Amerihost Development, Inc. v. Bromanco, Inc. ( 1998 )


Menu:
  •                     IN THE COURT OF APPEALS
    OF THE
    STATE OF MISSISSIPPI
    NO. 98-CA-00762-COA
    AMERIHOST DEVELOPMENT, INC.                                  APPELLANT
    v.
    BROMANCO, INC.; K & K BATHTUB REPAIR; DIAMOND DOOR GROUP,
    INC.; DEER PARK FENCE & INSULATION CO.; GREY PLUMBING, INC.;
    S & L CREATIVE CARPET; VICKSBURG PAINT & GLASS COMPANY;
    PRECISION ROOF SERVICES, INC.; VINZANT CONSTRUCTION;
    CONTROLLED AIR COMFORT COMPANY; SOUTHERN ELECTRIC
    SUPPLY COMPANY, INC.; WRIGHT'S PAINTING; BRUCE COPES
    ELECTRICAL, INC.; METROPOLIS BUILDERS SUPPLY; PARADISE
    POOLS & SPAS; BARRY LANDSCAPE, INC.; UNITED PIPING, INC.;
    UPTON PLASTERING; MID- SOUTH LUMBER & SUPPLY, INC.; W. J.
    RUNYON & SON, INC.; TESA/ENTRY SYSTEMS, INC. AND GEE &
    STRICKLAND, INC.                                              APPELLEES
    DATE OF JUDGMENT:           4/15/1998
    TRIAL JUDGE:                HON. FRANK G. VOLLOR
    COURT FROM WHICH APPEALED: WARREN COUNTY CIRCUIT COURT
    ATTORNEYS FOR APPELLANT:    PHIL B. ABERNETHY
    JEFFREY TODD WAYCASTER
    RICHARD M. DYE
    ATTORNEYS FOR APPELLEES:    ROBERT BAILESS
    CHARLES L. BALCH III
    JAMES L. PENLEY JR.
    LUCIUS B. DABNEY JR.
    NATURE OF THE CASE:         CIVIL - CONTRACT
    TRIAL COURT DISPOSITION:    CASINO HELD LIABLE TO SUBCONTRACTOR FOR
    AMOUNTS PAID TO GENERAL CONTRACTOR
    FOLLOWING STOP PAYMENT NOTICE GIVEN BY
    SUBCONTRACTOR
    DISPOSITION:                AFFIRMED IN PART AND REVERSED AND REMANDED
    IN PART AND REVERSED AND RENDERED IN PART -
    02/08/2000
    MOTION FOR REHEARING FILED: 02/22/2000 - denied 06/20/2000
    CERTIORARI FILED:
    MANDATE ISSUED:
    BEFORE McMILLIN, C.J., IRVING, AND THOMAS, JJ.
    THOMAS, J., FOR THE COURT:
    ¶1. Amerihost Development, Inc. appeals the judgment of the Circuit Court of Warren County, raising the
    following assignments as error:
    I. WHETHER A SINGLE STOP PAYMENT NOTICE EXERCISING THE RIGHTS OF
    ONE SUBCONTRACTOR PURSUANT MISS. CODE ANN. § 85-7-181 CONFERS THE
    BENEFITS AND PROTECTIONS OF SAID STATUTE UPON ALL
    SUBCONTRACTORS AND SUPPLIERS REGARDLESS OF WHETHER EACH
    SUBCONTRACTOR OR SUPPLIER INDIVIDUALLY PROVIDED NOTICE OF THEIR
    RESPECTIVE CLAIMS.
    II. WHETHER THE TRIAL COURT ERRED IN AWARDING PRE AND POST-
    JUDGMENT INTEREST OF FUNDS INTERPLED AND ON DEPOSIT WITH THE
    COURT CLERK.
    III. WHETHER THE TRIAL COURT ERRED IN ITS AWARD OF ATTORNEYS' FEES.
    ¶2. Bruce Copes Electric, Inc., on cross-appeal, appeals the judgment of the Circuit Court of Warren
    County and raises the following assignment as error:
    IV. WHETHER THE TRIAL COURT ERRED IN FINDING THAT BRUCE COPES
    ELECTRIC, INC. WAS NOT ENTITLED TO ANY OF THE FUNDS INTERPLED.
    ¶3. As to the appeal of Amerihost Development, Inc., finding reversible error, we reverse and render in
    part and reverse and remand in part. As to the cross-appeal of Bruce Copes Electric, Inc., finding no error,
    we affirm.
    FACTS
    ¶4. Amerihost Development, Inc., an Illinois corporation licensed to operate in Mississippi, is the owner and
    developer of a construction project known as Days Inn, Rainbow Park, in Vicksburg, Mississippi. On July
    25, 1994, Amerihost entered into a construction contract with the Ohio corporation Bromanco, as general
    contractor of the hotel project. The original lump sum contracted price of the project was $1,971,977.
    However, as the project progressed change orders increased the original contracted price to a new total of
    $2,011,082.83. Amerihost solely financed the project; therefore, no construction lender was involved.
    Amerihost made irregular inspections of the project site through its personnel, but nevertheless trusted and
    relied heavily on Bromanco's expertise as the general contractor. The contract specified that periodic
    progress payments would be made to Bromanco as the project progressed minus a ten percent retainage.
    The contract required that Bromanco submit periodic applications for payment with stated completion
    percentages and the appropriate lien waivers prior to Amerihost's remittance of payment. A total of eight
    progress payments were made to Bromanco between October 13, 1994 and April 30, 1995. Initially
    Bromanco provided the appropriate applications and the project progressed without any apparent
    problems of major significance. However, as the project neared completion Bromanco began to submit
    applications for payment without complete lien waivers and in fact submitted some duplicate lien waivers.
    Yet, no stop notices were sent during this period to Amerihost by any subcontractors, materialmen, or
    suppliers until mid April 1995.
