George Waltman v. Engineering Plus, Inc. ( 2019 )


Menu:
  •                    IN THE SUPREME COURT OF MISSISSIPPI
    NO. 2017-CA-01747-SCT
    GEORGE WALTMAN AND LIBERTY MUTUAL
    INSURANCE COMPANY
    v.
    ENGINEERING PLUS, INC.
    DATE OF JUDGMENT:                        11/16/2017
    TRIAL JUDGE:                             HON. LESTER F. WILLIAMSON, JR.
    TRIAL COURT ATTORNEYS:                   JAMES A. WILLIAMS
    LESLIE C. GATES
    MARGARET Z. SMITH
    ROBERT A. MILLER
    KATHLEEN I. CARRINGTON
    JONATHAN C. TABOR
    CHRISTOPHER MICHAEL FALGOUT
    JOHN S. GONZALEZ
    LINDSEY BLACKWELL HARRIS
    COURT FROM WHICH APPEALED:               LAUDERDALE COUNTY CIRCUIT COURT
    ATTORNEYS FOR APPELLANTS:                JAMES A. WILLIAMS
    LINDSEY BLACKWELL HARRIS
    ATTORNEYS FOR APPELLEE:                  ROBERT A. MILLER
    MARGARET Z. SMITH
    KATHLEEN I. CARRINGTON
    NATURE OF THE CASE:                      CIVIL - PERSONAL INJURY
    DISPOSITION:                             AFFIRMED - 03/07/2019
    MOTION FOR REHEARING FILED:
    MANDATE ISSUED:
    BEFORE KITCHENS AND KING, P.JJ., AND COLEMAN, J.
    KITCHENS, PRESIDING JUSTICE, FOR THE COURT:
    ¶1.   In 2013, Lauderdale County contracted with Norman Enterprises, Inc., a roofing
    company, to repair the roof of the Ulmer Building in Meridian, Mississippi. George
    Waltman, an employee of Norman Enterprises, fell through the roof while performing work.
    Waltman sued Engineering Plus, Inc., the project engineer, claiming it should have warned
    him of the dangerous condition of the roof. Engineering Plus moved for summary judgment,
    arguing it had no duty to warn Waltman. The Lauderdale County Circuit Court agreed and
    granted summary judgment to Engineering Plus. We affirm.
    FACTS AND PROCEDURAL HISTORY
    ¶2.    In the summer of 2012, the Lauderdale County Board of Supervisors sought to replace
    the roofs of several county-owned buildings. A representative of the Board contacted Terrell
    Temple, an engineer and the president of Engineering Plus, to hire Temple’s company as the
    project engineer for the Ulmer Building and Mount Barton School roof-repair projects in
    Meridian, Mississippi. Engineering Plus prepared the project details, the contract documents,
    and the bid paperwork to facilitate the Board’s hiring a general contractor. Those documents
    set forth the scope of the projects and the responsibilities of the general contractor.
    ¶3.    In February 2013, Lauderdale County advertised for bids using the documents
    prepared by Engineering Plus. Norman Enterprises submitted a bid, which the county
    accepted. On March 18, 2013, Lauderdale County entered into a contract that incorporated
    the bid details, with Norman Enterprises as the general contractor for the Ulmer Building
    project.
    ¶4.    George Waltman, an employee of Norman Enterprises, worked on the Ulmer Building
    project. After Norman Enterprises had received the notice to proceed with the project,
    Waltman went to the Ulmer Building on July 23, 2013, to begin removing debris from the
    2
    roof in preparation for the repairs. Within minutes of arriving at the site, Waltman stepped
    onto a deteriorated area of the roof and fell through, suffering injuries.
    ¶5.    Waltman sued the project engineer, Engineering Plus, claiming that it knew of the
    dangerous condition of the roof and should have warned him. Engineering Plus filed a
    motion for summary judgment on the basis that it had no contractual or common law duty
    to warn Norman Enterprises’s employees of the condition of the roof. The circuit court
    agreed with Engineering Plus.
    ¶6.    On November 16, 2017, the circuit court entered a memorandum opinion and order
    in which it granted Engineering Plus’s motion for summary judgment and dismissed the
    cause. Waltman appealed.
    STANDARD OF REVIEW
    ¶7.    When parties appeal a grant or denial of summary judgment, this Court employs a de
    novo standard of review. Bullock v. Life Ins. Co. of Miss., 
    872 So. 2d 658
    , 660 (¶ 6) (Miss.
    2004). On de novo review, no deference is given to a lower court’s decision. McArthur v.
    Ingalls Shipbuilding, Inc., 
    879 So. 2d 500
    , 502 (Miss. Ct. App. 2004). This Court reviews
    all the evidence in the light most favorable to the non-moving party. 
    Id.
    ANALYSIS
    ¶8.    “When the proof regarding only one element of a plaintiff’s claim fails, the defendant
    is entitled to summary judgment, despite any factual disputes regarding the remaining
    elements of the claim.” Hernandez v. Vickery Chevrolet-Oldsmobile Co., 
