Bitterrooters for Planning, Inc. v. Montana Department of Environmental Quality , 388 Mont. 453 ( 2017 )


Menu:
  •                                                                                          09/05/2017
    DA 16-0429
    Case Number: DA 16-0429
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    
    2017 MT 222
    BITTERROOTERS FOR PLANNING, INC., and
    BITTERROOT RIVER PROTECTIVE ASSOCIATION, INC.
    Plaintiffs and Appellees,
    v.
    MONTANA DEPARTMENT OF ENVIRONMENTAL
    QUALITY, an agency of the State of Montana,
    Defendant and Appellant,
    STEPHEN WANDERER and GEORGIA FILCHER,
    Defendants, Intervenors and Appellants.
    APPEAL FROM:       District Court of the First Judicial District,
    In and For the County of Lewis and Clark, Cause No. ADV 15-32
    Honorable Mike Menahan, Presiding Judge
    COUNSEL OF RECORD:
    For Appellant:
    Alan F. McCormick (argued), Stephen R. Brown, Garlington, Lohn,
    Robinson, Missoula, Montana
    Edward Hayes (argued), Kirsten H. Bowers, Special Assistant
    Attorneys General, Helena, Montana
    For Appellees:
    Jack R. Tuholske (argued), Tuholske Law Office, P.C., Missoula,
    Montana
    David K. W. Wilson, Jr., Morrison, Sherwood, Wilson, & Deola, Helena,
    Montana
    For Amicus:
    Derf L. Johnson, Montana Environmental Information Center,
    Helena, Montana
    Argued and Submitted: March 29, 2017
    Decided: September 5, 2017
    Filed:
    __________________________________________
    Clerk
    2
    Justice Dirk Sandefur delivered the Opinion of the Court.
    ¶1       The Montana Department of Environmental Quality (DEQ) appeals from an order
    of the Montana First Judicial District Court granting summary judgment to Bitterrooters
    for Planning, Inc., and Bitterroot River Protective Association, Inc., (collectively
    Bitterrooters) that DEQ violated the Montana Environmental Policy Act1 (MEPA) by
    issuing a wastewater discharge permit for an unnamed “big box” retail merchandise store
    near Hamilton, Montana, without considering environmental impacts of the construction
    and operation of the facility other than water quality impacts and impacts of the
    construction of the required wastewater treatment system. Intervenors and current owners
    of the site, Stephen Wanderer and Georgia Filcher (Landowners), join that appeal and
    further appeal the District Court’s related summary judgment that MEPA requires DEQ to
    identify the owner or operator of the contemplated retail store. We reverse, in part, and
    affirm, in part.
    ISSUES
    1. Does MEPA require DEQ to consider non-water quality related environmental
    impacts of the construction and operation of a retail store facility as secondary
    impacts of the issuance of a Montana Water Quality Act (MWQA) permit to
    discharge facility wastewater into the ground from an onsite wastewater treatment
    system?
    2. Does MEPA require DEQ to identify the actual owner or operator of a wastewater
    treatment facility prior to issuing a MWQA groundwater discharge permit?
    1
    Title 75, Chapters 1-3, MCA.
    3
    BACKGROUND
    ¶2     On April 3, 2014, DEQ received an application for a Montana groundwater
    pollution control system (MGWPCS) permit2 to discharge Level 2 wastewater3 into Class 1
    groundwater on the site of a contemplated commercial development at the intersection of
    U.S. Highway 93 and Blood Lane near Hamilton, Montana. The contemplated discharge
    would occur via a proposed onsite wastewater treatment facility and drainfield designed to
    treat sanitary and floor drain discharges from a 156,529 square-foot retail store facility to
    be constructed on the site. The groundwater discharge would eventually migrate
    down-gradient to the nearby Bitterroot River in Ravalli County.
    ¶3     DEQ received the application under submittal letter, dated March 31, 2014, from
    CT Consultants, an engineering firm in Columbus, Ohio. The letter bore the signature of
    John D. Zaleha, E.I., “Project Engineer.” The application consisted of DEQ standard
    Forms 1 and GW-1 with referenced attachments. As supplemented at DEQ’s request, the
    application identified the type and nature of the contemplated facility or operation by
    reference to a Standard Industrial Code (SIC 5311) indicating a retail merchandise and
    grocery facility. An included project site map indicated a large retail facility and parking
    lot that would together cover approximately half of the 16.54 acre site. The application
    2
    Sections 75-5-401 through -405, MCA (DEQ duty to regulate wastewater discharge pursuant to
    Board of Environmental Review rules), and Admin. R. M. Title 17, chapter 30, parts 1 and 10
    (MGWPCS rules).
    3
    A “Level 2 treatment” system is a subsurface wastewater treatment system that “(a) removes at
    least 60% of total nitrogen as measured from the raw sewage load to the system or systems or
    (b) discharges a total nitrogen effluent concentration of 24 mg/L or less.” Admin. R. M.
    17.30.702(11). The proposed wastewater treatment facility was designed to remove greater than
    90 percent of total nitrogen.
    4
    listed the various types of contemplated effluents with their respective characteristics. As
    proposed, the treatment system would on average handle 5,100 gallons of effluent from
    sanitary wastes (95%) and floor drains (5%). As supplemented, except for identification
    of the contemplated facility name and the actual contemplated owner or operator, the
    application included all standard information typically required by DEQ for issuance of a
    MGWPCS permit.
    ¶4     The certification and signature sections of both DEQ application forms listed
    Ravalli County real estate broker Lee Foss (Foss) as the permit applicant. Section C of
    Form 1 also listed Foss as the “Facility Contact.” The “Facility Information” sections of
    both forms listed the property’s state property tax identification number (Parcel #698800)
    as the “Facility Name.” Section F of Form 1 listed Foss as the “Applicant (Operator)” of
    the contemplated facility and that the listed “Operator” was not the property owner.
    ¶5     By correspondence to Foss dated April 21, 2014, DEQ identified and requested
    additional information regarding various application “deficiencies” including, inter alia,
    clarification of the name of the facility and the name of the permitee who would be “the
    responsible entity” to insure compliance with permit conditions for the authorized
    discharge. By subsequent correspondence, CT Consultants, through Project Engineer
    Zaleha, reiterated that the facility name was Parcel #698800 and that Foss would be the
    permitee, as originally listed.    DEQ’s Supplemental Responses to Plaintiffs’ First
    Discovery Requests indicated that the agency’s Director specifically “asked Mr. Foss to
    disclose the identity of the developer of the property” but “Mr. Foss declined to do so.”
    5
    ¶6     It is undisputed on the record that real estate broker Lee Foss had no intention of
    actually owning or operating the contemplated facility. He requested the MGWPCS permit
    to facilitate the sale of the property to a particular third-party known to Foss and
    Landowners. Upon sale of the property, Foss would transfer the permit to the intended
    owner or operator who would construct and operate the retail store.4
    ¶7     In May 2014, DEQ issued a Draft Checklist Environmental Assessment (draft EA),
    a draft wastewater discharge permit, and a permit fact sheet. The draft EA identified the
    proposed agency action as the issuance of a permit authorizing “discharge of treated
    domestic water via a subsurface drainfield [pursuant to] the Montana Groundwater
    Pollution Control System (MGWPCS) permit program” established by Admin. R. M.
    Title 17, chapter 30, part 10. The draft EA stated that the limited purpose of the permit
    was:
    to regulate the discharges of pollutants to state waters from the regulated
    facility. Issuance of an individual permit will require the applicant to
    implement, monitor and manage practices to prevent pollution and the
    degradation of ground water.
    The draft permit specified allowable discharge limits for total nitrogen and total
    phosphorus and specified ongoing water quality monitoring and reporting measures
