Everett Kennard v. Mississippi Environmental Quality Permit Board ( 2005 )


Menu:
  •                          IN THE SUPREME COURT OF MISSISSIPPI
    NO. 2005-CC-01472-SCT
    SIERRA CLUB, EVERETT KENNARD AND
    BOSWELL KENNARD
    v.
    MISSISSIPPI ENVIRONMENTAL QUALITY
    PERMIT BOARD AND WILLIE (BILL) CARROLL
    COOK d/b/a COOK SWINE FARM
    DATE OF JUDGMENT:                             05/23/2005
    TRIAL JUDGE:                                  HON. ROBERT L. LANCASTER
    COURT FROM WHICH APPEALED:                    OKTIBBEHA COUNTY CHANCERY COURT
    ATTORNEY FOR APPELLANTS:                      ROBERT B. WIYGUL
    ATTORNEYS FOR APPELLEES:                      RICKY L. BOGGAN
    JAMES T. McCAFFERTY
    NATURE OF THE CASE:                           CIVIL - STATE BOARDS AND AGENCIES
    DISPOSITION:                                  AFFIRMED - 11/30/2006
    MOTION FOR REHEARING FILED:
    MANDATE ISSUED:
    BEFORE SMITH, C.J., GRAVES AND DICKINSON, JJ.
    DICKINSON, JUSTICE, FOR THE COURT:
    ¶1.     In this administrative dispute, the Mississippi Environmental Quality Permit Board
    (“Permit Board”) issued an air pollution control permit to the owner and operator of a swine
    concentrated animal feeding operation (“CAFO”).        Several neighbors appealed the Permit
    Board’s decision.      Finding that the agency’s decision to issue the permit was supported by
    substantial evidence, we must affirm.
    BACKGROUND FACTS AND PROCEEDINGS
    ¶2.     Bill Cook is the owner and operator of a CAFO in Oktibbeha County, Mississippi. The
    facility includes eight barns housing up to 7,040 swine as they are being grown from
    approximately forty to fifty pounds each to approximately 250 pounds each. The barns have
    slatted floors to allow the manure to drop into a holding area, and a collection system flushes
    the waste into an anaerobic lake. The liquid is later drawn from the top of the lake and sprayed
    as fertilizer on fields. There is no dispute that Cook’s facility meets the exacting federal and
    state requirements for CAFOs with respect to the control of water pollution.                    This case
    revolves around the sole issue of the facility’s satisfaction of state air quality standards.
    ¶3.     When Cook’s facility began operations in 1996, the Permit Board did not require air
    pollution permits for swine CAFOs.               As such, the Permit Board only issued a National
    Pollutant Discharge Elimination System (“NPDES”) permit to Cook.                        That decision was
    appealed to the Chancery Court of Oktibbeha County by Everett Kennard and others, and the
    chancellor held the CAFO was required to obtain an air permit. The Permit Board and Cook
    then appealed the decision to this Court.
    ¶4.     While the matter was on appeal, the Mississippi Legislature amended Miss. Code Ann.
    Section 49-17-29 (Rev. 2002) to allow the Mississippi Environmental Quality Commission
    (“Commission”) to establish categories of sources not required to obtain an air permit and to
    allow for the issuance of multimedia permits, that is, permits combining both water pollution
    and air pollution control standards.             Because the resulting regulatory amendment by the
    Commission did not exempt CAFOs, the parties agreed Cook would submit an application for
    an air permit.
    2
    ¶5.    On December 13, 1999, Cook submitted his application.              The Mississippi Department
    of Environmental Quality (“MDEQ”), acting as technical staff for the Permit Board, created
    a draft permit and published a public notice on October 18, 2000, inviting public comment on
    the draft permit. After receiving many comments, MDEQ conducted a public hearing on May
    31, 2001. On March 12, 2002, MDEQ recommended to the Permit Board that an air pollution
    control chapter be added to Cook’s existing NPDES permit, thus transforming it into a
    multimedia permit.1   These controls included the construction of a windbreak wall behind the
    exhaust fans of each housing unit based on MDEQ staff determinations that the exhaust fans
    were the primary source of off-site odor transfer.        After further review, the Permit Board
    accepted MDEQ’s recommendation and issued the multimedia permit to Cook.
