow the prescribed
    change-order process as outlined in the contract. Tony’s also asserted a promissory-
    estoppel claim, arguing that Tony’s had detrimentally relied on Kraus-Anderson’s promise
    that Tony’s would be paid for the change-order work.
    ISD moved for summary judgment on the ground that Tony’s did not have a contract
    with ISD and that ISD did not know, direct, or communicate with Lastovich or any of his
    employees about Tony’s change-order work. After a hearing, the district court granted
    summary judgment in favor of ISD. It dismissed Tony’s quantum meruit, quasi contract,
    and unjust-enrichment claims, concluding that Tony’s failed to demonstrate that ISD
    benefitted from its work through illegal, unlawful, or unjust means. Citing Lundstrom
    Constr. Co. v. Dygert, it recognized that Tony’s could potentially recover if unusual
    circumstances were present, such as direct contact between Tony’s and ISD, but there was
    no evidence in the record that ISD knew about the change orders as they happened. 
    254 Minn. 224
    , 232, 
    94 N.W.2d 527
    , 533 (1959). It also denied Tony’s promissory-estoppel
    claim, as there was no evidence of a promise between the parties. It pointed to Tony’s
    admission that ISD never directed a change order or promised to pay for a change order.
    Tony’s appeals.
    4
    DECISION
    “On appeal from summary judgment, we review whether there are any genuine
    issues of material fact and whether the district court erred in its application of the law.”
    STAR Ctrs., Inc. v. Faegre & Benson, L.L.P., 
    644 N.W.2d 72
    , 76 (Minn. 2002). “We view
    the evidence in the light most favorable to the party against whom summary judgment was
    granted . . . [and] review de novo whether a genuine issue of material fact exists.” Id. at
    76-77. “We also review de novo whether the district court erred in its application of the
    law.” Id. at 77. “Once the moving party has made a prima facie case that entitles it to
    summary judgment, the burden shifts to the nonmoving party to produce specific facts that
    raise a genuine issue for trial.” Bebo v. Delander, 
    632 N.W.2d 732
    , 737 (Minn. App. 2001),
    review denied (Minn. Oct. 16, 2001).
    “Unjust enrichment is an equitable doctrine that allows a plaintiff to recover a
    benefit conferred upon a defendant when retention of the benefit is not legally justifiable.”
    Caldas v. Affordable Granite & Stone, Inc., 
    820 N.W.2d 826
    , 838 (Minn. 2012). A party
    who prevails on an unjust-enrichment action is in essence entitled to an award in quantum
    meruit. See Sharp v. Laubersheimer, 
    347 N.W.2d 268
    , 271 (Minn. 1984); see also
    Hommerding v. Peterson, 
    376 N.W.2d 456
    , 459 (Minn. App. 1985) (stating that an action
    for unjust enrichment “is a quasi-contractual agreement implied by law”). “A party may
    recover under quantum meruit where he or she has conferred a benefit to another and has
    not received reasonable compensation for this act.” Busch v. Model Corp., 
    708 N.W.2d 546
    , 552 (Minn. App. 2006).
    5
    “Unjust enrichment requires that: (1) a benefit be conferred by the plaintiff on the
    defendant; (2) the defendant accept the benefit; and (3) the defendant retain the benefit
    although retaining it without payment is inequitable.” Zinter v. Univ. of Minn., 
    799 N.W.2d 243
    , 247 (Minn. App. 2011). Here, the parties agree that Tony’s conferred a benefit, and
    ISD received a benefit from the change orders allegedly performed by Tony’s.              In
    determining Tony’s unjust-enrichment claim, we are asked to determine whether ISD was
    unjustly enriched “in the sense that the term ‘unjustly’ could mean illegally or unlawfully.”
    Schumacher v. Schumacher, 
    627 N.W.2d 725
    , 729 (Minn. App. 2001) (quotation omitted).
    “Promissory and equitable estoppel imply the existence of a contract based on
    promises or conduct.” Cityscapes Dev., LLC v. Scheffler, 
    866 N.W.2d 66
    , 72 (Minn. App.
    2015). “A promissory estoppel claim requires: (1) a clear and definite promise; (2) that the
    promisor intended to induce the promisee’s reliance; (3) that the promisee relied on the
    promise to his or her detriment; and (4) that enforcement of the promise is necessary to
    prevent injustice.” Zinter, 799 N.W.2d at 246.
