Bruce Cope v. Thrasher Construction, Inc. ( 2017 )


Menu:
  •                 IN THE SUPREME COURT OF MISSISSIPPI
    NO. 2014-CT-01474-SCT
    BRUCE COPE, MARY COPE AND IKE W.
    THRASH
    v.
    THRASHER CONSTRUCTION, INC.
    ON WRIT OF CERTIORARI
    DATE OF JUDGMENT:               10/01/2014
    TRIAL JUDGE:                    HON. MICHAEL H. WARD
    TRIAL COURT ATTORNEYS:          TAYLOR B. McNEEL
    SAMUEL C. KELLY
    KAREN E. HOWELL
    NICHOLAS VAN WISER
    WILLIAM J. LITTLE
    COURT FROM WHICH APPEALED:      HARRISON COUNTY CIRCUIT COURT
    ATTORNEY FOR APPELLANTS:        NICHOLAS VAN WISER
    ATTORNEYS FOR APPELLEE:         TAYLOR B. McNEEL
    SAMUEL C. KELLY
    KAREN E. HOWELL
    NATURE OF THE CASE:             CIVIL - CONTRACT
    DISPOSITION:                    THE JUDGMENT OF THE COURT OF
    APPEALS IS REVERSED; THE
    JUDGMENTS OF THE COUNTY COURT
    AND CIRCUIT COURT OF HARRISON
    COUNTY ARE REINSTATED AND
    AFFIRMED - 11/30/2017
    MOTION FOR REHEARING FILED:
    MANDATE ISSUED:
    EN BANC.
    WALLER, CHIEF JUSTICE, FOR THE COURT:
    ¶1.    Thrasher Construction, Inc. (Thrasher) brought a third-party beneficiary action against
    Bruce Cope, Mary Cope, and Ike Thrash (the Copes and Thrash) in the County Court of the
    First Judicial District of Harrison County. Thrasher sought damages for payments owed for
    waterproofing the Inn by the Sea, a condominium in which the Copes and Thrash had
    acquired a full ownership interest by agreeing, in part, to pay all outstanding bills for work
    previously performed on the property. During trial, the county court dismissed the third-party
    beneficiary claim but allowed Thrasher to proceed on a quantum meruit theory of the case.
    The jury returned a verdict in favor of Thrasher for $69,290, and the county court entered
    judgment based on that verdict. The Copes and Thrash appealed the judgment to the Circuit
    Court of the First Judicial District of Harrison County, which affirmed the judgment of the
    county court. The Copes and Thrash then appealed to the Court of Appeals, arguing the facts
    do not support a recovery on quantum meruit. Thrasher cross-appealed, arguing the trial court
    erred in dismissing its third-party beneficiary claim.
    ¶2.    The Court of Appeals held quantum meruit was not the proper method of relief
    because the action should have proceeded as a third-party beneficiary claim. The Court of
    Appeals reversed the judgment and remanded for further proceedings consistent with its
    opinion. We agree the third-party beneficiary action was the appropriate basis for Thrasher’s
    recovery; however, because the trial court ultimately reached the correct result, no further
    proceedings are needed in this case.
    FACTS AND PROCEDURAL HISTORY
    2
    ¶3.   The facts of this case required for review on appeal are adequately set out by the
    Court of Appeals in its majority opinion. Cope v. Thrasher Const., Inc., 
    2016 WL 3523874
    ,
    at **1–2 (Miss. Ct. App. June 28, 2016).
    Inn by the Sea was destroyed by Hurricane Katrina in 2005. The owners of the
    individual units engaged SeaInn LLC (SeaInn) to develop a new complex and
    rebuild. SeaInn consisted of two members, Greg Stewart and Kenny Labelle.
    The unit owners conveyed their interest in the property to SeaInn in order to
    begin the project. SeaInn then hired Madison Homes as its general contractor.
    Greg Stewart is the only known representative of Madison Homes.
