P. M. Bruner Granitoid Co. v. Glencoe Lime & Cement Co. , 169 Mo. App. 295 ( 1912 )


Menu:
  • NORTONI, J.

    This is an appeal from an order of the court awarding plaintiff a new trial. Plain*298tiff’s suit is for injunctive relief. A restraining order is sought against defendant, to the end of preventing it from using a common switch, in part upon plaintiff’s property and in part upon defendant’s property, for purposes which were not' originally contemplated and which operates to impair the rights of plaintiff. After hearing the evidence, the court found the issue for defendant and dismissed the bill. However, it subsequently granted plaintiff a new trial for the reason that it erred in its conclusion that defendant was authorized to use the common switch for the purpose of reaching its property other than that contemplated in the original agreement between the parties with respect to establishing the switch. It is from this order, awarding the new trial to plaintiff, that defendant prosecutes the appeal.

    It appears that about 1889 one Goetz was engaged in the line and cement business and Bruner in the granitoid business. Goetz and Bruner agreed to purchase four lots of ground in the city of St. Louis, which were adjacent, with a view of conducting the business of each on separate lots. In accordance with this agreement, they purchased lots 8, 9, 10 and 11 of a certain city block numbered 2211. By an arrangement between the parties, Bruner took title by deed to lots 8 and 9 and Goetz took title by deed to lots 10 and 11. By a further agreement, Bruner and Goetz constructed the switch involved here along the line between lot 9, which was owned by Bruner, and lot 10, which was owned by Goetz. Each party contributed pro rata to installing the switch along the line which divided their properties, and the major part thereof rested, one-half on Bruner’s property and the other half on that of Goetz. The switch connected with the Missouri Pacific Railroad tracks. It was agreed and understood that the switch should be used in common by Bruner and Goetz in connection with their respective business conducted on the separate lots owned by each, and *299it was so used thereafter. Bruner established his granitoid business upon his property, lots 8 and 9, and in connection therewith erected a stone crusher adjacent to the switch. Goetz established on his property, lots 10 and 11, • his lime and cement business. Both parties used the common switch for the purpose of setting cars in and out in connection with the business of each. The business of each was not extensive at first and it appears that hut about one car a day was sufficient to supply either. Two and a half years after the switch was thus constructed, Goetz extended it to the south and across' the alley to connect with lots 22, 23, 24 and 25, which he occupied in connection with his business. The switch runs north and south. The four lots numbered 8, 9, 10 and 11, lying north of the alley, to which the switch was originally servient under the agreement, are about one hundred, sixty feet in length and, of course, the switch track on this property was about the same length, though there was a slight curve in it across one of the lots owned by Goetz. Subsequently the business of both of these parties was incorporated. The plaintiff here, an incorporated company, succeeded to the rights of Bruner and to the title to lots 8 and 9, while the defendant, Glencoe Lime & Cement Company, incorporated, succeeded to the rights of Goetz and to the title of lots 10 and 11. These two corporations, subsequently formed, succeeded as well to the rights pertaining to the use of the switch. Furthermore the defendant succeeded to the rights of Goetz as to so much of his business as was located on lots 22, 23, 24 and 25 south of the alley and to which the switch track had been extended by him in 1891.

    It appears defendant’s business has increased considerably during the period of time which elapsed, until, in recent years, it has employed the switch for setting in and out three or four cars per day. ‘When defendant sets in or takes out cars over this switch *300in connection with that part of its business located on lots 22, 23, 24 and 25 south of the alley, it becomes necessary for plaintiff to suspend its work and permit cars on the switch track adjacent to lot 9 occupied by it to be removed therefrom, in order that there may be a clear track for the shunting in or taking out of defendant’s ear beyond. Prom this it appears that plaintiff’s business is frequently impeded and interfered with by the act of defendant’s passing cars in and out over the common switch and upon its private property — lots 22, 23, 24 and 25 beyond the alley. It is because of this interference that the injunctive relief is sought, on the theory that the easement originally granted over a portion of plaintiff’s lot through the laying, and pertaining to the use, of the common switch did not contemplate a service to defendant beyond the alley on other property, but instead contemplated only the accommodation of the business of the two parties on the four lots originally purchased — lots 8, 9, 10 and 11 north of the alley.

