Mandell v. Bayliss ( 2016 )


Menu:
  •                                                                                                 08/23/2016
    DA 16-0015
    IN THE SUPREME COURT OF THE STATE OF MONTANA                                  Case Number: DA 16-0015
    
    2016 MT 205
    MICHAEL J. MANDELL,
    Plaintiff and Appellant,
    v.
    BAYLISS WARD and BAYLISS ARCHITECTS, P.C., et al.,
    Defendant and Appellee.
    APPEAL FROM:           District Court of the Sixth Judicial District,
    In and For the County of Park, Cause No. DV 13-152
    Honorable Brenda Gilbert, Presiding Judge
    COUNSEL OF RECORD:
    For Appellant:
    Karl Knuchel, Shenandoah R. Roath, Karl Knuchel, P.C., Livingston,
    Montana
    For Appellee:
    Alanah Griffith, Griffith Law Group, Bozeman, Montana
    Submitted on Briefs: June 15, 2016
    Decided: August 23, 2016
    Filed:
    __________________________________________
    Clerk
    Justice Jim Rice delivered the Opinion of the Court.
    ¶1     Appellant Michael J. Mandell (Mandell) contests the Sixth Judicial District
    Court’s granting of relief in quantum meruit and awarding of attorney fees to Appellees
    Bayliss Ward and Bayliss Architects, P.C. (Bayliss) in this residential construction
    dispute. We affirm in part, reverse in part, and remand for further proceedings. We
    address the following issues:
    1. Did the District Court err in granting equitable relief in quantum meruit,
    despite violation of the statutory requirement that residential construction contracts be in
    writing?
    2. Did the District Court err in awarding attorney fees for the entire case,
    including the quantum meruit claim?
    FACTUAL AND PROCEDURAL BACKGROUND
    ¶2     Mandell is the owner of real property in the Paradise Valley, outside of
    Livingston. He contacted architect Bayliss Ward via email in March 2012 to inquire
    whether Ward and Ward’s firm, Bayliss Architects, P.C.,1 would design and provide
    architectural services for a proposed house on the property. Mandell worked in Thailand
    as the events herein unfolded, so the communication between the parties was primarily
    electronic, especially through email.
    ¶3     Bayliss and Mandell engaged in extensive communications regarding the proposed
    construction project and Mandell’s budget. At one point, Bayliss stopped the process,
    stating to Mandell in an email: “After spending several hours on your residence, I am
    1
    The record indicates that Bayliss Ward is the sole shareholder of Bayliss Architects, P.C.
    Although Ward and the professional corporation are separate parties, their legal position herein is
    aligned and we refer to them jointly as “Bayliss” for the sake of simplicity.
    2
    going to have to stop work and decline any further effort towards your project. The
    budget for this project and the items that you want to include will be very difficult to
    achieve and I will not lead you as if we could really do your project for your budget.
    Your site it beautiful, but I cannot design a home for you with your budget.”
    ¶4     However, Mandell continued to pursue Bayliss, sending an email three days later,
    stating: “I think it would be beneficial for both of us to have every person floating the
    Yellowstone admire your work. . . . Maybe you can design something within my budget
    that I will be happy with.”      When Bayliss explained that the house Mandell was
    requesting would cost at least $170 per square foot, Mandell answered that “I may be
    able to swing the $170 per sq. ft[.] range if you think you can make it work. . . . Let’s
    just save where we can, without compromising quality and your style.” In June 2012, the
    parties met on the site, and Mandell testified that Bayliss agreed that he would design an
    approximately 2000 square foot home costing $300,000. Bayliss testified that the parties
    agreed to a construction price of $170 per square foot, with an 8-10% fee for architectural
    design and structural engineering of the project.