    In February 2009, Madison Homes contracted with Thrasher Construction in
    order to waterproof Inn by the Sea. Thrasher Construction was to be paid
    $106,600 for this project. Thrasher Construction worked on the Inn by the Sea
    project from April to July of 2009. Each month, it sent an invoice to Madison
    Homes, but none of the invoices were paid. Eventually, upon completion of
    sixty-five percent of the work on the Inn by the Sea project, Thrasher
    Construction stopped work due to nonpayment. Thrasher Construction then
    filed a Notice of Construction Lien against the Inn by the Sea property in
    September 2009. The amount due at the time that Thrasher Construction
    stopped work was $69,290, calculated based on the percentage of the project
    completed.
    Ike Thrash later purchased Labelle’s fifty percent interest in SeaInn. He then
    signed over part of his interest to Bruce Cope and Mary Cope. After realizing
    that neither Stewart nor Madison Homes was paying the subcontractors, Cope
    and Thrash entered into a settlement agreement with Stewart to remove him.
    Cope and Thrash agreed to take over and complete certain projects. Cope and
    Thrash agreed to pay the subcontractors on the Inn by the Sea project to the
    extent that the invoices provided by Stewart were “true, valid[,] and correct.”
    Attached to the agreement was a list of unpaid invoices for each project;
    Thrasher Construction’s multiple invoices were listed.
    Cope and Thrash then began to contact the subcontractors. They requested that
    the subcontractors come to Inn by the Sea during a specific two-day period to
    verify the work performed. Upon verification, Cope and Thrash would pay
    each subcontractor what was owed. Thrash contacted Thrasher Construction
    approximately four times during this two-day period, but Thrasher
    Construction did not come to the project to verify its work because of the
    3
    existing lien. Cope and Thrash paid every other subcontractor on the Inn by the
    Sea project. In November 2009, Thrasher Construction withdrew its lien.
    Thrasher Construction then filed a lawsuit against Madison Homes as well as
    Cope and Thrash claiming breach of contract. Specifically, Thrasher
    Construction alleged breach of contract as a third-party beneficiary against
    Cope and Thrash based on the settlement agreement.
    During trial, after Thrasher Construction’s case-in-chief, the county court
    dismissed the third-party beneficiary breach-of-contract claim after Cope and
    Thrash moved for a directed verdict. The court allowed Thrasher Construction
    to proceed on the theory of quantum meruit. The jury returned a verdict in
    favor of Thrasher Construction in the amount of $69,290. Cope and Thrash
    then filed a motion for a judgment notwithstanding the verdict (JNOV), which
    was denied by the county court. They appealed to the circuit court, which
    affirmed.
    
    Id.
     The Copes and Thrash then appealed to this Court, and we assigned the case to the Court
    of Appeals, where both sides raised the same arguments as before the circuit court.
    ¶4.    The Court of Appeals held Thrasher could not recover under quantum meruit but
    should have been allowed to proceed on its third-party beneficiary claim. Accordingly, the
    Court of Appeals reversed and rendered the judgment of the circuit court and reversed and
    remanded the judgment of the county court. With respect to remand, the Court of Appeals
    held further proceedings were necessary as to the third-party beneficiary action. Both sides
    filed petitions for certiorari, which we granted. Before this Court, the Copes and Thrash
    argue the Court of Appeals correctly reversed the quantum meruit claim but erroneously
    revived the third-party beneficiary claim. Thrasher argues the Court of Appeals incorrectly
    reversed the judgment, because under either a quantum meruit or a third-party beneficiary
    theory, the judgment of the county court should be affirmed.
    STANDARD OF REVIEW
    4
    ¶5.    The standards of review for a grant or denial of a directed verdict and judgment
    notwithstanding the verdict (JNOV) are identical. Coho Res., Inc. v. Chapman, 
    913 So. 2d 899
    , 904 (Miss. 2005). We review both “de novo as to the law applied by the trial court judge
    as well as the evidence presented during trial.” Johnson v. St. Dominics–Jackson Mem’l
    Hosp., 
    967 So. 2d 20
    , 22 (¶ 3) (Miss. 2007). This Court views the evidence in the light most
    favorable to the verdict, and if substantial evidence supports the verdict, we will affirm the
    judgment of the trial court. Adcock v. Miss. Transp. Comm’n, 
    981 So. 2d 942
    , 948 (¶ 25)
    (Miss. 2008). “For questions of law, the standard of review is de novo.” O’Neal v. O’Neal,
    
    17 So. 3d 572
    , 574 (¶ 11) (Miss. 2009) (citations omitted).
