Sheridan Electric Co-Op, Inc. v. Montana-Dakota Utilities ( 2014 )


Menu:
  •                                                                                           December 23 2014
    DA 14-0196
    Case Number: DA 14-0196
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    
    2014 MT 332
    SHERIDAN ELECTRIC CO-OP, INC.,
    a Montana rural electric cooperative,
    Plaintiff and Appellee,
    v.
    MONTANA-DAKOTA UTILITIES,
    a corporation,
    Defendant and Appellant.
    APPEAL FROM:            District Court of the Fifteenth Judicial District,
    In and For the County of Daniels, Cause No. DV 10-2013-2
    Honorable David Cybulski, Presiding Judge
    COUNSEL OF RECORD:
    For Appellant:
    Jeffery J. Oven, Steven R. Milch, Crowley Fleck PLLP; Billings, Montana
    For Appellee:
    Maxon R. Davis, Davis, Hatley, Haffeman & Tighe, P.C.; Great Falls,
    Montana
    Loren O’Toole, II, O’Toole Law Firm; Plentywood, Montana
    Submitted on Briefs: September 24, 2014
    Decided: December 23, 2014
    Filed:
    Clerk
    Justice Michael E Wheat delivered the Opinion of the Court.
    ¶1      Montana-Dakota Utilities (MDU) appeals from the judgment of the Fifteenth Judicial
    District Court, Daniels County, granting Sheridan Electric Co-op, Inc.’s (Sheridan) motion
    for summary judgment and denying MDU’s motion for summary judgment.
    FACTUAL AND PROCEDURAL BACKGROUND
    ¶2      The material facts are not in dispute. Sheridan is a Montana rural electric cooperative.
    MDU is an electric services provider. Both serve customers in the Madoc/Scobey area in
    Daniels County. Cahill Seeds, Inc. (Cahill) is a farm and seed retail business located
    approximately six miles east of Scobey, near the intersection of Highway 5 and North Madoc
    Road.
    ¶3      In 2011, Cahill began planning the construction of a new seed washing plant and
    submitted initial requests for electric service to MDU and Sheridan. The request stated that
    Cahill would require three-phase Wye power to operate the plant.
    ¶4      When Cahill made its request Sheridan had an existing distribution line carrying
    three-phase Wye power approximately 1.33 miles north of the Cahill site. Meanwhile, MDU
    had an existing line carrying three-phase Wye power located approximately 6.5 miles west of
    Cahill. MDU also had an existing transmission line carrying three-phase Delta power
    running along Highway 5, and a distribution line connected to that transmission line at its
    Madoc Substation, near the junction of Highway 5 and North Madoc Road, approximately
    300 feet from Cahill.
    2
    ¶5     Sheridan responded to Cahill’s request, stating that it could provide three-phase Wye
    power with the construction of a 1.33 mile line extension connecting its distribution line to
    Cahill. MDU told Cahill that it could not provide three-phase Wye power.
    ¶6     In September 2011, Cahill began building the seed washing plant. To provide power
    during construction, MDU installed a pole-mount transformer along the distribution line and
    extended a 285 foot single-phase service line to Cahill.
    ¶7     During 2012 and 2013, as construction neared completion and Cahill began to install
    equipment requiring three-phase Wye power, MDU upgraded its transmission and
    distribution systems near Cahill. MDU replaced the transformer at the Madoc substation
    with a Wye transformer, added a fourth “neutral” wire to the distribution line, replaced the
    pole mount transformer on the distribution line with a three-phase padmount transformer,
    and replaced the single-phase service line with three-phase service line. These upgrades
    allowed MDU to provide three-phase Wye power to Cahill.1 After completing its upgrades,
    MDU began providing three-phase Wye power to Cahill.
    ¶8     On January 14, 2013, prior to MDU completing its upgrades, Sheridan filed a
    complaint in District Court. Sheridan alleged that MDU violated the Montana Territorial
    Integrity Act (MTIA) when it extended power to Cahill. Sheridan argued that under the
    priority provisions of the MTIA it had the exclusive right to serve Cahill because it had a line
    capable of delivering three-phase Wye power located 1.33 miles away from Cahill, while
    MDU’s closest capable line was 6.5 miles away from Cahill. According to Sheridan,
    1
    An MDU employee testified that the fourth wire was a common addition to three-phase Wye lines
    but not a necessity.
    3
    MDU’s nearby distribution line did not meet the requirements of the MTIA because
    substantial upgrades to MDU’s distribution system were required to send three-phase Wye
    power along the line.
    ¶9     MDU responded, arguing that the MTIA only required that the “line” itself need have
    the capacity to carry the requisite load. MDU pointed out that the line itself had the physical
    capacity to carry three-phase Wye power, and only the transformers needed to be upgraded
    to provide three-phase Wye to Cahill.
    ¶10    Both sides moved for summary judgment. The District Court ruled in favor of
    Sheridan, finding that the 1.33 mile distance from Sheridan’s three-phase Wye transmission
    line to Cahill gave Sheridan priority over MDU, whose three-phase line was 6.5 miles away.