    ¶5     Mandell originally intended to have another party act as the general contractor on
    the project. However, this did not occur, and Mandell requested that Bayliss provide
    construction management services, in addition to the architectural and structural
    3
    engineering services. Bayliss agreed to do so for an additional payment of 7-10% of the
    construction costs as a construction management fee.2
    ¶6     The details of the parties’ agreement were not reduced to writing, but construction
    commenced, in Bayliss’ words, as a “fast track” project.              Mandell wired funds in
    payment of Bayliss’ invoices as the project continued, ultimately paying a total of
    $394,198.65. At trial, the parties disputed the occurrence of changes in the project, with
    Mandell testifying that he never approved any changes to the design, plans, or finishes,
    and Bayliss testifying that he consulted with Mandell on a number of changes as the
    project evolved, to which Mandell had typically responded to Bayliss to “[j]ust make it
    nice.” No written change orders were prepared. The home was essentially completed in
    2013, at which time Bayliss presented Mandell with a final invoice, identifying additional
    amounts still owing. Mandell refused to pay, and Bayliss filed a construction lien on the
    property in the amount of $138,241.35 in October 2013.
    ¶7     Mandell initiated this action, stating counts for breach of contract, declaratory
    judgment that the lien was invalid, and quiet title to the property. Bayliss answered and
    stated three counter-claims for foreclosure of the construction lien, quantum meruit, and
    breach of contract.
    2
    Bayliss testified in his deposition that he is not a licensed general contractor in Montana. He
    described his role as acting as a discounted general contractor for Mandell, stating: “[A]ll we’re
    doing is being [Mandell’s] agent, because he knows – he doesn’t know contractors, subs, things,
    so we’re trying to find the right people for the right job and go from there.” Bayliss admitted in
    his Answer that he was engaged to act as a “project manager and general contractor during
    construction,” and this was not a further issue in the litigation.
    4
    ¶8     Mandell sought summary judgment, arguing that because the parties had not
    reduced their agreement to writing, in violation of § 28-2-2201(2), MCA, the oral
    contract between them was invalid and unenforceable, and there was no basis for the
    construction lien on his property, nor any basis for Bayliss to claim breach of contract.
    The District Court partially granted Mandell’s claim for declaratory relief, concluding
    that because Bayliss failed to obtain a written contract for construction services, the
    contract for construction services was void and the lien for those services was invalid,
    leaving only that portion of the lien related for architectural services, in a maximum
    amount of $29,250, the amount claimed by Bayliss for those services. The District Court
    thus denied all claims for quiet title and foreclosure, awaiting trial to determine the final
    architectural lien amount.    Mandell did not request summary judgment on Bayliss’
    quantum meruit claim, and it was not addressed in the order. The District Court reserved
    the issue of attorney fees.
    ¶9     At trial, Bayliss produced evidence that $75,409.53 of the amount he had claimed
    was based upon invoices still owing for materials and subcontractors. The District Court
    issued Findings of Fact, Conclusions of Law and Order, concluding that Mandell owed
    $29,250 to Bayliss for architectural services and holding Mandell in breach of that
    contract between the parties. The court held that Bayliss’ construction lien was valid
    only for the $29,250 owed to him for architectural services, and ruled that, because
    Bayliss had established the lien, “the Court must award Bayliss [] its fees incurred for
    filing and recording the lien and reasonable attorney fees . . . .” The court further held
    5
    that “unjust enrichment and quantum meruit concepts apply to the transaction[,]” and
    awarded $75,409.53 as “an appropriate measure of quantum meruit damages.
    Mr. Mandell would be unjustly enriched if he retained the benefit of said services and
    materials, without paying for them.” The court summarily concluded that “[b]ased on the
    foregoing findings of fact and conclusions of law, Mr. Mandell cannot succeed to prove
    any of his claims.”
    ¶10    The District Court conducted a hearing on attorney fees.          Mandell disputed
    Bayliss’ entitlement to any fees beyond those related to establishing the construction lien
    related to architectural services. Bayliss called an expert witness who testified briefly of
    her opinion that the quantum meruit, breach of contract, and construction lien claims
    were inseparably intertwined. The District Court thereafter issued an order granting the
    entirety of Bayliss’ attorney fees and costs in the case. Mandell appeals.