    DISCUSSION
    ¶6.    The Court of Appeals held Thrasher presented a valid third-party beneficiary claim,
    which should not have been dismissed on directed verdict. We agree.
    ¶7.    “A third person may enforce a promise made for his benefit even though he is a
    stranger to the contract or to the consideration.” Miss. High School Activities Ass’n, Inc. v.
    Farris, 
    501 So. 2d 393
    , 395–96 (Miss. 1987) (citation omitted). To enforce the promise, the
    third-party’s beneficiary status “must spring from the terms of the contract itself.” Burns v.
    Washington Savings, 
    251 Miss. 789
    , 796, 
    171 So. 2d 322
    , 325 (1965). To determine third-
    party beneficiary status, this Court uses the following analysis:
    (1) When the terms of the contract are expressly broad enough to include the
    third party either by name as one of a specified class, and (2) the said third
    party was evidently within the intent of the terms so used, the said third party
    will be within its benefits, if (3) the promisee had, in fact, a substantial and
    articulate interest in the welfare of the said third party in respect to the subject
    of the contract.
    5
    Simmons Housing, Inc. v. Shelton, 
    36 So. 3d 1283
    , 1286 (¶ 10) (Miss. 2010) (quoting
    Yazoo & M.V.R. Co. v. Sideboard, 
    161 Miss. 4
    , 
    133 So. 669
    , 671 (1931)).
    ¶8.    The relevant section of the settlement agreement between the Copes and Thrash and
    Stewart provides:
    Cope and Thrash shall be responsible for the payment of all outstanding bills
    and invoices for work performed and materials supplied on the following
    projects:
    - Inn by the Sea (Seainn, LLC);
    ...
    This shall be accomplished as follows:
    a. Stewart has provide[d] a list of all invoices received to date, and the identity
    of persons/entities with unbilled work-in-process for [Inn by the Sea] to
    Thrash and Cope which is attached hereto as “Exhibit 1";1
    ...
    c. Thrash, along with Stewart, shall be entitled to contact any of the
    subcontractors or suppliers for the purposes of determining the fact that such
    sums are, in fact, due and owing and represent work performed or materials
    provided to [Inn by the Sea]. To the extent that the invoices do not represent
    such sums, they shall not be payable by Thrash and Cope. To the extent that
    they are true, valid[,] and correct payables as to [Inn by the Sea], Cope and
    Thrash shall pay same within 7 days.
    (Emphasis added.)
    ¶9.    The Copes, Thrash, and Stewart entered into an agreement for the express benefit of
    Thrasher. They named Thrasher a beneficiary under their contract. The agreement plainly sets
    out the parties’ intent: “Cope and Thrash shall be responsible for the payment of all
    1
    Thrasher Construction, Inc., is specifically named in the attached exhibit, as well
    as the sums due to Thrasher.
    6
    outstanding bills and invoices for work performed and materials supplied on [Inn by the
    Sea].” Thrasher had an outstanding bill on Inn by the Sea, which the Copes and Thrash
    agreed to pay to Thrasher by name. As the Court of Appeals correctly held, “Thrasher
    Construction qualifies as a third-party beneficiary.” Cope, 
    2016 WL 3523874
    , at *4 (¶ 18).
