Redinger v. French , 216 Mont. 16 ( 1985 )


Menu:
  •                                     No. 84-413
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1985
    VICTOR T. IPEDINGER, ARLAN D. FRYER,
    HELEN J. FRYER, as F & R PROPERTIES,
    a co-partnership,
    Plaintiffs and Respondents.
    GEORGE D. FRENCH, YELLOWSTONE
    INVESTMENT AND DEVELOPMENT, INC.,
    a Delaware corp; EDWARD L. BOND,
    individually, and FIRST BANK BILLINGS,
    Defendants and Appellants.
    APPEAL FROM:    District Court of the Thirteenth Judicial District,
    In and for the County of Yellowstone,
    The Honorable Diane G. Barz, Judge presiding.
    COUNSEL OF RECORD:
    For Appellants:
    Brad L. Arndorfer, Billings, Montana
    For Respondents:
    Harris, Morin    &   Collins; Robert P. Morin, Billings,
    Montana
    Submitted on Briefs:   Jan. 18, 1985
    Decided: May 2 , 1985
    Filed:         : j985
    Mr. Justice Fred J. Weber delivered the Opinion of the Court.
    In this action in Yellowstone County District Court, the
    plaintiffs sought a cancellation of a contract for deed.
    Defendants, Edward L. Bond and Yellowstone Investment and
    Development, Inc. (herein called Defendants), appeal judgment
    of   forfeiture by         the defendants of all            interest in the
    payments and the real property and the award of attorney's
    fees and costs to the plaintiffs.           We a.ffirm.
    The issues are:
    1.   Did the defendants fail to file a notice of appeal
    within the required time?
    2.   Was the contract for deed in this case actually a
    mortgage?
    3.   Was the liquidated damages clause in the contract
    for deed actually a penalty clause?
    The extended written contract for deed dated May                      18,
    1977, required that the defendants pay the sum of $26,000
    plus 9 percent interest per annum with a down payment of
    $1,300, monthly payments of $200 on principal and interest,
    plus $30 monthly payments on a separate tax reserve account.
    ?'he contract        further     provided   that     the    balance   of   the
    purchase price with interest should be payable on May 15,
    1982.
    We      set forth the        findings of fact, as made by             the
    District Court, from which no appeal has been taken.                  On May
    3, 1982, plaintiffs sent a letter to the attorney for the
    defendants advising of the impending balloon payment date of
    May 15, 1982, and pointing out that the principal balance of
    $23,500.74, interest in the amount of $168.06, and escrow fee
    of $29.58, resulting in a total of $23,698.38, would be due.
    Defendants        failed   to   pay    on the due     date.      Appropriate
    notices      of    default      were   served   on    the     defendants   in
    accordance with the contract for deed.                 The contract provided
    that the plaintiffs take possession of the premises upon
    defendants' failure to cure the default within 60 days and
    for the redelivery of various papers in the bank escrow.
    Defendants Edward          L.    Bond, individually, and             Yellowstone
    Investment and Development, Inc., instructed the escrow agent
    not to redeliver the papers in escrow.                   Defendants retained
    possession    of     the     property        notwithstanding the        contract
    provisions.
    On October 4, 1982, plaintiffs filed a complaint seeking
    cancellation of the contract for deed.                   During the pendency
    of   the    action     and       the    trial,      defendants     remained    in
    possession of the property and received and retained the
    rental     proceeds.            The    District     Court    found    that    the
    defendants were        not       entitled     to    relief   from     forfeiture
    because they were grossly negligent in failing to perform in
    accordance with the terms and provisions of the contract and
    the defendants therefore were not entitled to any equitable
    relief.
    From the findings of fact, the District Court made the
    following conclusions of law.                 The defendants failed to pay
    the balloon payment of $23,698.38 on or before May 15, 1982.
    The defendants had forfeited any and all payments under the
    contract and all right, title and interest in and to the real
    property.      The plaintiffs were fully reinvested with all
    right, title and interest in the premises.                   The contract for
    deed was terminated, and the escrow bank was to deliver to
    plaintiffs all papers in escrow.                   By judgment dated June 1,
    1984, the District Court restated its conclusions of law and
    awarded     attorneys'          fees    of     $7,270.10     and     costs    and
    disbursements of $514.29 to plaintiffs.
    Did the defendants fail to            file a notice of appeal
    within the required time?
    Pla.intiff contends that defendants failed to file their
    notice   of     appeal within     the time prescribed         by    Rule   5,
    M. R.App.Civ. P., which provides that an appeal must be taken
    within    30 days      from the    service of notice of entry              of
    judgment.
    Following the service by mail of notice of entry of the
    June 1, 1984 judgment, new defense counsel was substituted.
    On June 12, 1984, defendants filed a motion to amend the
    judgment pursuant to Rule 52 (b), M.R.Civ.P.               That motion was
    timely made.       On June 20, 1984, defendants filed a notice of
    hearing for June 28, 1984, and completed service by mail on
    that date.       On June 28, 1984, the District Court heard the
    oral arguments and took the matter under advisement.                On July
    13, 1984, the District Court entered its order denying the
    motion to amend.       On August 13, 1984, defendants filed their
    notice of appeal.
    A motion for amendment of judgment under Rule 52(b),
    M.R.Civ.P.      is controlled by Rule 59.       Rule 59 (g), M.R.Civ.P.
    provides that the motion shall be served not later than 10
    days    after    the   service    of   the   notice   of    the    entry   of
    judgment.       Rule 59 (d), M. R.Civ. P. in pertinent part states:
    "Hearing on the motion shall be had within 10 days
    after it has been served        ...
    except that at any
    time after the notice of hearing on the motion has
    been served the court may issue an order continuing
    the hearing for not to exceed 30 days. In case the
    hearing is continued by the court, it shall be the
    duty of the court to hear the same at the earliest
    practicable date thereafter, and the court shall
    rule upon and decide the motion within 15 days
    after the same is submitted.    If the court shall
    fail to rule upon the motion within said time, the
    motion shall, at the expiration of said period, be
    deemed denied."
    The defendants did not serve a notice of motion at the
    same time as the motion itself.              The District Court did not
    receive a request to continue the motion, as authorized under
    the rule.        The hearing date of June 28 was not within the
    initial 10-day period.           However, the June 28 hearing date was
    well within the total of 40 days which the rule allows for
    the hearing.        A     notice of hearing was given within the
    initial 10-day period.           We find that a technical failure to
    obtain     a   continuance      from the     District Court       is not    a
    sufficient reason to invalidate the proceedings where the
    hearing is held within the period prescribed by the rule.
    The denial of the motion on July 13, 1984, was exactly
    within the 15-day maximum of the rule.                Finally, since 30
    days from July 13 was Sunday, August 12, the filing of the
    notice of appeal on Monday, August 13, was within the 30-day
    maximum permitted by the rule.
    We conclude that the notice of appeal was timely filed.
    I1
    Was      the contract      for deed    in this case actually a
    mortgage?
    The defendants set forth an extensive contention that
    this contract for deed should be considered a mortgage.                    In
    addition, they argue that all contracts for deed should be
    declared mortgages.             This i s a new theory which was not
    .
    presented to the District Court at any time prior to the
    entry of findings of fact, conclusions of law and judgment.
    The   first      time     the    theory    was   presented    was    in   the
    defendants'       brief    supporting      the   motion      to   amend   the
    judgment.
    In    Mont.   Williams      Double    Diamond   v.     Royal   Village
    (1980), 
    186 Mont. 359
    , 365-66, 
    607 P.2d 1120
    , 1124, a case
    involving the cancellation of a written contract for deed,
    this Court sta.ted:
    "Appellants assert as grounds for their second
    issue of review that it is evident from both the
    contract of sale and the manner in which appellants
    and respondents performed it that the contracts
    entered into between appellants and individual
    third party purchasers constitute a joint venture
    between appellants and respondents making them
    iointly bound. This issue was not presented to the
    District Court and as such cannot be raised for the
    first time on appeal. Northern Plains v. Board of
    Natural Resources (1979), Mont., 
    594 P.2d 297
    , 309,
    36 St.Rep. 666, 680; Spencer v. Robertson (1968),
    
