Comphealth, Inc. v. Highland View Outpatient Surgical Center , 240 Mont. 366 ( 1989 )


Menu:
  •                                  No. 89-150
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1989
    COMPHEALTH, INC.,
    Plaintiff and Appellant,
    -VS-
    HIGHLAND VIEW OUTPATIENT SURGICAL
    CENTER, a Montana corporation,
    Defendant and Respondent.
    APPEAL FROM:     ~ i s t r i c tCourt of the Second Judicial ~istrict,
    In and for the County of Silver Bow,
    The Honorable Arnold Olsen, Judge presiding.
    COUNSEL OF RECORD:
    For Appellant:
    Larry Jent, Bozeman, Montana
    For Respondent:
    Leonard J. Haxby, Butte, Montana
    Submitted on ~ r i e f s : Aug. 10, 1989
    Decided:    December 22, 1989
    r-
    Filed:   m
    Justice William E. Hunt, Sr., delivered the Opinion of the
    Court.
    plaintiff and appellant, Comphealth, Inc., brought this
    breach of contract action against defendant, Highland vie67
    Outpatient Surgical Center.    Following a bench trial, the
    District Court of the Second Judicial District, Silver Bow
    County, found in favor of the defendant. From this judgment,
    plaintiff appeals. We affirm.
    The following issue is dispositive of the appeal:
    Did defendant breach the contract between the parties by
    giving oral notice of its intent to cancel when the agreement
    required 30 days written notice of termination?
    Defendant, a Montana corporation, is a freestanding
    outpatient surgical center located in Butte. In late June,
    1984, it entered into a contract with plaintiff, a Utah
    corporation, in which plaintiff agreed to provide a locum
    tenens (substitute) physician acceptable to defendant at a
    rate of $2,950 per week for a period from July 30, 1984 to
    August 27, 1984.      The contract included a cancellation
    clause, which granted defendant the right to terminate the
    agreement by giving 30 days written notice.     The clause
    provided that failure to give the required notice would
    result in liquidated damages.
    At   the time   the parties entered   into the   contract,
    defendant was in the process of constructing the surgical
    center building. Defendant anticipated that the center would
    open on July 30, 1984.    Thus, the parties agreed that the
    contract would commence on that date. However, on July 10,
    1984, defendant notified plaintiff that the center's opening
    would be delayed due to a plumbers' strike in the Butte area.
    plaintiff consented to postpone the commencement of the
    contract. A new contractual period was never agreed upon by
    the parties.
    On the day after it learned of the plumbers' strike,
    plaintiff mailed to defendant the curricula vitae of two
    anesthesiologists. One, Dr. Tilby, was available for the
    anticipated term of the contract. The other, Dr. Plon, was
    unavailable for the initial contractual period.        Plaintiff
    submitted Dr. Plon's statistics, however, in the event the
    assignment extended longer than anticipated or in case Dr.
    Plon would fit defendant's needs better than Dr. Tilby.
    The parties dispute whether defendant ever accepted Dr.
    Tilby.   plaintiff's agent, Sharon Thompson, testified that
    Dr. St. John, the president of defendant corporation, had
    indicated that Dr. ~ i l b y would be acceptable and that
    plaintiff should plan to send him to work when the center was
    completed.    Dr. Tilby also testified that plaintiff had
    informed him that he was to fill the temporary position.
    Dr. St. John, on the other hand, testified that he had
    never accepted Dr. ~ i l b y because ~ i l b y ' s file did not
    satisfactorily explain why his hospital privileges had been
    temporarily suspended in 1981. The ~istrictCourt found that
    defendant had never accepted the physician.
    In late July or early August, 1984, Dr. St. John
    notified plaintiff by telephone that the defendant would no
    longer need plaintiff 's services because it had hired a
    permanent anesthesiologist. Defendant did not follow up this
    phone conversation with written notice of cancellation.
    On November 28, 1984, plaintiff filed this action,
    alleging that defendant had breached the contract by failing
    to give adequate notice of cancellation and failing to pay
    liquidated damages as provided in the contract. On December
    1, 1988, trial was held before the ~istrict Court, sitting
    without a jury.    The court heard the testimony of Dr. St.
    John and accepted the depositions of Ms. Thompson and Dr.
    Tilby.   On December 29, 1988, the ~istrict Court issued