    required by DEQ. The permit fact sheet described the wastewater treatment system, point
    of discharge effluent limits, site hydrogeology, and vicinity groundwater quality issues.
    4
    Opposition comments in the administrative record presume that the contemplated retail store will
    be a Walmart store.
    6
    The fact sheet further explained DEQ’s rationale for the proposed terms and conditions of
    the permit.
    ¶8     The draft EA concluded that, as treated and discharged beyond the “approved
    mixing zone” on the property, the contemplated wastewater discharge would not exceed
    applicable water quality standards and thus would have no “significant adverse effects [on]
    the human and physical environment.”         The draft EA referenced a similar lack of
    significant impact on various standard physical environment checklist factors. Inter alia,
    the draft EA included a statement that “construction of the facility will alter” the existing
    undeveloped use of the land but not impact any “listed vegetative species.” Though finding
    no significant adverse impact on various standard human environment checklist factors,
    the draft EA concluded that the construction and operation of “the facility” would have the
    potential to increase commercial activity in the area, increase traffic in the area, create
    temporary jobs during construction, create permanent jobs post-construction, and increase
    local tax revenue.
    ¶9     DEQ received written comments from approximately 160 individuals and members
    of local organizations. More than 80 people attended a public hearing on September 18,
    2014. Due to the high level of public interest and technical difficulties with its electronic
    public comment submission system, DEQ extended the public comment period until
    October 15, 2014. On November 17, 2014, DEQ released a final EA and associated fact
    sheet and concurrently issued the requested wastewater discharge permit to Foss as
    originally recommended in the draft EA.
    7
    ¶10    With a few exceptions, the final EA mirrored the draft EA.              Based on new
    information provided by commenters regarding the existence of a down-gradient natural
    spring near the project area, the final EA noted that DEQ lowered the permissible level of
    phosphorous discharge from the proposed wastewater treatment facility. Inter alia, the
    document concluded that the treatment system and expected wastewater discharges to
    groundwater would result in “no potential adverse impact to elk winter range.”
    ¶11    DEQ organized public comments by topic and prepared 106 formal responses to
    address public concerns. The agency noted that most issues raised by commenters were
    “beyond the scope” of the agency’s EA analysis, and declined to address various stated
    public concerns about non-water quality related impacts of the construction and operation
    of the larger retail facility, including the potential spread of noxious weeds, “light
    pollution,” noise pollution, air pollution, soil pollution, permanent traffic increases, traffic
    safety, building aesthetics, scenic degradation, the risk of decreases in nearby residential
    property values, and the effect of marketplace competition on other local businesses and
    employees. The final EA further stated that DEQ had no authority to require the developer
    to build at an alternative site in Hamilton to allow connection to the city sewage treatment
    system and thereby eliminate the need for the contemplated groundwater discharge. The
    final EA did address questions regarding the adequacy of self-monitoring of the treatment
    facility by the owner or operator and public perception of a need for additional down-
    gradient water quality monitoring.
    ¶12    The final EA referenced various secondary impacts identified in the draft EA, but
    this time more narrowly characterized them as impacts resulting from the construction of
    8
    the subject wastewater treatment system rather than impacts of the larger construction and
    operation of the retail facility. The final EA ultimately concluded that MEPA did not
    require a formal environmental impact statement (EIS) “because the project lacks
    significant adverse effects to the human or physical environment.” With reference to
    DEQ’s limited authority to regulate groundwater discharges “to ensure the protection of
    the beneficial uses of state waters and compliance with the applicable water quality
    standards,” the EA concluded that DEQ complied with all applicable MEPA requirements.
    ¶13    On January 14, 2015, Bitterrooters petitioned the Montana First Judicial District
    Court for judicial review on the asserted grounds that DEQ’s wastewater discharge
    permitting process violated the Montana Water Quality Act (MWQA), MEPA, and the
    public’s right to participate in governmental deliberations under Article II, Section 8 of the
    Montana Constitution and § 2-3-101, MCA, et seq. Bitterrooters alleged that the issuance
    of the wastewater discharge permit violated MWQA by failing to adequately consider the
    impact of the contemplated wastewater discharge on the water quality of the nearby
    Bitterroot River and tributaries. They alleged that the permit violated both MWQA and
    MEPA by failing to adequately consider the cumulative water quality impacts of
    wastewater discharges from the contemplated retail facility in conjunction with previously
    permitted discharges from the nearby Grantsdale subdivision. Bitterrooters asserted that
    the process further violated MEPA by failing to adequately consider the secondary impacts
    of the larger construction and operation of the retail facility unrelated to water quality. On
    May 16, 2016, on consideration of the parties’ respective motions to dismiss and for
    summary judgment pursuant to M. R. Civ. P. 12(b)(6) and 56, the District Court:
    9
    (1)    dismissed Bitterrooters’ right-to-participate claim as time-barred by the
    applicable statute of limitations, §§ 2-3-114 and -213, MCA;
    (2)    granted summary judgment that DEQ violated MWQA by failing to
    adequately consider:
    (A)    the effect of the contemplated discharge of nitrate-contaminated
    groundwater on the quality of nearby surface waters in violation of
    § 75-5-301(5)(d), MCA, and Admin. R. M. 17.30.715(1)(d); and
    (B)    the cumulative water quality effects of wastewater discharges from
    the contemplated retail facility and the nearby Grantsdale subdivision
    in violation of Admin. R. M. 17.30.715(2)(a);
    (3)    granted summary judgment that DEQ violated MEPA by failing to
    adequately consider:
    (A)    the cumulative water quality effects of wastewater discharges from
    the contemplated retail facility and the nearby Grantsdale subdivision
    as required by § 75-1-208(11), MCA, and Admin. R. M. 17.4.603(7)
    and (12); .609(3)(d) and (e);
    (B)    impacts of the construction and operation of the contemplated retail
    facility as secondary impacts of issuance of the wastewater discharge
    permit in violation of Admin. R. M. 17.4.603(12) and (18) and
    .609(3)(d) and (e); and
    (4)    granted summary judgment that Admin. R. M. 17.4.609(3)(d) (criteria for
    evaluation of cumulative and secondary impacts of state action on physical
    environment) required DEQ to identify the “facility operator if the operator’s
    identity has the potential to impact vegetation, aesthetics, human health and
    safety, industrial and commercial activities, employment, tax revenues,
    demand for government services, or other environmental resources.”
    ¶14   DEQ appeals only the District Court’s ruling that it violated MEPA by failing to
    consider environmental impacts of the construction and operation of the facility other than
    water quality impacts and impacts of the related construction of the required wastewater
    treatment system. Landowners join DEQ’s appeal and further separately appeal the District
    10
    Court’s ruling that Admin. R. M. 17.4.609(3)(d) requires disclosure of the identity of the
    actual contemplated owner or operator of the retail facility.
    STANDARDS OF REVIEW
    ¶15    We review a district court’s grant or denial of summary judgment, and related
    conclusions of law, de novo for correctness. Smith v. BNSF Railway, 
    2008 MT 225
    , ¶ 10,
    