    STANDARD OF REVIEW
    ¶11    Mandell’s appeal involves a review of both the District Court’s findings of fact
    and conclusions of law. When reviewing conclusions of law, this Court looks to see
    “whether the district court correctly interpreted the applicable law.”       James Talcott
    Constr., Inc. v. P&D Land Enters., 
    2006 MT 188
    , ¶ 26, 
    333 Mont. 107
    , 
    141 P.3d 1200
    .
    This Court applies a clearly erroneous standard using a three-part test to review a district
    court’s findings of fact. Talcott Constr., ¶ 26. “A district court’s findings are clearly
    erroneous if they are not supported by substantial credible evidence, if the trial court has
    misapprehended the effect of the evidence, or if a review of the record leaves this Court
    6
    with the definite and firm conviction that a mistake has been committed.” Morton v.
    Lanier, 
    2002 MT 214
    , ¶ 12, 
    311 Mont. 301
    , 
    55 P.3d 380
    (citing Guthrie v. Hardy, 
    2001 MT 122
    , ¶ 24, 
    305 Mont. 367
    , 
    28 P.3d 467
    ).
    ¶12    This Court reviews a trial court’s order granting or denying attorney fees and costs
    for abuse of discretion. Talcott Constr., ¶ 27.
    DISCUSSION
    ¶13 1. Did the District Court err in granting equitable relief in quantum meruit,
    despite violation of the statutory requirement that residential construction contracts be in
    writing?
    ¶14    Section 28-2-2201, MCA, part of legislation enacted in 2009, provides as follows:
    Residential construction contracts -- disclosure and warranty requirements.
    (1) For the purposes of this section, “residential construction contract”
    means a contract between a general contractor and an owner for the
    construction of a new residence.
    (2) All residential construction contracts that are subject to the provisions
    of this section must be in writing and must contain the following:
    (a) a disclosure that the general contractor has a current general
    liability policy;
    (b) a disclosure that the general contractor has a workers’
    compensation policy or is an independent contractor without employees;
    (c) a provision setting out the billing cycle establishing the payment
    schedule to be followed by the owner;
    (d) a provision establishing procedures for handling change orders by
    the owner;
    (e) a statement of all inspections and tests that the general contractor
    will perform or have performed prior to, during, or upon completion of
    construction and a statement that the owner is entitled to receive the results
    7
    of any tests conducted by the general contractor or conducted at the general
    contractor’s request;
    (f) a statement that the owner is entitled at the owner’s expense to have
    any inspections and tests conducted that the owner considers necessary; and
    (g) a statement that the general contractor is providing an express
    warranty that is valid for a period of at least 1 year from completion of the
    construction project. The warranty must provide detailed descriptions of
    those components that are included or excluded from the warranty, the
    length of the warranty, and any specialty warranty provisions or time
    periods relating to certain components. The warranty provisions must also
    clearly set forth the requirements that must be adhered to by the buyer,
    including the time and method for reporting warranty claims, in order for
    the warranty provision to become applicable.
    ¶15    Mandell argues that the District Court erred by permitting Bayliss to pursue relief
    under the equitable theory of quantum meruit because such relief circumvents
    § 28-2-2201(2), MCA, which requires that residential construction contracts be in
    writing. Mandell argues that a quantum meruit claim undermines the purposes of the
    statute, which he summarizes as “help[ing] to prevent conflicts that arise between
    builders and homeowners.” He cites to Featherman v. Kennedy, 
    122 Mont. 256
    , 260, 
    200 P.2d 243
    , 245 (1948), where we stated in regard to a statute requiring real estate
    brokerage contracts to be in writing, that “[t]o hold there could be recovery upon
    quantum meruit is to ‘open the door to the very abuses the statute was enacted to prevent,
    and defeat its manifest purpose.’” (citing Barney v. Lasbury, 
    107 N.W. 989
    , 991 (Neb.