    ¶5. On April 17, 1995 Amerihost received a statutory stop payment notice pursuant to 
    Miss. Code Ann. § 85-7-181
     (1972) in the amount of $25,000 from Wright's Painting Company, one of the subcontractors
    hired by Bromanco. The dispute between Wright, Amerihost, and Bromanco was subsequently resolved
    without Wright having ever participated in the instant action. On April 30, 1995, Bromanco submitted its
    last application for payment on the project in the amount of $272,819.13. On May 5, 1995, Amerihost
    received a notice letter from Southern Electric Supply Company informing Amerihost that they had not
    been paid approximately $30,881.56 by Bromanco and that said letter should be considered Southern's
    notice under applicable state statutes and a demand for immediate payment. The two stop payment notices
    received from Wright's Painting and Southern Electric totaled approximately $55,881.56. On May 15,
    1995, Amerihost paid Bromanco the $272,819.13 requested on April 30, 1995, but Amerihost still
    retained approximately $110,330.20. Despite that the project was substantially complete, Bromanco
    nevertheless defaulted as general contractor and failed to complete the project. As a result Amerihost hired
    its own work force to finish the project and expended approximately $19,844.62 of the retainage to
    complete the project leaving a retainage of $90,485.58.
    ¶6. Between May 15, 1995 and November 15, 1995, Amerihost received numerous stop payment notices
    and/or bills of account from several of the subcontractors and materialmen originally hired by Bromanco to
    work on the project. Consequently, on November 15, 1995, Amerihost interpled the remaining retainage of
    $90,485.58 into the registry of the Warren County Circuit Court.
    ANALYSIS
    I.
    WHETHER A SINGLE STOP PAYMENT NOTICE EXERCISING THE RIGHTS OF ONE
    SUBCONTRACTOR PURSUANT MISS. CODE ANN. § 85-7-181 CONFERS THE BENEFITS
    AND PROTECTIONS OF SAID STATUTE UPON ALL SUBCONTRACTORS AND
    SUPPLIERS REGARDLESS OF WHETHER EACH SUBCONTRACTOR OR SUPPLIER
    INDIVIDUALLY PROVIDED NOTICE OF THEIR RESPECTIVE CLAIMS.
    ¶7. Amerihost argues that the trial court erred in its interpretation of Miss Code Ann. § 85-7-181. In
    reaching its decision, the trial court interpreted § 85-7-181 as conferring the rights stated within that statute
    upon all subcontractors, materialmen and suppliers who had worked on the project despite whether each
    had availed themselves individually of the express terms of that statute's notice requirements once the owner
    is in receipt of at least one notice from anyone of them. This interpretation does not take into account that
    the lone notice merely asserts that individual subcontractor's amount in controversy and is silent with respect
    to the individual claims, if any, of the other subcontractors, materialmen, and suppliers. Particularly, in this
    case two individual notices, each asserting its own distinct claims and nothing more, were sent by separate
    subcontractors and suppliers: Wright's Painting on April 17, 1995 and Southern Electric Supply on May 5,
    1995. Both notices contained sufficient information under the stop notice statute, § 85-7-181, to qualify as
    notices under that statute. We quickly note that Southern Electric Supply was initially a supplier of a
    subcontractor, Copes Electric, rather than a supplier of the general contractor, Bromanco, and therefore
    not entitled to the protections of § 85-7-181. Material suppliers are general creditors in the absence of the
    afforded protections of § 85-7-181 covering subcontractors or materialmen of the general or prime
    contractor as subcontractors or materialmen to another subcontractor are not covered within the section.
    Associated Dealers Supply, Inc. v. Mississippi Roofing Supply, Inc., 
    589 So. 2d 1245
    , 1247 (Miss.
    1991). However, by virtue of a joint payment agreement entered into on February 8, 1995 between
    Southern, Bromanco, and Copes Electric, wherein Bromanco gave assurances that future payments for
    materials would be made jointly between Southern and Copes Electric, Southern was elevated from a
    supplier of a subcontractor to a supplier of the general contractor. Southern's elevated status, however,
    does not afford them the protections contained in § 85-7-181 for materials supplied and expenses incurred
    prior to the February 8, 1995 agreement.
    ¶8. The trial court concluded, with regard to the first notice received on April 17, 1995, that once an
    owner/developer is presented with a single statutory stop payment notice by one subcontractor then that
    lone notice places the owner/developer on notice that something is potentially afoul with the entire project;
    therefore, all funds due the general contractor at the time the notice is received must be bound in the hands
    of the owner until the matter is resolved. Amerihost argues that under the trial court's interpretation those
    subcontractors, materialmen and suppliers who failed to adhere to the express terms of the statute are
    nevertheless allowed to unjustly piggyback on the lone stop payment notice submitted by Wright. Amerihost
    asserts that this interpretation not only is contrary to the intended purpose of the statute as supported within
    the statute's express language but is also contrary and counter to public policy considerations affecting the
    construction industry in Mississippi.
    ¶9. Mississippi Code Annotated § 85-7-181 (1972) is as follows:
    When any contractor or master workman shall not pay any person who may have furnished materials
    used in the erection, construction, alteration, or repair of any house, building, structure, fixture, boat,
    water craft, railroad, railroad embankment, the amount due by him to any subcontractor therein, or
    the wages of any journeyman or laborer employed by him therein, any such person, subcontractor,
    journeyman or laborer may give notice in writing to the owner thereof of the amount due him and
    claim the benefit of this section; and, thereupon the amount that may be due upon the date of the
    service of such notice by such owner to the contractor or master workman, shall be bound in the
    hands of such owner for the payment in full, or if insufficient then pro rata, of all sums due such
    person, subcontractor, journeyman or laborer who might lawfully have given notice in writing to the
    owner hereunder, and if after such notice, the contractor or master workman shall bring suit against
    the owner, the latter may pay into court, the amount due on the contract; and thereupon all persons
    entitled hereunder, so far as known, shall be made parties and summoned into court to protect their
    rights, contest the demands of such contractor or master workman and other claimants; and the court
    shall cause an issue to be made up and tried and direct the payment of the amount found due in
    accordance with the provisions hereof; or in case any person entitled to the benefits hereof, shall sue
    the contractor or master workman, such person so suing shall make the owner and all other persons
    interested, either as contractors, master workmen, subcontractors, laborers, journeymen or
    materialmen, so far as known, parties to the suit (and any such party not made a party in any suit
    hereunder authorized may intervene by petition), and, thereupon the owner may pay into the court the
    amount admitted to be due on the contract or sufficient to pay the sums claimed, and the court shall
    cause an issue to be made up and award the same to the person lawfully entitled; in either case the
    owner shall not be liable for costs; but if the owner, when sued, with the contractor or master
    workman, shall deny any indebtedness sufficient to satisfy the sums claimed and all costs, the court
    shall, at the instance of any party interested, cause an issue to be made up to ascertain the true amount
    of such indebtedness and shall give judgment and award costs, and reasonable attorney's fees,
    according to the rights of the several parties in accordance herewith. In case judgment shall be given
    against such owner, such judgment shall be a lien, from the date of the original notice, and shall be
    enforced as other liens provided in this chapter. The owner shall not be liable in any event for a
    greater amount than the amount contracted for with the contractor.