    MDU appeals.
    STANDARDS OF REVIEW
    ¶11    We review a district court’s grant of summary judgment de novo.                 Scentry
    Biologicals, Inc. v. Mid-Continent Cas. Co., 
    2014 MT 39
    , ¶ 23, 
    374 Mont. 18
    , 
    319 P.3d 1260
    . We review a district court’s interpretation of a statute for correctness. State v.
    Madsen, 
    2013 MT 281
    , ¶ 8, 
    372 Mont. 102
    , 
    317 P.3d 806
    .
    DISCUSSION
    ¶12    We restate the issue as follows:
    ¶13    1. Did the District Court err in finding that Sheridan had the right to serve Cahill
    under the priority provisions of the MTIA?
    4
    ¶14      MDU asks us to reverse the District Court for three reasons. First, because MDU had
    the exclusive right to serve Cahill under § 69-5-105(1), MCA, by virtue of having the line
    nearest to Cahill with the capacity to serve Cahill. Second, because MDU added Cahill to its
    service territory when it began delivering single-phase construction power to Cahill in
    September 2011, and therefore Sheridan was prohibited from serving Cahill by § 69-5-104,
    MCA. Third, because granting priority to Sheridan would violate public policy and the
    legislative intent of the MTIA.
    ¶15      We will address each argument in turn.
    When Cahill submitted its request for three-phase Wye power, did MDU have
    priority to serve Cahill under § 69-5-105(1), MCA?
    ¶16      We first address the question of when a provider’s facilities are measured for purposes
    of determining priority for serving new consumers under the MTIA. Timing is important
    where, as in this case, an electric facilities provider is upgrading its facilities during the
    pendency of a dispute. The District Court implicitly held that priority should be determined
    at the time Cahill approached Sheridan and MDU about providing electric services. We
    agree.
    ¶17      Section 69-5-105(1), MCA, “Service to new consumers,” states:
    Except as provided in 69-5-106 and 69-5-113, the electric facilities provider
    that has a line nearest the premises and that has the capacity to serve the
    premises, as measured in accordance with subsection (2), shall provide electric
    service facilities to the premises initially requiring service after May 2, 1997.
    Without a premises in existence the statute would have no meaning. Furthermore, the statute
    clearly contemplates new premises, that is, premises that have recently come into existence.
    MTIA defines “premises” as “a building, residence, structure, irrigation pump, or facility to
    5
    which electrical service facilities are provided or are to be installed.” Section 69-5-102(12),
    MCA. When Cahill solicited bids for electrical services in early 2011, the plant became a
    “facility to which electrical services . . . [were] to be installed” which is to say a premises.
    The need to evaluate each party’s electrical service facilities arose at that time. Thus in
    assessing priority we will consider only the electric service facilities each party had in place
    when Cahill made its request for electrical service.
    ¶18    Having determined that we will only consider a provider’s electrical service facilities
    already in place in early 2011, we turn to the question of which party had priority under the
    MTIA. The answer to this question hinges upon the meaning of § 69-5-105(1), MCA.
    ¶19    MDU contends that the term “capacity” as used in § 69-5-105(1), MCA, refers to the
    physical capacity of the line as defined by § 69-5-102(11), MCA. “‘Line’ means any
    material that is used to convey electrical energy and that is normally energized between
    2,400 volts phase to ground and 14,400 volts phase to ground.” Section 69-5-102(11),
    MCA. Under MDU’s interpretation of the statute, MDU had priority because, at the time
    Cahill submitted its request for power, the line itself had the capacity to deliver three-phase
    Wye power, despite the fact that MDU’s nearby substation did not have the capacity to send
    three-phase Wye power down the line.
    ¶20    An alternative interpretation is that the statute requires the electric facilities provider
    to have the capacity to actually send the load down the line. “‘Electric facilities provider’
    means any utility that provides electric service facilities to the public.” Section 69-5-102(6),
    MCA. “‘Electric service facilities’ means any distribution or transmission system or related
    facility necessary to provide electricity to the premises, including lines.”             Section
    6
    69-5-102(7), MCA. Under this interpretation, Sheridan would have priority because its
    nearest distribution system, including line, was actually carrying three-phase Wye when
    Cahill made its request, while MDU’s distribution system required a substation upgrade in
    order to carry three-phase Wye.
    ¶21    The plain language of § 69-5-105(1), MCA, supports the latter interpretation. The
    sentence comprising § 65-5-105(1) contains two relative clauses: “that has a line nearest the
    premises,” and “that has the capacity to serve the premises.” Each clause begins with the
    relative pronoun “that.” The meaning of the statute rests on which noun, “electric facilities