    151 Mont. 507
    , 511, 
    445 P.2d 48
    , 50-51."
    See also, Sun Dial Land Co. v. Gold Creek Ranches (1982), 
    198 Mont. 247
    , 253, 
    645 P.2d 936
    , 940.
    Because this issue was not presented to the District
    Court, it cannot be raised for the first time on appeal.
    Was the liquidated damages clause in the contract for
    deed actually a penalty clause?
    The   District    Court   found     that    the   defendants   were
    grossly negligent in failing to perform under the contract
    and that they were not entitled to any equitable relief by
    virtue of the facts in this case.               The balloon payment was
    due May 15, 1982, and the judgment was entered almost two
    years later on June 1, 1984.            The defendants failed to make
    any significant efforts to correct the default during that 2
    year period.       The defendants remained in possession of the
    real property which was rented, retained the rents during
    that period, and a.lso retained the benefit of taking tax
    depreciation on the property.            The record does not show any
    attempt      on   defendants'    part    to     refinance    or   otherwise
    complete the actual purchase.           The contract for deed provided
    that the time of payment was of the essence.                The defendants
    were    informed    in   advance   of     the    balloon    payment   date.
    Notwithstanding that information and the subsequent delay of
    two years until entry of judgment, the defendants took no
    action to comply with the requirements of the contract for
    deed.   The total principal payment made by the defendants on
    the $26,000 contract was approximately $2,300.
    The   record   clearly   contains   substantial evidence to
    support the District Court's conclusion.          We   affirm the
    court's conclusion that the defendants are not entitled to
    relief from forfeiture.
    The judgment is affirmed.
    We concur:      Y
    ,
    

Document Info

Docket Number: 84-413

Citation Numbers: 216 Mont. 16, 699 P.2d 94, 1985 Mont. LEXIS 761

Judges: Weber, Turnage, Harrison, Sheehy, Morrison, Gulbrandson, Hunt

Filed Date: 5/2/1985

Precedential Status: Precedential

Modified Date: 10/19/2024