    344 Mont. 278
    , 
    187 P.3d 639
    ; Montana Trout Unlimited v. Montana Dep’t of Nat. Res. &
    Conserv., 
    2006 MT 72
    , ¶ 17, 
    331 Mont. 483
    , 
    133 P.3d 224
    . The standard of review of the
    sufficiency of an agency’s environmental review under MEPA is whether the decision was
    unlawful or arbitrary and capricious. Section 75-1-201(6)(a)(iii), MCA; Montana Wildlife
    Fed. v. Mont. Bd. of Oil & Gas Conserv., 
    2012 MT 128
    , ¶ 25, 
    365 Mont. 232
    , 
    280 P.3d 877
    . An agency decision is unlawful if it does not comply with governing laws and
    administrative rules. North Fork Preservation Ass’n v. Dep’t of State Lands, 
    238 Mont 451
    , 459, 
    778 P.2d 862
    , 867 (1989). We will sustain an agency’s interpretation of its rule
    “so long as it lies within the range of reasonable interpretation permitted by” the language
    of the rule. Clark Fork Coal. v. Montana Dep’t of Envt’l Quality, 
    2008 MT 407
    , ¶ 20, 
    347 Mont. 197
    , 
    197 P.3d 482
    .
    ¶16    An agency decision is arbitrary and capricious if made without consideration of all
    relevant factors or based on a clearly erroneous judgment. Clark Fork Coal., ¶ 21; North
    Fork Preservation Ass’n, 238 Mont at 465, 
    778 P.2d at 871
    . However, the arbitrary and
    capricious standard does not permit reversal “merely because the record contains
    inconsistent evidence or evidence which might support a different result.” Montana
    Wildlife Fed., ¶ 25. Rather, the decision “must appear to be random, unreasonable or
    11
    seemingly unmotivated based on the existing record.” Montana Wildlife Fed., ¶ 25. We
    cannot substitute our judgment for that of the agency but will not defer to an agency
    decision without a searching and careful review of the record to verify that the agency
    made a reasoned decision. Friends of the Wild Swan v. Dep’t of Nat. Res. & Conservation,
    
    2000 MT 209
    , ¶ 28, 
    301 Mont. 1
    , 
    6 P.3d 972
    ; North Fork Preservation Ass’n, 238 Mont.
    at 465, 
    778 P.2d at 871
    .
    DISCUSSION
    ¶17      Mindful of the Legislature’s constitutional duty to maintain and provide for a clean
    and healthful environment,5 and for the purpose of protecting our environment in balance
    with the right to use and enjoy private property free from undue government regulation,
    MEPA requires state agencies to conduct an environmental review of any
    contemplated agency action that may have an impact on the human environment. Sections
    75-1-102, -201(1), and -220(5), MCA. Within the required scope of review, MEPA
    requires agencies “to take a hard look” at the environmental impacts of contemplated
    agency action. Montana Wildlife Fed., ¶ 43. “Implicit in the requirement that an agency
    take a hard look at the environmental consequences of its actions is the obligation to make
    5
    Montana Constitution, Article IX, Section 1, provides:
    (1) The state and each person shall maintain and improve a clean and healthful
    environment in Montana for present and future generations.
    (2) The legislature shall provide for the administration and enforcement of this duty.
    (3) The legislature shall provide adequate remedies for the protection of the
    environmental life support system from degradation and provide adequate remedies
    to prevent unreasonable depletion and degradation of natural resources.
    See also, Mont. Const. art. II, § 3 (individual right to a clean and healthful environment).
    12
    an adequate compilation of relevant information, to analyze it reasonably, and to consider
    all pertinent data.” Clark Fork Coal., ¶ 47.
    ¶18       However, MEPA requirements are merely “procedural” and do not require an
    agency to reach any particular decision in the exercise of its independent authority.
    Section 75-1-102(1), MCA; Montana Wildlife Fed., ¶ 32. See also, § 75-1-102(3)(b), MCA
    (MEPA provides no additional regulatory authority to an agency and does not affect an
    agency’s specific statutory duties to comply with environmental quality standards); § 75-1-
    201(4)(a), MCA (reviewing “agency may not withhold, deny, or impose conditions on any
    permit or other authority to act based on” MEPA). The essential purpose of MEPA is to
    aid in the agency decision-making process otherwise provided by law by informing the
    agency and the interested public of environmental impacts that will likely result from
    agency actions or decisions. Sections 75-2-102(1)(b) and (3)(a), MCA. Because the
    Legislature modeled MEPA on the National Environmental Policy Act (NEPA),6 federal
    authority construing NEPA is generally persuasive guidance in the construction of similar
    provisions of MEPA. North Fork Preservation Ass’n, 238 Mont. at 457, 
    778 P.2d at 866
    ;
    Ravalli County Fish & Game Ass’n v. Montana Dep’t of State Lands, 
    273 Mont. 371
    , 377,
    
    903 P.2d 1362
    , 1367 (1995).
    ¶19 Issue 1: Does MEPA require DEQ to consider non-water quality related
    environmental impacts of the construction and operation of a retail store facility as
    secondary impacts of the issuance of a Montana Water Quality Act (MWQA) permit to
    discharge facility wastewater into the ground from an onsite wastewater treatment
    system?
    6
    