    ¶6.    The objectors to the permit (the Mississippi Chapter of the Sierra Club, Everett
    Kennard, and Boswell Kennard [hereinafter “Kennard”]), as well as Cook, requested an
    evidentiary hearing before the Permit Board regarding the multimedia permit.              The Permit
    Board required all parties to file written direct and rebuttal testimony from witnesses prior to
    the hearing.   In general, Kennard argued the permit required too little of Cook and was thus an
    arbitrary and capricious action, while Cook argued the permit required too much and was thus
    an action beyond the authority of the Permit Board.
    ¶7.    On September 10, 2002, the Permit Board conducted an evidentiary hearing on Cook’s
    multimedia permit.     The testimony of multiple lay witnesses and experts was presented by the
    parties and considered by the Permit Board.           At the conclusion of the hearing, the Permit
    1
    See the appendix for a list of the control features added to Cook’s NPDES permit in the new air
    requirements chapter.
    3
    Board deliberated and then voted to affirm its previous issuance of the Cook facility
    multimedia permit as written.
    ¶8.     Kennard again appealed the Permit Board’s decision to the Chancery Court of
    Oktibbeha County, and Cook cross-appealed. On August 25, 2003, the chancellor denied both
    the appeal and cross-appeal, finding that
    [t]he Permit Board has determined that the air pollution control conditions of
    the permit are necessary to operated the CAFO in compliance with the ambient
    air quality regulation. That decision is supported by substantial evidence, is not
    arbitrary or capricious, is within the power of the Permit Board to make and
    does not violate any statutory or constitutional right of Cook. The Permit Board
    has determined that additional air pollution control conditions are not necessary
    to operate the CAFO in compliance with the ambient air quality regulation. That
    decision is also supported by substantial evidence, is not arbitrary or capricious,
    is within the power of the Permit Board to make and does not violate a statutory
    or constitutional right of the Objectors.
    The chancellor also noted that “[a]n administrative appeal is not a means to have a court re-
    weigh evidence and reach a different conclusion.”       The chancellor found the Permit Board’s
    decision was supported by substantial evidence, was not arbitrary or capricious, was within the
    Permit Board’s power, and did not violate any party’s rights.           Therefore, the chancellor
    affirmed the Permit Board’s decision.
    ¶9.     Aggrieved, Kennard filed this appeal, raising three issues for our review: (1) whether
    the Permit Board’s interpretation of Mississippi Air Quality Standard APC-S-4 was
    unreasonable and contrary to the regulation’s plain language; (2) whether the Permit Board
    provided sufficient findings of fact and conclusions of law with respect to the technical and
    expert evidence presented to it; and (3) whether the Permit Board’s decision not to require a
    4
    monitoring regime for Cook’s facility was arbitrary and capricious.         We find no merit in
    Kennard’s assignments of error and affirm the chancellor’s judgment.
    DISCUSSION
    ¶10.    We review this matter under the same standard recognized by the chancellor in his
    review of the administrative order issued by the Permit Board.         Understanding he was not
    sitting as a fact-finder in a nuisance trial, but rather was acting as an appellate court reviewing
    a decision of an administrative agency, the learned chancellor articulated the correct standard
    as follows:
    An administrative appeal is not a means to have a court re-weigh evidence and
    reach a different conclusion. And a permit from an administrative agency is not
    an authorization to operate a nuisance. A court performs two different functions
    when determining whether to enjoin a permitted operation as a nuisance and
    when determining to reverse or affirm an administrative decision. The court
    must respect that difference. An equity suit is fact driven. An administrative
    appeal is law driven. Both proceedings are ultimately public policy driven. And
    public policy is uniquely fitted for the legislature. The legislature has delegated
    the permitting decision to the Permit Board.