    provider” or “line,” is antecedent to which relative pronoun. Under MDU’s interpretation
    “electric facilities provider” is antecedent to the first and “line” is antecedent to the second.
    However, the statute states: “the electric facilities provider that has a line nearest the
    premises and that has the capacity to serve the premises. . . .” Section 65-5-105(1), MCA
    (emphasis added).2
    ¶22    Here, the “and” is dispositive. Its placement in the sentence compels the conclusion
    that “electric facilities provider” is antecedent to both relative pronouns and therefore is the
    subject of each relative clause. Thus it is the “electric facilities provider” that must “[have] a
    2
    As part of its argument, MDU notes that the statute does not define “capacity” and correctly states
    that when a term is not defined by statute we consider that term to have its plain and ordinary
    meaning. In support of its position that the term “capacity” refers only to the line itself, MDU
    quotes Webster’s Third New International Dictionary, defining “capacity” as “the power or ability to
    hold, receive, or accommodate.” This definition is indeed appropriate when referring to the capacity
    of an electrical line. However, another equally plain and ordinary meaning of “capacity” is “the
    ability to . . . process . . . manufacture, or produce.” Webster’s Third New International Dictionary
    330 (1961). This definition is appropriate when referring to the capacity of an electrical facilities
    provider. The “plain and ordinary meaning” doctrine as applied to the term “capacity” does not lend
    support to either interpretation.
    7
    line nearest the premises” and it is the “electric facilities provider” that must “[have] the
    capacity to serve the premises.”
    ¶23    Therefore, under § 69-5-105(1), MCA, an electric facilities provider that has the line
    nearest the premises and that has the distribution system (including lines) with the capacity
    to provide electricity to the premises “shall provide electric service facilities to the
    premises. . . .” Section 69-5-105(1), MCA.
    ¶24    While it is undisputed that MDU’s distribution line had the capacity to supply
    three-phase Wye power, we conclude that MDU did not meet the requirements of
    § 69-5-105(1), MCA, because its distribution and transmission facilities did not have the
    capacity to provide three-phase Wye without a significant upgrade to its nearby substation.
    When Cahill made its request for three-phase Wye power in 2011, MDU’s nearest line with
    the distribution and transmission facilities necessary to provide three-phase Wye were more
    than six miles away, while Sheridan had a line with the necessary facilities less than two
    miles away. Therefore, the District Court did not err when it determined that Sheridan had
    priority to serve Cahill under § 69-5-105(1), MCA.
    Did Cahill become part of MDU’s “service territory” when it provided single-phase
    electricity to Cahill during the construction of the facility?
    ¶25    MDU argues that when it provided single-phase construction power to Cahill in
    September 2011, it added Cahill to its service territory, thus precluding Sheridan from
    providing electricity to Cahill pursuant to § 69-5-104, MCA. That statute states that “a
    utility may not provide electricity supply service to premises in another utility’s service
    territory.” § 69-5-104(1), MCA. A “service territory” is defined as “premises receiving
    8
    distribution service from a utility on January 1, 2011, and premises added pursuant to Title
    69, chapter 5.” Section 69-5-102(14), MCA.
    ¶26      Because MDU was not providing distribution service to Cahill on January 1, 2011,
    Cahill could only be made a part of MDU’s service territory if it was added pursuant to Title
    69, chapter 5. Under Title 69, chapter 5, priority for service to new customers is determined
    by § 69-5-105(1), MCA. We have already concluded that Sheridan had priority in providing
    electric services to Cahill under that section.3 Hence, when MDU extended single-phase
    electrical service to Cahill, it did not do so pursuant to Title 69, chapter 5. Thus, MDU
    providing construction power to Cahill did not result in Cahill being added to MDU’s service
    territory. Section 69-5-104(1), MCA, therefore, grants no priority to MDU and does not
    prohibit Sheridan from providing electricity supply service to Cahill.
    Would granting Sheridan priority to serve Cahill violate the legislative intent
    behind the MTIA?
    ¶27      MDU urges us to reverse the District Court because granting Sheridan priority to
    serve Cahill would violate the legislative intent behind the MTIA. In interpreting a statute
    “the office of the judge is simply to ascertain and declare what is in terms or in substance
    contained therein, not to insert what has been omitted or to omit what has been inserted.”
    § 1-2-101, MCA. If the language of the statute is unambiguous “no further interpretation is
    required, and we will resort to legislative history only if legislative intent cannot be
    determined from the plain wording of the statute.” Clarke v. Massey, 
    271 Mont. 412
    , 416,
    
