Hawley v. Board of Oil & Gas Conservation , 297 Mont. 467 ( 2000 )


Menu:
  • file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm
    No. 98-316
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    
    2000 MT 2
    297 Mont. 467
    993 P.2d 677
    MERRILL S. HAWLEY and CAROL HAWLEY,
    husband and wife and partners in HAWLEY OIL,
    formerly doing business as HAWLEY OIL COMPANY
    and Ted Hawley Company, HAWLEY HYDROCARBONS
    and HAWLEY NORTHRUP, Montana Partnerships;
    KIM HAWLEY and WAD HAWLEY, Individually
    and doing business as GALLUP CITY OIL COMPANY,
    a Montana Partnership,
    Plaintiffs and Respondents,
    v.
    BOARD OF OIL AND GAS CONSERVATION,
    DEPARTMENT OF NATURAL RESOURCES
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm (1 of 7)3/29/2007 10:50:50 AM
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm
    AND CONSERVATION, STATE OF MONTANA,
    DAVID W. BALLARD and THOMAS P. RICHMOND,
    Defendants and Appellants.
    APPEAL FROM: District Court of the Ninth Judicial District,
    In and for the County of Pondera,
    The Honorable Marc G. Buyske, Judge presiding.
    COUNSEL OF RECORD:
    For Appellants:
    Hon. Joseph P. Mazurek, Attorney General; Robert M. Gentry, Assistant
    Attorney General, Natural Resource Damage Program, Helena, Montana
    For Respondents:
    Kim M. Hawley, Pro Se, Conrad, Montana
    Submitted on Briefs: October 28, 1999
    Decided: January 6, 2000
    Filed:
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm (2 of 7)3/29/2007 10:50:50 AM
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm
    __________________________________________
    Clerk
    Justice W. William Leaphart delivered the Opinion of the Court.
    ¶1This is an appeal by the Board of Oil and Gas Conservation, Department of Natural
    Resources and Conservation, (the "Board") from an order of the Ninth Judicial District
    Court, Pondera County, vacating the Board's September 4, 1997 administrative Order
    (hereafter Board Order No. 104-97) and October 1, 1997, Order to Terminate Production
    Operations in wells being operated by Respondents, Merrill S. Hawley and Carol Hawley,
    partners in Hawley Oil ("Hawley").
    ¶2The issue presented is whether the Board, absent an emergency, has authority to order
    that producing oil wells be shut-in. We reverse the decision of the District Court.
    Background
    ¶3On May 14, 1997, the Board issued an order requiring Hawley to appear and show
    cause why its various companies' bonds should not be doubled and why other penalties
    should not be imposed as a result of Hawley having over eighty documented deficiencies
    since 1990 and being slow to correct deficiencies brought to its attention and to correct
    production methods to prevent future oil spills or pit problems. At the show cause hearing,
    Field Inspector Sasaki testified, noting evidence of oil leaking from tanks, flow lines, and
    pits at over twenty Hawley well locations. Hawley did not contest Mr. Sasaki's testimony
    in this regard.
    ¶4The Board then issued an order requiring Mr. Hawley to file a written report with the
    Board as to the condition of each well and each production facility. The order further
    stated that if the Board determined that no "SUBSTANTIAL progress in coming into
    compliance" had been made by September 3, 1997, all Hawley wells would be suspended
    until further notice.
    ¶5In Board Order No. 104-97, the Board determined that no substantial progress had been
    made and granted Hawley until October 1, 1997 to bring operations into compliance. The
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm (3 of 7)3/29/2007 10:50:50 AM
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm
    order further stated that if Hawley was not in full compliance with the Board's rules and
    orders by October 1, 1997, the Board administrator would order that production be
    terminated at all Hawley facilities. By order dated October 1, 1997, the Board
    administrator found that all Hawley facilities were not in compliance, that progress
    towards compliance was minimal, and directed that production of oil from Hawley
    operations cease.
    ¶6Hawley then filed suit against the Board in District Court, seeking a temporary and
    permanent injunction enjoining the enforcement of the Board's October 1, 1997 Order to
    Terminate Production Operations. The District Court temporarily enjoined enforcement of
    the order and scheduled a show cause hearing. Following the show cause hearing, the
    District Court continued the temporary restraining order and ordered the filing of written
    memoranda. After considering the briefs, the District Court concluded that the actions of
    the Hawleys, as conceded by the Board, did not give rise to emergency action under § 82-
    11-151, MCA, which allows the administrator to order immediate closure or shutdown of
    any well which threatens imminent and substantial pollution. The District Court then
    reasoned that the balance of the statutory scheme pertaining to enforcement of Board
    orders
    leads this Court to conclude the Board must seek judicial enforcement of its non-
    emergency orders. These statutes specifically authorize and direct the Board to seek
    judicial assistance in the form of injunctive relief, Section 82-11-147, and enforcement of
    monetary penalties, Section 82-11-149. This specific direction leaves nothing to be
    implied as to the scope of the Board's authority to enforce its non-emergency orders.
    Standard of Review
    ¶7The issue before the Court involves an interpretation of § 82-11-147, MCA. When we
    review a district court's conclusions of law, our standard of review is plenary and we must
    determine whether the court's conclusions are correct as a matter of law. See Lane v.
    Farmers Union Ins., 
    1999 MT 252
    , ¶ 15, 56 St.Rep. 990, ¶ 15, ___ P.2d ___, ¶ 15.
    Discussion
    ¶8Hawley contends that, in the absence of facts warranting emergency action under § 82-
    11-151, MCA, the Board has no statutory authority to order that production be terminated;
