four-star-enterprises-equipment-inc-rgh-llc-and-county-of ( 2014 )


Menu:
  • FOUR STAR ENTERPRISES              )
    EQUIPMENT, INC., RGH, LLC,         )
    )
    Plaintiffs-Appellants, )
    )
    AND COUNTY OF GREENE/GREENE )
    COUNTY COMMISSION, EX REL, AND )
    FOR THE USE AND BENEFIT OF FOUR )
    STAR ENTERPRISES EQUIPMENT,        )
    INC., AND RGH, LLC,                )
    )
    Plaintiffs,            )
    )
    vs.                         )                           No. SD32781
    )                           Filed: December 9, 2014
    EMPLOYERS MUTUAL CASUALTY          )
    COMPANY,                           )
    )
    Defendant-Respondent.  )
    APPEAL FROM THE CIRCUIT COURT OF GREENE COUNTY
    Honorable J. Dan Conklin, Circuit Judge
    Before Sheffield, P.J., Rahmeyer, J., and Lynch, J.
    REVERSED AND REMANDED WITH DIRECTIONS
    PER CURIAM. This case involving section 107.1701 comes to us on a $20,000
    claim, with two separate lawsuits and seventeen years of litigation. Under section
    107.170, “[s]tatutory payment bonds shift the ultimate risk of nonpayment from [eligible]
    1
    All statutory references are to RSMo Cum. Supp. 1995.
    1
    workman and suppliers to the surety on public work projects,” and offer eligible “laborers
    and materialmen some assurance of payment.” City of Kansas City, Missouri ex rel.
    Lafarge North America Inc. v. Ace Pipe Cleaning, Inc., 
    349 S.W.3d 399
    , 403-04
    (Mo.App. W.D. 2011). In Missouri, public property “is protected from,” and “cannot be
    encumbered by,” mechanic’s liens. 
    Id. Four Star
    Enterprises Equipment, Inc. (“Four
    Star”)2 claims it rented equipment to a subcontractor on a public work project and, as a
    result, was eligible to seek recovery under the general contractor’s section 107.170
    statutory payment bond for items covered by the bond. 
    Id. at 404-07.
    Four Star obtained
    a default judgment against the subcontractor, and then filed suit against Employers
    Mutual Casualty Company (“EMC”), the surety for the statutory payment bond.
    The trial court, however, denied Four Star’s claim for collection of the judgment. We
    reverse and remand.
    Factual and Procedural Background
    From what can be gleaned from the record, Four Star sold and rented equipment
    – “mainly” construction equipment. The underlying cause of action began when Four
    Star leased construction equipment to Fred and Mark Townlian doing business as T & T
    Construction (collectively, “T & T” or “Subcontractor”), which Four Star alleged was for
    use on Greene County’s Plainview Road project. D & E Plumbing and Heating, Inc. (“D
    & E” or “General Contractor”) was the general contractor for the project and hired T &
    T. As required by section 107.170, D & E issued a payment bond for the road project
    with EMC as surety. T & T did not fully pay Four Star for the rental of the equipment.
    2
    Four Star assigned its claim to the appellant RGH, LLC, midway through litigation in the lower court.
    For purposes of our analysis in this appeal, any distinction is irrelevant. For clarity, we simply refer to the
    appellant as “Four Star.”
    2
    In May 1997, Four Star sued T & T, D & E, and EMC to recover payment for rental of
    the equipment. All three defendants were served with a summons.
    Subcontractor did not appear or file an answer. General Contractor and EMC
    appeared, filed and argued several motions, and engaged in discovery before filing
    answers in June 2003. After General Contractor and EMC filed answers in June 2003,
    Four Star3 filed an affidavit of Fred Townlian and an affidavit of a representative of Four
    Star that same month. After filing answers, General Contractor and EMC also requested
    and were granted two changes of judge, engaged in further discovery, and requested and
    were granted at least one continuance of trial.
    On September 1, 2005, the case was set for trial before a jury on November 21,
    2005. At Four Star’s request, and apparently without any advance notice to D & E or
    EMC, the trial court then entered a default judgment in favor of Four Star against
    Subcontractor on November 16, 2005. Two days later, Four Star voluntarily dismissed D
    & E and EMC from the suit without prejudice, making the default judgment final. The
    default judgment remains in effect as it was not appealed and has not been set aside.
    The November 16, 2005 docket entry states, “Formal judgment is signed and
    filed.” The judgment itself is entitled “Judgment,” is signed by the trial court, is dated
    November 16, 2005, and entered judgment in favor of Four Star against Subcontractor in
    the amount of $18,873.18 for the “unpaid principal” attributable to Subcontractor’s rental
    of a 553 Gehl forklift and bucket used on the Plainview Road project from September 17,
    1996 through January 17, 1997, $29,725.26 for accrued interest from February 21, 1997,
    and $4,000 for attorney’s fees. The judgment also indicates that the “evidence adduced”
    3
    On June 1, 1999, Four Star assigned its claim against Subcontractor to RGH, LLC, and Four Star then
    merged into an unrelated corporation.