    By statutory mandate, “[a]ppeals shall be considered only upon the record as made before the
    Permit Board.” Miss. Code Ann. § 49-17-29(5)(b) (Rev. 2002). See also Golden Triangle
    Reg’l Solid Waste Mgmt. Auth. v. Concerned Citizens Against the Location of the Landfill,
    
    722 So. 2d 648
    , 652 (Miss. 1998). This Court has previously held:
    Matters of law will be reviewed de novo, with great deference afforded an
    administrative agency’s construction of its own rules and regulations and the
    statutes under which it operates. Therefore, an agency’s decision will not be
    disturbed on appeal absent a finding that it (1) was not supported by substantial
    evidence, (2) was arbitrary or capricious, (3) was beyond the power of the
    administrative agency to make, or (4) violated some statutory or constitutional
    right of the complaining party.
    5
    McDerment v. Miss. Real Estate Comm’n, 
    748 So. 2d 114
    , 118 (Miss. 1999) (internal
    citations omitted).
    ¶11.    Substantial evidence is “something less than a preponderance of the evidence but more
    than a scintilla or glimmer.   The reviewing court is concerned only with the reasonableness of
    the administrative order, not its correctness.” Miss. Dep’t of Envtl. Quality v. Weems, 
    653 So. 2d 266
    , 280-81 (Miss. 1995) (internal citations omitted).           An action “is arbitrary or
    capricious if the agency entirely failed to consider an important aspect of the problem, or
    offered an explanation for its decision that runs counter to the evidence before the agency or
    is so implausible that it could not be ascribed to a difference in view or the product of agency
    expertise.”     Id. at 281 (internal citations omitted).   A rebuttable presumption exists in favor
    of agency decisions, and this Court may not substitute its own judgment for that of the agency.
    Miss. Comm’n on Envtl. Quality v. Chickasaw County Bd. of Supervisors, 
    621 So. 2d 1211
    ,
    1216 (Miss. 1993).
    ¶12.    Against this background of authority and precedent establishing our standard of review,
    we now proceed to review the Permit Board’s decision.
    I.       Whether the Permit Board’s interpretation of Mississippi Air
    Quality Standard APC-S-4 was unreasonable and contrary to the
    regulation’s plain language.
    ¶13.    Kennard takes issue with the Permit Board’s interpretation of Mississippi Air Quality
    Standard APC-S-4, arguing the Permit Board erroneously focused on a single factor and
    ignored the factors favorable to the objectors.       This led to an unreasonable interpretation of
    the regulation at odds with its plain and unambiguous language.      Therefore, Kennard argues the
    6
    Permit Board’s decision should be reversed and the matter remanded with instructions as to
    the regulation’s proper interpretation.
    Mississippi Air Quality Standard APC-S-4
    ¶14.    This Court’s only precedent addressing state regulation of odor is Mississippi Air &
    Water Pollution Control Permit Board v. Pets & Such Foods, Inc., 
    394 So. 2d 1353
    , 1355
    (Miss. 1981), where this Court reversed the agency’s decision because the regulation in effect
    at that time failed to set an objective standard “with which to measure concentrations of odors
    in the ambient air.”     The next year, the Legislature addressed the regulation’s deficiency by
    amending Miss. Code Ann. Section 49-17-19 (Rev. 2002) to read, “[i]n establishing ambient
    air quality standards for odor, the commission shall adopt recognized objective standards if
    they exist. In the absence of a recognized objective ambient air quality standard for odor, the
    commission may adopt such subjective standards as may be appropriate.”
    ¶15.    Based on the amended statute, the Commission adopted the current version of APC-S-4,
    which provides:
    There shall be no odorous substances in the ambient air in concentrations
    sufficient to adversely and unreasonably:
    (1)    affect human health and well-being;
    (2)    interfere with the use of enjoyment of property; or
    (3)    affect plant or animal life.
    In determining that concentrations of such substances in the ambient air are
    adversely and unreasonably affecting human well-being or the use or enjoyment
    of property of plant or animal life, the factors to be considered by the
    Commission will include, without limiting the generality of the foregoing, the
    number of complaints or petitioners alleging that such a condition exists, the
    frequency of the occurrence of such substances in the ambient air as confirmed
    by the Department of Environmental quality staff, and the land use of the
    affected area.
