Evan Johnson & Sons Construction, Inc. v. State of Mississippi ( 2001 )


Menu:
  •                         IN THE SUPREME COURT OF MISSISSIPPI
    NO. 2001-CA-01675-SCT
    EVAN JOHNSON & SONS CONSTRUCTION, INC.
    v.
    THE STATE OF MISSISSIPPI AND TOMPKINS,
    BARRON & FIELDS ARCHITECTS, A PARTNERSHIP
    DATE OF JUDGMENT:                                 08/27/2001
    TRIAL JUDGE:                                      HON. W. SWAN YERGER
    COURT FROM WHICH APPEALED:                        HINDS COUNTY CIRCUIT COURT
    ATTORNEYS FOR APPELLANT:                          RICHARD M. DYE
    PHIL B. ABERNETHY
    ATTORNEYS FOR APPELLEES:                          OFFICE OF THE ATTORNEY GENERAL
    BY: T. HUNT COLE, JR.
    EDWARD OMER PEARSON
    PETER LARKIN DORAN
    T. CALVIN WELLS
    BARRY CLAYTON CAMPBELL
    NATURE OF THE CASE:                               CIVIL - CONTRACT
    DISPOSITION:                                      AFFIRMED - 03/04/2004
    MOTION FOR REHEARING FILED:
    MANDATE ISSUED:
    EN BANC.
    CARLSON, JUSTICE, FOR THE COURT:
    ¶1.     The State of Mississippi Military Department (State) and Tompkins, Barron & Fields Architects
    (Tompkins) were granted summary judgment dismissing with prejudice all claims asserted against them by
    Evan Johnson & Sons Construction, Inc. (Johnson) under a construction contract. The State was also
    thereafter granted summary judgment as to its counterclaim for liquidated damages against Johnson and its
    surety in the amount of $119,150.34, and a final judgment consistent with the opinion and order was
    likewise entered the same day for this amount with post-judgment interest at the rate of 8% per annum.
    Johnson appeals the ruling of the circuit court citing numerous errors. Finding that the motions for summary
    judgment dismissing Johnson’s claims were properly granted in favor of the State and Tompkins and that
    the State’s motion for summary judgment as to its counterclaim for liquidated damages against Johnson was
    likewise properly granted, this Court affirms the final judgment entered consistent with these opinions by
    the Circuit Court of the First Judicial District of Hinds County.
    FACTS AND PROCEEDINGS IN THE TRIAL COURT
    ¶2.     On May 16, 1995, Johnson was awarded a contract to build the STARC Armory facility which
    was owned by the State through the Mississippi National Guard. Tompkins was selected as the architect.
    Independent Roofing, Inc. (Independent Roofing) was Johnson's roofing subcontractor. A portion of the
    project required Johnson to construct a curved barrel vault roof. Prior to the bids being submitted,
    prospective bidders raised several questions concerning how this roof was to be constructed. In response
    to these questions, Tompkins prepared Addendum No. 1 which consisted of seven drawings clarifying the
    design of the curved portion of the barrel vault roof.
    ¶3.     Johnson completed all portions of the project except the construction of the curved portion of the
    roof, which was to be performed by Independent Roofing. As construction of the curved portion of the
    roof was begun, Independent Roofing informed Johnson that the construction as specified in the plans and
    in Addendum No. 1 would not achieve the results sought by the State. Johnson notified the State of
    Independent Roofing's discovery; however, the State and Tompkins instructed Independent Roofing to
    install the roof as specified in the design. Notwithstanding this clear directive from the State and Tompkins
    to construct the roof in compliance with the original plans and Addendum No. 1, Johnson attempted to
    2
    place the roof over a structure of corrugated "S" deck which did not incorporate the use of bent or rolled
    "Z" purlins. As Independent Roofing was constructing the last layer of the roof, the State rejected the
    project stating it did not produce the appearance the State desired.
    ¶4.     After work was ceased, two cure notices were sent to Johnson directing the company to proceed
    with the project. After an eleven-month impasse, Johnson finally presented this dispute for hearing before
    a Contract Dispute Review committee on April 30, 1997. The committee found that Johnson had deviated
    fromthe design and specifications without written authorization. The review committee also recommended
    that Johnson replace the existing roof with one constructed in accordance with the design and
    specifications. On May 6, 1997, after a review of the committee's recommendations the Adjutant General
    directed Johnson to complete the roof.