    42 U.S.C. § 4321
    , et seq.
    13
    ¶20    MEPA requires an agency to produce a formal environmental impact statement
    (EIS) if an agency action will significantly affect the quality of the human environment.
    Section 75-1-201(1)(b)(iv), MCA; Montana Wildlife Fed., ¶ 43. However, MEPA does
    not require an EIS if a preliminary EA determines that the agency action will not
    significantly affect the quality of the human environment. Section 75-1-201(1)(b)(iv),
    MCA; Admin. R. M. 17.4.607(2) and .608 (general environmental review requirements);
    Kadillak v. Anaconda Co., 
    184 Mont. 127
    , 134, 
    602 P.2d 147
    , 152 (1979). An EA thus
    serves as both the initial tool for determining whether a more intensive EIS is necessary
    and as the mechanism for required environmental review of agency actions that will likely
    impact the environment but not sufficiently to require an EIS. Sections 75-1-102(1) and
    (3)(a), -201(1)(a) and (b)(i)(B), and -220(5), MCA (EIS/EA purposes, definitions,
    legislative intent, and general requirements for “adequate review” of environmental impact
    of “state actions”); Admin. R. M. 17.4.607(2) through (4) and 17.4.608, (environmental
    review requirements and significant impact evaluation criteria). On appeal, Bitterrooters
    do not contest DEQ’s determination that an EA would suffice as the mechanism for
    required environmental review based on its threshold determination that issuance of the
    contemplated wastewater discharge permit will not significantly affect the quality of the
    human environment.7 Bitterrooters similarly do not challenge DEQ’s identification and
    evaluation of alternatives to the issuance of a discharge permit as required by §§ 75-1-
    7
    It is undisputed on the record that the contemplated wastewater discharge will not exceed a 7.5
    mg/L nitrate concentration thus effecting a “nonsignificant change” in groundwater quality that
    will not cause degradation to surface water under § 75-5-301(5)(d), MCA (MWQA water quality
    standards).
    14
    201(1)(b)(i)(B) and -220(1), MCA. Therefore, we review Bitterrooters’ assertion of error
    only as it relates to the sufficiency of the final EA as the mechanism of required MEPA
    review.
    ¶21    Except for requiring evaluation of cumulative impacts of a proposed project “when
    appropriate,” § 75-1-208(11), MCA, MEPA does not specify the required contents or scope
    of a preliminary EA. See, e.g., §§ 75-1-102(1) and (3), -201(1)(b)(i)(B), and -220(5),
    MCA. In this context, the Legislature has directed the Montana Board of Environmental
    Review (BER) to promulgate rules specifying the general MEPA requirements for DEQ
    actions. Sections 75-5-103(3) and -201, MCA (BER rulemaking authority under MWQA);
    Admin. R. M. 17.4.102, .607(2) through (4), .608, and .609. An EA may be in a “standard
    checklist” form for “routine action with limited environmental impact.” Admin. R. M.
    17.4.609(2). For other actions, an EA must be in a narrative form “containing a more
    detailed analysis of specified criteria.” Admin. R. M. 17.4.609(2) and (3). In either form,
    an EA must include, inter alia, “an evaluation of the impacts, including cumulative and
    secondary impacts,” on the “physical environment” and on the “human population in the
    area to be affected by the proposed action.” Admin. R. M. 17.4.609(3)(d) and (e); see also,
    §§ 75-1-102(1) and (3)(a), -201(1)(a), -208(11), and -220(5), MCA (in re cumulative
    impacts). Impacts may be adverse, beneficial, or both. Admin. R. M. 17.4.608(2).
    ¶22    Relevant criteria for evaluation of secondary impacts of the proposed action on the
    physical environment include, “where appropriate[,] terrestrial and aquatic life and
    habitats; water quality, quantity, and distribution; geology; soil quality, stability, and
    moisture; vegetation cover, quantity and quality; aesthetics; air quality; unique,
    15
    endangered, fragile, or limited environmental resources; historical and archaeological sites;
    and demands on environmental resources of land, water, air and energy.” Admin. R. M.
    17.4.609(3)(d) (emphasis added). The term “human environment” includes “biological,
    physical, social, economic, cultural, and aesthetic factors that interrelate to form the
    environment.” Admin. R. M. 17.4.603(12). Relevant criteria for evaluation of secondary
    impacts of a proposed action on the affected human population include, “where
    appropriate, social structures and mores; cultural uniqueness and diversity; access to and
    quality of recreational and wilderness activities; local and state tax base and tax revenues;
    agricultural or industrial production; human health; quantity and distribution of
    employment; distribution and density of population and housing; demands for government
    services; industrial and commercial activity; locally adopted environmental plans and
    goals; and other appropriate social and economic circumstances.”            Admin. R. M.
    17.4.609(3)(e) (emphasis added).      By operation of the qualifying language “where
    appropriate,” the laundry lists of secondary impact evaluation criteria in Admin.
    R. M. 17.4.609(3)(d) and (e), are not mandatory evaluation criteria in every case. Rather,
    the relevance or propriety of particular criterion, if any, depends on the nature of the
    proposed state action in each particular case.
    ¶23    Though it mandates “adequate review” of potential environmental impacts of state
    actions, MEPA does not specifically define what constitutes a triggering state action. See,
    e.g., §§ 75-1-102(1), -201(1)(b)(iv), -220(5), MCA. See also, § 75-1-220(8), MCA
    (defining “state-sponsored project” and distinguishing state-sponsored projects from
    projects or activities involving the issuance of a state permit). In the current absence of a
    16
    statutory definition, administrative rule defines state “action” to include an “activity
    involving the issuance of a . . . permit . . . for use or permission to act by the agency.”
    Admin. R. M. 17.4.603(1); see also, § 75-1-102(3)(a), MCA (MEPA applies to state
    agency “decisions”). In this case, the state action triggering MEPA review was the
    proposed issuance of a DEQ MGWPCS groundwater discharge permit pursuant to Title
    75, chapter 5, part 4, MCA, and Admin. R. M. Title 17, chapter 30, part 10.
    ¶24    For purposes of MEPA, “secondary impact” means “a further impact to the human
    environment that may be stimulated or induced by or otherwise result from a direct impact
    of the action.” Admin. R. M. 17.4.603(18). MEPA statutes and rules do not define the
    term “direct impact.” By comparison, NEPA does not define a “direct impact” but defines
    “direct effects” as effects or impacts “caused by the action . . . at the same time and place.”
    
    40 C.F.R. § 1508.8
    (a) (emphasis added). In concluding that Admin. R. M. 17.4.609(3)(d)
    and (e) required DEQ to consider impacts of the construction and operation of the facility
    beyond those merely related to water quality or the construction of the required wastewater
    system, the District Court essentially concluded that those other impacts were secondary
    impacts of the issuance of the permit itself rather than of the permitted activity. In other
    words, the construction and operation of the retail store would not occur “but for” the
    issuance of the wastewater permit. Thus, the District Court expansively shifted the focus
    of MEPA on impacts caused by the permitted action to the much broader and more
    attenuated action and resulting impacts that would not occur “but for” the issuance of the
    permit.
    17
    ¶25    The District Court’s expansive tail-wagging-the-dog reasoning is backwards as a
    matter of fact and erroneous as a matter of law. Logically, the permitted wastewater
    discharge from the facility, and the related construction of its component wastewater
    treatment system, are not the causes-in-fact of the larger construction and operation of the
    retail store. Rather, the construction and operation of the retail store are the causes-in-fact
    of the wastewater discharge and related treatment system. MEPA, like NEPA, requires “a
    reasonably close causal relationship” between the subject government action and the
    particular environmental effect. Department of Transportation v. Public Citizen, 
    541 U.S. 752
    , 767, 
    124 S. Ct. 2204
    , 2215 (2004); Metropolitan Edison Co. v. People Against
    Nuclear Energy, 
    460 U.S. 766
    , 773, 
    103 S. Ct. 1556
    , 1561 (1983) (NEPA requires a
    “reasonably close causal relationship between a change in the physical environment and
    the effect at issue”); see also, Admin. R. M. 17.4.603(1) (defining state “action” in terms
    of the permitted activity); 
    40 C.F.R. § 1508.8
    (a) (defining “direct effect” as an impact
    “caused by the action”).
    ¶26    In Public Citizen, various unions and environmental groups asserted that a
    sub-agency of the U.S. Department of Transportation (USDOT) responsible for regulating
    motor carrier safety violated NEPA by failing to consider potential environmental impacts
    of increased Mexican commercial truck traffic in the U.S. when it adopted safety
    regulations applicable to Mexican trucks independently authorized to operate in the U.S.
    by the controversial North American Free Trade Agreement (NAFTA). Public Citizen,
    
