in-the-matter-of-the-verified-application-and-petition-of-liberty-energy ( 2014 )


Menu:
  •                In the Missouri Court of Appeals
    Western District
    IN THE MATTER OF THE VERIFIED      )
    APPLICATION and PETITION OF        )
    LIBERTY ENERGY (MIDSTATES) CORP    )
    d/b/a LIBERTY UTILITIES TO CHANGE  )
    ITS INFRASTRUCTURE SYSTEM          )
    REPLACEMENT SURCHARGE,             )
    )
    MISSOURI PUBLIC SERVICE            )
    COMMISSION,                        )
    Respondents, )
    v.                                 )                   WD77089
    )
    THE OFFICE OF PUBLIC COUNSEL,      )                   FILED: July 29, 2014
    Appellant. )
    APPEAL FROM THE PUBLIC SERVICE COMMISSION
    BEFORE DIVISION ONE: MARK D. PFEIFFER, PRESIDING JUDGE,
    LISA WHITE HARDWICK AND GARY D. WITT, JUDGES
    The Office of the Public Counsel appeals from the Missouri Public Service
    Commission's order approving the request of Liberty Energy (Midstates) Corp. d/b/a/
    Liberty Utilities ("Liberty") to change its Infrastructure System Replacement Surcharge
    ("ISRS"). Public Counsel contends the Commission's order is unlawful because it
    allows Liberty to recover costs that are not authorized by the ISRS statutes. For
    reasons explained herein, we affirm.
    FACTUAL AND PROCEDURAL HISTORY
    The Commission is the state administrative agency responsible for regulating
    public utilities, including gas corporations, in Missouri. In re Laclede Gas Co., 
    417 S.W.3d 815
    , 817 (Mo. App. 2014). Liberty is a Missouri corporation and a natural gas
    provider. It is a "gas corporation" and "public utility" under Sections 386.020(18) and
    (43), RSMo Cum. Supp. 2013,1 and, therefore, is subject to the Commission's
    regulatory power. 
    Id. Public Counsel
    is a state agency that has the discretion to
    represent the interests of consumers in all utility proceedings before the Commission
    and in all appeals of Commission orders. 
    Id. In 2012,
    Liberty purchased substantially all of the assets that Atmos Energy
    Corporation ("Atmos") used to provide natural gas and transportation services in
    Missouri. The Commission issued new certificates of convenience and necessity to
    Liberty for the service areas formerly served by Atmos, and the Commission approved
    Liberty's adoption of Atmos's tariffs.
    Among the tariffs that Liberty adopted were Atmos's ISRS tariffs for each of its
    three rate districts. The ISRS statutes, Sections 393.1009, 393.1012, and 393.1015,
    provide a method for gas corporations to recover eligible infrastructure system
    replacement costs between general rate cases through a surcharge on their customers'
    bills. Section 393.1009(3) defines "eligible infrastructure system replacements" as gas
    utility plant projects that:
    (a) Do not increase revenues by directly connecting the infrastructure
    replacement to new customers;
    (b) Are in service and used and useful;
    1
    All statutory references are to the Revised Statutes of Missouri 2000, as updated by the 2013
    Cumulative Supplement.
    2
    (c) Were not included in the gas corporation's rate base in its most recent
    general rate case; and
    (d) Replace or extend the useful life of an existing infrastructure[.]
    Section 393.1009(5) defines "gas utility plant projects," in pertinent part, as:
    (a) Mains, valves, service lines, regulator stations, vaults, and other
    pipeline system components installed to comply with state or federal
    safety requirements as replacements for existing facilities that have worn
    out or are in deteriorated condition;
    (b) Main relining projects, service line insertion projects, joint
    encapsulation projects, and other similar projects extending the useful life
    or enhancing the integrity of pipeline system components undertaken to
    comply with state or federal safety requirements[.]
