The Inn By The Sea Homeowner's Association, Inc. v. SeaInn, LLC , 2015 Miss. LEXIS 379 ( 2015 )


Menu:
  •               IN THE SUPREME COURT OF MISSISSIPPI
    NO. 2013-CA-02013-SCT
    INN BY THE SEA HOMEOWNER’S
    ASSOCIATION, INC.
    v.
    SEAINN, LLC, DRACE CONSTRUCTION CORP.,
    CARUBBA ENGINEERING, SOUTHERN CROSS
    CONSTRUCTION COMPANY, HARRY BAKER
    SMITH ARCHITECTS II, PLLC AND GREG
    STEWART
    DATE OF JUDGMENT:             10/31/2013
    TRIAL JUDGE:                  HON. JOHN C. GARGIULO
    TRIAL COURT ATTORNEYS:        DAVID C. GOFF
    ADAM STONE
    NICHOLAS VAN WISER
    THOMAS L. CARPENTER
    WILLIAM J. LITTLE, JR.
    COURT FROM WHICH APPEALED:    HARRISON COUNTY CIRCUIT COURT
    ATTORNEYS FOR APPELLANT:      ROSS DOUGLAS VAUGHN
    JOSEPH L. McREYNOLDS
    DAVID C. GOFF
    ATTORNEYS FOR APPELLEES:      NICHOLAS VAN WISER
    KAYTIE MICHELLE PICKETT
    ADAM STONE
    THOMAS LYNN CARPENTER, JR.
    VINCENT AUGUST NOLETTO, JR.
    CARTER R. HALE
    LEAH NICHOLS LEDFORD
    WILLIAM J. LITTLE, JR.
    NATURE OF THE CASE:           CIVIL - CONTRACT
    DISPOSITION:                  AFFIRMED - 07/30/2015
    MOTION FOR REHEARING FILED:
    MANDATE ISSUED:
    BEFORE WALLER, C.J., CHANDLER AND KING, JJ.
    CHANDLER, JUSTICE, FOR THE COURT:
    ¶1.    This action was brought by Inn By the Sea Homeowner’s Association, Inc. (“IBTS”)
    against various defendants involved in the development, design, and construction of Inn By
    the Sea Condominiums in Pass Christian when the condominiums were rebuilt after they
    were destroyed by Hurricane Katrina. Within a year of reconstruction, significant problems
    with the building began to manifest, problems allegedly related to defects in the design and
    construction of the property. The trial court granted summary judgment to the defendants
    after excluding the damages testimony of IBTS’s expert witnesses. We find that the trial
    court did not abuse its discretion in excluding the plaintiff’s witnesses, and therefore affirm
    the grant of summary judgment.
    FACTS AND PROCEEDINGS BELOW
    ¶2.    According to IBTS, the appellant-plaintiffs, Inn By the Sea Condominiums began
    showing signs of significant structural defects within a year of the issuance of the Certificate
    of Occupancy in 2009. ITBS sued the developer, various contractors, the structural engineer,
    the architect, and ten John Does as “unknown persons that provided material services, acted
    in a supervisory capacity, or were otherwise involved in the construction of the
    Condominiums.”1 The parties entered into an Agreed Scheduling Order on March 3, 2012,
    with a trial date set for December 3, 2012. IBTS hired Michael Bailey of Kyle Associates,
    LLC, as its expert structural engineer and Alfred Hayes of Hayes Architect as its expert
    1
    Prior to filing suit, IBTS sent notice of the defects and a request for timely repairs
    to the developer and general contractor pursuant to the requirements of Mississippi’s New
    Home Warranty Act. See Miss. Code Ann. §§ 83-58-1 to 83-58-17 (Rev. 2011).
    2
    architect to investigate and identify defects in the design and construction of the property.
    IBTS timely designated these experts on June 16, 2012, and produced a copy of the
    witnesses’ reports and cost estimates. Bailey estimated costs to correct engineering design
    defects to be $1,830,000. Hayes identified twenty-three design and construction defects
    which he estimated would cost $1,322,000 to repair. He subsequently updated his report in
    August 2012 and revised his repair estimate to $2,689,000 for the twenty-three identified
    defects. His report contained a description of each defect and a rounded, ballpark cost
    estimate to repair each defect. For example, Item Two states:
    2.     Condenser Equipment is installed on wood sleepers with pieces of
    roofing used as straps. This is not complying with code wind loading.