    ¶10.   The only argument the Copes and Thrash have raised, both before the lower courts
    and this Court, challenging Thrasher’s third-party beneficiary claim is that the third-party
    beneficiary agreement contained “a specific condition precedent which was not met by
    Thrasher.” The Copes and Thrash claim Thrasher was required to meet with them during a
    specific two-day period for settling claims. Since Thrasher did not appear during those two
    days, it failed to meet the “condition precedent.” However, as the Court of Appeals observed,
    “no such condition [was] present in the settlement agreement that required Thrasher
    Construction to respond within two days to a request to verify the work performed at Inn by
    the Sea.” Id. at *5 (¶ 20). The only relevant conditions were that the Copes and Thrash could
    verify the work, and “to the extent that [the invoices were] true, valid[,] and correct,” the
    Copes and Thrash were required to pay them.
    ¶11.   We agree with the Court of Appeals that “[a] reading of the settlement agreement
    shows that the only way Cope and Thrash would not be responsible for paying Thrasher
    Construction is if the work was never performed.” Id. at *5 (¶ 21). A jury has determined
    Thrasher performed the work. As a result, Thrasher should have been allowed to proceed on
    its third-party beneficiary claim.
    7
    ¶12.   Despite the error, a new trial is not needed in this case. We have held, “if the judgment
    of [a trial court] can be sustained for any reason, it must be affirmed, and even though the
    trial judge based it upon the wrong legal reason.” Patel v. Telerent Leasing Corp., 
    574 So. 2d 3
    , 6 (Miss. 1990). This Court has an “obligation to affirm a trial court judgment correct
    as a matter of law, even though the trial court may have been mistaken in its reason for
    granting the judgment.” Shewbrooks v. A.C. & S. Inc., 
    529 So. 2d 557
    , 564 (Miss. 1988),
    superceded by statute on other grounds as stated in N. Am. Midway Entm’t, LLC v. Murray,
    
    200 So. 3d 437
    , 439 n. 4 (Miss. 2016). In other words, we will uphold a judgment where a
    “lower court reaches the right result for the wrong reason.” Finnie v. Lee County Bd. of
    Supervisors, 
    186 So. 3d 831
    , 834 (¶ 7) (Miss. 2016) (quoting Falco Lime, Inc. v. Mayor and
    Aldermen of City of Vicksburg, 
    836 So. 2d 711
    , 725 (¶ 62) (Miss. 2002)).
    ¶13.   While the third-party-beneficiary action was dismissed erroneously, the county court
    reached the correct result in this case. Thrasher worked on Inn by the Sea. The Copes and
    Thrash agreed to pay Thrasher for its work. Under either third-party beneficiary or quantum
    meruit, Thrasher is entitled to the damages awarded in the county court. See Estate of
    Johnson v. Adkins, 
    513 So. 2d 922
    , 926 (Miss. 1987) (holding that, even though incorrect
    legal theory supported trial court judgment, where “the finding of fact is consistent with the
    judgment[,] it will be affirmed.”). The amount awarded by the jury under the quantum meruit
    theory, $69,290, equals the amount of damages proven by Thrasher in pursuit of its third-
    party beneficiary claim.
    8
    ¶14.   We see no reason to remand this case for further proceedings. No factual questions
    are left to be decided. As the Court of Appeals observed, “[t]he facts point so
    overwhelmingly in favor of Thrasher Construction that reasonable jurors could not have
    arrived at a contrary verdict.” Cope, 
    2016 WL 3523874
    , at *5 (¶ 22). Therefore, the
    judgments of the county court and circuit court must stand.
    CONCLUSION
    ¶15.   Thrasher’s third-party beneficiary claim should not have been dismissed. However,
    the county court reached the correct result but for the wrong reason. Therefore, no further
    proceedings are needed in this case. Accordingly, we reverse the judgment of the Court of
    Appeals and reinstate and affirm the judgments of the circuit court and county court in favor
    of Thrasher.
    ¶16. THE JUDGMENT OF THE COURT OF APPEALS IS REVERSED; THE
    JUDGMENTS OF THE COUNTY COURT AND CIRCUIT COURT OF HARRISON
    COUNTY ARE REINSTATED AND AFFIRMED.
    RANDOLPH AND KITCHENS, P.JJ., KING, COLEMAN, MAXWELL, BEAM
    AND CHAMBERLIN, JJ., CONCUR. ISHEE, J., NOT PARTICIPATING.