    The provisions of this section allowing the award of attorney's fees shall only apply to actions the
    cause of which accrued on or after July 1, 1987.
    ¶10. In arguing its interpretation of § 85-7-181, Bromanco, Inc. places great weight on the legislative
    history of the section, specifically the amendments to the 1906 Code by the 1918 Act. The present statute
    is essentially the same as that which was amended by the 1918 Act. Bromanco argues that with the
    language additions contained in the 1918 Act, so also came the legislative intent to broaden the statute's
    protections to include all members of the protected class of materialmen and subcontractors once a single
    notice is sent and received. Under Bromanco's interpretation, the first solitary notice asserting one member's
    individual right of lien is also for the benefit of all subcontractors, suppliers, and laborers who had the right
    to file a stop notice, but failed to actually file their respective notices.
    ¶11. First we note that 
    Miss. Code Ann. § 85-7-181
     is the product of statutory enactment dating to 1880
    and is therefore open to statutory construction:
    This particular statute was first passed in 1880. However, Mississippi had a mechanics' lien act as
    early as 1838. The lien under Sec. 372 is purely a creature of statute and did not exist at common
    law. In its absence materialmen and laborers would be only general creditors of the contractor.
    Although the statute should be construed liberally to effectuate its purposes, laborers and materialmen
    have no lien on the money owed by the owner to the contractor until they give the statutory stop
    notice to the owner. Two systems of liens have been adopted by statutes in various states for the
    protection of materialmen and laborers. One is known as the Pennsylvania system. It confers a direct
    and independent lien, irrespective of the rights of the principal contractor. The other system, called the
    New York system, which is that created by Section 372, confers a lien by subrogation to the rights of
    the independent contractor. The materialmen or laborers under such a statute are entitled to a lien only
    when the contractor is entitled to one, and there is something due or to become due to the principal
    contractor from the owner.
    Chancellor v. Melvin, 
    211 Miss. 590
    , 599, 
    52 So. 2d 360
    , 364-65 (1951) (citations omitted).
    ¶12. While the current statutory construction is open to differing interpretations, we do have at our disposal
    another rule of statutory construction which may be used by this Court in our efforts to ascertain the intent
    of the legislature and the meaning of the statute before us today. When the necessity for construction arises:
    It is generally regarded as permissible to consider the consequences of a proposed interpretation of a
    statute, where the act is ambiguous in terms and fairly susceptible of two constructions. Under such
    circumstances, it is presumed that undesirable consequences were not intended; to the contrary, it is
    presumed that the statute was intended to have the most beneficial operation that the language
    permits. It is accordingly a reasonable and safe rule of construction to resolve any ambiguity in a
    statute in favor of a beneficial operation of the law, and a construction of which the statute is fairly
    susceptible is favored, which will avoid all objectionable, mischievous, indefensible, wrongful, evil, and
    injurious consequences.
    73 AM JUR. § 258 page 427-28 (1974); See Dawson v. Townsend & Sons, Inc., 
    735 So. 2d 1131
    (¶37) (Miss. Ct. App. 1999) (holding that when a statute is ambiguous and subject to multiple
    interpretations, courts need to understand the possible effects in order not to interpret the statute in such a
    way as to cause absurd results); Chandler v. City of Jackson Civil Service Comm'n, 
    687 So. 2d 142
    ,
    144-45 (Miss. 1997) (holding that when construing a statute, all possible repercussions and consequences
    of construction should be considered); Evans v. Boyle Flying Serv., Inc., 
    680 So. 2d 821
    , 825-26 (Miss.
    1996) (holding that in construing statutes, unthought of results must be avoided if possible, especially if
    injustice follows, and unwise purpose will not be imputed to legislature when reasonable construction is
    possible); Allred v. Webb, 
    641 So. 2d 1218
    , 1222 (Miss. 1994) (holding that when no valid reason exists
    for one of two possible constructions of statute, interpretation with no valid reason ought not be adopted);
    McCaffrey's Food Mkt., Inc. v. Mississippi Milk Comm'n, 
    227 So. 2d 459
    , 465 (Miss. 1969) (holding
    that the statutory construction which is most beneficial and which will avoid objectionable consequences will
    be adopted).
    ¶13. We quickly note that under Bromanco's argument and submitted interpretation, owners who have
    hired a general contractor to ensure the actual construction of the project would suddenly have themselves
    vaulted into the shoes of the general contractor regardless of whether they have the expertise to complete
    the project once a single stop payment notice is received. This would circumvent the precise reason that
    general contractors are hired. Owners would be left with the arduous task of obtaining information on the
    current work performed, the supplies and materials provided and those current amounts due to the various
    subcontractors, materialmen and suppliers.
    ¶14. In addressing the nature of the relationship between a Amerihost and Bromanco, the trial court held
    that Amerihost negligently or wilfully failed to follow the funds into the project and that such failure
    proximately caused the losses claimed by the subcontractors and materialmen. The trial court concluded
    that Amerihost, as both owner and lender, was liable for all unpaid subcontractor's claims, even if such
    subcontractor's claims exceeded the contract amount due to its failure to properly monitor the progress of
    the work and payments to Bromanco as applied under the holding reached in First National Bank of
    Greenville v. Virden, 
    208 Miss. 679
    , 
    45 So. 2d 268
     (1950). Virden is, however, distinguishable from the
    case before us today. The Virden case was decided on the context of mortgage law when an issue of
    preference arises between competing liens: a deed of trust on the project held by a bank or mortgagee on
    advances made under a previously executed mortgage and a mechanic's or materialmen's lien on materials
    and labor supplied on the project. Virden, 
    208 Miss. at 685
    , 
    45 So. 2d at 270
    . In Virden, the supreme
    court held that where a bank accepts a deed of trust on property from the contractor and advances
    proceeds to the contractor for housing lots and materials to be used in the construction of houses, but failed
    to see that the funds were actually going into the housing construction and merely remitted loan proceeds as
    the contractor requested them, then the bank's lien was only superior to liens of materialmen to the extend
    that the loan proceeds actually went into the project. Id.