    3
    included the “affidavits” of Fred Townlian and a Four Star representative, and the
    “admissions” of Fred Townlian. The docket sheet for the case shows that a copy of the
    docket sheet was mailed to counsel for General Contractor and EMC on November 16,
    2005.
    Subsequently, in September 2006, RGH, LLC, and Four Star filed suit against
    EMC to: (1) collect the default judgment under the statutory payment bond issued by
    General Contractor for Greene County’s Plainview Road project and for which EMC was
    surety (Count I), and (2) recover additional damages for “vexatious[] refus[al] to pay” the
    default judgment pursuant to sections 375.296 and 375.420 (Count II).
    Four Star’s evidence tended to show that Four Star rented a Gehl forklift and
    bucket to Subcontractor that Subcontractor used on Greene County’s Plainview Road
    project from September 17, 1996 through January 17, 1997, but did not fully pay Four
    Star the amount owed under the rental agreement. EMC’s evidence tended to show that
    General Contractor terminated Subcontractor before September 17, 1996, and that
    Subcontractor did not perform any work on the Plainview Road project after being
    terminated. At trial, counsel for EMC acknowledged that the earlier lawsuit that gave
    rise to the default judgment was “very similar to this lawsuit, same parties, same set of
    facts.” The statutory payment bond issued by General Contractor, and for which EMC
    was surety, was admitted by agreement of the parties.
    At trial, EMC steadfastly objected to certain documents offered into evidence by
    Four Star. Although the trial court noted those objections, all documents offered by Four
    Star during trial were admitted into evidence. Before trial, Four Star requested that the
    4
    trial court issue “specific findings as to any reason or basis for the denial of any portion
    of [Four Star’s] bond claim.”
    More than a year after the trial concluded, the trial court adopted verbatim the
    forty-three pages of EMC’s proposed findings and incorporated those findings into its
    judgment denying both of Four Star’s claims. The judgment reversed numerous
    evidentiary rulings made during the trial admitting documents offered by Four Star and
    excluded those documents from evidence and consideration by the trial court in arriving
    at its judgment. Four Star now appeals this judgment.
    Four Star raises six claims on appeal: (1) The trial court failed to comply with
    Four Star’s Rule 73.014 request for findings of fact; (2) The trial court erroneously
    declared the law of a surety’s liability under a statutory payment bond; (3) The trial
    court’s judgment was against the weight of the evidence; (4) The trial court erroneously
    declared that the claims were barred by the statute of limitations; (5) The trial court
    abused its discretion by reversing evidentiary rulings sua sponte after trial; and (6) The
    trial court erred by refusing to hold EMC liable for vexatious refusal to pay on the bond.5
    Because all of Four Star’s points involve in some manner documentary evidence
    that was admitted during the trial and then excluded from evidence after trial by the
    judgment, we begin our review with Four Star’s fifth point, which we find dispositive of
    this appeal.
    Standard of Review
    The admission or exclusion of evidence is within the sound discretion of
    the trial court. Where evidence is excluded, the issue is whether or not the
    trial court abused its discretion, not whether the evidence was admissible.
    4
    All rule references are to Missouri Court Rules (2014).
    5
    Four Star withdrew its sixth point in its reply brief.
    5
    A trial court abuses its discretion when the ruling is clearly against the
    logic of the circumstances and is so arbitrary and unreasonable as to shock
    one’s sense of justice and indicates a lack of careful consideration. We
    give substantial deference to the trial court’s decision to admit or exclude
    evidence because of its superior opportunity to evaluate the proffered
    evidence in the context of the trial. We will affirm the trial court’s
    evidentiary ruling unless there is a substantial or glaring injustice. To
    reverse, we must find that the trial court’s error in excluding evidence was
    prejudicial and not harmless and that the error materially affected the
    merits of the action. A ruling within the trial court’s discretion is
    presumed correct, and the appellant bears the burden of showing abuse of
    discretion and prejudice.
    Romeo v. Jones, 
    144 S.W.3d 324
    , 332 (Mo.App. E.D. 2004) (internal citations omitted).