    Equipment should be installed on structural curbs flashed into the roof
    or rated equipment racks with pipe legs that can be flashed into roofing
    system. Design/Negotiation and Construction Observation Fee
    $3,000.00. Construction Cost $100,000. E&O Item 1 and 5.
    (Emphasis added.) The description of each defect ended similarly with a cursory rounded
    statement of the construction cost.
    ¶3.    In late August 2012, IBTS learned that Michael Bailey had suddenly left his job,
    moved out town, and could not be located or further made available as an expert on this case.
    At a hearing on September 12, 2012, the trial court orally continued the case without a new
    trial date in order for IBTS to find a new engineering expert. IBTS hired Ashton Avegno, a
    retired principal of Kyle Associates and a structural engineer with more than forty years of
    experience to replace Bailey. Avegno provided his report on November 2, 2012. In addition
    to largely agreeing with Bailey’s original report, Avegno also expressed concern that the
    foundation pilings “as designed” were overloaded by as much as “2.82 times its safe capacity
    3
    and the as built piling would be loaded 2.16 times its capacity.” He recommended that a “pile
    load test . . . be done at the site using the same size and length pile as the existing.”
    ¶4.    Avegno was unwilling, however, to provided exact itemized cost estimates for the
    items of engineering defects he identified. He estimated a total repair budget for all items
    between “$1,660,000 and $4,020,000.” He openly stated that the “costs provided here are my
    best estimates” but that he was “not a qualified estimator or contractor and therefore cannot
    be liable for the accuracy of these numbers. If more accurate numbers are needed then a
    licensed contractor or cost estimator should be engaged to provide them.”
    ¶5.    Also on November 2, 2012, IBTS filed a Motion for Trial Setting and Scheduling
    Order, proposing a trial date of April 15, 2013, with deadlines for the plaintiff’s experts to
    be designated by November 8, 2012, and the defendant’s experts to be designated by
    December 7, 2012. IBTS informed the court that IBTS had been unable to depose any of the
    defendants’ witnesses, including any of the defendants, and that the new scheduling order
    should be issued to allow IBTS to conduct depositions and to seasonably supplement its
    expert reports. The defendants objected to the proposed new scheduling order, arguing that
    the deadline for expert designations had passed and that Avegno should not be allowed to
    offer any new opinions, including his opinion that the foundation piles were overloaded.2
    ¶6.    The court heard IBTS’s motion for a new scheduling order on December 21, 2012.
    It granted IBTS’s motion to depose the defendants but limited IBTS’s right to supplement
    2
    IBTS also filed a Mississippi Rule of Civil Procedure 9(h) motion on December 5,
    2012 to substitute two of the “John Does” with Nosidam of Mississippi, Inc., and Greg
    Steward d/b/a Madison Homes. The court denied this motion.
    4
    its expert reports based only information learned in the depositions and excluding new
    information learned from the test piles recommended by Avegno. The court reset trial for
    August 12, 2013, and established new deadlines for completion of discovery by April 12,
    2013, with dispositive or Daubert3 motions to be filed by May 13, 2013.
    ¶7.    IBTS filed a motion for clarification or reconsideration on January 11, 2013, arguing
    that the defendants would not be prejudiced by a more extensive expert supplementation
    given the new trial date, new discovery deadlines, and the fact that the defendants had been
    on notice of potential structural defects in the foundation piles since November 2, 2012. The
    court denied IBTS’s motion for reconsideration (among other motions) after a hearing on
    March 14, 2013. IBTS had supplemented its motion for reconsideration, pointing out that,
    in the February 2012 deposition of defendant Carubba Engineering, Carubba had
    acknowledged that it had not used any pile load tests or geotechnical reports to verify load
    capacity or soil conditions at the construction site. Rather, despite having written on three
    separate occasions to the project architect that a pile load test was needed, he ultimately used
    a safe allowable load for his calculations “from my experience as a design engineer in these
    types of soils.” IBTS argued that, since the court’s previous order permitted supplementation
    of the expert report with evidence obtained from the depositions, opinions on the piles and
    the results of the pile tests should appropriately be allowed.4
    3
    Daubert v. Merrell Dow Pharms., Inc., 
    509 U.S. 579
    , 
    113 S. Ct. 2786
    , 125 L. Ed 2d
    469 (1993)
    4
    While acknowledging that the court had ruled not to allow the formal
    supplementation of expert testimony with opinions on the piles, IBTS circulated a copy of
    Avegno’s April 9, 2013, supplemental report, based on the results of the test piles, which
    5
    ¶8.    The court held a hearing on July 30, 2013, to hear eighteen separate in limine motions,
    including Daubert and dispositive motions. Included were defense motions to exclude the
    expert testimony of Hayes and Avegno under Mississippi Rule of Evidence 702. The
    defendants asserted that Hayes had failed to offer detailed support or explanation for his
    opinion on construction repair costs, and that Avegno was, by his own admission, not
    qualified to provide any opinion on costs. IBTS argued that the court should defer ruling on
    the reliability of the experts’ costs estimates until trial, when it would have the benefit of
    their testimony.