    ¶15. However, in the case sub judice we are faced with deciding an issue not from a mortgage standpoint
    and the resulting priorities of liens between a mortgagee and a materialman, as the Amerihost project was
    privately funded, but rather from that of mechanics' lien law as was addressed in Engle Accoustic & Tile,
    Inc. v. Grenfell, 
    223 So. 2d 613
     (Miss. 1969). While Engle may not fall squarely on all fours, it does
    however have sufficient analysis to afford us the appropriate avenue to aid us in our decision. In Engle, suit
    was brought by several subcontractors against the project's owners and architect for balances due them as
    a result of the prime contractor's default. The owners, Dr.s Melvin, Marland, and Grenfell, entered into a
    contract with Fran Builders, a partnership composed of Guy Lowe, Jr. and Hudson Turner, the prime
    contractor, on November 23, 1965 for the construction of a multistory office building in Jackson,
    Mississippi. The construction contract was on a cost plus fixed percentage basis without a performance
    bond. Various subcontractors and materialmen were employed by Fran to work on the project and supply
    building materials. As the project progressed, Fran made nine applications for payment for labor and
    materials furnished. Each application was submitted to the owner's architect for verification before payment
    was remitted. In late August 1966, it became apparent that Fran had not paid all laborers and materialmen
    involved in the project and work ceased shortly thereafter. Fran was later declared bankrupt. None of the
    laborers or materialmen filed a stop payment notice on their claims until after the owners had paid Fran in
    full under its ninth and last application for payment.
    ¶16. The Mississippi Supreme Court, in reaching a favorable decision for the owners, acknowledged the
    difficult consequences resulting from its decision: "[I]t is regrettably true that either the appellants will lose
    their labor and materials in the amounts stated or the Owners will be forced to make a double payment. It
    does not necessarily follow, however, that the Owners were in the best position to have prevented the
    loss." Engle, 223 So. 2d at 618. As was the case in Amerihost, the owners in Engle, initiated the overall
    project and trusted and relied heavily upon their prime contractor to complete the contracted project
    without any difficulties or problems. The Engle court further acknowledged that the subcontractors and
    materialmen also relied on and trusted Fran, but their reliance and trust were as equally misguided and
    displaced as were that of the owners. However, in ultimately deciding which party, the owners or the
    laborers and materialmen, were in the best position to prevent the resulting losses, the Mississippi Supreme
    Court held that none of the subcontractors or materialmen had availed themselves of a specific remedy
    afforded them by statute, specifically Miss. Code 1942 Ann. § 372 (1956). Id. The court went on to hold
    that so long as advance payments to the prime contractor by the owners, whether "intentional or
    unintentional," extinguish debt and are paid prior to receipt of the statutory stop payment notices, liability is
    precluded on the part of the owners. Id. at 619.
    ¶17. As was the basis for the supreme court's holding in Engle, subcontractors and materialmen are not left
    without recourse under the current statutory construction of § 85-7-181 provided they invoke its benefits
    and protections though their own due diligence in accordance with the statutory requirements. Those who
    failed to avail themselves of its benefits now seek to circumvent the statutory requirements and ride the
    coat-tails of those subcontractors and materialmen who actually asserted their rights. To allow such a result
    would offend justice. See Riley Bldg. Supplies, Inc. v. First Citizens Nat. Bank, 
    510 So. 2d 506
    , 508-09
    (Miss. 1987) (holding that law governing materialmen's liens is product of enactments of legislature and
    materialmen hold liens against property only to extent that they have brought themselves within terms of
    statute); Frierson Bldg. Supply Co. v. Homestead Sav. & Loan Ass'n., 
    193 So. 2d 421
    , 423-24 (Miss.
    1966) (holding in action to recover for building materials furnished to vendor-builder, it was incumbent
    upon vendor's materialman to comply with lien statutes, and injustice would arise to simply allow
    enforcement of lien against innocent purchasers for value who secured loan on property without actual
    notice of claim which materialman failed to place on record); Jones Supply Co. v. Ishee, 
    249 Miss. 515
    ,
    521-22, 
    163 So. 2d 470
    , 472-73 (1964) (holding that statutory prerequisites must be strictly complied
    with to gain statutory benefits and that upon failure to take proper action required by statute as condition
    precedent to benefits of statute, their remedies are those of common creditors). With this in mind we hold
    that it would be destructive of the overall purpose of the construction of § 85-7-181 to hold, as the trial
    court did, that the legislature intended for one notice to serve as right of lien by all potential subcontractors
    and materialmen who have labored and provided supplies but have not followed the requirements of the
    same. Accordingly, we reverse and render the decision.
    II.
    WHETHER THE TRIAL COURT ERRED IN AWARDING PRE AND POST-JUDGMENT
    INTEREST OF FUNDS INTERPLED AND ON DEPOSIT WITH THE COURT CLERK.
    ¶18. In view of our disposition of the previous issue, the present issue of whether the trial court erred in
    awarding pre and post-judgment interest on the interpled funds is for naught and now moot.
    III.
    WHETHER THE TRIAL COURT ERRED IN ITS AWARD ATTORNEYS' FEES.
    ¶19. Amerihost argues that the trial court erred in awarding attorneys' fees to the appellees when, in fact,
    Amerihost is entitled to an award of attorneys' fees and costs by virtue of its asserted mere-disinterested
    stake holder status. The trial court's ruling entailed an award of attorneys' fees grounded in law under 
    Miss. Code Ann. § 85-7-181
     to "[t]he laborers, subcontractors and persons who furnished materials and
    established liens," and a denial of an award of attorneys' fees to Amerihost, whom the trial court concluded
    had "actively opposed the claims presented" and therefore was not a mere-disinterested stake holder.
