State of Missouri, Ex Rel., Eric S. Schmitt, Attorney General and Missouri Department of Natural Resources v. Zill, Inc. ( 2020 )


Menu:
  •          IN THE MISSOURI COURT OF APPEALS
    WESTERN DISTRICT
    STATE OF MISSOURI, EX REL.,                  )
    ERIC S. SCHMITT, ATTORNEY                    )
    GENERAL AND MISSOURI                         )
    DEPARTMENT OF NATURAL                        )
    RESOURCES,                                   )
    )
    Appellant,                    )
    )
    v.                                           )          WD82850
    )
    ZILL, INC.,                                  )          Opinion filed: June 9, 2020
    )
    Respondent.                   )
    APPEAL FROM THE CIRCUIT COURT OF JACKSON COUNTY, MISSOURI
    THE HONORABLE SANDRA MIDKIFF, JUDGE
    Division Three: Anthony Rex Gabbert, Presiding Judge,
    Edward R. Ardini, Jr., Judge and W. Douglas Thomson, Judge
    The Missouri Department of Natural Resources (“DNR”) appeals the judgment of the
    Circuit Court of Jackson County denying injunctive relief and civil penalties in a lawsuit brought
    by DNR against Zill, LLC (“Zill”), the owner and operator of a gas station in Kansas City, for an
    alleged petroleum spill. Finding no error, we affirm.
    Factual and Procedural Background
    In January 2015, residents living near 31st Street and Cleveland Avenue in Kansas City,
    Missouri, complained of a strong odor of petroleum vapors in their homes. DNR investigated and
    found the presence of liquid petroleum in the sewer lines. After excavating the area, crews removed
    50-to-100 gallons of petroleum. DNR suspected that the source of the petroleum was Inner City
    Oil, a nearby gas station owned and operated by Zill.1 DNR issued a Declaration of Hazardous
    Substance Emergency (“Declaration”) to Zill, which instructed Zill to take remediation measures
    to stop the spill, abate the vapors in the nearby homes, and clean up the spilled petroleum.
    Upon receiving the Declaration, Zill attempted to work with DNR by hiring a consultant
    to conduct tank tightness tests, site characterizations, and other remediation activities as requested
    by DNR.
    DNR dug monitoring wells2 near Zill’s gas station and the Cleveland Avenue homes, and,
    upon testing the wells, DNR found petroleum present in several of them, including wells located
    on Zill’s property. DNR also determined that the electronic monitoring system for Zill’s
    underground storage tanks indicated a leak. Based on this information, DNR sued Zill, seeking, in
    Count I, injunctive relief for failing to abate the hazardous substance emergency; in Count II,
    reimbursement for cleaning the spilled petroleum; and, in Count III, injunctive relief and civil
    penalties for violation of the Underground Storage Tank Release Abatement regulations.3
    After DNR filed suit, a technician employed by the manufacturer of Zill’s underground
    storage tanks inspected the tanks and found a pinhole leak in one tank. The technician repaired the
    leak and concluded that leaked fuel had not escaped the outer rib of the tank. Based on this
    1
    DNR’s suspicion that Zill was the cause of the spill was based on a 2006 spill at the same gas station. In 2006, DNR
    performed a surface resistivity geophysical survey, which revealed that there was a fracture in the bedrock between
    Zill’s gas station and the homes on Cleveland Avenue. A surface resistivity geophysical survey uses electrical currents
    to determine the resistance of the subsurface of the earth.
    2
    Monitoring wells consist of pipes placed into the ground with screens where ground water and possible contaminants
    can pass through. These wells allow DNR to monitor the ground water for any contaminants.
    3
    DNR’s petition included additional claims that were dismissed before trial and are not relevant to this appeal.
    Counts I and III of DNR’s lawsuit were tried to the trial court while Count II was tried to a jury.
    2
    information, Zill provided inspection and site characterization reports to DNR and denied that it
    was the source of the petroleum in the sewer lines.
    At trial, DNR presented evidence that an underground storage tank at Zill’s gas station had
    a leak, that the geography at the gas station would cause released petroleum to migrate towards
    the affected homes, and that DNR did not believe the spilled petroleum could have come from an
    alternative source.