    541 U.S. at 758-62
    , 
    124 S. Ct. at 2210-12
    . The sub-agency’s EA narrowly focused on
    environmental impacts of the increase in roadside safety inspections that would result from
    18
    its more stringent vehicle safety regulations. Public Citizen, 
    541 U.S. at 761
    , 
    124 S. Ct. at 2212
    . The EA concluded that NEPA did not require the sub-agency to consider the broader
    environmental impacts of increased Mexican truck traffic in the U.S. because NAFTA, and
    related presidential action, was the cause of the traffic increase, not the sub-agency’s safety
    regulations. Public Citizen, 
    541 U.S. at 761
    , 
    124 S. Ct. at 2212
    . On review, the U.S. Ninth
    Circuit Court of Appeals agreed with the environmental groups and unions that the
    sub-agency EA violated NEPA because, even though NAFTA was the cause of the traffic
    increase, Mexican trucks could not operate here unless they complied with the
    sub-agency’s safety regulations. Public Citizen, 
    541 U.S. at 761
    , 
    124 S. Ct. at 2212
    .
    ¶27    On appeal, the United States Supreme Court characterized the Ninth Circuit’s
    expansive construction of NEPA as “a particularly unyielding variation of ‘but for’
    causation, where an agency’s action is considered a cause of an environmental effect even
    when the agency has no authority to prevent the effect.” Public Citizen, 
    541 U.S. at 767
    ,
    
    124 S. Ct. at 2215
    . The Supreme Court held that the Ninth Circuit’s expansive “but for”
    standard of causation was “insufficient to make an agency responsible for a particular
    effect” because “NEPA requires ‘a reasonably close causal relationship’ between the
    environmental effect and the alleged cause.” Public Citizen, 
    541 U.S. at 767
    , 
    124 S. Ct. at 2215
     (quoting Metropolitan Edison Co., 
    460 U.S. at 773-74
    , 
    103 S. Ct. at 1561
    ). By
    analogy to the “familiar doctrine of proximate cause from tort law,” the Court characterized
    NEPA’s more demanding causation standard as drawing a “manageable line between those
    causal changes that may make an actor responsible for an effect and those that do not.”
    Public Citizen, 
    541 U.S. at 767
    , 
    124 S. Ct. at 2215
    . The Supreme Court thus analyzed the
    19
    requisite causal connection triggering NEPA review as a function of NEPA’s essential
    purposes to ensure that (1) agencies adequately consider environmental impacts of their
    actions and (2) the interested public can monitor agency proceedings and “play a role” in
    the agency decision-making process and the implementation of the decisions. Public
    Citizen, 
    541 U.S. at 768
    , 
    124 S. Ct. at 2216
    . The Court emphasized NEPA’s essential
    informational purpose to allow the interested public to “provide input as necessary to the
    agency making the relevant decisions.” Public Citizen, 
    541 U.S. at 768
    , 
    124 S. Ct. at 2216
    (emphasis added).
    ¶28    Noting that the USDOT motor carrier safety sub-agency had no authority to regulate
    the increase in Mexican truck traffic caused by NAFTA, the Supreme Court concluded that
    requiring the sub-agency to consider impacts it could not prevent would not serve NEPA’s
    essential purposes. Public Citizen, 
    541 U.S. at 768-69
    , 
    124 S. Ct. at 2216
    . Thus, the Court
    held that an “agency cannot be considered a legally relevant ‘cause’” of an effect when the
    agency cannot prevent the effect in the lawful exercise of its limited authority. Public
    Citizen, 
    541 U.S. at 770
    , 
    124 S. Ct. at 2217
    . See also, Winnebago Tribe of Neb. v. Ray,
    
    621 F.2d 269
    , 273 (8th Cir. 1980) (Corps of Engineers’ NEPA review authority limited to
    review of matters within its regulatory jurisdiction notwithstanding that larger power line
    project was necessarily contingent on water-crossing permit); Save the Bay, Inc. v. U.S.
    Army Corps of Engineers, 
    610 F.2d 322
    , 327 (5th Cir. 1980) (Corps of Engineers’ NEPA
    review authority limited to review of matters within its regulatory jurisdiction
    notwithstanding that larger pipeline project was necessarily contingent on water-crossing
    permit); Residents for Sane Trash Solutions v. U.S. Army Corps of Engineers, 
    31 F. Supp. 20
    3d 571, 588-90 (S.D. N.Y. 2014) (Corps of Engineers’ NEPA review authority limited to
    review of matters within its regulatory jurisdiction notwithstanding that larger garbage
    plant project was contingent on harbor dredging permit).
    ¶29    We reached a similar result under MEPA in Montana Wilderness Ass’n v. Montana
    Bd. of Health & Env’tl Sciences, 
    171 Mont. 477
    , 
    559 P.2d 1157
     (1976). In that case,
    wilderness and environmental protection groups challenged the sufficiency of an EIS
    issued by DEQ’s predecessor agency, the Department of Health and Environmental
    Services (DHES), incident to issuance of a certificate of approval of a proposed 95-acre
    subdivision in the Big Sky resort area for compliance with applicable water supply, sewage,
    and solid waste disposal regulations. Montana Wilderness Ass’n, 171 Mont. at 478-82,
    
    559 P.2d at 1158-59
    . The plaintiffs asserted that DHES violated MEPA by failing to
    consider the potential environmental impacts of the proposed subdivision beyond the
    impacts of the water supply, sewage, and solid waste disposal issues within the scope of
    DHES’ regulatory authority. Montana Wilderness Ass’n, 171 Mont. at 480-82, 
    559 P.2d at 1159
    . Reasoning that the proposed subdivision could not proceed without the requested
    water supply, sewage, and solid waste disposal regulation compliance certificate, the
    District Court concluded that MEPA required DHES to consider all potential
    environmental impacts of the subdivision regardless of the limited scope of its regulatory
    authority. Montana Wilderness Ass’n, 171 Mont. at 482-83, 
    559 P.2d at 1160
    . We
    reversed, holding that the District Court’s reasoning erroneously extended DHES “control
    over subdivisions beyond” the scope of its limited authority to enforce applicable water
    supply, sewage, and solid waste disposal regulations. Montana Wilderness Ass’n, 171
    21
    Mont. at 484-85, 
    559 P.2d at 1161
    . In so holding, we noted that the Legislature placed
    general regulatory control over subdivisions in the hands of local governments rather than
    agencies of the State. Montana Wilderness Ass’n, 171 Mont. at 485-86, 
    559 P.2d at
    1161
    (citing 1973 Montana Subdivision and Platting Act); see also, §§ 75-1-102(1)
    and -201(1)(b), MCA (MEPA applicable to state agencies only).
    ¶30    In this case, the District Court concluded that “Montana Wilderness is no longer
    binding authority” on the asserted grounds that it is contrary to MEPA’s statutory command
    that agencies comply with the environmental review requirements “to the fullest extent
    possible” and similarly “at odds with subsequent NEPA case law requiring agencies to
    consider reasonably foreseeable indirect effects of an action, even when local or state
    entities are authorized to make the ultimate decision.” However, as pertinent, MEPA
    remains substantially unchanged and this Court has not overruled or limited Montana
    Wilderness in the 40 years since we issued it. More significantly, while MEPA and NEPA
    do indeed command agencies to comply with applicable environmental review
    requirements “to the fullest extent possible,” we cannot properly construe MEPA in
    isolation.   MEPA and NEPA must be construed in harmony with the substantive
    limitations of an agency’s applicable regulatory authority. Public Citizen, 
    541 U.S. at 769
    ,
    