    findings    fact and conclusions       law.  The court found
    that defendant had not breached       the contract but had
    terminated the agreement in an appropriate and timely
    fashion.   The court further found that plaintiff had not
    suffered any damages.     Plaintiff appealed to this Court.
    On appeal, plaintiff raises several issues, including
    whether the ~istrict Court applied the correct law in
    determining the enforceability of liquidated damages, whether
    the District Court correctly determined the nature of the
    contract, and whether defendant had actually accepted the
    physician offered by plaintiff.    We need not answer these
    questions, however, because our conclusion that the defendant
    adequately complied with the cancellation provisions in the
    contract effectively disposes of the appeal.
    Plaintiff argues that defendant's method of cancelling
    the contract was both untimely and procedurally improper and,
    therefore, triggered the agreement's liquidated damages
    clause. We do not agree.
    Substantial credible evidence supports the District
    Court ' s finding that defendant gave adeq.uate, timely notice
    of cancellation. The District Court found:
    6. [Tlhere was a thirty-day cancellation of the
    contract and based upon the testimony of Dr. Tilby
    and Dr. St. John, the Plaintiff was advised in late
    July or the first week in August, that Defendant
    was no longer in need of the services of the
    Plaintiff, that since they had not found a suitable
    physician, that the Defendant had found a physician
    of its own and had no further need for the services
    of the Plaintiff. Since the surgery center did not
    open until September 14, 1984, the notice was given
    more than thirty days in advance of any need for a
    physician.     Although this notice was not in
    writing, the overwhelming testimony reveals that no
    further search was made by the plaintiff after that
    date. The contract was in fact cancelled in late
    July or the first week of August, 1984, in
    substantial compliance with the agreement.
    In addition, we note that, due to the uncertainty
    created by the plumbers' strike, the intitial contractual
    period had been postponed and a new commencement date for the
    performance of the contract had not been agreed upon by the
    parties. Under the particular facts of this case, where at
    the time of cancellation a specific performance period had
    not been agreed upon by the parties and where notice was
    actually given more than 30 days prior to any possible
    performance date, defendant gave timely notice of termination
    of the contract.
    Furthermore, even though defendant gave oral rather than
    written notice of cancellation, the notice was procedurally
    adequate.   plaintiff does not now contest, nor has it ever
    contested, that it did not receive oral notice of
    cancellation.    Plaintiff accepted the notice and took no
    further action in reliance upon the contract.       In fact,
    shortly after defendant's telephone call, plaintiff notified
    Dr. Tilby that he would not be filling the anesthesiologist
    position.
    The present case can be distinguished from our earlier
    decision, Tomsheck v. Doran (1953), 
    126 Mont. 598
    , 
    256 P.2d 538
    , where we stated that exact compliance with contractual
    terms regarding notice of cancellation is an essential
    prerequisite to cancellation. Unlike the present case, the
    plaintiff in Tomsheck did not substantially comply with the
    terms of the cancellation provision. Although the Tomsheck
    contract required a one-year notice of cancellation, the
    plaintiff instituted a suit for rescission of the contract.
    only one day after he delivered the termination notice to
    defendant.  Moreover, in Tomsheck substantial prejudice to
    the non-cancelling defendant in the form of forfeiture of
    land would have resulted had we failed to hold plaintiff
    strictly to the terms of the contract.
    In the present    case, defendant   substantially   complied
    with the terms governing notice o f cancellation.    Therefore,
    the District Court did not err in finding that defendant did
    not breach the contract and in refusing to award liquidated
    damages.
    ~f firmed.
    b7e concur:
    4,/4. 4 7
    c -
    Chlef Justice
    

Document Info

Docket Number: 89-150

Citation Numbers: 1989 Mont. LEXIS 342, 240 Mont. 366, 783 P.2d 1385

Judges: Hunt, Turnage, Harrison, Sheehy, Gulbrandson, McDonough, Weber

Filed Date: 12/22/1989

Precedential Status: Precedential

Modified Date: 11/11/2024