    7
    Through this amendment, the Commission provided the necessary objective standards by
    adding three reasonably measurable parameters.
    ¶16.     According to Kennard, the Permit Board improperly focused on the second factor, “the
    frequency of the occurrence of such substances in the ambient air as confirmed by the
    Department of Environmental quality staff,” and since MDEQ staff could not confirm the
    existence of off-site odors, the Permit Board obviously failed to consider the other factors
    when issuing a permit with such lax restrictions.          Kennard points to passages in the Permit
    Board’s findings allegedly bearing out this erroneous interpretation, such as the following:
    The factors required to be considered by the Commission limit the applicability
    of the section in recognition that APC-S-4 is a subjective standard, the
    application of which by the Commission or Permit Board must rely in chief on
    the expertise of the agency and the evidence gathered by its staff. Thus, the
    Commission built into the regulation the requirement that violations of the
    standard be judged not only by the land use of the area and the number of
    complaints received from the public, but also by the number of times that
    MDEQ staff can confirm these occurrences. That part of the standard will
    almost always work to limit the Commission’s and the Permit Board’s
    involvement with odor issues to those cases where MDEQ staff can verify the
    nature, frequency, and severity of the complaints.
    ¶17.     Generally, this Court accords great deference to an agency’s interpretation of its own
    rules and regulations. Molden v. Miss. State Dep’t of Health, 
    730 So. 2d 29
    , 32-33 (Miss.
    1998).      However, where        an administrative agency’s interpretation is contrary to the
    unambiguous terms or best reading of a statutory provision, the agency is not entitled to
    deference. Miss. Gaming Comm’n v. Imperial Palace of Miss., Inc., 
    751 So. 2d 1025
    , 1029
    (Miss. 1999).     In this case, we find no error in the Permit Board’s construction and application
    of the pertinent regulations.
    8
    ¶18.    Kennard’s claim that the Permit Board ignored the complaints made by neighbors of
    the CAFO is not supported by the record. The Permit Board detailed several of the neighbors’
    complaints in its findings, and it ultimately affirmed the imposition of multiple air quality
    control requirements.     In fact, the Permit Board noted that “[i]t is chiefly in response to the
    complaints of offsite odors registered by the Kennard family and other Cook neighbors that
    MDEQ suggested several odor control features be included in the Cook facility multimedia
    permit . . . .” Kennard’s dissatisfaction with the extent of air quality control measures ordered
    by the Permit Board does not indicate the Permit Board disregarded complaints by neighbors
    or suggest the Permit Board elevated MDEQ staff findings to a level of unwarranted
    importance.
    ¶19.    APC-S-4 requires the Permit Board to examine three relatively objective factors in
    arriving at its permitting decisions, and the regulation also allows for additional considerations.
    The Permit Board had before it credible, albeit conflicting, evidence, and we are unable to say
    it did not consider all of this evidence in arriving at its decision. The record does not indicate
    the Permit Board’s interpretation and application of APC-S-4 was contrary to the plain
    language of the regulation.      As such, its interpretation is entitled to the requisite deference by
    this Court. See Miss. State Tax Comm’n v. Mask, 
    667 So. 2d 1313
    , 1314 (Miss. 1995).2
    Economic burden of air quality control measures
    ¶20.    Kennard also argues the Permit Board unreasonably interpreted various regulations to
    find it “[could not] include terms that impose a large economic burden in the permit.” Not only
    2
    Kennard’s position that the Permit Board’s decision is no more than a litigating position, and thus
    not entitled to deference, is equally unpersuasive. The Permit Board considered the necessary factors
    under APC-S-4 and arrived at a decision supported by substantial evidence.
    9
    does Kennard overstate the conclusion of the Permit Board with respect to the role of
    economically burdensome control measures, Kennard cannot show that the Permit Board’s
    interpretation of the regulatory scheme was in any way erroneous or unreasonable.