    In July 2013, Liberty filed a petition with the Commission to change its ISRS to
    recover costs incurred due to infrastructure system replacements that Liberty made
    from June 1, 2012 through May 31, 2013. Pursuant to Section 393.1015.2(1), when a
    petition to establish or change an ISRS is filed, the Commission is required to conduct
    an examination of the proposed ISRS. The Commission's Staff may examine the
    petitioning gas corporation's information to confirm that the costs are in accordance with
    the ISRS statutes and that the proposed charges are properly calculated. §
    393.1015.2(2). Staff may then submit a report of its examination to the Commission no
    later than sixty days after the petition was filed. 
    Id. The Commission
    may hold a
    hearing on the petition and must "issue an order to become effective not later than one
    hundred twenty days after the petition [was] filed." § 393.1015.2(3).
    In this case, Staff from the Commission's Auditing and Energy Units conducted
    an investigation of Liberty's ISRS petition. Liberty sought to recover costs for 275
    distinct projects. Of these 275 projects, Staff's investigation included reviewing 36
    3
    Liberty work orders totaling approximately $2.2 million, which was about 58% of the
    amount that Liberty requested in its ISRS petition.2
    The work orders that Staff examined provided enough information to
    demonstrate that the projects involved replacement of steel or polyethylene pipe. Some
    projects included the installation of either gas safety valves or excess flow valves. The
    work orders noted the age of the pipe being replaced and any corrosion or other
    defects. Staff determined that the work orders involved pipe replacements that
    improved the integrity of the system, rather than maintenance expenses, such as
    merely wrapping a pipe.
    Additionally, Staff reviewed Liberty's project sub-ledger, which designated
    whether a project included material, supplies, overhead, or labor, and whether the
    project was performed for the integrity of the system or for growth. The costs included
    in the project sub-ledger were detailed enough for Staff to understand the activities and
    costs incurred for each job.
    In reviewing Liberty's initial calculations, Staff noticed that Liberty had included
    some growth projects, which are not eligible for recovery in an ISRS under Section
    393.1009(3)(a). Staff removed those projects when it performed its own calculations.
    Staff also identified other errors and omissions in the data provided by Liberty, including
    summation errors; errors in accumulated depreciation, deferred income taxes, property
    taxes, depreciation rates, and conversion factors; and formula errors. Staff filed a
    report, with two subsequent updates, recommending several adjustments to Liberty's
    ISRS petition to correct the identified errors and omissions. Staff then calculated an
    2
    According to Staff, if this were a general rate case and not an ISRS request, it would be able to examine
    significantly more project work orders because Staff has more time to conduct its investigation in a
    general rate case.
    4
    adjusted ISRS. Liberty agreed with Staff's recommendations and calculations in the
    adjusted ISRS.
    Public Counsel filed a motion requesting that the Commission reject Liberty's
    ISRS petition or schedule an evidentiary hearing. In its motion, Public Counsel
    asserted, among other things, that Liberty was seeking to recover expenses in its
    proposed ISRS that were not authorized by Section 393.1009(5).
    The Commission held an evidentiary hearing, and the parties argued their
    positions in post-hearing briefs. One of the arguments that Public Counsel made was
    that Liberty should not be allowed to recover its expenses for infrastructure that was
    replaced because it was accidentally or negligently damaged by a third party, such as a
    when a contractor accidentally struck a main or service line while digging. Public
    Counsel contended that the replacement of a pipe that was accidentally damaged
    during excavation activity did not satisfy Section 393.1009(5)(a)'s requirement that the
    replacement was for "existing facilities that have worn out or are in deteriorated
    condition." (Emphasis added.)
    The Commission rejected this argument, however, and approved Liberty's ISRS
    petition as corrected by Staff's adjusted ISRS. In its report and order, the Commission
    noted that the term "deteriorated" was commonly defined as "to lower in quality,
    character, or value." Applying this definition, the Commission concluded that a pipe that
    has been damaged by a third party is in deteriorated condition "because it has been
    lowered in quality, character, or value, although that deterioration has occurred quicker
    than what happens normally through the passage of time." Therefore, the Commission
    determined that Liberty's projects replacing pipes that were damaged by a third party
    5
    qualified as "gas utility projects" under Section 393.1009(5)(a). Additionally, the
    Commission found that those projects qualified as "gas utility projects" under Section
    393.1009(5)(b), because they were "projects extending the useful life or enhancing the
    integrity of pipeline system components."