    124 S. Ct. at 2217
    ; Montana Wilderness Ass’n, 171 Mont. at 484-85, 
    559 P.2d at 1161
    ;
    §§ 75-1-102(3)(b) and -104(1), MCA (MEPA provides no additional regulatory authority
    to an agency and does not affect an agency’s specific statutory duties to comply with
    environmental quality standards).     See also, §§ 75-1-102(1) and -201(4)(a), MCA
    (reviewing “agency may not withhold, deny, or impose conditions on any permit or other
    22
    authority to act based on” MEPA); Flint Ridge Development Co. v. Scenic Rivers Ass’n,
    
    426 U.S. 776
    , 787, 
    96 S. Ct. 2430
    , 2438 (1976) (quoting NEPA legislative history
    indicating Congressional intent that federal agencies comply with NEPA requirements “‘to
    the fullest extent possible’ under their statutory authorizations”); Calvert Cliffs Coord.
    Comm. v. U.S. Atomic Energy Comm., 
    449 F.2d 1109
    , 1115 (D.C. Cir. 1971) (noting NEPA
    § 102 intent to require agency compliance with NEPA requirements to fullest extent
    possible within scope of independent agency authority).
    ¶31    In support of its ruling, the District Court cited Chelsea Neighborhood Ass’n v. U.S.
    Postal Service, 
    516 F.2d 378
     (2nd Cir. 1975) (requiring U.S. Postal Service to consider
    impacts of contemplated third-party construction of multi-story housing project on top of
    a contemplated ground floor postal vehicle maintenance facility as a secondary impact of
    construction of the postal facility); City of Davis v. Coleman, 
    521 F.2d 661
    , 679-82 (9th
    Cir. 1975) (requiring USDOT to consider environmental, economic, and social effects of
    future urban development as indirect impacts of contemplated construction of a new
    interstate freeway interchange); and Sierra Club v. Marsh, 
    769 F.2d 868
     (1st Cir. 1985)
    (requiring Federal Highway Administration and Corps of Engineers to consider
    environment impacts of contemplated heavy industrial development as indirect impacts of
    issuance of federal funding and permits for construction of a cargo ship port and causeway
    on an undeveloped island adjacent to an industrialized seaport). With some variations and
    distinctions, the cases cited by the District Court are arguably consistent with Bitterrooters’
    expansive “but for” theory of MEPA causation insofar as they focused on potential impacts
    of contemplated future development that would result beyond the agency authority over
    23
    the action that triggered NEPA review in the first place. However, the federal Circuit
    Courts decided those cases long before the U.S. Supreme Court clarified the appropriate
    standard of NEPA causation in Public Citizen. Thus, in light of Public Citizen, prior
    inconsistent lower court decisions in Chelsea, Davis, and Sierra Club are distinguishable
    and insufficiently persuasive to overrule or limit Montana Wilderness.
    ¶32    In apparent recognition of this problem, Bitterrooters cite Save Our Sonoran, Inc.
    (SOS) v. Flowers, 
    408 F.3d 1113
     (9th Cir. 2005) (requiring Corps of Engineers to consider
    impacts of private construction of gated community in Arizona desert as secondary impacts
    of issuance of permit to dredge and fill dry streambeds that collected and carried occasional
    heavy rain runoff) as additional support for the District Court’s ruling. However, SOS is
    factually distinguishable because: (1) the Corps had authority to regulate the filling of dry
    streambeds in the Arizona desert; (2) dry capillaries to the streambeds inextricably
    permeated the entirety of the subdivision site; and (3) extensive filling of the entirety of
    the system on the subdivision site would impact plants and animals dependent on water
    collected by the system. SOS, 
    408 F.3d at 1118-23
    . Despite loose dictum that NEPA
    required the Corps to consider environmental impacts “with no impact on [its]
    jurisdictional waters,” the Ninth Circuit actually recognized Public Citizen’s more
    stringent NEPA causation standard and merely held that the requisite “causal nexus”
    existed on the unique facts of the case between the Corps’ independent regulatory authority
    and the subject environmental impacts. SOS, 
    408 F.3d at 1121-23
    . Consequently, SOS is
    24
    not persuasive authority upon which to distinguish Public Citizen or overrule or limit
    Montana Wilderness.8
    ¶33    We hold that MEPA, like NEPA, requires a reasonably close causal relationship
    between the triggering state action and the subject environmental effect. We reject the
    unyielding “but for” causation standard asserted by Bitterrooters to the effect that a state
    action is a cause of an environmental impact regardless of whether the agency, in the lawful
    exercise of its independent authority, can avoid or mitigate the effect. We hold that, for
    purposes of MEPA, an agency action is a legal cause of an environmental effect only if the
    agency can prevent the effect through the lawful exercise of its independent authority. As
    in Public Citizen, requiring a state agency to consider environmental impacts it has no
    authority to lawfully prevent would not serve MEPA’s purposes of ensuring that
    agencies    and    the    interested    public    have    sufficient    information     regarding
    relevant environmental impacts to inform the lawful exercise of agency authority. Sections
    75-1-102(3), -104(1), -201(4)(a), MCA. Section 75-1-201(1), MCA, merely requires state
    8
    Eliminating any doubt as to its adherence to Public Citizen, the Ninth Circuit more recently
    observed:
    Even when a major federal action occurs, however, NEPA remains subject to a
    “rule of reason” that frees agencies from preparing a full EIS on “the environmental
    impact of an action it could not refuse to perform.” Pub. Citizen, 
    541 U.S. at 769
    ,
    