    Zill presented expert testimony showing that the petroleum found in the monitoring wells
    contained lead and MTBE and was degraded such that it could not have been released from Zill’s
    gas station during the time Zill owned the station.4 Zill also presented evidence showing that the
    geography of its gas station, which sits in a bowl at the top of a hill, would not have allowed for
    petroleum released from its tanks to flow toward the homes on Cleveland Avenue. Zill’s expert,
    therefore, concluded that the petroleum found by DNR originated from another source.
    The jury unanimously found that Zill was not responsible for the cleanup costs related to
    the spill (Count II),5 and the trial court entered its judgment on Counts I and III in favor of Zill.
    DNR appeals. Additional facts will be discussed throughout this opinion.
    Discussion
    DNR raises three points on appeal. In its first two points, DNR alleges that the trial court
    misapplied the law in denying DNR the injunctive relief it sought in Counts I and III. In Point III,
    DNR asserts that the trial court erred in granting Zill’s motion for directed verdict on DNR’s claim
    for civil penalties under Count III of its amended petition. We find no error.
    4
    Zill purchased the gas station in 2003. Leaded gasoline was outlawed in 1973, and MTBE, a gasoline additive, was
    banned in Kansas City in 2002.
    5
    DNR does not appeal the jury verdict on Count II.
    3
    Points I & II
    In Point I, DNR alleges that the trial court erred in finding Zill not liable for the petroleum
    spill, arguing that the trial court misapplied the law by requiring DNR to prove that Zill was the
    sole source of contamination involved in the hazardous substance emergency. In Point II, DNR
    claims that the trial court erred in denying its request for injunctive relief pursuant to the
    Underground Storage Tank Release Abatement regulations, arguing that the trial court misapplied
    the law by considering only portions of the regulations DNR alleged Zill violated and by conflating
    Counts I and III in DNR’s amended petition. Because both of these points allege the trial court
    misapplied the law, we address them together.
    Standard of Review
    “The judgment of the trial court in a court-tried civil case will be sustained ‘unless there is
    no substantial evidence to support it, unless it is against the weight of the evidence, unless it
    erroneously declares the law, or unless it erroneously applies the law.” Swallow Tail, LLC v. Mo.
    Dep’t of Conservation, 
    522 S.W.3d 309
    , 314 (Mo. App. W.D. 2017) (quoting Murphy v. Carron,
    
    536 S.W.2d 30
    , 32 (Mo. banc 1976)). “A claim that the judgment erroneously declares or applies
    the law, [ ] involves review of the propriety of the trial court’s construction and application of the
    law.” Pearson v. Koster, 
    367 S.W.3d 36
    , 43 (Mo. banc 2012) (citing White v. Dir. of Revenue, 
    321 S.W.3d 298
    , 308 (Mo. banc 2010)). “This Court applies de novo review to questions of law decided
    in court-tried cases.”
    Id. (citing StopAquila.org
    v. City of Peculiar, 
    208 S.W.3d 895
    , 899 (Mo.
    banc 2006)).
    Point I
    In Point I, DNR claims that the trial court erroneously applied the law by “requir[ing] DNR
    to prove Zill was the source of all the contamination identified in the area, when the [statute] only
    4
    required DNR to prove that Zill’s hazardous substance was involved in the hazardous substance
    emergency.”
    In its judgment denying DNR injunctive relief, the trial court made the following relevant
    findings:
    37. This court finds there was no credible evidence to establish by a preponderance
    of the evidence that a release from Zill’s gas storage tank(s) was the cause of the
    leak of free-floating petroleum product observed by [DNR] in January, 2015.
    ...
    44. Plaintiffs alleged, but failed to prove by a preponderance of the evidence, that
    a release of more than fifty gallons of liquid petroleum product was released from
    Zill’s underground tanks or property at any relevant time prior to January, 2015.
    There was no credible evidence that Zill’s underground tank or stored petroleum
    product was the source of the free-floating petroleum product observed by [DNR]
    in January, 2015.
    45. There was no credible evidence to establish by a preponderance of the evidence
    that the prior release from Zill’s land in 2006 was the source of the free petroleum
    product that appeared in the lateral and main sewer line or in the excavation hole at
    30th and Cleveland in January, 2015.