    ¶5.     As of the scheduled completion date of May 8, 1997, the roof had not been completed by
    Johnson, and the contract was then terminated by the State. The contract was later rebid, and the roof was
    eventually completed on October 6, 1998, by Mandal's of Gulfport. However, it was not built according
    to the original design and specifications due to the fact that in order to save time, the State and Tompkins
    modified the design substituting bent pipe for the "Z" purlins.
    ¶6.     On November 21, 1997, Johnson filed a complaint against the State and Tompkins in the Circuit
    Court of the First Judicial District of Hinds County. This five-count complaint charged (1) breach of
    contract by the State due to the State’s alleged failure to submit plans and specifications which would
    produce the desired result; (2) breach of implied warranty by the State; (3) negligence by Tompkins; (4)
    wrongful termination and breach of contract by the State; and, (5) breach of contract by the State due to
    the State’s alleged failure to make timely payments under the contract. The State filed a counterclaim
    3
    against Johnson for liquidated damages and costs paid to complete the project. On December 15, 1999,
    Tompkins, joined by the State, filed a motion for summary judgment to dismiss Johnson's action with
    prejudice. A hearing was held on May 15, 2000, and the circuit judge took the motion under advisement
    for subsequent ruling. On September 18, 2000, the circuit judge entered his 14-page Memorandum
    Opinion and Order on Motions for Summary Judgment in which he found, inter alia, that Johnson had no
    good justification for non-performance, and thus, summary judgment was granted against Johnson and in
    favor of the State and Tompkins. In this same opinion and order, the circuit judge dismissed with prejudice
    all claims asserted by Johnson against the State and Tompkins, and also kept viable the State’s
    counterclaim for liquidated damages against Johnson.
    ¶7.     On May 14, 2001, the State filed a motion for summary judgment on its counterclaim for liquidated
    damages. After a hearing held on July 16, 2001, the trial court took the motion under advisement and on
    August 27, 2001, entered its 7-page Opinion and Order on State’s Claim for Liquidated Damages. In its
    opinion and order, the trial court granted the State’s motion for summary judgment and found that a
    judgment for the State and against Johnson and its surety in the amount of $119,150.34 should be entered.
    On the same day, the trial court entered its final judgment consistent with the opinion.
    ¶8.     On September 13, 2001, Johnson attempted to supplement the record with numerous affidavits
    and deposition transcripts.1 What amounted to Johnson’s second attempt to supplement the record (see
    1
    Of significant import is the fact that likewise, four days prior to the summary judgment hearing of
    July 16, 2001, Johnson filed a notice of filing with attached affidavits and depositions (consuming 191 pages
    of the record) in an effort to defeat the State’s motion for summary judgment. In a separate order entered
    on August 27, 2001, the same day as the entry of the opinion and final judgment, the circuit judge granted
    the State’s motion to strike this evidentiary material, finding in its order that the materials consisted “either
    of matters previously submitted and already considered by the Court and rejected, or of new affidavits that
    4
    footnote 1) was met by a joint motion from the State and Tompkins. That motion was filed with this Court,
    and on July 30, 2002, a single justice order was entered on behalf of the Court thereby striking from the
    record some 1,160 pages (pages 906 - 2065). Johnson timely appealed and raises the following issues
    before this Court:
    1. Whether the trial court erred in granting defendant's motion for partial summary
    judgment as to whether defendants wrongfully terminated the construction contract and
    whether Evan Johnson was entitled to a time extension, delay damages and extra work
    costs.
    2. Whether the trial court erred in granting defendant's subsequent motion for summary
    judgment as to whether the state was entitled to recover from Evan Johnson liquidated
    damages and the costs to complete the contract.
    3. Whether the trial court erred in finding as a matter of law that Evan Johnson was in
    material breach of its contract so as to justify defendant's termination of the contract for
    default.