    Having found that the ISRS projects remaining after Staff's calculation of the
    adjusted ISRS were "gas utility projects," the Commission further found that the projects
    were "eligible infrastructure system replacements" under Section 393.1009(3).
    Specifically, the Commission found that the projects did not increase revenues by
    directly connecting to new customers; were in service, used, and useful; were not
    included in Liberty's rate base in its most recent general rate case; and replaced or
    extended the useful life of an existing infrastructure.
    In determining the amount of the ISRS to authorize, the Commission noted that
    Public Counsel did not present any evidence that Staff's adjusted ISRS calculations
    were incorrect and that Public Counsel did not make its own ISRS calculations. The
    Commission also found that Staff's witnesses were more credible than Public Counsel's
    witness regarding the evaluation of Liberty's ISRS request because the testimony of
    Staff's witnesses was more detailed and precise. The Commission, therefore,
    authorized a change to Liberty's ISRS to allow it to recover revenues of $572,662, which
    was the amount proposed in Staff's adjusted ISRS.
    Liberty filed a new ISRS tariffs in compliance with the Commission's order, and
    the Commission approved the tariffs. Public Counsel filed an amended application for
    rehearing, which the Commission denied. Public Counsel appeals.
    STANDARD OF REVIEW
    6
    Appellate review of the Commission's order is limited to determining whether it is
    lawful and reasonable. State ex rel. MoGas Pipeline, LLC v. Pub. Serv. Comm'n, 
    366 S.W.3d 493
    , 495-96 (Mo. banc 2012). An order is lawful if the Commission acted within
    its statutory authority. State ex rel. Sprint Mo., Inc. v. Pub. Serv. Comm'n, 
    165 S.W.3d 160
    , 164 (Mo. banc 2005). The Commission's order "has the presumption of validity."
    
    Id. An order
    is reasonable if it is supported by substantial, competent evidence, it is not
    arbitrary or capricious, and the Commission has not abused its discretion. State ex rel.
    Praxair, Inc. v. Pub. Serv. Comm'n, 
    344 S.W.3d 178
    , 184 (Mo. banc 2011).
    ANALYSIS
    In its sole point on appeal, Public Counsel contends the Commission's order is
    unlawful and unreasonable because it allows Liberty to recover costs through the ISRS
    that are not authorized by the ISRS statutes. Specifically, Public Counsel argues that
    the Commission erred in finding that Liberty's projects replacing pipes that were
    damaged by a third party are "gas utility plant projects" under Section 393.1009(5)(a):
    (a) Mains, valves, service lines, regulator stations, vaults, and other
    pipeline system components installed to comply with state or federal
    safety requirements as replacements for existing facilities that have worn
    out or are in deteriorated condition[.]
    (Emphasis added.) Public Counsel asserts that the Commission erroneously
    interpreted the phrase "are in deteriorated condition" to include pipes that have been
    damaged by third parties. Public Counsel insists that the reference to facilities in
    "deteriorated condition" includes only those facilities whose quality has been gradually
    lowered over time, rather than facilities that have been destroyed or damaged
    immediately through a third party's accident or negligence.
    7
    The interpretation of a statute is a matter of law, which this court reviews de
    novo. 
    Laclede, 417 S.W.3d at 819
    . While the "'interpretation and construction of a
    statute by an agency charged with its administration is entitled to great weight,'" we
    "exercise[ ] independent judgment and must correct erroneous interpretations of law."
    Sprint 
    Mo., 165 S.W.3d at 164
    (quoting Foremost-McKesson, Inc. v. Davis, 
    488 S.W.2d 193
    , 197 (Mo. banc 1972)).