    652 So. 2d 179
    ,
    183 (Miss. 1995) (citing Grisham v. John Q. Long V.F.W. Post, 
    519 So. 2d 413
    , 416 (Miss.
    3
    1988)). The issue in this case involves only one element of George Waltman’s claim:
    whether Engineering Plus had a duty to warn him of the dangerous condition of the roof. For
    an engineer to have an affirmative duty to warn of dangerous conditions, the engineer must
    have taken on, either by contract or conduct, the responsibility of maintaining the safety of
    the construction project. McKean v. Yates Eng’g Corp., 
    200 So. 3d 431
    , 435 (Miss. 2016).1
    I.     Engineering Plus did not assume a duty by contract.
    ¶9.    George Waltman argues that Engineering Plus assumed a contractual duty to supervise
    the Ulmer Building project based on the following language in the contract between
    Lauderdale County and Norman Enterprises: “It is further agreed that the work[] shall be
    done under the direct supervision and to the complete satisfaction of the County Engineer or
    his authorized representatives.”2 The contract as a whole, however, indicates that the parties
    did not intend for Engineering Plus to be responsible for the safety of Waltman.
    ¶10.   The contract specifies that Norman Enterprises was
    responsible for all loss or damage arising out of the nature of the work
    aforesaid, or from the action of the elements, and unforeseen obstruction or
    difficulties which may be encountered in the prosecution of the same and for
    all risks of every description connected with the work for faithfully completing
    the whole work[.]
    The contract further provides that Norman Enterprises “shall satisfy [itself] of the existing
    size and conditions of the project area.” Other provisions of the contract reinforce the
    1
    Although an architect’s duty was at issue in McKean, the context of that opinion
    makes clear that the rule extends to engineers as well.
    2
    This is the only provision in the contract that arguably could create a duty.
    4
    proposition that Norman Enterprises was the only party responsible for safety at the project’s
    work site.
    ¶11.   American Jurisprudence, Second Edition, sets out the following general rules of
    contract interpretation when two or more provisions are arguably in conflict:
    Where there is an apparent repugnancy or conflict between two clauses or
    provisions of a contract, it is the province and duty of the court to find
    harmony between them and to reconcile them if possible. . . . No contract
    provision should be construed as being in conflict with another unless no other
    reasonable interpretation or construction is possible. . . . Where a repugnancy
    is found between clauses, . . . [t]he clause contributing most essentially to the
    contract is entitled to the greater consideration, and a subsidiary provision
    should be so interpreted as not to be in conflict with what clearly appears to be
    the dominant purpose of the contract. . . . [T]his rule is tempered by the
    corollary that the more specific clause controls the more general.
    17A Am. Jur. 2d Contracts § 374 (citations omitted).
    ¶12.   The above contract provisions limited the responsibility for Waltman’s safety—while
    at the work site—specifically to Norman Enterprises. These specific provisions control the
    more general provision that reads, the work “shall be done under the direct supervision of”
    Engineering Plus.
    ¶13.   Engineering Plus did not assume a duty by contract to warn Waltman of the dangerous
    condition of the Ulmer Building’s roof.
    II.    Engineering Plus did not assume a duty by conduct.
    ¶14.   “[T]o determine whether an engineer ha[s] a supervisory duty outside the provisions
    of [a] contract,” this Court expressly has adopted the “seven-factor test used in [Hanna v.
    Huer, Johns, Neel, Rivers & Webb . . . .]” McKean, 200 So. 3d at 434-35 (citing Hanna v.
    Huer, Johns, Neel, Rivers & Webb, 
    233 Kan. 206
    , 
    662 P.2d 243
     (1983), superseded by
    5
    statute as recognized in Edwards v. Anderson Eng’g, Inc., 
    284 Kan. 892
    , 
    166 P.3d 1047
    (2007)).
    Those factors are: (1) actual supervision and control of the work; (2) retention
    of the right to supervise and control; (3) constant participation in ongoing
    activities at the construction site; (4) supervision and coordination of
    subcontractors; (5) assumption of responsibilities for safety practices; (6)
    authority to issue change orders; and (7) the right to stop the work.
    