    Minnesota law establishes that, other than the statutory right to a mechanic’s lien1
    or other special statutory remedies, subcontractors generally have no right to a personal
    judgment against the owner where there is no contractual relationship between them. See
    Johnson & Peterson, Inc. v. Toohey, 
    285 Minn. 181
    , 183-84, 
    172 N.W.2d 326
    , 328 (1969);
    Duluth Lumber and Plywood Co. v. Delta Dev., Inc., 
    281 N.W.2d 377
    , 384 (Minn. 1979);
    1
    Property owned by a school district is exempt from mechanics’ liens under the common-
    law public policy exemption to the mechanic’s lien statute. GME Consultants, Inc. v. Oak
    Grove Dev. Inc., 
    515 N.W.2d 74
    , 75 (Minn. App. 1994).
    6
    see also Lundstrom Constr. Co., 
    254 Minn. at 232
    , 94 N.W.2d at 533 (suggesting that
    subcontractors might be allowed to recover against homeowners when unusual
    circumstances are present); Skjod v. Hofstede, 
    402 N.W.2d 839
    , 840-41 (Minn. App. 1987)
    (holding that, absent unusual circumstances such as direct contact or communication
    between the owner and subcontractor, a subcontractor does not have an equitable remedy
    against a homeowner for work or materials furnished if there was no contract between the
    parties). But a subcontractor may be entitled to recovery if an owner is unjustly enriched
    by the subcontractor’s work or under the theory of promissory estoppel.
    Caselaw describing the liability of homeowners to subcontractors contemplates
    simple, well-defined contractual relationships between three parties: a homeowner who
    contracts with a general contractor to complete work, and the contractor who subcontracts
    all or part of the work to a subcontractor. In contrast, the case at bar presents a complex
    series of relationships between five parties who have each entered into contracts with one
    or more parties: an owner-school district, a program manager, a construction manager, a
    general contractor, and a subcontractor. Tony’s asserts that within these contractual
    relationships there is a genuine issue of material fact as to whether Kraus-Anderson acted
    as the agent of ISD during the renovation project. There is a “long-standing common-law
    notion that a principal is liable for the act of an agent committed in the course and within
    the scope of agency.” Bedow v. Watkins, 
    552 N.W.2d 543
    , 547 (Minn. 1996). “Vicarious
    liability may be imposed when a master-servant or principal-agent relationship exists
    between the tortfeasor and a third party.” Urban ex rel. Urban v. American Legion Post
    184, 
    695 N.W.2d 153
    , 160 (Minn. App. 2005), aff’d, 
    723 N.W.2d 1
     (Minn. 2006).
    7
    Viewing the evidence in the light most favorable to the nonmoving party, the
    deposition testimony establishes that Tony’s was placed under considerable pressure to
    complete numerous change orders during the project. As the project deadline became
    closer, Kraus-Anderson and Tony’s adopted a practice of going around the contractual
    provision requiring Hammerlund’s written authorization prior to Tony’s performing
    change-order work. Lastovich acted under the belief that he would be paid for the change-
    order work at the end of the project but did not receive payment.
    Provisions within the contractual agreement between ISD and JCI also support
    Tony’s argument that Kraus-Anderson acted as the agent of ISD, the principal. Sections
    2.1.4 and 4.1.1 of the contract state that Kraus-Anderson is a subconsultant for the
    renovation project and that “[t]he term JCI means Johnson Controls, Inc., or its
    [s]ubconsultants.” Further, section 4.2.1 of the contract provides that JCI will act as ISD’s
    representative during construction and that “JCI will have authority to act on behalf of
    [ISD] only to the extent provided in the [c]ontract.” In essence, the contract language
    establishes that Kraus-Anderson, as subconsultant, was also JCI, and it had the authority
    to act on behalf of ISD.
    But despite this record evidence, we conclude that, as a matter of law, Tony’s is
    unable to pursue any claim against ISD because it dismissed with prejudice all claims
    against Kraus-Anderson. By releasing Kraus-Anderson, the agent, Tony’s also effectively
    released the principal, ISD, from any liability including unjust enrichment and promissory
    estoppel. See Booth v. Gades, 
    788 N.W.2d 701
    , 708 (Minn. 2010) (noting that the court
    has “long recognized” the common-law rule that the release of the agent releases the
    8
    principal); Reedon of Faribault, Inc. v. Fid. & Guar. Ins. Underwriters, 
    418 N.W.2d 488
    ,
    491 (Minn. 1988) (holding that the release of the insurer’s agent also released the principal
    from vicarious liability); Serr v. Biwabik Concrete Aggregate Co., 
    202 Minn. 165
    , 177,
    
    278 N.W.2d 355
    , 362 (1938) (stating that it is “well settled that a valid release . . . of the
    servant releases the master”).
    We conclude that the district court properly granted ISD summary judgment on
    Tony’s claims.
    Affirmed.
    9