    Our goal in interpreting Section 393.1009(5)(a) is to ascertain the legislature's
    intent from the language used and give effect to that intent, if possible. 
    Laclede, 417 S.W.3d at 820
    . If the legislature's intent is "clear and unambiguous, then we are bound
    by that intent." 
    Id. "We 'look
    beyond the plain meaning of the statute only when the
    language is ambiguous or will lead to an absurd or illogical result.'" 
    Id. (citation omitted).
    In considering whether Section 393.1009(5)(a)'s reference to facilities that "are in
    deteriorated condition" includes those that have been damaged by third parties, we note
    that the term "deteriorated" is not defined in Chapter 393. Where no statutory definition
    exists, we are to give statutory terms "'their plain and ordinary meaning as derived from
    the dictionary.'" MoGas 
    Pipeline, 366 S.W.3d at 498
    (citation omitted).
    The dictionary definition of the term "deteriorate" is: "to make inferior in quality or
    value:   IMPAIR";   "to grow worse"; "become impaired in quality, state, or condition:
    DEGENERATE."        W EBSTER'S THIRD NEW INTERNATIONAL DICTIONARY OF THE ENGLISH
    LANGUAGE UNABRIDGED 616 (1993). Applying this definition to Section 393.1009(5)(a),
    facilities that are in "deteriorated" condition are those that have been made inferior or
    become impaired in quality, state, or value. While the term "deteriorated" may also
    8
    describe diminution or impairment that has occurred gradually over time, as evidenced
    by the alternative meaning "to grow worse," the definition is not restricted to describing
    only diminution or impairment that has occurred over time. Rather, "deteriorated" is
    broadly defined, allowing the Commission latitude in deciding whether costs are
    recoverable under this section.
    Because pipes that have been damaged by a third party are facilities that have
    been made inferior or become impaired in quality, state, or value, they constitute
    facilities that the Commission could have properly determined to be in "deteriorated"
    condition under the plain language of Section 393.1009(5)(a). Therefore, the
    Commission's decision to allow Liberty to recover its costs, through the ISRS, for
    projects replacing such facilities is lawful and reasonable.3 Public Counsel's point is
    denied.
    3
    During oral argument, the issue was raised as to whether allowing Liberty to use the ISRS to recover its
    costs to replace pipes damaged by a third party's or its own employees' negligence would lead to a
    double recovery for Liberty, because either the third party or insurance presumably would compensate
    Liberty for those costs. First, we note that the Commission's decision, and, in turn, this appeal, concern
    only the recovery of costs for damage caused by a third party, not damage caused by Liberty's
    employees. Second, Public Counsel addressed the double recovery issue before the Commission. In its
    response to Public Counsel's concerns, Liberty stated in its post-hearing brief that it credits any
    compensation received from either third parties or insurance to the relevant project number. Liberty
    explained that, if the recovery occurs before an ISRS filing, it is reflected in the ISRS filing. If the recovery
    occurs after the ISRS filing, then it is reflected in the true-up in the rate case. This is consistent with the
    ISRS statutes, which provide that the Commission is not bound by its approval of an ISRS and, during a
    subsequent general rate proceeding, may "undertake to review the prudence of such costs."
    § 393.1015.8. See also § 393.1015.9 (stating that "[n]othing in this section shall be construed as limiting
    the authority of the commission to review and consider infrastructure system replacement costs along
    with other costs during any general rate proceeding of any gas corporation"). Section 393.1015.8 further
    provides that, "[i]n the event the commission disallows, during a subsequent general rate proceeding,
    recovery of costs associated with eligible infrastructure system replacements previously included in an
    ISRS, the gas corporation shall offset its ISRS in the future as necessary to recognize and account for
    any such overcollections." These statutory provisions guard against any double recovery by the gas
    corporation.
    9
    CONCLUSION
    We affirm the Commission's report and order.
    ____________________________________
    LISA WHITE HARDWICK, JUDGE
    ALL CONCUR.