    4. Whether the trial court erred in finding as a matter of law that the plans and
    specifications issued by defendants were not defective and that the state did not breach its
    implied warranty that the plans, when followed, would produce the desired result.
    5. Whether the trial court erred in finding no disputed issue of material fact on the above
    issues, and in rejecting and ignoring the affidavit of Evan Johnson's architectural expert
    witness, Lynton B. Cooper.
    6. Whether the trial court erred in finding that there was no disputed issue of material fact
    as to the reasonableness of the completion costs incurred by the state after termination of
    Evan Johnson's contract, even if the default termination had been proper.
    7. Whether the trial court erred in finding that there was no disputed issue of material fact
    as to the state's entitlement to assess liquidated damages against Evan Johnson, even if the
    default termination had been proper.
    could have been submitted on the same issue of fault prior to the May 15, 2000, hearing on summary
    judgment, but were not.” The trial court based its action in striking this evidentiary material on Miss. R. Civ.
    P. 56(c)-(d) and our decisions in Jones v. James Reeves Contractors, Inc., 
    701 So. 2d 774
    , 786
    (Miss. 1997); and, Richardson v. APAC-Miss., Inc., 
    631 So. 2d 143
    , 146 (Miss. 1994). The trial
    court likewise acknowledged in its separate opinion and order that it had by separate order struck this
    evidentiary material and not considered these documents in rendering its decision. By this Court’s order
    entered on July 30, 2002, the appellees’ motion to strike these pages (688-878) from the appellate record
    was passed for consideration with the merits of this appeal and by order entered on February 27, 2004,
    this Court granted the motion to strike.
    5
    8. Whether the trial court erred in finding summary judgment was appropriate as to both
    defendants, or either of them.
    ¶9.     In addition to these issues, Tompkins submit the following issues for consideration which were also
    adopted by the State:
    9. Whether summary judgment is appropriately granted against a contractor who claims
    impossibility of performance where the record reflects objective evidence that another
    contractor has successfully complied with the challenged design and/or specification, and
    completed the challenged construction.
    10. Whether a government contractor may defeat summary judgment based on
    unavailabilityof materials when objective evidence produced in the court below establishes
    the availability of those materials.
    11. Whether a government contractor may defeat summary judgment in a case alleging
    negligent design without showing that the challenged plans were, in fact, attempted and
    followed.
    12. Whether the trial court properly granted summary judgment where the objective
    evidence showed Evan Johnson & Sons could not produce evidence in support of essential
    elements of the their case on negligent design and/or wrongful termination.
    ¶10.    For sake of clarity, the issues identified by Johnson, Tompkins, and the State have been
    consolidated into two issues for purposes of this opinion.
    DISCUSSION
    ¶11.    This Court employs a de novo standard in reviewing a trial court's grant of summary judgment.
    Short v. Columbus Rubber & Gasket Co., 
    535 So. 2d 61
    , 65 (Miss. 1988). Summary judgment may
    only be granted where there are no genuine issues of material fact such that the moving party is entitled to
    judgment as a matter of law. M.R.C.P. 56(c). The trial court must carefully review all evidentiary matters
    in the light most favorable to the non-moving party. Brown v. Credit Ctr., Inc., 
    444 So. 2d 358
    , 362
    (Miss. 1983). If in this view, the moving party is entitled to judgment as a matter of law, summary judgment
    should be granted. Id.
    6
    I.      WHETHER THE TRIAL COURT ERRED IN GRANTING THE
    STATE'S AND TOMPKINS, BARRON & FIELDS'S MOTION FOR
    PARTIAL SUMMARY JUDGMENT AS TO WHETHER THE STATE
    WRONGFULLY TERMINATED THE CONSTRUCTION
    CONTRACT.
    A. Genuine Issue of Material Fact
    ¶12.      Johnson argues there were clear issues of fact created by discovery produced by Johnson which
    were ignored and rejected by the trial court. Johnson argues because the trial court tried issues of fact on
    a Rule 56 motion, the grant of summary judgment should be reversed and remanded for a trial on the
    merits.