    124 S. Ct. 2204
    . Thus, “where an agency has no ability to prevent a certain effect
    due to its limited statutory authority over the relevant actions,” the agency “[does]
    not need to consider the environmental effects arising from” those actions. 
    Id. at 770
    , 
    124 S. Ct. 2204
    .
    Alaska Wilderness League v. Jewell, 
    788 F.3d 1212
    , 1225-26 (9th Cir. 2015) (holding that
    federal agency approval of oil and gas lease for off-shore drilling on Alaska’s Arctic coastline
    did not trigger NEPA consideration of sufficiency of oil company’s oil spill response plan where
    company otherwise satisfied legal criteria for lease approval within scope of agency authority).
    25
    agencies to comply with applicable MEPA requirements “to the fullest extent
    possible” within the scope of the lawful exercise of their independent authority. Accord,
    §§ 75-1-102(3), -104(1), -201(4)(a), MCA.
    ¶34    Contrary to the assertions of the dissent in Montana Wilderness and Bitterrooters
    here, our holdings in these cases do not gut MEPA. In accordance with its express
    language, MEPA still requires state agencies to adequately consider, “to the fullest extent
    possible” within the scope of their independent authority, all direct and secondary
    environmental impacts that will likely result from the specific activity conducted or
    permitted by the agency. The problem for Bitterrooters is that the broader environmental
    impacts of the larger construction and operation of the retail store are not subject to MEPA
    review because the Legislature has not placed general land use control in the hands of a
    state agency. As recognized in Montana Wilderness over 40 years ago, the Legislature has,
    with limited exceptions, placed general land use control beyond the reach of MEPA in the
    hands of local governments. See, Title 76, chapters 1-3, MCA (Subdivision and Platting
    Act and local zoning enabling Acts). Regardless of MEPA’s manifest beneficial purpose
    and Bitterrooters’ otherwise compelling public policy arguments, we simply cannot
    properly stretch MEPA beyond the limits of its language and stated purpose to fill an
    environmental review gap created by the Legislature and remaining within its domain to
    remedy if so inclined.
    ¶35    In this case, the District Court did not conclude that DEQ failed to adequately
    consider the secondary environmental impacts, as defined by Admin. R. M. 17.4.609(3)(d)
    and (e), of the permitted wastewater discharge or related construction of the required
    26
    wastewater treatment system. Rather, the District Court concluded that DEQ violated
    Admin. R. M. 17.4.609(3)(d) and (e) by failing to consider other non-water quality related
    impacts of the larger construction and operation of the facility as secondary impacts of
    issuance of the contemplated MWQA wastewater discharge permit.                 Bitterrooters
    acknowledge that, had DEQ expanded the scope of its EA beyond its water quality
    regulatory authority to consider those impacts as demanded, it would have had no authority
    to deny or limit the requested MWQA wastewater discharge permit to prevent or mitigate
    those impacts. See, §§ 75-1-102(3)(b), -104(1), and -201(4)(a), MCA. Thus, issuance of
    the requested MWQA wastewater permit was not a legal cause of environmental impacts
    of the larger construction and operation of the retail facility unrelated to water quality or
    the construction of the required wastewater treatment system. We hold that the District
    Court erroneously concluded that DEQ violated MEPA, in contravention of Admin.
    R. M. 17.4.609(3)(d) and (e), by failing to further consider the environmental impacts of
    the construction and operation of the facility other than water quality impacts and impacts
    of the related construction of the required wastewater treatment system.
    ¶36 Issue 2: Does MEPA require DEQ to identify the actual owner or operator of a
    wastewater treatment facility prior to issuing a MWQA groundwater discharge permit?
    ¶37    Incident to its MEPA secondary impacts ruling, the District Court further ruled:
    When it reconsiders Foss’ application, . . . DEQ must identify the facility
    operator if the operator’s identity has the potential to impact vegetation,
    aesthetics, human health and safety, industrial and commercial activities,
    employment, tax revenues, demand for government services, or other
    environmental resources.
    27
    In context, and by comparison of similar language, we infer the unattributed source of the
    referenced criteria to be Admin. R. M. 17.4.603(12) and .609(3)(d) and (e) (cumulative and
    secondary impact evaluation criteria). Thus, the District Court essentially ruled that MEPA
    requires DEQ to identify the contemplated facility operator if the facility operator, in
    conjunction with the nature of the operation, is predisposed to operate the facility in a
    manner that has the potential to impact any of the evaluation criteria referenced in Admin.
    R. M. 17.4.609(3)(d) and (e).
    ¶38    Landowners assert that the District Court improperly crafted an unnecessary and
    unworkable test from whole cloth. They further assert that District Court’s test is no test
    at all because it will always require DEQ to speculatively assess potential environmental
    impacts of a subject activity based on the identity, reputation, and past practices of the
    contemplated facility owner and operator. Landowners finally assert that the test is
    unnecessary in any event because all interested parties now know the identity of the
    contemplated owner and operator of the subject facility, i.e., Walmart, and that
    Admin. R. M. 17.30.1360 will ultimately require identification, and afford DEQ an
    opportunity for subsequent review of permit conditions, upon the eventual transfer of the
    permit to the actual contemplated owner or operator.
    ¶39    Bitterrooters contrarily assert that the identity of the contemplated owner and
    operator of a permitted facility is information directly relevant to consideration of the
    potential environmental impacts of the construction and operation of the facility as a whole.
    Without citation to any statutory or administrative provision of MEPA or MWQA,
    Bitterrooters assert that “secretive planning serves no legitimate public policy purpose”
    28
    and “leaving the identity of the true applicant a secret violates the letter and spirit of
    MEPA.” DEQ is strangely silent on the issue.
    ¶40    At the crux of the matter, contrary to Landowners’ assertion, the transfer of an
    agency permit to a new owner or operator generally will “not trigger [MEPA] review.”
    Section 75-1-201(1)(d), MCA (permit transfer triggers MEPA only upon “a material
    change in terms or conditions” of the permit or as otherwise provided by law). Page 13,
    Section M, of the subject DEQ-Foss MGWPCS permit expressly provides that “[t]his
    permit may be automatically transferred” to a new permitee on thirty-day notice to DEQ,
    payment of applicable fees, and submittal of a written transfer agreement between Foss
    and the transferee “containing a specific date for transfer of permit responsibility, coverage,
    and liability between them.” Thus, Landowners’ assertion that subsequent identification
    of the actual owner or operator on transfer of the permit will remedy any legitimate
    environmental concern is somewhat disingenuous given that the contemplated transfer will
    not likely trigger MEPA review.        By the same token, despite the facial appeal of
    Bitterrooters’ concern that non-disclosure of the identity of the contemplated owner or
    operator of a facility could potentially result in inadequate review of an agency action
    otherwise subject to MEPA, the concern is unsubstantiated on the factual record in this
    case. More significantly, Bitterrooters’ assertion, and the District Court’s resulting ruling,
    is unsupported by any legal authority other than the general principle that MEPA requires
    an agency to adequately compile and assess all environmental data relevant to a particular
    agency action. See, Clark Fork Coal., ¶ 47; Ravalli County Fish & Game Ass’n, 273 Mont.
    at 381, 
    903 P.2d at 1369
    . Rather than follow the parties down the garden path into the
    29
    public policy realm of the Legislature while DEQ stands quietly by, we more
    fundamentally and appropriately look to the largely overlooked governing requirements
    for MWQA permits.
    ¶41   With its limited focus on identification and assessment of relevant environmental
    impacts of proposed state agency actions, MEPA does not govern what information an
    application must contain for issuance of an agency permit subject to MEPA review. For
    the sole purpose of determining the deadlines for agency completion of required
    environmental review under § 75-1-208(4)(a), MCA, and Admin. R. M. 17.4.620, MEPA
    defines a “complete application” as:
    an application for a permit, license, or other authorization that contains all
    data, studies, plans, information, forms, fees, and signatures required to be
    included with the application sufficient for the agency to approve the
    application under the applicable statutes and rules.
    Section 75-1-220(3), MCA (emphasis added).         As contemplated by the highlighted
    language of § 75-1-220(3), MCA, MWQA governs what information an application must
    contain for issuance of an MGWPCS discharge permit. Sections 75-5-401 and -402, MCA
    (DEQ duty under MWQA to regulate wastewater discharge pursuant to BER rules);
    Admin. R. M. Title 17, chapter 30, parts 1 and 10 (BER groundwater discharge rules).
    ¶42   As pertinent, MWQA rules expressly provide that the “owner or operator of any
    proposed source . . . which may discharge pollutants into state ground waters shall file a
    completed MGWPCS permit application” at least 180 days prior to the proposed operation.
    Admin. R. M. 17.30.1023(3) (emphasis added). All MGWPCS permit applications “must
    be submitted on [DEQ] forms . . . and must contain” certain enumerated information “as
    30
    deemed necessary by” DEQ. Admin. R. M. 17.30.1023(4). Pursuant to its “one common
    system for issuing permits for point sources9 discharging pollutants into state waters,” DEQ
    requires MGWPCS permit applicants to submit applications on DEQ standard Forms 1 and
    G-W. Admin. R. M. 17.30.1023(4), and (6), .1301(1). See also, DEQ Form GW-1 (“this
    form must be accompanied by DEQ Form 1”) and Admin. R. M. 17.30.1304(5) and
    .1322(1)(a) and (b) (“all applicants shall submit applications” on DEQ standard Form 1
    available at http://perma.cc/MD4G-2XPW).                For purposes of the applicable MWQA
    regulations and DEQ Form 1, the term “‘owner or operator’ means any person who
    owns . . ., operates, controls, or supervises a point source.” Admin. R. M. 17.30.1304(48).
    MGWPCS rules specifically command that:
    No application will be processed by [DEQ] until all of the requested
    information is supplied and the application is complete. [DEQ] shall make a
    determination of the completeness of the information with 30 calendar days
    of receipt of an application.
    Admin. R. M. 17.30.1024(1) (emphasis added).
    ¶43     Here, the subject wastewater permit application identified real estate broker Lee
    Foss as the applicant and contemplated operator of the proposed retail facility and required
    wastewater treatment system. However, it is undisputed on the record that Foss was never
    going to be the actual owner or operator of the facility. He requested the MGWPCS permit
    to facilitate the sale of the property to a particular third-party known to Foss and
    9
    “‘Point source’ means a discernible, confined, and discrete conveyance, including but not limited
    to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, or vessel
    or other floating craft, from which pollutants are or may be discharged.” Section 75-5-103(29),
    MCA; Admin. R. M. 17.30.1304(51).
    31
    Landowners who would then construct and operate the facility. Upon sale of the property,
    Foss would transfer the permit to the intended owner and operator. Thus, Foss was not the
    owner or operator, or even the contemplated owner or operator, of the subject facility as
    referenced in Admin. R. M. 17.30.1023(3) and DEQ Form 1.
    ¶44    DEQ’s April 29, 2014 notice of application deficiencies and its Director’s
    subsequent inquiry of Foss, clearly manifest that DEQ was aware of the standard
    requirement that a MGWPCS application identify the actual owner or operator of the
    subject facility responsible for the contemplated wastewater discharge. DEQ must “issue,
    suspend, revoke, modify, or deny permits to discharge sewage . . . into state waters . . .
    consistently with [BER] rules.” Section 75-5-402(1), MCA (emphasis added). Why or on
    what basis DEQ acquiesced to Foss’ refusal to identify the actual contemplated owner or
    operator of the facility is unclear from the record on appeal. Regardless, we hold that, as
    implemented by DEQ Form 1 (Ver. 1.2 – Rev. 5/12), Admin. R. M. 17.30.1023(3) and
    .1024(1), requires DEQ to identify the actual owner or operator of the contemplated facility
    for which an applicant seeks the subject wastewater discharge permit.10 We will affirm a
    district court ruling that reaches the right result even if for the wrong reason. Earth
    Resources Ltd. Partnership v. North Blaine Estates, Inc., 
    1998 MT 254
    , ¶ 29, 
    291 Mont. 216
    , 
    967 P.2d 376
    . For the foregoing reasons, we affirm the District Court’s summary
    10
    Except as otherwise warranted upon balancing of Montana Constitution, Article II, Sections 9
    and 10 (public’s right to know and right to individual privacy), this information “is a matter of
    public record and open to public use.” Section 75-5-105, MCA.
    32
    judgment that DEQ must identify and disclose the actual contemplated owner or operator
    of the facility for which the applicant seeks the subject wastewater discharge permit.
    CONCLUSION
    ¶45     We hereby reverse the District Court’s summary judgment that DEQ violated
    MEPA, in contravention of Admin. R. M. 17.4.609(3)(d) and (e), by failing to further
    consider environmental impacts of the construction and operation of the facility other than
    water quality impacts and impacts of the related construction of the required wastewater
    treatment system. We further hereby affirm the District Court’s summary judgment that
    DEQ must identify and disclose the actual contemplated owner or operator of the subject
    retail store facility.
    /S/ DIRK M. SANDEFUR
    We concur:
    /S/ MIKE McGRATH
    /S/ LAURIE McKINNON
    /S/ MICHAEL E WHEAT
    /S/ BETH BAKER
    /S/ JAMES JEREMIAH SHEA
    /S/ JIM RICE
    33
    