    46. There is no credible evidence to establish by a preponderance of the evidence
    that Zill’s property, land, storage tanks or stored petroleum was the source of
    petroleum product or vapors reported on the west side of Cleveland in 2014, 2015
    or 2016.
    The Hazardous Substance Cleanup statute provides that DNR “[m]ay require the person
    having control over a hazardous substance involved in a hazardous substance emergency to clean
    up the hazardous substance and take any reasonable actions necessary to end a hazardous substance
    emergency[.]” § 260.510(2), RSMo.6 A “hazardous substance emergency” is defined as “[a]ny
    release of petroleum . . . in excess of fifty gallons[.]” § 260.500(6)(b), RSMo. A “person having
    control over a hazardous substance” includes “any person . . . storing, . . . a hazardous substance
    6
    Statutory references are to the Missouri Revised Statutes 2010, updated through the 2014 supplement.
    5
    when a hazardous substance emergency occurs[.]” § 260.500(8), RSMo. “Release” is defined as
    “any threatened or real emission, discharge, spillage, leakage, pumping, pouring, emptying or
    dumping of a substance into or onto the land, air or waters of the state . . . unless the substance is
    confined and is expected to stay confined to property owned, leased or otherwise controlled by the
    person having control over the substance[.]” § 260.500(9), RSMo.
    DNR argues in Point I that the trial court improperly increased DNR’s burden by requiring
    it to show that Zill was the only source of the contamination found in the area of the Cleveland
    Avenue homes. We agree with DNR that it is not necessary for the agency to prove that a defendant
    was the sole source of all of the hazardous substances involved in a hazardous substance
    emergency. However, we reject DNR’s view that the trial court applied a different legal standard.7
    Indeed, a review of the judgment makes clear that the trial court’s ruling in favor of Zill was not
    the product of a misplaced view that DNR was required to establish that Zill was solely responsible
    for all of the released petroleum found in the impacted area but rather was based on its
    determination that DNR had failed to establish that Zill was responsible for any of the petroleum
    involved in the hazardous substance emergency.8 In so doing, the trial court properly applied the
    law.
    7
    DNR focuses on a comment made by the trial court during a break in the trial after DNR had presented its evidence
    when the trial court noted, “I think it is clearly established in State’s evidence that there was a release, that does not
    appear to be, has not been disputed or in any way denied.” However, DNR takes this statement out of context as the
    comment was made while the parties debated the extent of the evidence Zill could present in its defense. Zill later
    presented evidence that the release had not originated from its property. Further, “‘[o]ur review is ordinarily limited
    to the written judgment and does not extend to oral comments made by the trial court, which are not part of the
    judgment.’” Noble v. Noble, 
    456 S.W.3d 120
    , 128 (Mo. App. W.D. 2015) (quoting Harvey v. Dir. of Revenue, 
    371 S.W.3d 824
    , 826 (Mo. App. W.D. 2012)).
    8
    DNR heavily focuses its argument on the evidence it presented at trial. We note that DNR does not assert an against-
    the-weight-of-the-evidence challenge or argue that there was not substantial evidence supporting the trial court’s
    findings. Moreover, even if it had made such challenges, “‘[i]n reaching its judgment the trial court is free to believe
    any, all, or none of the evidence presented at trial.’” Brady v. Starke, 
    517 S.W.3d 28
    , 35 (Mo. App. W.D. 2017)
    (quoting Hunter v. Moore, 
    486 S.W.3d 919
    , 925 (Mo. banc 2016)). Here, the trial court clearly concluded that DNR
    had failed to present sufficient evidence to establish that Zill’s petroleum was involved in the hazardous substance
    emergency.
    6
    Point I denied.
    Point II
    In Point II, DNR alleges that the trial court erred in denying the injunctive relief it sought
    against Zill in Count III for violating the regulations pertaining to underground storage tanks,
    arguing that the trial court erroneously applied the law by “focus[ing] only on part of the regulatory
    requirements Zill was alleged to have violated and conflat[ing] Counts I and III in DNR’s
    Amended Petition.”