    1906)). Mandell also cites In re Estate of Braaten, 
    2004 MT 213
    , ¶ 12, 
    322 Mont. 364
    ,
    
    96 P.3d 1125
    , where we rejected a quantum meruit claim in light of the “absolute”
    wording of a statute prohibiting oral agreements for a devise from an estate.
    8
    ¶16    Bayliss argues that Featherman and Braaten involved particular statutes of fraud
    that are discrete exceptions to the broader rule that “where one party repudiates a contract
    or breaches it by non-performance, the injured party may seek restitution of the unjust
    enrichment whether the Statute of Frauds applies or not.” Robertus v. Candee, 
    205 Mont. 403
    , 407, 
    670 P.2d 540
    , 542 (1983). Bayliss’ argument finds support in the recent Third
    Restatement of Restitution and Unjust Enrichment, which provides that equitable claims
    may be brought despite statutes requiring contracts to be in writing so long as the statute
    does not “prohibit a claim in restitution as well as a claim on the contract itself.”
    Restatement (Third) of Restitution and Unjust Enrichment, § 31 (2011). On this point,
    Bayliss notes that § 28-2-2201, MCA, does not contain language prohibiting equitable
    claims. Bayliss further disputes Mandell’s argument that permitting equitable claims
    would undermine the statute.      Noting concerns expressed in the statute’s legislative
    hearings about homeowners choosing not to fight liens despite defects in construction
    because of the fear they would have to pay attorney fees, Bayliss states that Ҥ 28-2-2201
    did [] away with a very powerful tool in any general contractor’s kit, the construction
    lien. By doing so, a contractor cannot recover attorney’s fees and must prove the fair
    value of his services.” Bayliss states that his failure to have a written contract led to the
    District Court forcing him to forfeit his construction management fee, but that forfeiture
    of the costs of materials and subcontractors in addition would be harsh and inequitable, as
    Mandell has received the benefit of these costs.
    9
    ¶17    “All contracts may be oral except such as are specially required by statute to be in
    writing.” Section 28-2-901, MCA. Section 28-2-2201(2), MCA, requires a “residential
    construction contract” to be in writing. An oral contract, when expressly required to be
    in writing, is void. See, e.g., Hanson v. Water Ski Mania Estates, 
    2005 MT 47
    , ¶¶ 17-21,
    
    326 Mont. 154
    , 
    108 P.3d 481
    (to be valid, a transfer of rights to run with land had to be in
    writing pursuant to § 28-2-903, MCA). Therefore, the District Court did not err in
    holding that the agreement between Mandell and Bayliss for residential construction
    services was void for failure to be reduced to writing. Further, because a contractor’s lien
    rights arise from a “real estate improvement contract,” § 71-3-523, MCA, the District
    Court correctly held that the voiding of the contract eliminated Bayliss’ lien rights for the
    construction management services he provided.
    ¶18    Turning to the question of whether equitable remedies remain under the statute,
    we are persuaded by Bayliss’ arguments. Section 28-2-2201, MCA, does not prohibit
    equitable remedies, a factor emphasized by the Restatement. The statute’s purpose of
    protecting the homeowner is not undermined by equitable remedies, because the statute
    operates to eliminate a contractor’s lien rights and the ability to collect attorney fees.
    Where the homeowner has reaped a benefit from the contractor’s efforts, unjust
    enrichment should be prevented. See 
    Robertus, 205 Mont. at 408-09
    , 670 P.2d at 542
    (“The theory of unjust enrichment requires that a person who has been unjustly enriched
    at the expense of another must make restitution to the other.”) (citation omitted); see also
    Brown v. Thornton, 
    150 Mont. 150
    , 156, 
    432 P.2d 386
    , 390 (1967) (quantum meruit
    10
    theory “arises not from consent of the parties but from the law of natural justice and
    equity, and is based on the doctrine of unjust enrichment.”). Here, although the District
    Court denied Bayliss’ construction management fee as a matter of equity, Mandell
    nonetheless also received the materials and services provided by subcontractors.