    After hearing the evidence, the court dismissed the bill and gave judgment for defendant, as though plaintiff’s business was not impaired and its rights were not infringed or interfered with through defendant’s use of the switch for the purpose of setting in and taking out cars quite beyond the original property contemplated in the agreement pertaining to the common switch. But the court concluded, and we believe properly so, that it erred in respect of this matter, and thereafter set the judgment aside and ordered a new trial of the issue.

    On this appeal from the order awarding a new trial, it is first argued by defendant that the record is devoid of evidence tending to prove that the switch was originally installed to serve-the business of the parties located upon lots 8, 9,10 and 11 only, and therefore plaintiff’s suit must fail, for it is said, unless the agreement under which the switch was laid, restricted *301its use as servient to the property of plaintiff’s lots 8 and 9 and the property of defendant — lots 10 and 11 — alone, it is clear that defendant was not imposing an additional burden upon plaintiff’s property by employing the switch in carrying cars over it to its property south of the alley, which is lots 22, 23, 21 and 25. It is true there is no direct evidence to be found in the record touching this matter, but the question was not at issue under the pleadings, for the plaintiff set out this agreement in its petition in plain and concise words, and defendant did not deny it in the answer. The petition avers that the switch was originally laid under an agreement, in part upon the property of Bruner and in part upon the property of Goetz, along the line dividing Bruner’s lot 9 from Goetz’s lot 10, and that the cost of construction was borne equally and paid equally by each of said parties. In this connection, it is averred that, “It was agreed and understood between the said Charles W. Goetz and P. M. Bruner that the said switch should be built upon the said property as the said switch was afterward located and built, and that it should be used exclusively cmcl equally for their business carried on upon said lots and no other.” Here is an express averment, which is material to the issue, that the switch was laid by the parties as servient to the business carried on by the parties on lots 8, 9, 10 and 11, and no other. Besides this, it appears throughout the petition that such was the arrangement under which the common switch was constructed by the parties, and that the business on each of lots 8, 9, 10 and 11 was entitled to an equal use of the switch, but none other.

    Defendant did not deny this averment in its answer in any manner whatever. There is no general denial in the answer, but, on the contrary, it specifically admits that plaintiff has the right to the use of the switch mentioned in the petition and denies only *302that it ever interfered with the use of the switch by plaintiff or interfered with any rights of plaintiff in the switch, or that it has ever threatened to interfere therewith. This being true, the averment in the petition concerning the agreement under which the switch was laid is admitted, for the statute provides that every material allegation of the petition not controverted by the.answer shall, for the purposes of the case, be taken as true. [See sec. 1830, R. S. 1909.] The averments of the petition touching this matter were material and, as they were not denied, are to be treated identically as though they were established by the .evidence. It was unnecessary to introduce proof touching these matters which were admitted on the record, and it would have been superfluous to do so. [See Marshall v. Thames, etc. Ins. Co., 43 Mo. 586; State ex rel. v. Henderson, 86 Mo. App. 482, 488.] It must therefore be taken as conceded, and, indeed, the case does concede, that the switch was originally laid in 1889 under an agreement between the adjacent owners which constituted it a common switch for the use of the business of the two conducted on lots 8, 9, 10 and 11, and none other. By this oral agreement, an easement was established along the portion of lot 9 occupied by the switch, owned by plaintiff’s predecessor in title, in favor of defendant and its predecessor in title, servient to lots 10 and 11 now owned by defendant. And an easement was likewise established in favor of plaintiff along that portion of lot 10 occupied by the switch, owned by defendant and its predecessor in title, servient to lots 8 and 9, owned by plaintiff and its predecessor in title. Beyond this the easement does not obtain, unless it has been acquired through prescription.

    It appears that defendant’s business has considerably increased in volume in recent years, and, therefore, instead of setting one car a day upon the switch, it now passes in and out as many as four. These cars *303are principally passed over the switch as originally constructed beyond the alley over the extension constructed by Groetz in 1891 and upon lots 22, 23, 24 and 25. As it is necessary to pass all the cars to the lots beyond the alley over the switch as first constructed, this operates to impede and interfere with plaintiff’s business. It is said that every time a car is passed by defendant over the track to the lots beyond the alley, plaintiff’s car adjacent to its stone crusher on lots 8 and 9 must be moved out, in order to make the way clear. While this moving of cars is done, the work of plaintiff’s plant must frequently suspend until the car, which its men are engaged in loading or unloading, is reset in position. No one can doubt that such an operation impedes and interferes with plaintiff’s business, and furthermore it casts an additional burden upon plaintiff’s estate, for, under the original agreement, its lots 8 and 9 were in no respect servient to lots 22, 23, 24 and 25 of defendant, which are located beyond the alley.