    Count I of DNR’s amended petition sought injunctive relief based on the allegation that
    Zill failed to complete abatement measures related to the hazardous substance emergency. Count
    III, on the other hand, sought injunctive relief and civil penalties based on alleged violations of the
    Underground Storage Tank Release Abatement and Investigation regulations set out in 10 CSR
    26-2.050 through 10 CSR 26-2.075,9 which were alleged to include failing to conduct a tank
    tightness test; failing to prevent further release of petroleum into the environment; and failing to
    take certain initial abatement steps, including the submission of certain reports to DNR.
    “To be entitled to an injunction, a party must demonstrate: 1) no adequate remedy at law;
    and 2) irreparable harm will result if the injunction is not awarded.” Zoological Park Subdist. of
    the Metro. Park Museum Dist. v. Smith, 
    561 S.W.3d 893
    , 896 (Mo. App. E.D. 2018) (citing
    Beauchamp v. Monarch Fire Prot. Dist., 
    471 S.W.3d 805
    , 813 (Mo. App. E.D. 2015)). Moreover,
    injunctive relief is only available to require a party “to do or to refrain from doing a particular
    thing.” Comm’n Row Club v. Lambert, 
    161 S.W.2d 732
    , 736 (Mo. App. E.D. 1942) (citation
    omitted); see also 
    Smith, 561 S.W.3d at 896
    (citation omitted) (“The purpose of an injunction is to
    prevent actual or threatened acts that constitute real injury.”). Thus, DNR was entitled to seek
    9
    CSR citations are to the Missouri Code of State Regulations, effective December 30, 2011.
    7
    injunctive relief against Zill only for those statutory or regulatory violations that were still
    occurring at the time of trial.
    DNR’s amended petition alleged four continuing violations: (1) “From July 15, 2015, to
    the present, Zill failed to submit a report to the Department summarizing the initial abatement steps
    taken;” (2) “From July 15, 2015, to the present, Zill has failed to provide data on the estimated
    quantity of the release;” (3) “From July 15, 2015, to the present, Zill failed to provide information
    on the surrounding population, subsurface soil conditions, location of subsurface sewers,
    climatological conditions and land use;” and (4) “From July 15, 2015, to the present, Zill failed to
    submit information to [DNR] collected to characterize the release.” As a result, the trial court
    properly focused on these four ongoing claims when it considered granting injunctive relief and
    disregarded allegations relating to past violations that had been resolved. See Williams v. Williams,
    
    99 S.W.3d 552
    , 560 (Mo. App. W.D. 2003) (quoting Metts v. City of Pine Lawn, 
    84 S.W.3d 106
    ,
    109 (Mo. App. E.D. 2002); Fugel v. Becker, 
    2 S.W.2d 743
    (Mo. 1928)) (“Since the purpose of an
    injunction is not to afford a remedy for what is past but to prevent future mischief, not being used
    for the purpose of punishment or to compel persons to do right but merely to prevent them from
    doing wrong, rights already lost and wrongs already perpetrated cannot be corrected by injunction,
    and the party aggrieved must seek some other remedy for redress[.]”).
    In support of its claims of ongoing violations of the underground storage tank regulations,
    DNR presented the testimony of one of its former environmental scientists, who had been the
    project manager overseeing Zill’s site. This witness testified that Zill had not timely completed
    many of the items required in the regulations, had failed to complete the site characterization10
    10
    A site characterization under the regulations includes “information about the site and the nature of the release,
    including information gained while confirming the release or completing the initial abatement measures[.]”
    8
    mandated by 10 CSR 26-2.074,11 and had not recovered all of the spilled petroleum practicable as
    required by 10 CSR 26-2.075. However, the environmental scientist acknowledged that she had
    retired in April 2017 and did not know what had been completed by Zill after that date.12
    Significantly, the individual who assumed the role of project manager upon his predecessor’s
    retirement did not testify at trial, and DNR submitted no additional evidence in support of Count
    III.
    In denying injunctive relief, the trial court found that DNR “ha[s] not established by a
    preponderance of the evidence what, if any additional abatement procedure or site characterization
    work is required of Defendant Zill.” The trial court further found that “[t]here is no credible
    evidence from DNR that the reports of Defendant Zill, through its retained consultants, were
    insufficient to satisfy the regulatory requirements” and that DNR’s “claim for injunctive relief
    entirely fails to meet its burden by a preponderance of the evidence[.]”