    ¶9.    The court granted the motion to exclude Avegno from testifying as to monetary
    damages, finding that he was not qualified by his own admission and that he had declined to
    permit supplementation of his report to provide the basis for his cost estimates.
    ¶10.   However, the Court denied the motion to exclude Hayes’s damages testimony, and at
    the request of the defense continued trial and ordered Hayes to supplement his report. The
    court denied both parties’ motions for summary judgment at that time. The order stated in
    relevant part:
    Furthermore, this Court holds that the Inn is granted two weeks from the date
    of this hearing, which is August 13, 2013, in which to provide Alfred
    Hayes’[s] summary of the grounds for each opinion relating to cost. This Court
    will then take up any motions pertaining to that supplementation if any such
    motions are needed.
    This Court further continues this case from its August 12, 2013 setting, to a
    time convenient for this Court and the parties.
    confirmed that the foundation piles were indeed overloaded. He opined that as many as 110
    additional piles would be needed to stabilize the foundation, at a cost ranging between
    $500,000 and $800,000.
    6
    ¶11.   In response to the trial court’s order for supplementation, Hayes added a ten-paragraph
    affidavit with exhibits to his report. He identified the RS Means Construction Cost Data as
    the basis for his cost estimates. He asserted that RS Means is “the most used and respected
    guide available to the construction industry” and that the RS Means “method of estimating
    is widely accepted as one of the most accurate forms of pricing available.”
    ¶12.   Hayes attached an Exhibit B demonstrating a “step by step analysis” of how he used
    RS Means to estimate the cost as applies to the roof replacement item, which was the third
    of the twenty-three items identified as structural design defects in his report. He further
    asserted that each “of the enumerated items in my report [is] contained within [M]eans and
    [was] researched for Inn By the Sea.” Hayes used a 2008 version of RS Means to select the
    data used to calculate the repair estimate.
    ¶13.   The defendants moved to strike Hayes’s supplementation and renewed their motion
    for summary judgment. The court granted the defendants’ motion to exclude Alfred Hayes’s
    damages testimony as well as the defendant’s motion for summary judgment and final
    judgment on October 31, 2013. The order stated in part:
    Plaintiff filed his supplementation at 11:07 PM, on August 13, 2013, the last
    day of the two week period. The supplementation included calculations on
    only one of the 24 cost items . . .
    Thus, the Court finds that the Defendants are in no better position than they
    were on August 12, 2013. The substance and details supporting the damage
    estimates should have been disclosed, and this Court ordered them disclosed.
    This disclosure ordered by this Court extended to all calculations and
    methodology used to reach estimates for all 24 cost items, but were only
    provided for Cost Item No. 3. This Court finds that as to Number 3, which
    calculations were derived from an obsolete manual, the 2008 edition of RS
    Means, is unreliable.
    7
    . . . This Court grants the Defendants’ motion to exclude the testimony of Fred
    Hayes as to his damages calculations. This Court notes that as a result, there
    are no damages estimates left for the Plaintiff to present as evidence in this
    trial. Accordingly, summary judgment is granted as to all defendants in this
    cause of action.
    ¶14.   Below is a timeline summary of the major pretrial events in this litigation:
    March 2012           Original Agreed Scheduling Order entered with trial date
    of Dec 3, 2012.
    June 2012            IBTS’s timely initial disclosure of experts and expert
    reports.
    August 2012          IBTS’s structural expert Bailey disappears; trial
    continued without date.
    November 2012        Avegno designated as replacement for Bailey,
    recommends test piles; IBTS proposes new scheduling
    order and trial date.
    December 5, 2012 IBTS files motion to substitute two new parties under
    M.R.C.P. 9(h)
    December 21, 2012 Hearing held in which court grants IBTS’s motion to
    depose defendants but limits expert supplementation to
    new information gained in depositions; excludes any
    future test pile results or testimony. Trial set for August
    12, 2013
    March 14, 2013       Court hears and denies IBTS’s motion to reconsider
    limitation of expert supplementation of pending test pile
    results considering Carubba’s deposition testimony
    regarding foundation piles.