    But it is said that, though such be true, it appears defendant has acquired a prescriptive right through the long years of user of the switch since the' summer of 1891, in passing cars over the same and upon lots 22, 23, 24 and 25 beyond the alley. Defendant introduced no evidence whatever at the trial, and the prescriptive right from user must be found, if at all, in the evidence given for plaintiff. We discover nothing in the record to sustain this argument. In order to establish a prescriptive right there must appear, first, a user for a period at least equal to that of the Statute of Limitations in cases at law; second, that .the user was adverse; third, that it was under a claim of right; and, fourth, notice to the owner of the user and of its character and of the claim of right. A mere permissive use will not suffice. [Anthony v. Kennard Bldg. Co., 188 Mo. 704, 87 S. W. 921.] There can be no doubt that defendant and its predecessor have used the *304switch since 1891 for a purpose quite beyond that contemplated by plaintiff’s predecessor in title in the original grant and that plaintiff and its predecessor possessed full knowledge during all of the years touching the user, but there is naught in the case suggesting this use was an adverse one. Indeed, all of the circumstances suggest the contrary. It is true that, where the use of an easement has continued for the prescriptive period unexplained, it will be presumed to have been adverse in some cases; but this presumption does not obtain if the use is of such a character or the circumstances attending it are such as to show that it was a mere privilege enjoyed by leave of the owner. [See 22 Am. & Eng. Ency. Law (2 Ed.), 1202; Washburn’s Easements (4 Ed.), 156.]

    If this were a case where defendant and its predecessor used the switch for all those years and plaintiff and its predecessor suffered it without making any use of the switch on their own part, the presumption would be.highly influential here. However this may be,, it is of slight importance in the circumstances attending the situation and the use, for it appears plaintiff and its predecessor used the switch all of the time in connection with its business. The use of defendant and its predecessor in passing, cars over the switch to the lots beyond the extent of the easement for many years did not interfere with plaintiff’s rights in the least, and it was therefore but neighborly to permit it. It appears to have been only recently that defendant’s business has expanded until the extra user or burden imposed by it upon plaintiff’s estate has become of such proportions as to materially interfere with its business. Because of tins, it is sought to revoke the permit theretofore enjoyed. It seems to be the generally accepted rule in cases such as this, where both the owner and another use the way and it appears that the use of the other person in no manner interferes with that of the owner or injures the road, that *305the courts will treat such use as permissive only and not sufficient, in the absence of a more positive and direct showing, to establish the claim of adverse user. On this question our own Supreme Court has recently said in Anthony v. Kennard, 188 Mo. 704, 724, 87 S. W. 921: “But if the owner of the land opens a road across it for his own use and uses it and keeps it open for his own use, the fact that he sees his neighbor also making use of it, under circumstances that in no way injures the road or interferes with his own use of it, does not justify the inference that he is yielding 'to his neighbor’s claim of right or that his neighbor is asserting any right; it signifies only that he is permitting his neighbor to use the road.” It is said in such cases the use of a way by others does not necessarily import adverse user under a claim of right and exclusive within the meaning of that term; but from the fact that it is kept open and used by the owner for his own purposes, it is to be inferred rather that the use by others is by his consent and permission. [See Wood v. Reed, 30 N. Y. Supp. 112.]

    There is not a suggestion in the record that defendant or its predecessor in title ever asserted any adverse claim of right with respect to the use of this switch, and the entire proposition depends upon the mere fact that it was permitted to use it at a time when such use in no manner interfered with the rights of plaintiff or its predecessor who was all of the time using the switch in its own business as well. Obviously the presumption of adverse user may not arise amid facts and circumstances thus appearing, for such facts and circumstances attending the use are sufficiently strong to repel it, in that they suggest a mere permission.

    The court did not err in awarding plaintiff a new trial. The judgment should be affirmed and the cause *306remanded for further proceedings. It is so ordered.

    Reynolds, P. J., and Caulfield, J., concur.

Document Info

Citation Numbers: 169 Mo. App. 295

Judges: Caulfield, Nortoni, Reynolds

Filed Date: 12/31/1912

Precedential Status: Precedential

Modified Date: 10/16/2022