    Discussion
    Four Star contends that the following evidence was admitted at trial and then later
    excluded from evidence in the trial court’s judgment: (1) Four Star’s first proof of claim
    submitted to EMC; (2) Four Star’s supplemented proof of claim; (3) the judgment against
    T & T; (4) Four Star’s contract assigning its claim to RGH, LLC; (5) a statement of the T
    & T account record with Four Star; (6) a statement of attorney’s fees; (7) the daily log
    book of Greene County; (8) a second daily log book of Greene County; (9) the pickup
    ticket for the equipment; (10) the delivery ticket for the equipment; and (11) the rental
    contract between Four Star and T & T. Regarding a few of these exhibits, the judgment
    is somewhat ambiguous as to whether they were excluded from evidence.6 Nevertheless,
    certain previously admitted exhibits that are crucial to Four Star’s case and its points on
    appeal were clearly found to be inadmissible in the judgment. Particularly, Four Star, in
    6
    For example, regarding the statement of attorney’s fees, the judgment states that EMC objected to the
    admissibility of the exhibit but it never expressly sustains the objection. Regarding the Greene County
    daily log books, the judgment finds that EMC’s objection to admissibility should have been sustained to the
    first exhibit and then continues in the next sentence to discuss the second exhibit as if that exhibit would be
    inadmissible for the same reason, but never expressly says so.
    6
    part, claims that the trial court misapplied the law in excluding the default judgment from
    evidence and in declining to treat the default judgment as binding on EMC.7
    We will review whether the trial court abused its discretion in excluding exhibits
    from evidence by its judgment that were previously admitted into evidence during trial
    without distinguishing among the different exhibits within that group.8 We initially note
    that Rule 73.01 requires a court in a case tried without a jury to “rule upon all objections
    to evidence as in jury cases.” Rule 73.01(a). Some case law, however, suggests that the
    rules excluding evidence are less strictly enforced in a court-tried case. Gardner v.
    Robinson, 
    759 S.W.2d 867
    , 868 (Mo.App. S.D. 1988). Here, we are not presented with a
    mere exclusion of evidence at trial. Rather, the evidence in question was admitted during
    7
    See generally City of Independence v. Kerr Construction Paving Company, Inc., 
    957 S.W.2d 315
    , 319-
    20, 324-25 (Mo.App. W.D. 1997) (holding that a surety’s liability for items covered by a statutory payment
    bond issued pursuant to section 107.170 is coextensive with the bond principal’s liability for these items,
    and the surety is liable as a matter of law to the extent of the principal’s liability for these items); Stoops v.
    Wittler, 1 Mo.App. 420, 423-24 (Mo.App. St.L.D. 1876) (concluding “a judgment against the principal is
    conclusive against the surety, though he be not a party to the suit, if he have notice of the proceeding, or, at
    least, where he has been a party defendant and has filed an answer, though before trial the suit be dismissed
    as to him,” and “a judgment binds none but parties and privies,” and, in dicta, suggesting that the same
    principle would apply to a default judgment); Home Insurance Co. of New York v. Savage, 
    103 S.W.2d 900
    , 902 (Mo.App. K.C.D. 1937) (finding it unnecessary to decide whether a default judgment entered
    against a principal in a lawsuit against the principal and two sureties was binding on the sureties, but stating
    in dicta “[m]any authorities hold that a judgment against the principal, obtained under circumstances
    identical with those here, absent fraud, collusion, or clerical error in its entry, is conclusive on the
    sureties”); City of Kansas City, Missouri ex rel. Lafarge North America Inc. v. Ace Pipe Cleaning, Inc.,
    
    349 S.W.3d 399
    , 404 & n.11 (Mo.App. W.D. 2011) (a subcontractor is in direct privity of contract with the
    general contractor, and, for the purpose of determining the right of a sub-subcontractor to a subcontractor to
    recover under a statutory payment bond issued pursuant to section 107.170, the law adopts the legal fiction
    that the sub-subcontractor also is in privity of contract with the general contractor though that technically is
    not true); State of Missouri ex rel. Family Support Division v. Stovall-Reid, 
    163 S.W.3d 519
    , 521-22
    (Mo.App. E.D. 2005) (“[r]es judicata prevents a party from re-litigating issues judicially determined in a
    previous action, even when the judgment was entered by default,” and notice of the default judgment
    hearing is not relevant where the default judgment has not been set aside and remains in effect) (italics
    added, and internal citation omitted); and Xiaoyan Gu v. Da Hua Hu, No. ED100001, 
    2014 WL 3728710
    ,
    at *8 (Mo.App. E.D. July 29, 2014) (res judicata “applies to the parties and their privies,” and “[f]or privity
    to exist, . . . the interests of the party and non-party must be ‘so closely intertwined that the non-party can
    fairly be considered to have had his or her day in court’”) (quoting Stine v. Warford, 
    18 S.W.3d 601
    , 605
    (Mo.App. W.D.2000)).
    8
    We may do so because we make no finding regarding the underlying issue of whether the individual
    exhibits were admissible. 
    Romeo, 144 S.W.3d at 332
    .
    7
    the trial. It was only after the trial concluded, when Four Star could no longer present
    any other evidence, that the trial court, at the invitation and request of EMC,9 excluded
    the previously admitted evidence. The issue in this appeal is whether the procedure
    employed by the trial court in admitting this evidence at trial and then excluding it by its
    judgment was an abuse of discretion. We conclude that it was.