    April 9, 2013        IBTS circulates proposed supplementation of Avegno’s
    expert report including the results of the test pile
    indicating that piles are overloaded and as many as 110
    additional piles would be needed to stabilize the
    foundation, at a cost ranging between $500,000 and
    $800,000.
    8
    July 30, 2013       Trial continued without new trial date at request of
    defendants to require supplementation of Hayes’s expert
    report by August 13, 2013, “to provide Alfred Hayes’s
    summary of the grounds for each opinion relating to
    cost.” Avegno excluded from testifying as to cost
    damages due to his statement in his initial report that he
    was not a qualified cost estimator.
    August 13, 2013     Hayes supplements report with ten-paragraph affidavit
    and Exhibit B with itemized calculations for Item 3 roof
    repairs. (Exhibit A describes the 2008 RS Means
    Construction Costs Data. The parties agree that RS
    Means is generally reliable; the defendants object to the
    use of the 2008 version as outdated).
    October 31, 2013    Court excludes Hayes’s testimony on damages as
    unreliable and grants summary judgment to the
    defendants due to lack of proof of damages.
    Inn By the Sea timely appealed. Because we find the question of whether IBTS’s experts
    were properly excluded dispositive, we do not address the other issues raised by IBTS on
    appeal.
    DISCUSSION
    ¶15.   This Court reviews grants of summary judgment de novo. Smith ex rel. Smith v.
    Gilmore Mem’l Hosp., Inc., 
    952 So. 2d 177
    , 181 (Miss. 2007). The evidence will be
    reviewed in the light most favorable to the party opposing summary judgment. Bowie v.
    Montfort Jones Mem’l Hosp., 
    861 So. 2d 1037
    , 1041 (Miss. 2003). Rulings regarding the
    admissibility of expert testimony are reviewed for abuse of discretion. Miss. Transp.
    Comm’n v. McLemore, 
    863 So. 2d 31
    , 40 (Miss. 2003).
    WHETHER THE TRIAL COURT ABUSED ITS DISCRETION IN
    EXCLUDING THE EXPERT DAMAGES TESTIMONY OF ALFRED
    HAYES AND ASHTON AVEGNO.
    9
    ¶16.   IBTS argues that the trial court abused its discretion in excluding Hayes’s expert
    testimony regarding cost damages. Hayes’s qualifications and the relevance of his testimony
    are not in question. Rather, the defendants successfully challenged the reliability of Hayes’s
    method and his failure to disclose the basis of the majority of his cost opinions. Mississippi
    Rule of Evidence 702 provides that:
    If scientific, technical, or other specialized knowledge will assist the trier of
    fact to understand the evidence or to determine a fact in issue, a witness
    qualified as an expert by knowledge, skill, experience, training, or education,
    may testify thereto in the form of an opinion or otherwise, if (1) the testimony
    is based upon sufficient facts or data, (2) the testimony is the product of
    reliable principles and methods, and (3) the witness has applied the principles
    and methods reliably to the facts of the case.
    Under Mississippi Rule of Civil Procedure 26(b)(4)(A)(I),
    A party may through interrogatories require any other party to identify each
    person whom the other party expects to call as an expert witness at trial, to
    state the subject matter on which the expert is expected to testify, and to state
    the substance of the facts and opinions to which the expert is expected to
    testify and a summary of the grounds for each opinion.
    ¶17.   The reliability of expert testimony is analyzed under the nonexhaustive factors
    adopted from Daubert v. Merrell Dow Pharmaceuticals, Inc., 
    509 U.S. 579
    , 
    113 S. Ct. 2786
    ,
    125 L. Ed 2d 469 (1993), which include:
    (1) whether the expert’s theory can be or has been tested;
    (2) whether the theory has been subjected to peer review and publication;
    (3) the known or potential rate of error of a technique or theory when applied;
    (4) the existence and maintenance of standards and control; and
    (5) the degree to which the technique or theory has been generally accepted in
    the scientific community.
    10
    Miss. Transport. Comm’n v. 
    McLemore, 863 So. 2d at 37
    (Miss. 2003). The Daubert test
    is not meant to be so tightly applied that it replaces traditional methods for challenging
    “shaky, but admissible” expert testimony, through “[v]igorous cross examination,
    presentations of contrary evidence, and careful instruction on the burden of proof.” 