    The trial court did not misapply the law by denying DNR’s claims for injunctive relief on
    the alleged ongoing violations, nor did it conflate the claims in Count I with those in Count III.
    Rather, the trial court found that DNR failed to put forth sufficient evidence to meet its burden of
    establishing that there were reports or data required by the regulations that Zill had failed to provide
    to DNR. Thus, we do not find that the trial court misapplied the law in denying DNR the injunctive
    relief that it sought under Count III.
    Point II denied.
    11
    The environmental specialist admitted on cross-examination that Zill submitted site characterization reports in 2015,
    but she could not say whether DNR responded.
    12
    Trial was held in January 2018.
    9
    Point III
    In Point III, DNR claims that the trial court erred in granting Zill’s request for a directed
    verdict denying DNR’s request for civil penalties.
    At the close of all of the evidence, Zill moved for a directed verdict, arguing that (1) the
    statute authorizing the imposition of civil penalties requires that the owner or operator of an
    underground storage tank violate an order issued by DNR, and (2) DNR had not issued such an
    order to Zill. The trial court agreed.
    Our review of a court-tried case is governed by the principles set forth in Murphy v. Carron,
    
    536 S.W.2d 30
    , 32 (Mo. banc 1976).13 See City of St. Louis v. Riverside Waste Mgmt., L.L.C., 
    73 S.W.3d 794
    , 796 (Mo. App. E.D. 2002). We will affirm the judgment of the trial court “unless
    there is no substantial evidence to support it, unless it is against the weight of the evidence, unless
    it erroneously declares the law, or unless it erroneously applies the law.” 
    Murphy, 536 S.W.2d at 32
    . “For factual disputes, the evidence and all reasonable inferences from the evidence are ‘viewed
    in the light most favorable to the trial court’s judgment, and all contrary evidence and inferences
    must be disregarded.’” B.K. v. Mo. State Hwy. Patrol, 
    561 S.W.3d 876
    , 879 (Mo. App. W.D. 2018)
    (quoting Miller v. Gammon & Sons, Inc., 
    67 S.W.3d 613
    , 618 (Mo. App. W.D. 2001)). “‘Statutory
    interpretation is an issue of law that this Court reviews de novo’”
    Id. (quoting Finnegan
    v. Old
    Republic Title Co. of St. Louis, 
    246 S.W.3d 928
    , 930 (Mo. banc 2008)).
    DNR argues that “the trial court focused only on § 319.127, RSMo, and erroneously
    concluded that § 319.127, RSMo, authorizes civil penalties only when the responsible party fails
    13
    We understand that DNR appeals from the trial court’s grant of Zill’s motion for a directed verdict. “In a bench
    trial, however, there is no jury verdict to direct, so such a motion was improper.” BMJ Partners v. King’s Beauty
    Distrib. Co., 
    508 S.W.3d 175
    , 177 n.2 (Mo. App. E.D. 2016) (citation omitted). Instead, we construe it as a motion
    for judgment.
    Id. On appeal,
    we apply the standard of review applicable to a court-tried case.
    10
    to comply with an order and absent an order, no request for civil penalties lie, in that Count III
    requested civil penalties under §§ 319.139 and 319.127, RSMo, both of which authorize DNR to
    commence a civil action for appropriate relief including civil penalties regardless of whether DNR
    issued an order.”
    DNR’s interpretation of these statutes is incorrect.14 In order to obtain civil penalties for
    violations of the underground petroleum storage tank regulations under section 319.127, RSMo,
    DNR must first issue an order to the alleged violator of the regulations.15
    Under section 319.127.1, RSMo, “[e]xcept as provided in this section, whenever on the
    basis of any information, [DNR] determines that any person is in such violation, [DNR] may issue
    an order requiring compliance within a reasonable specified time period, pursuant to chapter 260,
    or [DNR] may commence a civil action in a court of competent jurisdiction in which the violation
    occurred for appropriate relief, including a temporary or permanent injunction.” This provision
    does not require DNR to issue an order prior to commencing a civil action in a circuit court seeking
    “appropriate relief, including a temporary or permanent injunction.”