    ¶21.    The Mississippi Administrative Procedures Act requires that prior to the adoption of
    a rule or significant amendment, each agency proposing such rule must consider the “economic
    impact the rule will have on the citizens of our state and the benefits the rule will cause to
    accrue to those citizens.”          Miss. Code Ann. Section 25-43-3.105 (Rev. 2002).     Moreover,
    Miss. Code Ann. Section 49-17-34(2) (Rev. 2002) specifically mandates that
    [a]ll rules, regulations and standards relating to air quality, water quality or air
    emissions or water discharge standards promulgated by the commission after
    April 16, 1993 shall be consistent with and shall not exceed the requirement of
    federal statutes and federal regulations, standards, criteria and guidance relating
    to air quality, water quality, or air emission or water discharge standards.[3]
    ¶22.    Finally, the Legislature has given the following unambiguous instructions regarding the
    adoption of environmental regulations:
    It is the intent of the Legislature to provide protection for the public health and
    safety and the environment for the citizens of Mississippi. In providing for such
    protection, the Legislature recognizes that environmental rules and regulations
    should have an identifiable scientific basis and should be adopted after
    consideration of the costs to the regulated community of implementing the rule
    or regulation.
    Act of July 1, 1994, ch. 598 § 2(1), 1994 Miss. Laws (codified as amended at Miss. Code Ann.
    § 49-2-11 (Rev. 2002)).
    ¶23.    Given this legislative framework, the Permit Board properly read APC-S-4 to require
    cost effective measures, if possible, to achieve the stated goal of the regulation. Additionally,
    3
    Significantly, there are no federal air quality standards.
    10
    nowhere in the Permit Board’s findings does the agency state that costly control measures will
    never be ordered. It simply found that in this case, current violations of APC-S-4 did not exist
    to a degree that would justify the imposition of conditions in Cook’s permit that would place
    a potentially insurmountable economic burden on the facility.                   Crediting the evidence
    presented by MDEQ staff and the expert testimony of Dr. Mike Williams, the Permit Board
    found the installation of a windbreak wall was a reasonable means of meeting state air quality
    standards, and the more elaborate measures advocated by Kennard’s expert, Dr. Ronald Miner,
    were unnecessary.
    ¶24.    Despite     Kennard’s      protestations   to   the   contrary,   the   Permit   Board obviously
    determined the requirements it placed in Cook’s air quality permit would result in the facility’s
    compliance with state air quality standards.            Its interpretation of APC-S-4 was neither
    unreasonable nor contrary to the plain language of the regulation.        Therefore, this Court defers
    to the Permit Board’s interpretation.
    II.     Whether the Pe rmit Board provided sufficient findings of fact and
    conclusions of law with respect to the technical and expert
    evidence presented to it.
    ¶25.    Kennard next argues the Permit Board ignored “voluminous technical evidence and
    expert testimony submitted with respect to the odor and human health impacts of industrial hog
    farms,” resulting in findings of fact and conclusions of law insufficient for appellate review.
    Thus, Kennard asks this Court to reverse the Permit Board’s decision and remand the matter
    so proper findings can be made.
    ¶26.    We have held that an agency must clearly explain its factfinding and reasoning for a
    decision in order to facilitate review by the courts. McGowan v. Miss. State Oil & Gas Bd.,
    11
    
    604 So. 2d 312
    , 324 (Miss. 1992). Conclusory remarks alone do not equip a court to review
    the agency’s findings. Miss. Sierra Club, Inc. v. Miss. Dep’t of Envtl. Quality, 
    819 So. 2d 515
    , 524 (Miss. 2002).        Accordingly, findings on factual issues must be specific enough for
    the reviewing court to determine whether the decision is supported by substantial evidence.
    Id. at 523.
    ¶27.    In this case, the Permit Board was presented with conflicting yet credible testimony
    from expert witnesses, lay witnesses, and MDEQ staff.       The Permit Board drafted twenty-five
    pages of findings and conclusions which referenced key portions of the evidence offered by
    Kennard.      While the findings may not have referred to each piece of technical evidence before
    the Permit Board, this Court does not require administrative agencies to exhaustively discuss
    in their findings every bit of evidence presented for their consideration.   Rather, the agency’s
    findings must be specific enough to allow this Court to evaluate whether the decision is
    supported by substantial evidence.