    Id. at 37.
    “The threshold for admissibility is not great, keeping in mind the fact that Mississippi Rule
    [of Evidence] 401 favors the admission of evidence when it has probative value.” Utz v.
    Running & Rolling Trucking, Inc., 
    32 So. 3d 450
    , 457 (Miss. 2010).
    ¶18.   Seasonable supplementation of expert testimony is required under the guidelines of
    Mississippi Rule of Civil Procedure 26(f). The function of the supplementation requirement
    is to fairly inform the opposing party of the evidence against it with an opportunity to meet
    it and to avoid “trial by ambush.” Hyundai Motor Am. v. Applewhite, 
    53 So. 3d 749
    , 758
    (Miss. 2011). Defendants are entitled to supplementation on “the identity of each person
    expected to be called as an expert witness at trial, the subject matter on which the person is
    expected to testify, and the substance of the testimony . . . . A duty to supplement responses
    may be imposed by order of the court, agreement of the parties, or at any time prior to trial
    through new requests for supplementation of prior responses.” M.R.C.P. 26(f)(1) & (3).
    ¶19.   Multiple reliable methods of calculating construction damages are available to experts
    depending on the nature of the cause of action and best evidence available of the underlying
    facts and data. See Schwartzkopf & McNamara, General Methods of Damage Calculation,
    Calc. Constr. Dmgs. § 1.03 (2014). What matters on a case-by-case basis is adherence to the
    principles of Mississippi Rule of Evidence 702 and Mississippi Rule of Civil Procedure 26,
    11
    and, in particular, adherence to the requirement that experts disclose the basis of their
    opinions with sufficient specificity to allow defendants to prepare a defense and avoid trial
    by ambush. Cost estimates do not have to be presented with mathmatical certainty; rather,
    sufficient evidence should be presented so that the trier of fact can determine damages within
    a reasonable certainty.
    ¶20.   In Sumrall Church of Lord Jesus Christ v. Johnson, 
    757 So. 2d 311
    (Miss. Ct. App.
    2000), our Court of Appeals found the appropriate measure of damages was the actual repair
    cost that already had been incurred by the plaintiff in fixing the deficiencies of the electrical
    contractor. We affirmed the reliability of repair-cost estimates in Hoover v. United Services
    Auto. Association, 
    125 So. 3d 636
    (Miss. 2013), where a qualified expert “used a cost-plus
    estimate based on known values to arrive at his calculations. He assessed that it would cost
    $40 per square foot to replace the roof, and multiplied this by the total square footage of the
    house.” 
    Id. at 645.
    ¶21.   Of particular significance is our unanimous decision in the products liability case
    Hyundai Motor America v. Applewhite, 
    53 So. 3d 749
    , 758 (Miss. 2011), in which we
    affirmed a defendant’s right to not be ambushed at trial with previously undisclosed
    calculations forming the basis for the plaintiff’s expert opinions, even when the new
    disclosure did not alter the original expert conclusions. In Hyundai, we found reversible
    error in the plaintiff’s failure to disclose (via formal supplementation) changes in the velocity
    calculations its experts used to form opinions on a car-crash impact. Even though the expert’s
    ultimate conclusions remained the same, we found that the defendants had been ambushed
    12
    in preparation of their defense, which relied on the initial velocity disclosures as the basis for
    preparing the defense.
    ¶22.   Generally speaking, the annually published RS Means Construction Cost manual is
    a reliable industry source of data and has been used with approval in cases involving expert
    testimony on damages. See Traco Steel Erectors, Inc. v. Comtrol, Inc., 
    222 P.3d 1164
    (Utah
    2009); Hale v. Big H Constr., Inc., 
    288 P.3d 1046
    (Utah Ct. App. 2012). But merely
    disclosing that a five-year-old RS Means manual is the general basis for the conclusory
    estimates on twenty-two of twenty-three items of alleged structural damages amounting to
    several million dollars does not provide a sufficient disclosure of data for a trier of fact to
    determine that the estimates have been calculated with reasonable accuracy or for a defendant
    to meet the evidence.5 As it is, the testimony is unreliable because it fails to disclose the basis
    of the expert opinion.
