G Urban Companies, Inc. v. Roseville Area Schools ISD 623 ( 2023 )


Menu:
  •                  This opinion is nonprecedential except as provided by
    Minn. R. Civ. App. P. 136.01, subd. 1(c).
    STATE OF MINNESOTA
    IN COURT OF APPEALS
    A23-0573
    G Urban Companies, Inc.,
    Appellant,
    vs.
    Roseville Area Schools ISD #623,
    Respondent.
    Filed December 4, 2023
    Affirmed
    Schmidt, Judge
    Ramsey County District Court
    File No. 62-CV-21-4872
    Beau D. McGraw, McGraw Law Firm, P.A., Lake Elmo, Minnesota (for appellant)
    Zachary J. Cronen, Squires, Waldspurger & Mace, P.A., Minneapolis, Minnesota (for
    respondent)
    Considered and decided by Ross, Presiding Judge; Schmidt, Judge; and
    Halbrooks, Judge. ∗
    ∗
    Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to
    Minn. Const. art. VI, § 10.
    NONPRECEDENTIAL OPINION
    SCHMIDT, Judge
    Appellant G Urban Companies Inc. (G Urban) challenges the summary-judgment
    dismissal of its claims of breach of contract, unjust enrichment, and promissory estoppel
    against respondent Roseville Area Schools ISD #623 (the district), arguing that issues of
    material fact regarding the bidding process that led to the parties’ contract preclude
    summary judgment on all three claims. Because the plain language of the parties’ contract
    defeats the breach-of-contract claim and the existence of an enforceable contract precludes
    equitable relief, we affirm.
    FACTS 1
    In mid-2019, the district began a construction project at a middle school that
    included work on its track and field. The district’s construction manager solicited bids for
    the project, posting plans and specifications for bidding on the platform iSqFt. The bidding
    documents were also available in several other locations, including the Minnesota Builders
    Exchange (MBEX). The work scope for the project called for “removal of existing track
    aggregate as required to install engineered soil.” An addendum to the bidding documents
    (Addendum No. 2) also referenced “engineered soil” and included a drawing (C200) that
    used shading to show installation of engineered soil as part of the project.
    1
    Consistent with our review of an order granting summary judgment, our recitation of the
    facts includes only undisputed facts that we view in the light most favorable to G Urban as
    the nonmoving party. Trebelhorn v. Agrawal, 
    905 N.W.2d 237
    , 241 (Minn. App. 2017).
    2
    G Urban submitted a bid, offering to complete the work for $1,650,000. In its bid,
    G Urban acknowledged that it received and examined the bidding documents and addenda.
    After all bids were publicly opened and read at the Roseville Area Schools District Center,
    G Urban was revealed to be the lowest bidder. The parties thereafter reviewed the scope
    of the project, confirming that it included installation of a new engineered soil track.
    G Urban told the district that its bid did not account for installing engineered soil because
    it obtained a drawing from MBEX that did “not indicate that engineered soil is required for
    the surface of the track.” G Urban asserted that the apparent inconsistency in bidding
    documents made the bidding process unfair and requested that the district either award it
    the project and later provide for additional compensation for installing engineered soil or
    reject all bids and allow for rebidding. The district denied the requests.
    Instead, the construction manager explained that the district intended to accept
    G Urban’s bid amount as is “with no intention of accepting a change order.”                   The
    construction manager further offered that if G Urban was “not in agreement they may
    withdraw their bid.” G Urban responded that it “will not agree to withdraw its bid” and
    reiterated its requests for the district to award the contract to G Urban with the additional
    cost for the engineered soil or for the district to re-bid the entire project. The district replied
    that G Urban will be “expected and required to utilize engineered fill in the track areas.”
    The district also noted that it “will strongly oppose any effort by G. Urban, post-award, to
    assert a claim of entitlement to additional compensation for such fill.” G Urban did not
    withdraw its bid.
    3
    The district’s school board held a public meeting to award the project. G Urban’s