    ¶13.      The crux of Johnson's argument lies with the affidavit of Lynton B. Cooper. Johnson contends this
    affidavit is all that is necessary to create a genuine issue of material fact as to the claims of negligence against
    Tompkins and as to the claims of breach of warranty and contract against the State. Johnson claims
    Cooper's affidavit specifically outlines the inadequacies of the design and the reasons the design fails to
    comply with the standard of care which should be exercised by a reasonably prudent architect.
    ¶14.      Johnson also argues that there are numerous other documents and testimony, aside from the
    affidavit of Cooper, which create a genuine issue of material fact. Johnson claims Tompkins had difficulty
    interpreting its own design sixteen months after Johnson had begun building the armory referenced by
    correspondence between Tompkins and Berridge Manufacturing Company. Johnson argues the roof
    installed by the replacement contractor was not built according to the original plans and specifications.
    Johnson also argues the full scale model was inadequate because the model only attempted to recreate the
    first two sections, not all eight sections.
    7
    ¶15.    The State argues the trial court correctly applied Rule 56 standards in granting summary judgment
    in favor of the State and Tompkins regarding Johnson's alleged wrongful termination. The State contends
    Johnson did not demonstrate any genuine issue of material fact. The State argues Johnson offered only
    conclusory assertions which the trial court correctly rejected.
    ¶16.    In reviewing Cooper's affidavit, the trial court determined it to be "conclusory in nature, and without
    substantial support for the conclusions being drawn." The trial court found that the plans were followed by
    the replacement contractors and the contractors who built the full scale model of a portion of the roof. The
    trial court further found that there were no genuine issues of material fact remaining for trial and, therefore,
    granted summary judgment in favor of the State and Tompkins.
    ¶17.    This Court has continuously held:
    Summary judgments should be granted with great caution. Smith v. Sanders, 
    485 So. 2d 1051
    , 1054 (Miss. 1986); Brown, 444 So.2d at 363. The Comment to Rule 56 provides
    that "the court cannot try issues of fact on a Rule 56 motion; it may only determine whether
    there are issues to be tried." Brown, 444 So.2d at 362. When there is doubt as to
    whether a genuine issue of material fact exists, the non-moving party should be given the
    benefit of that doubt, and the motion should be denied. Id.
    In spite of this requirement of caution in granting summary judgment, this Court has held
    that the non-moving party must be diligent in opposing the motion for summary judgment.
    Smith v. H.C. Bailey Companies, 
    477 So. 2d 224
    , 233 (Miss. 1985); Bourn v.
    Tomlinson Interest, Inc., 
    456 So. 2d 747
    , 749 (Miss. 1984). Moreover, in order for
    summary judgment to be inappropriate, there must be genuine issues of material fact; the
    existence of a hundred contested issues of fact will not thwart summary judgment where
    none of them is material. Shaw v. Burchfield, 
    481 So. 2d 247
    , 252 (Miss. 1985). A fact
    issue is material if it tends to resolve any of the issues properly raised by the parties. Pearl
    River County Bd. of Sup'rs v. South East Collections Agency, Inc., 
    459 So. 2d 783
     (Miss. 1984).
    8
    . . . In Galloway et al. v. The Travelers Insurance Co. et al, 
    515 So. 2d 678
    (Miss. 1987), this Court quoted with approval the following language from the Celotex
    Corp. v. Catrett, 
    477 U.S. 317
    , 
    106 S. Ct. 2548
     (1986), decision:
    In our view, the plain language of Rule 56(c) mandates the entry of
    summary judgment, after adequate time for discovery and upon motion,
    against a party who fails to make a showing sufficient to establish the
    existence of an element essential to that party's case, and on which that
    party will bear the burden of proof at trial. In such a situation, there can be
    "no genuine issue as to any material fact," since a complete failure of proof
    concerning an essential element of the non-moving party's case necessarily
    renders all other facts immaterial.
    Galloway, at 683.
    Grisham v. John Q. Long V.F.W. Post, No. 4057, Inc., 
    519 So. 2d 413
    , 415-16 (Miss. 1988).