    In Jones v. Wells Fargo Auto Finance, LLC, a trial court ruled on a motion to
    dismiss without an evidentiary hearing despite the fact that both parties had requested an
    evidentiary hearing. 
    383 S.W.3d 472
    , 474-75 (Mo.App. W.D. 2012). The sua sponte
    ruling required reversal because the losing party could not have known that the trial court
    intended to rule solely on their motion papers and therefore was deprived of an
    opportunity to argue otherwise to the court. 
    Id. at 477.
    Similarly, the trial court’s procedure employed here of excluding evidence by its
    judgment that was previously admitted during trial deprived Four Star of any
    foreknowledge that the trial court intended to rule on a more limited amount of evidence
    than Four Star had presented and had been admitted into evidence at trial. Ruling on a
    crucial piece of evidence after the record has been closed places the parties in the
    untenable position of not knowing what additional evidence is needed to complete their
    case. Estate of Loik, 
    426 A.2d 1134
    , 1137 (Pa. 1981).
    Having reasonably relied upon the trial court’s admission of its proffered
    evidence at trial, this procedural device also deprived Four Star of any opportunity to
    present other evidence, in lieu of the post-trial excluded evidence. Once the trial court
    9
    “Findings of fact and conclusions of law by a court sitting without a jury ordinarily should not encompass
    or consist of evidentiary rulings[.]” 89 C.J.S. Trial § 1259. Because findings of fact can be adopted after
    the close of evidence, it would be inappropriate to include evidentiary rulings therein because “[a] ruling on
    objections to evidence or motions to strike evidence should be made as soon as possible at the time that the
    objection or motion is made.” 88 C.J.S. Trial § 243 (internal footnotes omitted).
    8
    decided to exclude the previously admitted evidence, the failure to give Four Star a
    chance to offer other evidence in lieu of the previously admitted and then excluded
    evidence shocks this Court’s sense of fairness and justice. This failure substantially
    hindered Four Star’s fair ability to present its case and therefore prejudiced Four Star.10
    Portions of this evidence, e.g. the rental agreement between Four Star and T & T, were
    crucial to Four Star’s claims; therefore, this is an error that materially affected the merits
    of this action. The trial court abused its discretion in excluding evidence by its judgment
    that it had previously admitted at trial without giving Four Star an opportunity to offer
    other evidence in lieu of the subsequently excluded evidence. Four Star’s fifth point is
    granted.
    Conclusion
    The judgment is reversed and the case is remanded to the trial court for further
    proceedings consistent with this opinion. If, on remand, the trial court determines that
    10
    This Court appreciates EMC’s counsel’s candor about the fairness issue during oral argument:
    EMC’s counsel: All the evidence that came in I objected to. The judge changed his mind
    on the validity of my objections. The way these things are tried with a court-tried case,
    you all know that the courts on a court-tried case basically take in all the evidence except
    that which is obviously plain error and they can take all that stuff with the case and they
    can change their . . . .
    Judge Rahmeyer: He didn’t do that though. The court didn’t say “I’m taking this with
    the case.”
    EMC’s counsel: No, he did not.
    Judge Rahmeyer: He really ruled retroactively that this evidence is not admissible.
    EMC’s counsel: Yeah, he ruled retroactively.
    Judge Rahmeyer: And you have to admit that does not comply with any sort of due
    process or any sort of fairness.
    EMC’s counsel: I admit that.
    “The preferable practice is for the trial court to prepare its own specific findings of fact and conclusions of
    law so as to better insure that all issues raised are addressed and that erroneous allegations of fact or law . . .
    are not incorporated in a court order.” Malone v. State, 
    747 S.W.2d 695
    , 699 (Mo.App. E.D. 1988).
    9
    the proffered evidence was properly excluded, Four Star should be given a chance to
    offer additional evidence.11
    11
    Because the trial court denied Four Star’s claim under General Contractor’s statutory payment bond, the
    trial court did not consider, nor do we, EMC’s claims that (1) all or a portion of the “unpaid principal”
    awarded in the default judgment was beyond the scope of the relief Four Star sought in its petition (EMC
    asserts Four Star’s petition sought only “rent”) and also beyond the scope of those items that are
    recoverable under a statutory payment bond issued pursuant to section 107.170, and (2) the interest and
    attorney fees awarded in the default judgment are beyond the scope of those items that are recoverable
    under a section 107.170 statutory payment bond. See generally Edward V. Crites & Joseph C. Blanner,
    Payment Bonds for Public Works Contractors, 70 J. Mo. Bar, Jan.-Feb. 2014, at 18 for a general discussion
    of statutory payment bonds issued pursuant to section 107.170 for public works and the items that are
    recoverable under those bonds.
    10