    ¶28.    The Permit Board has provided such findings, including a discussion of the testimony
    by Dr. Miner, Kennard’s expert who recommended more restrictive control measures, and an
    explanation of the technical evidence and testimony refuting Dr. Miner’s conclusions.        The
    findings reveal the Permit Board rejected Dr. Miner’s “worst-case view” based on testimony
    and technical evidence presented by Dr. Williams; Dwight Wylie, Chief of MDEQ’s Air
    Division; Jerry Cain, Chief of MDEQ’s Environmental Permits Division; and the Iowa
    Concentrated Animal Feeding Operations Air Quality Study, Final Report (Iowa State
    University and The University of Iowa Study Group, February 2002).
    12
    ¶29.      Essentially, the crux of Kennard’s complaint with the Permit Board’s findings is that
    the agency did not give the desired discussion of or credence to his evidence and expert.
    However, that dissatisfaction does not equate with insufficient findings.             The Permit Board
    included ample discussion of the reasoning for its findings, allowing for proper appellate
    review.       The Permit Board found that odor problems existed at Cook’s facility, although
    perhaps not to the extent argued by Kennard, and it took positive steps to address those
    problems with the inclusion in Cook’s permit of an air pollution chapter requiring several
    control measures, including a windbreak wall.           Finally, it fully explained its decision not to
    include further measures suggested by Kennard’s expert, Dr. Miner.4
    ¶30.      The Permit Board provided sufficient findings of fact and conclusions of law with
    respect to the technical and expert evidence presented to it.            The decision to affirm the air
    permit as previously issued was supported by substantial evidence, was neither arbitrary nor
    capricious, was within the Permit Board’s power, and was not violative of any party’s rights.
    As such, this Court affirms the Permit Board’s decision.
    III.    Whether the Pe rmit Board’s decision not to require a monitoring
    regime for Cook’s facility was arbitrary and capricious.
    ¶31.      Kennard finally argues the Permit Board’s failure to require a program to monitor odor
    as a term in Cook’s permit was arbitrary, capricious, and contrary to law. We find no legal
    merit to this argument. As a separate issue, the Permit Board directed MDEQ staff “to develop
    a monitoring program around the Cook facility to try to determine with some degree of
    4
    Kennard’s charge that the Permit Board’s decision was merely a way to avoid making a difficult
    and politically volatile decision is completely unsupported by either the facts or the law, and it does not
    warrant discussion by this Court.
    13
    accuracy the strength and frequency of occurrence of offsite odor,” and to report back with its
    findings.     Then, should the collection of additional data so require, the permit could be
    reopened and amended based on the new information.         As previously noted, the Permit Board
    believed that Cook’s facility emitted some amount of objectionable odor, but its extent was
    difficult to quantify.   The Permit Board’s decision to further study the situation and possibly
    revise the permit based on the results of that study cannot be considered arbitrary or
    capricious.
    CONCLUSION
    ¶32.    Faced with conflicting yet credible testimony, the Permit Board made the following
    observation:
    Put bluntly, if the Permit Board accepts only the testimony of Kennard’s
    witnesses, then the permit recommendations of MDEQ are not sufficient. But
    if the Permit Board accepts only the testimony of Cook’s witnesses, then the
    Permit Board has no justification for requiring the additional odor and emission
    control elements of the multimedia permit. The Permit Board finds that the
    objective truth, if such a state exists with odor, is somewhere in the middle.
    After evaluating the evidence presented by both sides, the Permit Board arrived at a decision
    imposing several air quality control requirements on Cook’s facility.       We agree with the
    chancellor that the Permit Board’s decision was supported by substantial evidence and may not
    be disturbed on appeal.
    ¶33.    Kennard’s attack on the Board’s decision is very different from a claim of nuisance or
    some other civil wrong which requires a showing of wrongful conduct directed at him.       In his
    appeal of the decision of the Permit Board, the sole question is whether the Permit Board’s
    decision to issue the permit was supported by substantial evidence in the record and within the
    14
    body’s legislative grant of authority.   It was, and therefore we affirm both the judgment of the
    chancellor and the decision of the Permit Board.