    897 P.2d 1085
    , 1088 (1995).
    3
    See supra, ¶¶ 15-23.
    9
    ¶28    Because we have found that the language of § 69-5-105(1), MCA, unambiguously
    grants priority to the electric facilities provider that has both the line nearest the premises and
    the capacity to serve the premises we will not look to legislative history in interpreting the
    statute further. The statute clearly grants priority to Sheridan.
    CONCLUSION
    ¶29    We conclude that the language of § 69-5-105(1), MCA, unambiguously grants priority
    to Sheridan because it had the line closest to Cahill and the distribution system capacity to
    serve Cahill. Based on that finding, we determine that MDU did not add Cahill to its service
    territory pursuant to Title 69, chapter 5, when it extended single-phase construction power to
    Cahill in September 2011. We decline to resort to an examination of legislative history
    where the statute in question is unambiguous.
    ¶30    For the foregoing reasons, we hold that the District Court did not err in finding that
    Sheridan has the right to serve Cahill under the priority provisions of the MTIA.
    ¶31    Affirmed.
    /S/ MICHAEL E WHEAT
    We Concur:
    /S/ JAMES JEREMIAH SHEA
    /S/ PATRICIA COTTER
    /S/ BETH BAKER
    /S/ JIM RICE
    10
    

Document Info

Docket Number: DA 14-0196

Judges: Wheat, Shea, Cotter, Baker, Rice

Filed Date: 12/23/2014

Precedential Status: Precedential

Modified Date: 11/11/2024