    ¶18.    We agree with the trial court that the Cooper affidavit was conclusory and did not present a
    material issue of genuine fact. In his Memorandum Opinion and Order, the circuit judge stated:
    In particular, Cooper states in conclusory fashion that the plans and specifications were
    defective, unclear and/or ambiguous. The Court has reviewed the proof regarding the plans
    and specifications in the original form and in the re-bid form, and finds that there can be no
    legitimate dispute that the plans and specifications could be followed, and were followed
    in connection with the actual roof construction completed by Mandal's Inc. and
    construction of the full scale model of the roof portion which has been demonstrated to the
    Court through photographs.
    ¶19.    The circuit judge was presented with numerous documents by all parties to this action, and he
    determined there was no competent or probative proof submitted by Johnson to rebut the evidence
    presented by the State and Tompkins. Johnson's argument that the trial court improperly tried issues of fact
    on a Rule 56 motion is without merit.
    B. Negligence and Defective Design
    9
    ¶20.      Although the trial court, Tompkins and the State relied heavily on Johnson's failure to prove
    impossibility of performance, Johnson argues that this claim is not one for impossibility of performance, but
    for negligence and defective design. Instead Johnson contends the plans and specifications for the curved
    portion of the barrel vaulted roof were defective and ambiguous; therefore, it argues that the termination
    of Johnson's contract for failure to complete the roof was wrongful and a breach of contract. Johnson
    claims the issue of defective and ambiguous plans and specifications is a genuine issue of material fact which
    should be submitted to a jury.
    ¶21.      Tompkins argues Johnson repeatedly claimed it was impossible to construct the roof using the
    Tompkins design. However, neither Johnson, nor its subcontractor, ever made any attempt to construct
    the roof according to the plans and specifications. This led to Johnson's dismissal from the contract.
    ¶22.      Tompkins argues that in order for Johnson to recover from Tompkins based on defective plans and
    specifications, Johnson must establish that it attempted to build the structure in compliance with the plans
    and specifications provided and that the impossibility of construction and compliance with plans and
    specifications provided was impossible not only to Johnson, but to any other who would attempt to build
    the structure in accordance with the plans and specifications. Tompkins argues Johnson failed to meet all
    of these essential elements; therefore, the grant of summary judgment as to wrongful termination was
    proper.
    ¶23.      The State adopts the argument of Tompkins regarding defective design. The State also argues the
    replacement contractor was successfully able to accomplish the architect's design with a bent pipe
    substituted in place of the "Z" purlins. The State claims Johnson missed the scheduled completion date after
    never attempting to construct the roof as designed. The State also argues rolled "Z" purlins were
    10
    commercially available from a metals fabricator in California even though Johnson claimed such an item did
    not exist. The State also contends John Liggett of American Metal Works in Brandon was able to
    successfully construct a full scale model of Tompkins's design of the roof using the rolled "Z" purlins as
    called for in the design.
    ¶24.    As a finding of fact, the trial court determined that, although Johnson claimed it was impossible to
    construct the compound curved portion of the roof, the plans and specifications were not impossible with
    which to comply. The trial court stated the full scale model of a portion of the roof used rolled "Z" purlins
    which Johnson claimed did not exist.
    ¶25.    Under basic substantive law regarding contracts, several factors have been considered in evaluating
    a claim of commercial impossibility. Two of those factors are: (1) whether any other contractor was able
    to comply with the specifications, see Foster Wheeler Corp. v. United States, 
    206 Ct. Cl. 533
    , 546-
    47, 
    513 F.2d 588
    , 595 (1975), and (2) the extent of the contractor's efforts in meeting the specifications,
    see Oak Adec, Inc. v. United States, 
    24 Cl. Ct. 502
    , 504 (1991); Whittaker, Power Servs. Div.,
    79-1 B.C.A. (CCH) ¶ 13,805 (A.S.B.C.A.1979). The contractor must prove that the industry as a whole
    found the specifications impossible. Id. See also Jennie-O Foods, Inc. v. United States, 
    217 Ct. Cl. 314
    , 
    580 F.2d 400
    , 410 (1978); Foster Wheeler, 513 F.2d at 595.
    [C]ase law does support a requirement that the contractor demonstrate that the
    specifications were, from an objective point, incapable of performance. Natus Corp. v.
    United States, 
    178 Ct. Cl. 1
    , 10, 
    371 F.2d 450
    , 456 (1967); ESB, Inc., 81-1 B.C.A.