    However, both findings, the award of attorneys' fees to the laborers, subcontractors and materialmen and
    the denial of attorneys' fees to Amerihost, were grounded in erroneous interpretations of § 85-7-181 and
    therefore is of no substance in this issue. We note, however, that Amerihost's position opposing those
    claims presented after its May 15, 1995 payment of $272,819.13 to Bromanco was a defensive stance
    against the claims of those subcontractors and materialmen who sought to avail themselves of the
    protections of § 85-7-181 by virtue of the single stop notice sent by Wright's Painting Company on April
    17, 1995. We held this interpretation to be incorrect.
    ¶20. An award of attorneys' fees and costs in favor of the party representing interpleader action against the
    funds interpleaded into the court registry is a discretionary matter lying with the trial court. See Hartford
    Acc. & Indem. Co. v. Natchez Inv. Co., 
    161 Miss. 198
    , 
    132 So. 535
    , 539 (1931). The court may not,
    however, allow attorneys' fees to materialmen and subcontractors for attorneys representing their separate
    interests. Id.; But see, e.g. 
    Miss. Code Ann. § 85-7-181
     (1972) (statutory provision allowing an award of
    attorneys' fees to prevailing laborers and materialmen who have initiated suit as a result of an owner's denial
    of indebtedness). Amerihost argues that it not only instituted the interpleader action, but also interpled into
    the court registry sufficient amounts to cover those properly exercised claims which were timely submitted
    under the requirements of § 85-7-181. See Maryland Casualty Company v. Sauter, 
    377 F. Supp. 68
    ,
    70 (N.D. Miss. 1974) (holding that a party who has properly brought an interpleader action may be entitled
    to an award of attorneys' fees); Perkins State Bank v. Connolly, 
    632 F. 2d 1306
    , 1311 (5th Cir. 1980)
    (holding that party who initiates an interpleader action and qualifies as a mere disinterested stake holder
    may be awarded reasonable attorneys' fees); Cogan v. U.S., 
    659 F. Supp. 353
    , 354 (S.D. Miss. 1987)
    (holding that a mere disinterested stake holder who properly brings an interpleader action may be awarded
    reasonable attorneys' fees).
    ¶21. Whether the facts and circumstances surrounding this issue justifies a determination that Amerihost is a
    mere disinterested stake holder warranting an award of attorneys' fees is a factual finding as yet undecided
    under a proper interpretation of law that is consistent with this opinion. An award of attorneys' fees would
    be contingent upon that finding. Therefore, we remand this issue to the lower court for a factual finding as to
    whether Amerihost's role in the interpleader proceedings arises to that of a mere disinterested stake holder.
    IV.
    WHETHER THE TRIAL COURT ERRED IN FINDING THAT BRUCE COPES ELECTRIC,
    INC. WAS NOT ENTITLED TO ANY OF THE FUNDS INTERPLED.
    ¶22. Bruce Copes Electric, Inc. argues that the lower court erred in finding that Copes was not entitled to
    any of the funds interpled by Amerihost Development, Inc. The lower court concluded that Copes had not
    proven that it was entitled to any of the interpled funds by virtue of the lack of credible evidence presented
    by Copes to support a claim against the interpled funds. The lower court held that the credible evidence
    established that Copes defaulted on its subcontract with Bromanco and failed to complete the project. The
    lower court further concluded that while Bromanco hired employees of Copes to complete the project, no
    change orders were executed by anyone authorizing the work Copes asserts was performed nor was any
    of the work included in the stop notice.
    ¶23. Having made a detailed review of the record concerning Copes's claim, we hold that the lower court
    had before it substantial evidence from which to deny Copes's claim and said ruling was not against the
    overwhelming weight of the credible evidence. This assignment of error is without merit.
    CONCLUSION
    ¶24. We reverse and render on the assignment of error raised in Issue I. It was error to hold that the notice
    of claim by one subcontractor inures to the benefits of those subcontractors and materialmen who had not
    complied with the notice requirements of § 85-7-181 and provided notice unaided by the diligence of
    others. Consequently, the additional $272,813.83 ordered deposited into the registry of the circuit court for
    the $272,813.83 remitted on May 15, 1995 to Bromanco and prior to any additional stop payment notices
    was error. We reverse and render on the assignment of error raised in Issue II regarding an award of pre
    and post-judgment interest. We reverse and remand on the assignment raised in Issue III for additional
    findings on the issue of whether Amerihost meets the requirements of a mere disinterested stake holder. The
    only fund from which the claimants may lay claim, is the $90,485.59 originally interpled into the registry of
    the court by Amerihost on November 15, 1995. With respect to the claim asserted by Southern Electric
    Supply Co., we affirm the trial court's conclusion of law contained in part E of its findings of fact and
    conclusions of law entered on February 13, 1998. Additionally, given the findings and conclusions reached
    in part E with respect to Southern's status as a supplier of the general contractor by virtue of the Joint
    Payment Agreement of February 8, 1995, we hold that the letter sent by Southern Electric Supply Co. on
    May 4, 1995 to Amerihost qualifies as a stop payment notice affording them the benefits of § 85-7-181 but
    limited to claims on materials supplied after February 8, 1995. We affirm the trial court's findings with
    respect to Copes Electric and its decision denying Copes Electric their asserted claim.
    ¶25. THE JUDGMENT OF THE WARREN COUNTY CIRCUIT COURT IS REVERSED AND
    RENDERED IN PART; REVERSED AND REMANDED IN PART AND AFFIRMED IN
    PART FOR PROCEEDINGS NOT INCONSISTENT WITH THIS OPINION. COSTS ARE
    ASSESSED EQUALLY AMONG THE PARTIES.
    McMILLIN, C.J., KING AND SOUTHWICK, P.JJ., BRIDGES, DIAZ, IRVING, AND
    PAYNE, JJ., CONCUR. LEE AND MOORE, JJ., NOT PARTICIPATING.
    SOUTHWICK, P.J., DISSENTING TO DENIAL OF MOTION FOR REHEARING
    ¶26. We have responded to a previously unanswered question about the statute on stop notices. 