    ¶19    We conclude that our holdings in Featherman and Braaten are distinguishable.
    Featherman dealt with a statute requiring real estate agency contracts to be in writing, the
    purpose of which was “to prevent fraud and perjury in the enforcement of obligations
    depending for their evidence on the unassisted memory of witnesses . . . .” 
    Featherman, 122 Mont. at 259
    , 200 P.2d at 244. We reasoned that permitting recovery upon quantum
    meruit “to the case of real estate brokers absolutely nullifies” the statute. 
    Featherman, 122 Mont. at 261
    , 200 P.2d at 245. We also distinguished those cases in which an
    unwritten contract was fully executed—as here—from a real estate agent’s claim. “The
    fact that the contract between the buyer and seller of the real estate has been fully
    performed has nothing to do with the contract between the seller and the agent claiming a
    commission. . . . [The seller] has done nothing that can be said to be referable to the oral
    agreement to pay a commission.” 
    Featherman, 122 Mont. at 262
    , 200 P.2d at 246. Thus,
    unlike Featherman, neither the claims nor defenses here depend on the “unassisted
    memory of witnesses,” the statute would not be “absolutely nullified” by equitable
    remedies, as explained above, and the contract here between the original parties to the
    transaction has allegedly been completed. Similar reasons distinguish Braaten. There,
    we held the statute at issue was stated in “absolute” terms, which, for obvious reasons,
    11
    stated an absolute prohibition on claims that a deceased party had orally promised to
    make a devise while he was alive, unless he had verified his promise in writing. Braaten,
    ¶ 12.
    ¶20     Other courts have reached the same conclusion on this issue. See, e.g., Shafer
    Elec. & Constr. v. Mantia, 
    96 A.3d 989
    , 996 (Penn. 2014) (allowing recovery under
    theory of quantum meruit when statute required contracts for home improvements to be
    in writing); Fleissner v. Fitzgerald, 
    937 N.E.2d 1152
    (Ill. 2010) (permitting equitable
    recovery despite oral contract for home repair services in violation of statute which
    required such contracts to be in writing).
    ¶21     We hold that the District Court did not err in declaring the parties’ residential
    construction contract void in light of § 28-2-2201(2), MCA, and also did not err in
    concluding that the statute does not prohibit equitable remedies and require absolute
    forfeiture.
    ¶22 2. Did the District Court err in awarding attorney fees for the entire case,
    including the quantum meruit claim?
    ¶23     Mandell first argues that the District Court fully adjudicated the construction lien
    in its summary judgment order, that any further time Bayliss’ attorney spent on the lien
    issue was unnecessary, and that the District Court erred by awarding any attorney fees for
    time spent on the lien after that date. While Mandell appears to concede that Bayliss is
    entitled to attorney fees for prosecution of the portion of the lien deemed valid for
    architectural services, he argues that the remaining claims are easily separable and have
    no statutory basis for a fee award.
    12
    ¶24    Bayliss contends that the District Court correctly awarded all of his attorney fees
    pursuant to the Lodestar analysis, citing Blue Ridge Homes, Inc. v. Thein, 
    2008 MT 264
    ,
    
    345 Mont. 125
    , 
    191 P.3d 374
    , and JTL Group, Inc. v. New Outlook, LLP, 
    2010 MT 1
    ,
    
    355 Mont. 1
    , 
    223 P.3d 912
    , for the proposition that his claims were all inextricably
    intertwined, and therefore were properly awarded.