Document Info

Docket Number: DA 16-0429

Citation Numbers: 2017 MT 222, 388 Mont. 453, 401 P.3d 712, 2017 Mont. LEXIS 562

Judges: Baker, McGRATH, Rice, Sandefur, Shea, Wheat

Filed Date: 9/5/2017

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (17)

calvert-cliffs-coordinating-committee-inc-v-united-states-atomic-energy , 449 F.2d 1109 ( 1971 )

Sierra Club v. John O. Marsh, Jr. , 769 F.2d 868 ( 1985 )

Save the Bay, Inc. v. The United States Corps of Engineers, ... , 610 F.2d 322 ( 1980 )

Chelsea Neighborhood Associations v. United States Postal ... , 516 F.2d 378 ( 1975 )

Amelia Smith v. B.N. Santa Fe Rai , 2008 MT 225 ( 2008 )

Kadillak v. Anaconda Co. , 184 Mont. 127 ( 1979 )

Save Our Sonoran, Inc. v. Flowers , 408 F.3d 1113 ( 2005 )

winnebago-tribe-of-nebraska-v-col-james-w-ray-district-engineer-omaha , 621 F.2d 269 ( 1980 )

North Fork Preservation Ass'n v. Department of State Lands , 238 Mont. 451 ( 1989 )

Montana Earth Resources Ltd. Partnership v. North Blaine ... , 291 Mont. 216 ( 1998 )

Friends of the Wild Swan v. Department of Natural Resources ... , 301 Mont. 1 ( 2000 )

Montana Wilderness Ass'n v. Board of Health & Environmental ... , 171 Mont. 477 ( 1976 )

Ravalli County Fish and Game Ass'n, Inc. v. Montana Dept. ... , 273 Mont. 371 ( 1995 )

City of Davis, a Municipal Corporation v. William T. ... , 521 F.2d 661 ( 1975 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

Clark Fork Coalition v. Montana Department of Environmental ... , 347 Mont. 197 ( 2008 )

Flint Ridge Development Co. v. Scenic Rivers Assn. of Okla. , 96 S. Ct. 2430 ( 1976 )

View All Authorities »