    Miss. Code Ann. § 85-7-181
     (Rev. 1999). The Court's view is that after receiving a stop notice, the owner of
    property on which construction is occurring only has to withhold sufficient proceeds to pay that claim and
    may release all other funds to the contractor. After further review on rehearing, I find that another
    interpretation of the statute is closer to its actual language. I would grant rehearing.
    ¶27. My brief answer is that the statute is explicit as to what happens if there is a suit -- all possible
    claimants to the funds are to be given notice. The statute is silent on the procedure for settling short of
    litigation. The majority concludes that the silence is a gap that permits the actions taken in this case. I take
    the silence to be a bar that prevents any procedures that are not the equivalent of what is in the statute. If
    the procedures set out in the statute are not to be followed, the owner cannot create his own short-form
    procedures that provide fewer protections. The notice that is given to all when there is litigation must be
    replicated if there is no suit. The owner should determine who is unpaid and not just satisfy the stop notices
    and give the contractor the rest.
    ¶28. I now look at the details of this conclusion.
    ¶29. Once receiving a stop notice, should the owner who has funds owing to the contractor make no more
    payments until learning who else may have payment problems? Alternatively, is the owner's duty limited to
    the total amount of the stop notices actually received? The statute is interminable in length, labyrinthine in
    style, and old. Why in the year 2000 we are trying to answer a question that should have been disposed of
    fifty years ago is baffling, but it may be that subcontractors generally avoid stop-notices for a variety of
    business as well as legal reasons.
    ¶30. The trial court found that several subcontractors who did not themselves file stop notices should
    receive the benefit of two other subcontractors' stop-notices. The majority mentions that the subcontractors
    make a detailed analysis of the statutory history. We do not review that analysis because we reject their
    interpretation on a more fundamental level. That level is that "where the Act is ambiguous in terms and fairly
    susceptible of two constructions. . . it is presumed that undesirable consequences were not intended; to the
    contrary, it is presumed that the statute was intended to have the most beneficial operation that the language
    permits." We find that the subcontractors' arguments would lead to absurd results and cite well-reasoned
    authority on the need to avoid that.
    ¶31. However, after considering the statute and reviewing its history, I find that the reading that we give to it
    also leads to unfortunate results. We said in our original opinion that to allow one stop notice to protect
    everyone creates this problem: "owners who have hired a general contractor to ensure the actual
    construction of the project would suddenly have themselves vaulted into the shoes of the general contractor
    regardless of whether they have the expertise to complete the project once a single stop payment notice is
    received. This would circumvent the precise reason that general contractors are hired. Owners would be left
    with the arduous task of obtaining information on the current work performed, the supplies and materials
    provided and those current amounts due to the various subcontractors, materialmen and suppliers."
    ¶32. Basically the idea is that if a supplier of a $1.50 light bulb is not paid and files a stop notice, it is absurd
    that no more money could be paid by the owner to the contractor until all subcontractors are contacted by
    the owner to see if they too are having problems. Agreed, but only because it is an extreme. If we focus on
    extremes, we will miss the more general operation of the statute.
    ¶33. A more realistic example of the operation of the statute comes from the facts of our case. Two
    subcontractors about 18 days apart filed stop notices totaling $55,000. Ten days later the owner paid the
    remaining money it owed to the contractor. The statute does not require service of the stop notice on other
    subcontractors, so they do not necessarily know of other payment problems. Notice of a claim may be filed
    in the lis pendens book, so perhaps subcontractors can daily or weekly monitor those. 
    Miss. Code Ann. § 85-7-197
    . Still, others who may soon learn they should file a stop notice may not yet have suffered payment
    problems, because they are on a different payment schedule. Their problems may arise weeks after a
    different subcontractor has reached critical stage with the contractor. So nothing in the filing of one stop
    notice necessarily is causing others to do the same.
    ¶34. What if instead of two stop notices, there had been five, or ten, all within the 18 day period? We
    would still be holding that even though evidence of a serious problem exists, the owner can pay the
    contractor so long as enough is held out for the stop-notices. I suggest that a not-overly-absurd result would
    be that a stop notice signals that some degree of problem exists with subcontractor payments. The majority
    insists that the owner not be vaulted into the role of the contractor by requiring the owner to ascertain
    whether other subcontractors are not being paid. The statute provides the means to avoid that situation by
    permitting the funds to be interpleaded with notice to all possible claimants. The majority in this Court
    agrees with the owner Amerihost that the problem is also avoided by payment solely to the complaining
    individuals if that is done prior to litigation.
    ¶35. I will later explain my basis for concluding that Amerihost's position is in error. What the foregoing
    proves at least for now is that the answer to our statutory interpretation issue is not reached by categorizing
    the subcontractors' position as absurd and the owner's as sweet reason. Significant inequities and hardship
    can arise under imaginable scenarios no matter which party's position is accepted. I think our task starts and
    largely ends with discerning the interpretation that is the more faithful reading of the language used in the
    statute.
    ¶36. The entire statute is quoted in the majority opinion. Its first independent clause (the first 436 words
    form one sentence), greatly redacted, is this:
    When a contractor . . . shall not pay any person who may have furnished materials used in the
    erection . . . of any . . . building, . . . any such person . . . may give notice in writing to the owner
    thereof of the amount due him and claim the benefit of this section.
    
    Miss. Code Ann. § 85-7-181
    . This is fairly straightforward and is not the problem. We have two such
    "persons" who gave notice in writing of the amount due them.
    ¶37. The next independent clause starts the confusion:
    thereupon the amount that may be due upon the service of such notice by such owner to the
    contractor . . . shall be bound in the hands of such owner for the payment in full, or if insufficient then
    pro rata, of all sums due such person . . . who might lawfully have given notice in writing to the owner
    hereunder.
    
    Id.
     The literal reading of this clause is that the amount due by the owner to the contractor -- not the amount
    of the claim -- shall be "bound" for the payment of all who "might lawfully have given notice." Does that
    mean the same thing as "could lawfully have given" notice, or does it mean those who actually gave notice?
    The persons who may lawfully give stop notices are subcontractors who are owed money by the
    contractor, i.e, those to whom the contractor is in default. "Might" is the past tense of "may." One definition
    of "might" is "to express possibility or probability or permission in the past." Am. Her. Dict. Eng. Lang.