    ¶34.    AFFIRMED.
    SMITH, C.J., WALLER, P.J., DIAZ, EASLEY, CARLSON, GRAVES AND
    RANDOLPH, JJ., CONCUR. COBB, P.J., NOT PARTICIPATING.
    15
    APPENDIX
    a.   The air requirements chapter requires the following best management practices:
    1.     Operators of the facility shall practice odor control methods during the
    course of manure removal and field application. Odor control methods
    shall be those methods identified in the Comprehensive Nutrient
    Management Plan (CNMP) created for the facility. Odor reduction and
    control shall be obtained through chemical, biological, or mechanical
    means where deemed appropriate.
    2.     Operators shall consider wind direction and other relevant conditions
    before spray application occurs.
    3.     Low pressure systems shall be used and spray head orientation such to
    minimize aerosol drift and stripping of volatile compounds.
    4.     Influent pipes shall not be designed such that a free fall of wastes occurs
    from the influent pipe to the lagoon or from the houses to the lagoon
    surface. Influent pipes shall be designed for below-water discharge into
    the lagoons.
    5.     Dead animals shall be stored in closed containers. These “dead boxes”
    shall be completely closed and sealed at all times except when
    depositing carcasses. Containers with damaged lids are prohibited. The
    Pollution Prevention Plan shall include an approvable method of
    treatment and/or disposal of contaminated soils around the dead animal
    handling and storage areas.
    6.     Facilities shall not expand operations, either in size or number of
    animals, prior to amending or enlarging the waste handling procedures
    and structures to accommodate any additional wastes that will be
    generated by the expanded operations. The facility shall not be expanded
    without Permit Board approval.
    7.     Waste handling, treatment, and management shall not result in the
    destruction or adverse modification of the critical habitat of endangered
    or threatened species, or contribute to the taking of endangered or
    threatened species of plant, fish, or wildlife.
    8.     Solids, sludges, manure, or other pollutants removed in the course of
    treatment or control of wastewaters shall be disposed of in a manner
    such as to prevent significant degradation of ambient air quality.
    16
    9.     Dead animals shall be properly disposed of off-site within three (3) days
    unless otherwise provided for by the State Board of Animal Health.
    Animals shall be disposed of in a manner to prevent significant
    degradation of ambient air quality. Incinerators require additional permit
    coverage from the Department and are not allowed by the issuance of
    this permit.
    10.    Collection, storage, and disposal of liquid and solid        waste should be
    managed in accordance with recognized practices of           good agricultural
    management.         The economic benefits derived             from agricultural
    operations carried out at the land disposal site shall be    secondary to the
    proper disposal of waste.
    b.   The air requirements chapter requires the permittee to submit a study plan to the Permit
    Board to determine the optimum barn flushing frequency in order to minimize odors
    associated with barn flushing by April 12, 2002 and begin implementation of the study
    plan by April 26, 2002.
    c.   The air requirement chapter requires the permittee to construct a dust control barrier
    (commonly known as an air dam or windbreak wall, or the equivalent) at a suitable
    distance behind the exhaust fans of each housing unit. The barrier shall extend from the
    ground to a height exceeding the tallest exhaust fan mounted in the housing unit and
    shall be as wide as the housing unit. Alternatively, mechanical dust collection devices
    may be installed on the individual exhaust fans.
    d.   The multimedia permit includes the broad reopener provision, as follows:
    This permit shall also be modified, or alternatively, revoked and reissued, for the
    inclusion of new Best Management Practices (BMPs) and technology
    requirements if the BMPs and technology requirements so approved:
    (a)    Contain different conditions or are otherwise more stringent than any
    BMP or technology requirement in the permit; or control any pollutant
    not limited in the permit.
    (b)    The Air Pollution Control Requirements established in this permit are
    subject to revision if and when more stringent regulatory requirements
    become applicable.
    17