    (CCH) ¶ 15,012 (A.S.B.C.A.1981). However, it is plain that this analysis evolved as an
    addition to an underlying demonstration of subjective impossibility (the
    contractor itself cannot do the work). The contractor must also show that no
    one else could perform. See Restatement (Second) of Contracts § 261 cmt. e
    (1981). Hence, the courts use an objective standard to prevent an
    11
    incompetent or negligent contractor from recovering by simply alleging that
    it (subjectively) could not perform the work. As stated by the board in ASC
    Sys. Corp., 78-1 B.C.A. (CCH) ¶ 13,119 (A.S.B.C.A.1978): "[p]erformance
    impossibility must be established on an objective basis, not subjectively. That
    is, the contractor may not rely solely upon his own inability to accomplish
    the specified task; he must also negate the possibility of performance by
    others...." ASC Sys., 78-1 B.C.A. at 64, 134. The objective standard is thus not
    intended to be a "sword" for plaintiffs alleging impossibility, but rather a
    "shield" to be used by defendants to deflect such charges by a contractor
    whose own inability was the cause of non-performance. The standard does
    not operate as Oak Adec contends to insulate the contractor from inquiry
    into its management of the contracts.
    Any question that a contractor must demonstrate its own effort to perform was answered
    by the Court of Claims in Jennie-O Foods. There, the court stated:
    The [commercial impracticability] doctrine may be utilized only when the
    promisor has exhausted all its alternatives, when in fact it is determined
    that all means of performance are commercially senseless. There can be
    little sympathy for contractors who seek refuge behind the label of
    commercial senselessness (impracticability) without proof that they have
    made an effort to obtain performance in an alternative fashion.
    Jennie-O Foods, 217 Ct. Cl. at 328, 580 F.2d at 409 (citation omitted). It is thus clear
    that the subjective experience of the contractor is a factor that must be considered when
    determining whether a contract is commercially impossible.
    Oak Adec, 24 Cl. Ct. at 505-06 (emphasis in original).
    ¶26.    Johnson failed in his burden of proving impossibility not only on a subjective basis, but also on an
    objective basis. The roof was successfully rebid and built substituting pipe for the rolled "Z" purlins. Also,
    a full scale model of a portion of the roof was constructed using rolled "Z" purlins as called for in the original
    plans and specifications. Although Johnson claimed materials were not available to meet the specifications
    because a rolled "Z" purlin did not exist, the trial court was presented with evidence of compound curved
    "Z" purlins which were obtained by American Metals of Brandon and successfully used in the full scale
    12
    model of a portion of the roof. Because Johnson failed to prove any other contractor was unable to comply
    with the original design and specifications and because Johnson failed to attempt to construct the roof
    according to the original design and specifications, this Court finds Johnson's claim for defective design must
    fail.
    ¶27.    Although Johnson claims it is not arguing impossibility but is suing for negligent design and wrongful
    termination, we agree with the trial court, Tompkins and the State that impossibility of performance is the
    true claim. Johnson stated materials were unavailable and the plans and specifications were defective;
    therefore, it was impossible to construct the roof as depicted in Addendum No. 1. However, Johnson
    made no effort to construct the structure as shown in the plans but instead attempted to place a roof over
    the structure that did not incorporate "Z" purlins, and therefore, did not achieve a satisfactory result. It was
    also determined that a metal supplier in California could supply bent or rolled "Z" purlins. The roof was
    successfully rebid and completed with modifications due to time constraints. A full scale model of a portion
    of the roof was also successfully completed using the original plans and Addendum No. 1. This Court finds
    summary judgment was proper because Johnson was unable to meet all the elements of its claim of
    defective design.
    II.      WHETHER THE TRIAL COURT ERRED IN GRANTING THE
    STATE'S SUBSEQUENT MOTION FOR SUMMARY JUDGMENT
    AS TO WHETHER THE STATE WAS ENTITLED TO RECOVER
    FROM EVAN JOHNSON LIQUIDATED DAMAGES AND THE
    COSTS TO COMPLETE THE CONTRACT.