    14
    DNR’s reliance on section 319.139, RSMo is misplaced. Section 319.139 provides that, under certain circumstances,
    “the director [of DNR] may issue an order assessing an administrative penalty upon the violator under this section.”
    There is no evidence that the director of DNR issued an order to Zill under this provision or otherwise attempted to
    assess administrative penalties in this matter. Nevertheless, DNR argues that section 319.139.5, which provides that
    “[t]he state may elect to assess an administrative penalty, or, in lieu thereof, to request that the attorney general or
    prosecutor file an appropriate legal action seeking a civil penalty in the appropriate circuit court[,]” vests it with stand-
    alone authority to pursue a civil penalty, untethered to the requirements of any other provision, and in the absence of
    any order issued by the director of DNR. We do not assign such a sweeping interpretation to this isolated provision.
    Instead, we find that section 319.139.5 simply confirms that DNR may request the filing of “an appropriate legal
    action seeking a civil penalty[ ]” as an alternative to pursuing an administrative penalty under section 319.139. Under
    these facts, such “an appropriate legal action seeking a civil penalty” would be brought under section 319.127. This
    interplay between section 319.139 (administrative penalties) and section 319.127 (civil penalties) is further validated
    by section 319.127.2 which states that “[a] civil monetary penalty under this section shall not be assessed for a
    violation where an administrative penalty was assessed under section 319.139.” Finally, as 
    discussed supra
    , an action
    for civil penalties under section 319.127 requires an order to have been issued by DNR.
    15
    DNR makes no argument on appeal that the declaration it issued to Zill constituted an order.
    11
    However, the following subsection provides that “[i]f an owner or operator fails to comply
    with an order under this section within the time specified, the department may commence a civil
    action in a court of competent jurisdiction for injunctive relief to prevent any such violation or
    further violation or for the assessment of a civil penalty not to exceed ten thousand dollars for each
    day, or part thereof, the violation occurred or continues to occur, or both as the court deems
    proper.” § 319.127.2, RSMo. Under the plain language of this subsection, the assessment of civil
    penalties springs only from the failure of an owner or operator of an underground storage tank to
    comply with an order issued by DNR under section 319.127.1, RSMo. Because DNR issued no
    such order to Zill, the statutorily imposed condition precedent for assessing civil penalties was
    lacking.
    Despite the clear requirement found in section 319.217.2, RSMo, that civil penalties are
    only available for violation of an order issued by DNR, DNR argues that section 319.127.1, RSMo,
    independently “authorizes DNR to seek a civil penalty as a form of ‘appropriate relief’” in the
    absence of such an order. This wholly ignores the requirements of section 319.127.2, RSMo, which
    plainly limits the assessment of civil penalties to those instances where a party has violated an
    order issued by DNR.
    “[T]here can be no doubt that a penal statute must be strictly construed and that a penalty
    may not be created by the construction of a statute but the penalty must clearly appear to have been
    intended to be created by the Legislature.” State ex rel. Danforth v. European Health Spa, Inc.,
    
    611 S.W.2d 259
    , 262 (Mo. App. W.D. 1980); see also City of Charleston ex rel. Brady v.
    McCutcheon, 
    227 S.W.2d 736
    , 738 (Mo. banc 1950) (additional citations omitted) (“Penal
    provisions of a statute, or of a statute penal in nature are always strictly construed, and can be
    given no broader application than is warranted by its plain and unambiguous terms.”). Thus, we
    12
    cannot construe the phrase “appropriate relief” found in section 319.127.1, RSMo, to authorize the
    assessment of civil penalties under circumstances in direct contradiction to the clear and
    unambiguous requirements established by the legislature in the subsequent subsection. Since
    section 319.127.2, RSMo, only permits civil penalties to be assessed for violations of an order
    issued by DNR and, in this case, DNR did not issue such an order to Zill, the trial court did not err
    in ruling in Zill’s favor on DNR’s request for civil penalties.
    Point III denied.
    Conclusion
    The judgment of the trial court is affirmed.
    __________________________________________
    EDWARD R. ARDINI, JR., JUDGE
    All concur.
    13