    Id.
     (quoting McKean v. Yates Eng’g Corp., 
    210 So. 3d 1037
    , 1044 (Miss. Ct. App. 2015)
    (quoting Hobson v. Waggoner Eng’g, Inc., 
    878 So. 2d 68
    , 72 (Miss. Ct. App. 2003))).
    ¶15.   With respect to this issue, Waltman argues only that Engineering Plus had knowledge
    of the dangerous condition of the roof. Knowledge of dangerous conditions, by itself, does
    not satisfy the Hanna factors. Indeed, a review of the entire record shows that no evidence
    was offered that Engineering Plus had responsibility for any supervision or control of the
    work, that Engineering Plus had participated in activities at the work site, that Engineering
    Plus had assumed responsibility for safety practices, or that Engineering Plus had the
    authority to issue changes or to stop the work.
    ¶16.   In the pleadings below and in his brief before this Court, Waltman does not allege any
    conduct that could satisfy the Hanna factors. Accordingly, Engineering Plus did not assume
    a duty by conduct.
    III.   Waltman’s remaining arguments are unavailing.
    ¶17.   Throughout his brief, Waltman makes several arguments that have no bearing on the
    controlling issue of whether Engineering Plus had a duty to warn of the dangerous condition
    of the Ulmer Building’s roof. For example, Waltman writes, “The relation of Engineering
    6
    Plus to Norman Roofing was that of owner-invitee. A business invitee is defined as someone
    who enters onto another’s premises at the invitation of the owner for the purpose of
    benefitting both parties.” We have read the entire record, and no evidence has been offered
    to suggest that Engineering Plus owned or controlled the Ulmer Building. Additionally,
    Waltman never asserted or pursued a premises liability claim at the trial level.
    CONCLUSION
    ¶18.   George Waltman did not establish that the defendant had a duty to warn him of the
    dangerous condition of the Ulmer Building’s roof. The Circuit Court of Lauderdale County
    correctly granted summary judgment in favor of Engineering Plus. We affirm the circuit
    court’s judgment.
    ¶19.   AFFIRMED.
    RANDOLPH, C.J., KING, P.J., COLEMAN,                           MAXWELL,        BEAM,
    CHAMBERLIN, ISHEE AND GRIFFIS, JJ., CONCUR.
    7
    

Document Info

Docket Number: NO. 2017-CA-01747-SCT

Judges: Kitchens, King, Coleman

Filed Date: 3/7/2019

Precedential Status: Precedential

Modified Date: 10/19/2024