    ¶28.    Johnson claims the grant of summary judgment in favor of the State regarding the counterclaim for
    liquidated damages was improper. Johnson argues because the State's termination of the contract was
    13
    wrongful, this claim must also fail. Johnson also claims there are fact issues as to the reasonable cost to
    complete the contract which would also make summary judgment inappropriate.
    ¶29.    The State argues the award of liquidated damages is specifically authorized by the express terms
    of the contract. Paragraph 5 of the government construction contract between the parties explicitly and
    expressly provides for the termination and award of contractual liquidated damages against the contractor
    for such delay-default:
    5.      TERMINATION FOR DEFAULT-DAMAGES OR DELAY-TIME
    EXTENSIONS-
    a.        If the contractor refuses or fails to prosecute the work, or any
    separable part thereof, with such diligence as will insure its completion
    within the time specified in this contract, or any extension thereof, or fails
    to complete said work within such time, the State may, by written notice
    to the contractor, terminate his right to proceed with the work or such part
    of the work as to which there has been delay. In such event the State may
    take over the work and prosecute the same to completion, by contract or
    otherwise, and the contractor and his sureties shall be liable to the State
    for...liquidated damages for delay, as fixed in the specifications or
    accompanying papers, until such reasonable time as may be required for
    the final completion of the work....
    Paragraph 108 of the contract between the parties expressly sets the contractual rate of liquidated damages
    for delay. It provides:
    108. LIQUIDATED DAMAGES-In case of failure on the part of the
    contractor to complete the work within the time fixed in the contract or
    any extensions thereof, the contractor shall pay to the State as liquidated
    damages, pursuant to the Clause of this contract entitledTERMINATION
    FOR DEFAULT-DAMAGES OR DELAY-TIME EXTENSIONS, the
    sum of $ 231.81 for each day of delay.
    (emphasis in original).
    14
    ¶30.      The trial court found that the completion date for Johnson was May 8, 1997, and the replacement
    contractor successfully completed the roof on October 6, 1998. At the contractually specified rate of
    $231.81 per day, the 514 days of delay equals $119,150.34 in liquidated damages.
    ¶31.      Johnson cites only one case as authority for its argument that the trial court incorrectly granted
    summary judgment as to the amount of damages, Miss. Transp. Comm'n v. SCI, Inc., 
    717 So. 2d 332
    (Miss. 1998). However, SCI is completely distinguishable from this case. SCI did not involve a specific
    contractual provision setting out liquidated damages for each day of delay as did the State's contract with
    Johnson. SCI also did not involve uncontroverted facts as to the scheduled completion date and the actual
    day of completion.
    ¶32.      Johnson never contested the method of calculation of liquidated damages. Through the documents
    submitted in response to the State's motion for summary judgment, Johnson only sought to relitigate the trial
    court's previous order dismissing its complaint against the State and Tompkins for negligence and defective
    design.
    ¶33.      The contract is clear as to the per-day amount of liquidated damages. Johnson provided no
    genuine issue of material fact to rebut the State's evidence. Therefore, we find that the trial court's grant
    of summary judgment in favor of the State as to liquidated damages was proper.
    CONCLUSION
    ¶34.      The trial court did not err in granting summary judgment in favor of the State and Tompkins as to
    Johnson's claims of negligence and defective design. The trial court also did not err in granting summary
    judgment in favor of the State as to its claim of liquidated damages against Johnson. Johnson was unable
    to demonstrate any genuine issue of material fact and was also unable to meet all the elements of its claim
    15
    of defective design. Therefore, we affirm the trial court’s grant of summary judgment in favor of State and
    Tompkins and its final judgment entered consistent therewith, which also included an award of damages
    against Johnson and in favor of the State in the amount of $119,150.34 plus post-judgment at the rate of
    8% per annum until paid.
    ¶35.    AFFIRMED.
    PITTMAN, C.J., SMITH, P.J., EASLEY AND DICKINSON, JJ., CONCUR.
    GRAVES, J., CONCURS IN RESULT ONLY. COBB, J., DISSENTS WITHOUT
    SEPARATE WRITTEN OPINION.          WALLER, P.J., AND DIAZ, J., NOT
    PARTICIPATING.
    16