    owner attended the meeting and spoke during the public-comment period, restating the
    request for additional compensation for installing engineered soils. The district awarded
    the project to G Urban. G Urban and the district thereafter executed a written contract. In
    defining the work that G Urban agreed to perform, the construction contract incorporated
    numerous bid documents, including Addendum No. 2 and drawing C200, which identify
    installation of engineered soil as part of the project. The district agreed to pay G Urban
    $1,650,000 for the work. The construction contract states that it “represents the entire and
    integrated agreement between the parties hereto and supersedes prior negotiations,
    representations or agreements, either written or oral.” The construction contract also
    permits modification of the scope of the work and the compensation if the parties agree to
    a “change order.”
    In early 2020, G Urban wrote to the construction manager requesting an additional
    $77,750 as “extra costs” for installing engineered soil, reiterating its position that some
    bidding documents did not clearly show that work as part of the project. The construction
    manager rejected the request, stating: “The expectation is that because [G Urban] accepted
    the project award that engineered fill will be provided throughout the track as shown in the
    project documents at no additional cost to the project.” G Urban completed the project,
    including installation of engineered soil.
    G Urban sued the district, alleging that the construction contract is an “enforceable
    agreement,” it requested a change order regarding installation of engineered soil, and the
    district breached the contract by “fail[ing] to approve [G Urban’s] change order and
    4
    refus[ing] to compensate [G Urban] for the use of engineered soils in the track and field
    area.” G Urban also asserted claims of unjust enrichment and promissory estoppel based
    on the district’s refusal to compensate it for installing engineered soil.
    The district moved for summary judgment, arguing that it did not breach the
    construction contract by declining to grant a change order because the contract required
    installation of engineered soil. The district also argued G Urban cannot receive equitable
    relief because a valid contract governs the parties’ actions. The district court agreed,
    granted summary judgment, and dismissed the case with prejudice. G Urban appeals.
    DECISION
    Summary judgment is proper if the moving party shows that “there is no genuine
    issue as to any material fact and the movant is entitled to judgment as a matter of
    law.” Minn. R. Civ. P. 56.01. On appeal, we review “the record to determine whether
    there is any genuine issue of material fact and whether the district court erred in its
    application of the law.” Dahlin v. Kroening, 
    796 N.W.2d 503
    , 504–05 (Minn. 2011). “We
    review a district court’s summary judgment decision de novo.” Riverview Muir Doran,
    LLC v. JADT Dev. Grp., LLC, 
    790 N.W.2d 167
    , 170 (Minn. 2010). We view the evidence
    “in the light most favorable to the party against whom judgment was granted.” Trebelhorn,
    905 N.W.2d at 241.
    5
    I.     The plain language of the construction contract defeats G Urban’s breach-of-
    contract claim.
    To prevail on a breach-of-contract claim, a plaintiff must prove three
    elements: “(1) formation of a contract, (2) performance by plaintiff of any conditions
    precedent to [its] right to demand performance by the defendant, and (3) breach of
    the contract by defendant.”   Park Nicollet Clinic v. Hamann, 
    808 N.W.2d 828
    , 833
    (Minn. 2011).
    G Urban and the district undisputedly formed a valid contract. Whether the district
    breached the construction contract depends on interpretation of the contract, which presents
    a question of law that we review de novo. Trebelhorn, 905 N.W.2d at 242. “If a contract
    is unambiguous, a court gives effect to the parties’ intentions as expressed in the four
    corners of the instrument, and clear, plain, and unambiguous terms are conclusive of that
    intent.” Christensen L. Off., PLLC v. Olean, 
    916 N.W.2d 876
    , 886 (Minn. App. 2018).
    G Urban argues that material fact issues preclude summary judgment on its claim
    that the district breached the construction contract because (1) inaccurate bidding