    that its sole remedy is to petition the District Court for an injunction pursuant to § 82-11-
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm (4 of 7)3/29/2007 10:50:50 AM
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm
    147(1)(a), MCA.
    ¶9Section 82-11-124, MCA, provides that, for the purpose of preventing waste, the Board
    shall regulate the drilling, producing, and plugging of wells. Section 82-11-111(2), MCA,
    states that the Board shall require measures to be taken to prevent contamination of or
    damage to surrounding land or underground strata caused by drilling operations and
    production and adopt and enforce rules and orders to effectuate the purposes and the intent
    of this chapter.
    ¶10The Board interprets its powers as set forth in the above statutes to include the
    necessary and implicit authority to order that a well be shut-in if required to accomplish
    the Board's statutory charge. The Board cites our decision in Christenot v. State, Dep't of
    Commerce (1995), 
    272 Mont. 396
    , 401, 
    901 P.2d 545
    , 548, for the proposition that an
    administrative agency's interpretation of a statute under its domain is presumed to be
    controlling. In Christenot, we held "the construction of a statute by the agency responsible
    for its execution should be followed unless there are compelling indications that the
    construction is wrong." Christenot, 272 Mont. at 401, 901 P.2d at 548 (citation omitted).
    ¶11Although we do not disagree that the Board's authority to require a shut-in may be
    implicit in its authority to regulate the drilling and producing of wells under § 82-11-124,
    MCA, we base our decision upon the express provisions of § 82-11-147(1)(b), MCA:
    82-11-147. Violations. (1) Notwithstanding any other provisions of this chapter, if the board
    finds upon receipt of evidence:
    (a) that a person is violating or threatening to violate this chapter or a rule or order of the
    board, the board may bring suit against that person in the district court of any county
    where the violation occurs or is threatened to restrain the person from continuing the
    violation or from carrying out the threat of violation; or
    (b) that a person is violating this chapter or a rule or order of the board in a manner for
    which the board is authorized to institute proceedings pursuant to 82-11-149, the board
    may issue an order either assessing a civil penalty in the amount prescribed in 82-11-149,
    up to a maximum administrative penalty of $125,000, or requiring compliance with this
    chapter or a rule or order, or both.
    (2) In a suit under subsection (1)(a), the court may grant to the board, without bond or
    other undertaking, such prohibitory and mandatory injunctions as the facts may warrant,
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm (5 of 7)3/29/2007 10:50:50 AM
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm
    including temporary restraining orders.
    ¶12Hawley's argument focuses entirely upon the provisions of § 82-11-147(1)(a), MCA,
    which gives the Board authority to initiate suit in district court to restrain a person from
    continuing a violation or from carrying out a threat of violation. Hawley's contention that
    this provision establishes the Board's exclusive remedy for non-emergency situations rings
    hollow in light of the provisions in subsection (b). Subsection (b) grants the Board
    authority to "issue an order either assessing a civil penalty in the amount prescribed in 82-
    11-149, up to a maximum administrative penalty of $125,000, or requiring compliance
    with this chapter or a rule or order, or both." Section 82-11-147(1)(b), MCA (emphasis
    added). If, as Hawley posits, the provisions of § 82-11-147(1)(a), MCA, were the
    exclusive remedy available to the Board, then the language of § 82-11-147(1)(b), MCA,
    authorizing an order requiring compliance with a "rule or order" would be rendered
    meaningless. Interpretations that give effect to the legislation are always preferred over
    interpretations that treat the statute as void or as mere surplusage. American Linen Supply
    v. Dep't of Revenue (1980), 
    189 Mont. 542
    , 545, 
    617 P.2d 131
    , 133; § 1-3-232, MCA.
    Clearly, under subsection (b), the Board has express authority to issue an order requiring
    compliance with a prior order of the Board. In the present case, that means that the Board
    had authority on October 1, 1997, to require compliance with its prior order of September
    4, 1997 by ordering termination of production.
    ¶13Hawley's contention that § 82-11-147(1)(a), MCA's injunctive remedy is exclusive is
    also belied by the provisions of § 82-11-149, MCA, which state that a person guilty of
    violating Board orders is subject to a civil penalty of $75 - $10,000 a day and that "[a]
    ction under this section does not bar enforcement of this chapter or of rules or orders
    issued under it by injunction or other appropriate remedy." Section 82-11-149(2), MCA
    (emphasis added). We conclude that injunction through judicial enforcement is not the
    exclusive remedy available to the Board in non-emergency situations and that the District
    Court erred in vacating Board Order No. 104-97 and the October 1, 1997 order
    terminating production in Hawley wells.
    ¶14Reversed and remanded for reinstatement of Board Order No. 104-97 and the Order to
    Terminate Production Operations, dated October 1, 1997.
    /S/ W. WILLIAM LEAPHART
    We concur:
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm (6 of 7)3/29/2007 10:50:50 AM
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm
    /S/ J. A. TURNAGE
    /S/ JIM REGNIER
    /S/ TERRY N. TRIEWEILER
    /S/ KARLA M. GRAY
    file:///C|/Documents%20and%20Settings/cu1046/Desktop/opinions/98-316_(01-06-00)_Opinion.htm (7 of 7)3/29/2007 10:50:50 AM
    

Document Info

Docket Number: 98-316

Citation Numbers: 2000 MT 2, 297 Mont. 467, 993 P.2d 677, 57 State Rptr. 5, 2000 Mont. LEXIS 2

Judges: Leaphart, Turnage, Regnier, Trieweiler, Gray

Filed Date: 1/6/2000

Precedential Status: Precedential

Modified Date: 10/19/2024