    ¶25    The District Court’s Decision and Order Ruling on Plaintiff’s Motion for
    Summary Judgment stated:
    All of these issues raise questions of fact that preclude summary judgment
    as to the issue of the construction lien, in so far as it reflects professional
    services for the [architectural] design of the home. . . . At this juncture,
    there are additional questions of fact that exist regarding the appropriate
    level of fees for the architectural services and whether some or all of the
    fees have been paid. . . . The amount of the architectural fee outstanding, if
    any, is the subject of further determination after resolution of the disputed
    fact inherent in this aspect of the case. . . . [B]ut the lien amount that can be
    claimed . . . may not exceed $29,250.
    After trial, the District Court found that “[t]he construction lien filed by Bayliss [], only
    so far as to the $29,250 for architectural services, is a valid lien.”
    ¶26    Although the District Court made potentially inconsistent statements about the
    status of the lien, we conclude upon review that the matter of the lien for architectural
    services was not finally adjudicated by the summary judgment order, as the court
    specifically found there were questions of fact remaining. After trial, the District Court
    determined the final amount of the lien, granting the $29,250 originally claimed.
    Because the matter was not considered final until trial, we conclude that further
    reasonable time expended by Bayliss’ counsel on this matter for trial is compensable.
    13
    Section 71-3-124(1), MCA, authorizes costs and attorney fees to be awarded to the
    prevailing party in a construction lien case.
    ¶27     Finally, we address the District Court’s award of attorney fees for Bayliss’
    remaining claims. “A court may award attorney fees only where a statute or contract
    provides for their recovery.” Thein, ¶ 78 (citing Stavenjord v. Mont. State Fund, 
    2006 MT 257
    , ¶ 21, 
    334 Mont. 117
    , 
    146 P.3d 724
    ). “[W]here a lawsuit involves multiple
    claims or theories, an award of attorney fees must be based on the time spent by the
    prevailing party’s attorney on the claim or theory under which attorney fees are
    allowable.” Thein, ¶ 78.
    ¶28     In Thein, Blue Ridge Construction brought claims against the homeowner that
    were similar to Bayliss’ claims here: breach of contract, foreclosure of construction lien,
    and quantum meruit. Thein, ¶ 13. The jury awarded both contract damages and recovery
    in quantum meruit, and Blue Ridge elected contractual damages. Thein, ¶ 18. The
    district court awarded attorney fees on all of Blue Ridge’s related claims, including the
    quantum meruit claim, because they were “inextricably intertwined.” Thein, ¶ 77. We
    affirmed the fee award, reasoning that the claims at issue were “inseparable.” Thein,
    ¶ 79.
    ¶29     However, this case differs from Thein as a matter of both law and fact. We are
    faced here with the application of a new statute not at issue in Thein. Bayliss has argued
    and we concluded above that quantum meruit is an available remedy here in part because
    § 28-2-2201, MCA, would not be undermined by such relief—a violation of the statute
    14
    still operates to eliminate the contractor’s lien rights, including attorney fees.       See
    Opinion, ¶¶ 16, 18. However, despite having forfeited attorney fees under the statute,
    Bayliss was nonetheless awarded fees on his quantum meruit claim in the final fee order.
    In order to give effect to the new statute, we conclude that the award of fees on the
    quantum meruit claim was error and must be reversed. Further, unlike Thein, the claims
    here in our view are not inseparable as a matter of fact, and the District Court’s finding to
    the contrary was clearly erroneous.       Though some factual questions remained, the
    architectural lien issue was largely established by the summary judgment order, and the
    District Court ultimately granted the amount it had set as the maximum amount for the
    lien in its earlier order.
    ¶30    We remand this matter to the District Court to enter an award of attorney fees due
    to Bayliss in conjunction with the prosecution of his lien for architectural services only,
    pursuant to the analysis for determining reasonable attorney fees, see JTL Group, ¶ 18,
    and for entry of an amended judgment.
    ¶31    Affirmed in part, reversed in part, and remanded for further proceedings consistent
    with this Opinion.
    /S/ JIM RICE
    We concur:
    /S/ MIKE McGRATH
    /S/ LAURIE McKINNON
    /S/ PATRICIA COTTER
    /S/ JAMES JEREMIAH SHEA
    15