    1143 (3d ed. 1992). To put the phrase in the present tense, it would be those who "may lawfully give
    notice." It is probably dangerous for us in the last year of the twentieth century to get overly focused on use
    of a word early in the same century. Even if our tenth grade English teachers "might" be convinced that there
    is one correct way to read this sentence, that may not be what the legislature in context should be said to
    have meant.
    ¶38. What is clear as a matter of literalism at least is that it is the entire amount in the hands of the owner
    that is bound -- "the amount that may be due upon the service of such notice by such owner to the
    contractor . . .shall be bound."
    ¶39. Going to the next clause, it states this:
    if after such notice, the contractor . . . shall bring suit against the owner, the latter may pay into court
    the amount due on the contract; and thereupon all persons entitled hereunder, so far as is known, shall
    be made parties and summoned into court . . ..
    
    Id.
     What is a fair reading of this section is that all subcontractors are given notice of the suit, not just those
    who have given stop notices. The statute goes on to say that the court will direct the payment to the persons
    entitled. The next section of the statute permits a subcontractor to bring a suit, and that person is to give
    notice to all other subcontractors. The owner may interplead everything that it has and let the workers fight
    it out. Alternatively, the owner may dispute individual claims and actively participate in the court's resolution.
    The important point for our issue is that all potential claimants are to be given notice no matter who initiates
    the litigation.
    ¶40. So among the matters that are relatively clear is that if a suit is filed, all subcontractors are summoned
    and not just those who have filed stop notices. Thus under our interpretation the silence in the statute
    regarding handling of stop notices without suit permits procedures that are inconsistent with those that apply
    when there is a suit. We have said when no suit is filed, the stop notice by itself is the extent of the owner's
    concern; when suit is filed, all subcontractors must be given notice.
    ¶41. Inconsistency does not prove the majority is in error; a statute may provide different protections at
    different stages in the process. To be precise, though, the statute provides no rules for what was done in
    this case. Acknowledging the inconsistency sets the stage for divining the interpretation that is closest to the
    statutory language, read in the context of the statutory purpose. Seeking the purpose of legislation should
    not lead a court away from the words of legislation, but the inquiry can provide a basis for resolving
    ambiguity. To determine purpose, we should accept the subcontractors' invitation to examine the significant
    amendments that were made to the statute in 1918 that adopted most of the confusing language. These
    amendments were almost certainly responding to a 1917 supreme court decision. Enochs Lumber v.
    Garber, 
    116 Miss. 229
    , 
    76 So. 730
     (1917). The pre-1918 statute gave priority to sub-contractors based
    on the date of the filing of their notices. Subcontractors did not share pro rata in the amount in the hands of
    the owner. If the total of the claims of the first two subcontractors to file stop notices consumed all the
    money then in the owner's hands, and five other subcontractors filed days or even minutes afterwards, those
    last five received nothing. 
    Id.,
     116 Miss. at 232.
    ¶42. The purpose of the 1918 amendments was explained in a case that is argued at great length in
    Bromanco's original and rehearing briefs. McNair v. M.L. Virden, 
    193 Miss. 232
    , 
    4 So. 2d 684
     (1941).
    The Virden briefs summarized in the Mississippi Reports version show how much the issue of the 1917
    Enochs case was before the court. What ultimately Virden decided is expressed in the last three pages of
    the opinion. 
    Id.,
     
    193 Miss. at 247-49
    . It agrees with much of the argument of the subcontractor here,
    namely, that the old law focused on the person who gave the notice and the new law on all "in the same
    class." The court said the "very purpose" of the new law
    "was to confer equal rights on all persons in the same class, regardless when, or whether, such
    persons had given the owner written notice, provided the owner yet had in his hands funds owing
    to the contractor when such claimants gave notice, or if notice was not given, the claim or
    claims were asserted in court. In other words, one notice stops the right of the owner to pay the
    contractor the amount claimed in that notice. [Bromanco calls that last sentence dicta.]
    "If other claimants in the same class subsequently give notice to the owner of their claims, or if they do
    not give the notice, but assert their claims in court, to which the owner is a party, all before the owner
    has paid out the funds which he had when the first notice was received, then all such persons share
    ratably in those funds."
    
    Id.,
     
    193 Miss. at 248
     (emphasis added). The subcontractor dislikes this entire last paragraph. I agree that
    much of this was dicta, but it cannot be disregarded solely for that reason.
    ¶43. The court then waxes eloquently on the general subject, and states that it is the furnishing of materials
    that is important, "not the giving of notice." 
    Id. at 249
    . The court is rejecting the old law's first-in-time rule,
    though, and we should not put too much weight on that phrase. The court says that if this is not what the
    new law means, they cannot figure out why the amendments were made.
    ¶44. The court stated that this was not "a case where the owner pays the balance to the one giving the
    notice before he receives such notice from others, or before others assert their claims in court. . . . We will
    deal with that when and if such situation arises" 
    Id. at 244
    . They may not have expected that it would be a
    Court of Appeals sixty years later that finally got to the issue. Nonetheless, we should not ignore that
    Virden specifically avoided deciding whether an owner's payment of all current stop notices and release of
    the remainder to the contractor satisfied the statutory process.
    ¶45. Thus, if one person gives the notice, the rights of the others who may not get paid do not depend
    solely on their filing notice. The holding explicitly only protects them if they alert the owner at least by a suit
    prior to when the money is disbursed that there are others who have a claim. The sole stop notice in Virden
    was for an amount larger than what the owner still retained; therefore the only funds subject to one or ten
    stop notices remained in the owner's hands.
    ¶46. The 1918 statutory change was focusing on the equity of providing "ratable" payments. So long as the
    owner still has funds in his hands at the time he becomes aware of the claims of the other subcontractors,
    whether by later stop notices or by suit, then those others get paid ratably and not in order until the fund is
    exhausted.