    documents were posted on MBEX, misleading G Urban regarding the project’s
    requirements; (2) the parties discussed a change order regarding engineered soil before
    executing the construction contract, and the construction contract permits G Urban to
    submit a change order; (3) the phrase “engineered soils” is ambiguous; and (4) the record
    contains conflicting evidence as to whether G Urban accessed the correct bid documents
    on iSqFt. Because none of these facts are material as to whether the district breached the
    construction contract, we are not persuaded.
    6
    In analyzing a breach-of-contract-claim, we look to the language of the contract
    itself. Christensen, 
    916 N.W.2d at 886
    . Unless that language is ambiguous, we will not
    consider extrinsic evidence of “previous understandings and negotiations.” Triple B & G,
    Inc. v. City of Fairmont, 
    494 N.W.2d 49
    , 53 (Minn. App. 1992). Here, the construction
    contract is not ambiguous. The contract plainly permits change orders, but it just as plainly
    provides that a change order “shall be based upon agreement among” the district, the
    construction manager, the architect, and G Urban. The construction contract does not
    require the district to agree to any change order that G Urban submits. Similarly, the
    contract plainly requires G Urban to install engineered soil—as part of the agreed-to work,
    for the agreed-to compensation—by incorporating Addendum No. 2 and drawing C200.
    G Urban does not dispute that the construction contract calls for installing
    engineered soil, only that G Urban did not have access to Addendum No. 2 and drawing
    C200 before bidding. But before signing the contract, G Urban undisputedly understood
    that the contract included engineered soil and declined to withdraw its bid. At oral
    argument, counsel argued withdrawing the bid was “impracticable . . . from an economic
    standpoint.” This argument inherently recognizes that G Urban made a business decision
    to sign the contract that included engineered soil, perform under the contract and install
    engineered soil, and take a calculated business risk that the district may not accept the
    change order for additional compensation for the engineered soil. G Urban’s business
    decision to sign the contract knowing the risks does not make the agreement unenforceable
    or prove that the district breached the contract. Accordingly, the district court did not err
    by granting summary judgment to the district on G Urban’s breach-of-contract claim.
    7
    II.    The construction contract precludes G Urban’s equitable claims.
    Unjust enrichment and promissory estoppel are equitable doctrines that allow a
    plaintiff to recover under circumstances when the parties’ rights are not governed by a
    contract.   Herlache v. Rucks, 
    990 N.W.2d 443
    , 450 (Minn. 2023) (defining unjust
    enrichment); Javinsky v. Comm’r of Admin., 
    725 N.W.2d 393
    , 398 (Minn. App. 2007)
    (defining promissory estoppel). These equitable claims afford relief in the absence of an
    adequate legal remedy, but they are not available when “the rights of the parties are
    governed by a valid contract.” Colangelo v. Norwest Morg., Inc., 
    598 N.W.2d 14
    , 19
    (Minn. App. 1999), rev. denied (Minn. Oct. 21, 1999).
    To avoid application of this rule, G Urban argues that the construction contract does
    not “completely” govern the parties’ rights because it is ambiguous “on what is meant by
    ‘engineered soils.’” We are not persuaded. Even if the phrase “engineered soils” is
    ambiguous, it does not make the construction contract incomplete; it simply permits
    consideration of extrinsic evidence to interpret it. See Trebelhorn, 905 N.W.2d at 242. But
    more importantly, as noted above, any ambiguity in the phrase “engineered soils” is
    immaterial as to whether the construction contract required G Urban to install engineered
    soil as part of the agreed-to work for the agreed-to compensation. Because a valid contract
    governs the parties’ rights and obligations with respect to installation of engineered soil
    and compensation for that work, the district court properly granted summary judgment to
    the district on G Urban’s equitable claims.
    Affirmed.
    8
    

Document Info

Docket Number: a230573

Filed Date: 12/4/2023

Precedential Status: Non-Precedential

Modified Date: 12/4/2023