    ¶23.   We reiterate that the timing and outcome of Daubert considerations are squarely
    within the discretion of the trial court. See Kumho Tire Co. v. Carmichael, 
    526 U.S. 137
    ,
    152, 
    119 S. Ct. 1167
    , 
    143 L. Ed. 2d 238
    (1999); Edmonds v. State, 
    955 So. 2d 787
    , 792
    (Miss. 2007). Pretrial obfuscation of the basis for expert opinions, especially when the court
    has ordered further disclosure, is a game of chicken that parties should not play in light of
    how our evidentiary standards have evolved to preclude trial by ambush. We note that the
    court excluded Hayes’s testimony only after continuing trial to give him the (mandatory)
    5
    We note that portions of the calculations provided for Item Three do include some
    aspects of calculation that could be extrapolated to the other items and create fodder for
    cross-examination and opposing expert testimony, such as sales tax and permitting costs.
    13
    opportunity to supplement his expert report with a specific basis for each of his opinions
    relating to cost.
    ¶24.   After carefully examining the transcript of the hearing and the court’s written order
    for supplementation, we agree with the trial court and the defendants that production of the
    basis for only one itemized opinion out of twenty-three was not in compliance with the
    degree of specificity reasonably ordered by the trial court. “The failure seasonably to
    supplement or amend a response is a discovery violation that may warrant sanctions,
    including the exclusion of evidence.” Hyundai Motor Am. v. 
    Applewhite, 53 So. 3d at 758
    ;
    Ekornes-Duncan v. Rankin Med. Cir., 
    808 So. 2d 955
    , 958 (Miss. 2002). We find that the
    trial court did not abuse its discretion in excluding Hayes’s testimony, particularly in light
    of the fact that the trial court continued the trial and granted additional time for
    supplementation.
    ¶25.   IBTS argues that the trial court also abused its discretion in finding that Avegno was
    unqualified to provide expert testimony relating to damages, and in refusing to permit
    supplementation of Avegno’s opinions relating to costs. IBTS argues that Avegno’s
    statements in his initial report should be taken in the context of his replacement of Bailey,
    that his experience and qualifications outlined in his curriculum vitae (which is part of the
    record) counter his initial cautious declamation of his qualifications to provide cost estimates,
    and that the trial court abused its discretion in failing to permit Avegno to supplement his
    initial report with specific basis for his cost estimates.
    14
    ¶26.   An expert is qualified “only if the witness possesses scientific, technical, or
    specialized knowledge on [the] particular topic” of his opinion. Bailey Lumber & Supply Co.
    v. Robinson, 
    98 So. 3d 986
    , 992 (Miss. 2012) (quoting Worthy v. McNair, 
    37 So. 3d 609
    ,
    616 (Miss. 2010)). We agree with IBTS that “a witness need not be a specialist in any
    particular profession to testify as an expert. The scope of the witness’s knowledge and
    experience, and not any artificial classification, governs the question of admissibility.” R.
    McNight & Son v. C. & I Entm’t, 
    100 So. 3d 1022
    (Miss. Ct. App. 2012) (quoting Univ. of
    Miss. Med. Ctr. v. Pounders, 
    970 So. 2d 141
    , 146 (Miss. 2007). But Avegno explicitly stated
    in his expert report that the range of between “$1,660,000 and $4,020,000” was merely his
    general estimate and that establishing sufficiently specific estimates would require bringing
    in someone more qualified.
    ¶27.   We cannot ignore Avegno’s statements and rely on the general assertion that
    Avegno’s background and experience do indeed indicate his qualifications to provide cost
    estimates if only given an opportunity to supplement. We find that the trial court did not
    abuse its discretion in granting the defendants’ Daubert motion to exclude Avegno as
    unqualified to provide expert opinions relating to cost.6
    CONCLUSION
    6
    IBTS has presented a much stronger argument that the trial court abused its
    discretion in refusing to permit the seasonable supplementation of Avegno’s expert report
    regarding deficiencies of the foundation piles of the condominiums. However, we do not
    address this argument, given our affirmation of summary judgment due to lack of admissible
    evidence of damages.
    15
    ¶28.   We affirm the trial court’s grant of summary judgment on the grounds that the
    plaintiff failed to present admissible expert opinions on damages. Hayes’s cost damages
    opinions lacked sufficient disclosure of the method and calculations that formed the basis of
    his report. Avegno was, by his own admission, not qualified to provide cost estimates relating
    to his other opinions on structural defects. Because we affirm summary judgment on these
    grounds, we do not find it necessary to address the other issues raised on appeal.
    ¶29.   AFFIRMED.
    WALLER, C.J., DICKINSON AND RANDOLPH, P.JJ., LAMAR, KITCHENS,
    PIERCE, KING AND COLEMAN, JJ., CONCUR.
    16