    ¶47. Since the amendments were directed at ending the full-payment in order of notice approach, it makes
    sense that it would not matter whether a notice was sent at all by someone in the same "class" as a claimant
    who had sent notice. I do not know what the court means by "class." It could be that the court was thinking
    in terms of subcontractors being one class, materialmen another, laborers another. I do not see how the
    statute can be read to differentiate the effect of a stop notice by category of persons entitled to give them,
    i.e., if a "journeyman" gives notice, then all other journeymen are protected but not subcontractors. No
    language makes that distinction. Regardless, that issue is not explored by the parties here.
    ¶48. Our case presents the issue that is unaddressed in the statute of the procedure that the owner must
    follow for resolving stop notice claims without litigation. The 1918 amendments were intended to prevent
    the order of the filing of the stop notices from controlling. So the amendments contemplate that stop notices
    are filed at different times, some later than others. The filing of the first stop notice is not like the filing of a
    civil complaint against multiple defendants, in which a schedule is by rule created for when the other parties
    have to respond. No definite time limits control what the owner does with the first notice or when others
    claimants file notices.
    ¶49. Does the owner after receiving a stop notice at 3:00 P.M. for less than the money then in his hands due
    to the contractor, have the right to pay that stop notice at 4:00 P.M. and give the remainder of the money to
    the contractor before day's end? What if another stop notice is filed at 8:00 A.M. the next day? The
    subcontractor who filed on the second day has made a prompt filing. Immediate payment to the contractor,
    reserving only the amount of the one stop notice, would undercut the protections that Virden states the
    statute is providing. Perhaps this is objectionable only if the immediate payment was unusual for the owner,
    but commercial reasonableness is not the linchpin of the statute. Notice is. Whose notice remains our issue.
    ¶50. We should also examine whether non-judicial writings on the subject have adopted any particular
    view. Two companion articles on the general legal area have appeared. One is not especially on point,
    though it identified the first stop notice statute as having been adopted in 1857. James M. Brown,
    Mechanics' Liens: An Interpretation of Section 356 as Amended, XXXVII Miss. L. J. 203, 208 (1966)
    . The more useful article is a supplement to the first. James M. Brown, Mechanics' Liens: Mississippi
    Notice Requirements, XXXVII Miss. L. J. 385 (1966).
    Its [the stop notice's] net effect was to prevent the owner, after he had received the notice, from
    making further disbursements under the contract until the subcontractor claims were paid in full or
    pro-rata out of remaining contract funds. Serving this notice often had the effect of abruptly halting
    construction pending accumulation, analysis, and negotiation of all potential claims arising therefrom.
    As a remedy designed to make available the maximum fund statutorily possible, it was very effective.
    Id at 387 (footnotes omitted). Professor Brown assumed that a stop notice froze all the funds and
    "accumulation" and analysis of all claims would then have to be performed. The article further discusses the
    statute but never draws a distinction between filing suit and the right of the owner to resolve the claim
    without litigation.
    ¶51. Somewhat relying on Brown's article but not totally agreeing with him were two writers of a law
    student comment. William L. Smith and Boswell Stevens Hazard, Comment, Mississippi Law Governing
    Private Construction Contracts: Some Problems and Proposals, 47 Miss. L. J. 437 (1976). They too
    are concerned with the absurd result of one small claim's freezing all the money, but still found that result to
    be a reasonable reading of the statute. Id. at 453-54. Unlike Professor Brown, students Smith and Hazard
    referenced the limitation of the 1941 Virden decision, namely that it did not address the effect of an owner's
    paying off the stop notice before receiving other subcontractors' claims. Id. at 453 n. 79. Still, in their view
    disbursement to the contractor after retaining enough to pay off the stop notice satisfies the statute. Id. at
    454.
    ¶52. I find these to be reasonable reviews of the law as it had been announced so far, recognizing that some
    questions had not yet been answered. What they could not describe but we must, is the situation in which
    "the owner pays the balance to the one giving the notice before he receives such notice from others, or
    before others assert their claims in court." Virden, 
    193 Miss. at 244
    .
    ¶53. In my view the question that requires answering arises from silence in the statute. The statute states that
    once a stop notice is given, the amount that the owner owes the contractor is frozen "for the payment in full,
    or if insufficient then pro rata, of all sums due such person, subcontractor, journeyman or laborer who might
    lawfully have given notice in writing to the owner." 
    Miss. Code Ann. § 85-7-181
    . The very next section of
    the statute discusses a suit brought by the subcontractor to resolve the dispute, which is then followed by an
    owner's right to file suit and interplead the funds. In both situations, notice is to be given "all persons entitled
    hereunder, so far as known. . . ." 
    Id. ¶54
    . The procedure for an owner to resolve the claims without a suit just is not addressed in the statute.
    The statute certainly does not say that the owner can just set aside enough for the known claims and pay the
    rest to the contractor.
    ¶55. Absent any stated procedure in the statute, and based on the Virden interpretation that the relevant
    language was intended to remove priority based on filing or even the need of filing by subsequent claimants
    in order to get stop notice protection, I find that there is a duty on the owner to make inquiries about the
    extent of claims. It is the equivalent of giving notice to everyone in litigation. The answer that we gave --
    only claims covered by stop notices have to be satisfied -- makes the owner's unilateral decision on whether
    to interplead or instead to pay without litigation incredibly significant on the protections that the statute gives.
    Since the owner does not even have the express statutory right to settle without suit, he should at least be
    required to duplicate the notice protections of a suit. Whether a new stop notice comes in a day or a week
    after the first one, our interpretation permits the owner to pay immediately after the first stop notice. That
    "protection" for subcontractors is inconsistent with the statute.
    ¶56. In conclusion, I do not find that the implications of the trial court's decision are any more disruptive to
    construction projects than is compelled by the language of the statute. If there is a stop notice, the statute
    explicitly provides that all funds are frozen and litigation may be commenced that will prevent any payments
    from being made. That is disruptive. All I find that the trial court added is that even if no suit is filed, the
    same protection applies to subcontractors who might have filed stop notices. The owner cannot pay some
    without discerning the overall situation.
    ¶57. The statute is ungainly and in some respects impractical. The legislature usefully could give serious
    attention to creating a more modern and less disruptive system. What exists creates problems. Still, it is not
    for this court to announce an improvement which, on balance, this may not even be.
    BRIDGES AND PAYNE, JJ., JOIN THIS SEPARATE OPINION.